CN109615700A - Three-dimension virtual reality tunnel monitoring system and its operating method - Google Patents

Three-dimension virtual reality tunnel monitoring system and its operating method Download PDF

Info

Publication number
CN109615700A
CN109615700A CN201811563806.6A CN201811563806A CN109615700A CN 109615700 A CN109615700 A CN 109615700A CN 201811563806 A CN201811563806 A CN 201811563806A CN 109615700 A CN109615700 A CN 109615700A
Authority
CN
China
Prior art keywords
tunnel
data
virtual reality
monitoring system
dimensional
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811563806.6A
Other languages
Chinese (zh)
Other versions
CN109615700B (en
Inventor
张智明
叶英
曹蕊
王晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Administration Road And Bridge Ltd Co
Beijing Municipal Engineering Research Institute
Original Assignee
Beijing Municipal Administration Road And Bridge Ltd Co
Beijing Municipal Engineering Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Administration Road And Bridge Ltd Co, Beijing Municipal Engineering Research Institute filed Critical Beijing Municipal Administration Road And Bridge Ltd Co
Priority to CN201811563806.6A priority Critical patent/CN109615700B/en
Publication of CN109615700A publication Critical patent/CN109615700A/en
Application granted granted Critical
Publication of CN109615700B publication Critical patent/CN109615700B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/05Geographic models
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T19/00Manipulating 3D models or images for computer graphics
    • G06T19/003Navigation within 3D models or images
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Software Systems (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Remote Sensing (AREA)
  • Computer Graphics (AREA)
  • Business, Economics & Management (AREA)
  • Computer Hardware Design (AREA)
  • Primary Health Care (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • General Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Alarm Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of three-dimension virtual reality tunnel monitoring systems, the three-dimension virtual reality tunnel monitoring system includes system client, three-dimensional emulation platform, database and two-dimentional Tunnel Excavation Monitoring system, wherein, system client provides system starting operation and user's logentry and operation interface, system client is made of three-dimension virtual reality emulation platform client and two-dimentional Tunnel Excavation Monitoring system client, three-dimensional emulation platform includes three-dimension virtual reality emulation platform client, the setting that three-dimension virtual reality emulation platform client provides login and operating parameter to three-dimension virtual reality emulation platform operates, and the data source of local data base is configured and is connected, two-dimentional Tunnel Excavation Monitoring system client provides the login and system parameter setting to two-dimentional Tunnel Excavation Monitoring system, to binding The input function of emergency preplan after the running parameter setting of hardware device and calamity.The present invention realizes real time data synchronization.

Description

Three-dimension virtual reality tunnel monitoring system and its operating method
Technical field
The present invention relates to construction monitoring technical field, especially with regard to a kind of three-dimension virtual reality tunnel monitoring system and Its operating method.
Background technique
With flourishing for China's Tunnel Engineering construction, safety monitoring and scientific construction during tunnel construction seem It is more and more important.It is most common solution using information-based monitoring early-warning system for the safe construction for solving the problems, such as tunnel Method is using manpower and material resources sparingly while can effectively reduce risk of loss.However, current safety for tunnel engineering monitoring system Mostly all using two-dimentional monitoring mode, there are monitoring data hysteresis quality, error rate is high, early warning and alarming is slow and causes risk can not In time the problems such as discovery, the unnecessary casualties and property loss that easily cause.With tunnel construction technology complexity Raising, construction monitoring data also become increasingly complex, and accuracy, the timeliness of data monitoring are also more and more important, if still Using two-dimensional monitoring system, it will lead to monitoring and be abstracted, be complicated, Risk-warning lag, monitoring result inevitably will appear larger Difference and mistake cannot carry out risk monitoring and control and early warning in time.Therefore, it is necessary to which traditional two-dimentional monitoring system is carried out technology It improves, raising system visualization level further improves monitoring and early warning effect, solution tunnel monitoring data is complicated, visuality is poor, The Risk-warning bottleneck problems such as not in time.With gradualling mature for Virtual Simulation, application field is also more and more diversified, It is to make up the effective way of traditional monitoring system shortcoming that the technology, which is introduced into Tunnel Excavation Monitoring system,.It is empty by introducing Quasi- emulation technology may be implemented construction site 3D visualization, make construction monitoring personnel in remote observation like being in construction site, Intuitively see very much the data of monitoring, all monitorings all execute in the state of visualization, guarantee long-range monitoring with The synchronization of phenomenon construction greatly improves the timeliness of risk discovery and Risk-warning.
The information disclosed in the background technology section is intended only to increase the understanding to general background of the invention, without answering When being considered as recognizing or imply that the information constitutes the prior art already known to those of ordinary skill in the art in any form.
Summary of the invention
The purpose of the present invention is to provide a kind of three-dimension virtual reality tunnel monitoring system and its operating method, can gram The shortcomings that taking the prior art.
To achieve the above object, the present invention provides a kind of three-dimension virtual reality tunnel monitoring system, the three-dimensional is existing Real tunnel monitoring system includes system client, three-dimensional emulation platform, database and two-dimentional Tunnel Excavation Monitoring system, In, system client provides system starting operation and user's logentry and operation interface, and system client is by three-dimensional Real emulation platform client and two-dimentional Tunnel Excavation Monitoring system client composition, three-dimensional emulation platform include three-dimensional empty Three-dimension virtual reality emulation platform is stepped in quasi- reality emulation platform client, the offer of three-dimension virtual reality emulation platform client Record and the setting of operating parameter operate, and the data source of local data base is configured and is connected, two-dimentional Tunnel Excavation Monitoring System client provides the login and system parameter setting to two-dimentional Tunnel Excavation Monitoring system, to the work of the hardware device of binding Make the input function of emergency preplan after parameter setting and calamity.
In a preferred embodiment, three-dimensional emulation platform is realized based on the 3D engine technique of OPENGL.
In a preferred embodiment, three-dimensional emulation platform is for providing building for tunnel three-dimensional simulation model Mould, the 3D visualization display of Tunnel Design survey data, construction monitoring data real-time update are shown and virtual channel model Animated walk-through and 3D browsing function.
In a preferred embodiment, database is made of local data base and remote network data library, local data Library is managed and is used by three-dimension virtual reality emulation platform, and relayed surveillanced network database is then by two-dimentional Tunnel Excavation Monitoring system pipes Reason, local data base and remote network data library carry out the synchronous and update of data by internet.
In a preferred embodiment, two-dimentional Tunnel Excavation Monitoring system has multiple information during constructing tunnel Automatic collection, wireless transmission, early warning and safety management function.
In a preferred embodiment, it is real to be able to carry out tunnel construction tunnel face image for two-dimentional Tunnel Excavation Monitoring system When acquisition, face STABILITY MONITORING, personnel and vehicle location management in hole, the data for surveying the various sensors of section to choosing are automatic Acquisition and comprehensive analysis, starting level Four early warning and emergency preplan.
In a preferred embodiment, three-dimensional emulation platform can be used in the modeling of tunnel threedimensional model, tunnel three Dimension Section chart drawing, tunnel three-dimensional line style is drawn, Tunnel Design information three-dimensional is shown, tunnel surveying information three-dimensional is shown, tunnel is applied Work progress msg is shown, tunnel three-dimensional virtual environment roaming browsing, Tunnel Excavation Monitoring data real-time display and work progress are pre- Report warning information prompt.
In a preferred embodiment, wherein it is synchronous that local data base is based on following steps progress data:
An interim concordance list is established in server-side database, interim concordance list changes for the additions and deletions of storage server client database Data index;Server end timing empties interim concordance list, and creates and empty record sheet, will empty in emptying record sheet Time insertion empty the creation time field of record sheet;Server by the increasing of database, delete and change operation all remember It records in interim concordance list, when needing synchronous local data base and server database, in reading service device client database The data that the needs recorded in interim concordance list are modified, execute corresponding data manipulation on local data base;And local visitor After each sync database data in family end, a text file is created in the machine, to store the modification time of the last item record.
The present invention also provides a kind of operating method such as preceding three-dimension virtual reality tunnel monitoring system, the operating methods Include the following steps: to log in two-dimentional Tunnel Excavation Monitoring system by webpage client, and by the design information and prospecting in tunnel The typings such as information;Three-dimension virtual reality emulation platform is logged in by client, and to the correlation of three-dimension virtual reality emulation platform Operating parameter is configured;Information acquisition module is acquired to monitoring and measurement data and handles and send it to server, Data management provides data input function, carries out data by visualization model and checks;Keeper's location information in database, Audio and video information and prospective design data, the measurement data of various kinds of sensors, Tunnel Design overview, advance geologic prediction data and Relevant early-warning and predicting information and emergency preplan;Telenet is written in design information and investigation information and monitoring data to tunnel Preservation and management are carried out in circuit-switched data, and newest data are updated;After the setting of virtual reality emulation platform, local data Library and the progress of relayed surveillanced network database are synchronous for the first time, and virtual reality engine, which starts and reads tunneling data from local data base, to be built Vertical three-dimensional tunnel model;And local data base periodically or according to presetting condition and remote network data library carries out data It keeps synchronizing, realizes the real-time update of data, two-dimentional Tunnel Excavation Monitoring system is when having detected data update by Xiang Sanwei Virtual emulation platform issues data update notification, assigns data more new command by three-dimensional emulation platform, completes a data It updates.
Compared with prior art, three-dimension virtual reality tunnel monitoring system of the invention and its operating method have following excellent Point: of the invention is mainly characterized by establishing the construction speed of three-dimensional tunnel simulation model simulation actual tunnel, and utilizes net Network data synchronization technology realizes virtual channel model and actual tunnel construction site real time data synchronization.The present invention can by three-dimensional It helps monitoring personnel to grasp field monitoring data in real time depending on the display system changed, quickly positions risk data position, it is existing to construction Field operation carries out safely instruction.The present invention has the characteristics that easy to operate, reaction is quick, objective interface, visualization are high, can Effectively ensure engineering safety and construction speed.The present invention can simulate Tunnel Construction Schedule, realize that three-dimensional visualization shows tunnel Construction site Real-time Monitoring Data and site operation personnel are positioned in real time and attendance management.The present invention can be in virtual reality tunnel It is realized in road and cross section deformation monitoring is surveyed to choosing.The present invention can realize the Risk-warning in work progress in virtual reality tunnel And disaster alarm, emergency preplan is implemented and disaster assistance guidance after providing calamity.The present invention effectively can help monitoring personnel virtual Construction site truth is grasped in real tunnel in real time, reduces the incorrect decision of monitoring personnel, improves working efficiency, reduces people Member's cost.The present invention uses unique method of data synchronization, avoids and is frequently answered in a manner of full library backup from server Database processed improves the efficiency and real-time property of local data update to local computer.
Detailed description of the invention
Fig. 1 is the composite structural diagram of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention.
Fig. 2 is the three-dimensional emulation platform functional structure of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention Figure.
Fig. 3 is the two-dimentional Tunnel Excavation Monitoring system function knot of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention Composition.
Fig. 4 is the work flow diagram of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention.
Fig. 5 is the database data table design drawing of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention.
Fig. 6 is the Database Systems menu design drawing of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention.
Fig. 7 is the data bank service menu design drawing of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention.
Fig. 8 is the method for data synchronization flow chart of three-dimension virtual reality Tunnel Excavation Monitoring system of the present invention.
Specific embodiment
With reference to the accompanying drawing, specific embodiments of the present invention will be described in detail, it is to be understood that guarantor of the invention Shield range is not limited by the specific implementation.
Unless otherwise explicitly stated, otherwise in entire disclosure and claims, term " includes " or its change Changing such as "comprising" or " including " etc. will be understood to comprise stated element or component, and not exclude other members Part or other component parts.
With reference to Fig. 1, the present invention is by system client 101, three-dimensional emulation platform 102, database 103 and two-dimentional tunnel Construction monitoring system 104 forms.System client provides system starting operation and user's logentry and operation interface, by three It ties up virtual reality emulation platform client and two-dimentional Tunnel Excavation Monitoring system client is constituted.Three-dimension virtual reality emulation platform The setting that client provides login and operating parameter to three-dimension virtual reality emulation platform operates, and to the number of local data base It is configured and connects according to source;Two-dimentional Tunnel Excavation Monitoring system client provides the login to two-dimentional Tunnel Excavation Monitoring system And system parameter setting, to the input function of emergency preplan after the running parameter setting and calamity of the hardware device of binding.It is three-dimensional Virtual emulation platform is realized based on the 3D engine technique of OPENGL, provides the modeling of tunnel three-dimensional simulation model, tunnel is set Meter survey data 3D visualization display, construction monitoring data real-time update show and the animated walk-through of virtual channel model and 3D browsing function.Database is made of local data base 105 and remote network data library 106, and local data base is by three-dimensional Real emulation platform management and use, relayed surveillanced network database then by two-dimentional Tunnel Excavation Monitoring system administration, the two pass through because Spy's net carries out the synchronization and update of data.Two-dimentional Tunnel Excavation Monitoring system, have multiple information during constructing tunnel from The functions such as dynamic acquisition, wireless transmission, early warning and safety management, can carry out tunnel construction tunnel face image real-time acquisition, area Personnel and vehicle location management in face stability monitoring, hole, the automatic data collection and synthesis of the various sensors of section are surveyed to choosing Analysis starts level Four early warning and emergency preplan.
With reference to Fig. 2, three-dimensional emulation platform of the invention, function contains the modeling of tunnel threedimensional model, tunnel three-dimensional Section chart drawing, tunnel three-dimensional line style is drawn, Tunnel Design information three-dimensional is shown, tunnel surveying information three-dimensional is shown, constructing tunnel Progress msg is shown, tunnel three-dimensional virtual environment roaming browsing, Tunnel Excavation Monitoring data real-time display and work progress are forecast Warning information prompt.Threedimensional model modeling in tunnel is the three-dimensional mould that virtual reality tunnel is established using the 3D modeling technology of OPENGL Type.It is to carry out 3D drafting according to section of five hearts in the tunnel circle design information to tunnel that tunnel three-dimensional cross-sections, which are drawn,.Tunnel is three-dimensional It is to excavate the 3D line style that line style information draws virtual channel according to the design in tunnel that line style, which is drawn,.Tunnel Design information three-dimensional is shown It is the tunnel overview that virtual channel is drawn according to the comprehensive design information in tunnel.It is according to tunnel that tunnel surveying information three-dimensional, which is shown, Geological mapping information and face geological information draw virtual channel geology section.It is root that Tunnel Construction Schedule information, which is shown, The construction speed information of virtual channel is drawn according to the practical excavation progress in tunnel.Three-dimensional virtual environment roaming browsing in tunnel utilizes dynamic State browser technology, with first person traveling and with 360 degree of visual fields observation virtual channel inside and outside situations in virtual channel. Tunnel Excavation Monitoring data real-time display and work progress forecasting and warning information alert are that monitoring is highlighted in virtual channel Data and construction risk alarm animation, quick prompt and positioning risk position.
With reference to Fig. 3, two-dimentional Tunnel Excavation Monitoring system of the invention, function contains user authority management and system is set It sets, information collection and data management, database and forecasting and warning management and aggregation of data analysis and specialty analysis.
User authority management and system setting, including user authority management, system operational parameters setting, relevant hardware devices Parameter setting three parts function.
Information collection and data management, including monitoring data acquisition and transmission, data processing and data typing, personnel positioning Data, audio and video information and Tunnel Design overview.
Database and forecasting and warning management, including advance geologic prediction data, forecast and warning information, emergency preplan and answer Anxious response.
Aggregation of data analysis and specialty analysis, including expert system, regression analysis, finite element analysis and gray theory.
With reference to Fig. 4, the workflow of three-dimension virtual reality Tunnel Excavation Monitoring system of the invention are as follows: pass through user first Login interface logs in the webpage client of three dimension system local client and two-dimentional system respectively;By three dimension system local client Local three-dimensional virtual emulation platform is logged in and operates, local data is controlled by local three-dimensional emulation platform and management;It is logical The webpage client for crossing two-dimentional system logs in two-dimentional Tunnel Excavation Monitoring system, and is managed to remote network data library.Two Dimension Tunnel Excavation Monitoring system is done acquisition in real time to Tunnel Excavation Monitoring data and is updated, and maintains from two-dimentional webpage client to three Local client of uniting sends corresponding data update notifying, and three dimension system local client receives after data update notifying to this Ground data assign data synchronic command, and actively passing through network and relayed surveillanced network database by local data base, to carry out data synchronous, Obtain newest monitoring data.Specific workflow is divided into following 6 stages:
(1) data inputting and operating parameter setting: logging in two-dimentional Tunnel Excavation Monitoring system by webpage client, and by tunnel The typings such as the design information in road and investigation information;Three-dimension virtual reality emulation platform is logged in by client, and to three-dimensional The related operating parameter of real emulation platform is configured.
(2) information collection and data management: information acquisition module monitoring and measurement data is acquired and is handled and by its It is sent to server, data management provides data input function, carries out data by visualization model and checks.
(3) database and forecasting and warning management: keeper's location information, audio and video information and prospective design in database Data, the measurement data of various kinds of sensors, Tunnel Design overview, advance geologic prediction data and relevant early-warning and predicting information With emergency preplan etc..
(4) remote data storage and synchronized update: design information and investigation information and monitoring data write-in to tunnel Preservation and management are carried out in relayed surveillanced network data, and newest data are updated.
(5) operation of virtual reality human-computer interaction: after the setting of virtual reality emulation platform, local data base and telenet Circuit-switched data library is synchronized for the first time, and virtual reality engine, which starts and reads tunneling data from local data base, establishes three-dimensional tunnel Model.
(6) data real-time update: local data base timing or according to presetting condition and remote network data library into Row data keep synchronizing, and realize the real-time update of data.Two-dimentional Tunnel Excavation Monitoring system will when having detected data update Data update notification is issued to three-dimensional emulation platform, data more new command is assigned by three-dimensional emulation platform, completes one Secondary data update.
With reference to Fig. 5, system database of the invention, the design of tables of data is by base station setting table, data acquisition tables and survey Point information table composition.
Table is arranged in base station, is made of neighbouring base station table and addition instruction catalogue.It is laid in neighbouring base station table record tunnel logical Believe the information of base station;Addition instruction catalogue, which records corresponding communication base station, needs instruction to be loaded.
Data acquisition tables are deleted by channel table, channel type table, channel data table, channel temporary data table and channel and are referred to Table is enabled to form.The number information of channel table recording channel;Channel type table has recorded the type information in channel;Channel data table note Record the collected data information in channel;The collected ephemeral data information of channel temporary data table recording channel;Channel, which is deleted, to be referred to Table is enabled to record the information that corresponding channel is deleted or added.
With reference to Fig. 6, system database of the invention, the design of system function table by user's table, user correspond to tunnel table, Rights management table, navigation management table, base station type table, base station end oral thermometer, direct-connected base station setting table, item types table, short message are faced When table, short message type table and port table composition.
The essential information and authority information of user's table record system user.
User corresponds to the information of tunnel table record user and corresponding Tunnel Engineering.
Rights management table records the authority information that different system accounts possesses.
The navigation management information of navigation management table record system.
Base station type table records type information belonging to communication base station.
Whether base station end oral thermometer records the communication port information of each communication base station, by base station polling cycle table and be arranged Direct-connected base station table composition.Base station polling cycle table records the time cycle information of the polling message packet of communication base station;Whether it is arranged Whether direct-connected base station table record communication base station is arranged to direct-connected communication base station.
Direct-connected base station setting table records relevant information of the communication base station as direct-connected communication base station when.
The type information of item types table record constructing tunnel construction project.
The interim storage information of the interim table record short message of short message.
Short message type table includes downlink short message category table, the type information of record construction early warning short message.
Port table records the enabled port list of system.
With reference to Fig. 7, system database of the invention, the design of business function table is by man-machine table, tunnel overview table, prospecting Table, picture collection table, automatic early-warning is arranged in design data library table, advanced prediction scheme table, geological record table, construction prediction scheme table, short message Responsibility list and alarm lamp instruction catalogue composition.
Man-machine table is made of personnel positioning information table, personnel positioning result table, staff attendance card table and attendance record table.People The relevant rudimentary information of personnel and equipment that machine location information table record needs to position;Personnel positioning result table records personnel positioning Location information;The basic information of staff attendance card table record personnel's attendance card;The attendance record of attendance record table record personnel Information.
Tunnel overview table is made of tunnel table, tunnel cross-section information table and Tunnel Project type list.Tunnel table records tunnel Essential information;Five heart circle cross section design informations in tunnel cross-section information table record tunnel;Tunnel Project type list record tunnel is built If type information belonging to engineering project.
The address prospective design early period data in prospective design data bank table record tunnel.
The address advanced prediction information of advanced prediction scheme table record tunnel excavation.
Edit and record information in the address of geological record table record tunnel excavation face.
Construction prediction scheme table is made of each side's duty list, supplementary measures table, expert decision-making table.Each side's duty list records sandhog The role information of each related side of journey;The related supplementary measures of supplementary measures table record tunnel excavation;Expert decision-making table records system Expert decision-making information.
Short message setting table is made of human-computer dialogue table, the interactive related setting information of record construction early warning short message.
Picture collection table is made of image data table, the image data information of record construction site acquisition.
Corresponding role information when automatic early-warning responsibility list records system automatic early-warning.
Alarm lamp instruction catalogue records alarm state information when system monitoring data are more than predetermined threshold.
With reference to Fig. 8, the synchronous method of data of the present invention is to the last updated data of network data base and the note of modification It records and is simultaneously saved in the form of index in an interim table, local program is according to the index of the interim table from remote network data library It reads newest data and local data base is updated, local data base and server-side database data is made to keep one It causes.Implement step are as follows:
(1) an interim concordance list is established in server-side database, table name SynchronousDB is used for storage server The index for the data that client database additions and deletions change, the table include following 7 fields: CRUD, CRUDGUID, DBName, TableName、PriKeys、CreateTime、Flag。
CRUD field, type are integer, the operation executed for storing this record.
CRUDGUID field, the major key as SynchronousDB table.
DBName field, type are character string, for storing the library name of the database where modification record.
TableName field, type are character string, for storing the table name where modification record.
PriKeys field, type are character string, for storing the major key set of modification record, the name value comprising each major key To set, divided with comma.
CreateTime field, for storing record creation time.
Flag field, type are integer, for identifying whether this record can be deleted.
(2) server timing empties interim concordance list SynchronousDB, and creates and empty record sheet, and table name is The time emptied is inserted into SynchronousDBTime table CreateTime field by SynchronousDBTime.
CreateTime field, for recording the time for emptying SynchronousDB table.When carrying out null clear operation, lead to Know that the machine client last time of connection empties the time of SynchronousDB table, if client is before this table records the time Without more new database, then client needs backup database again.
(3) server to the increasing of database, delete, change operation, interim concordance list SynchronousDB is all recorded In, until specific time needs synchronous local data base and server database, this table of reading service device client database record The data for needing to modify execute corresponding data manipulation on local data base, to keep local data base and server count It is consistent according to library data, after data synchronously complete, delete all records of Flag=1 in interim concordance list SynchronousDB.
The operation that server increases database data, deletes, changing is included in interim concordance list SynchronousDB Method are as follows: database name is included in the DBName field of table, table name is entered into TableName field, which major key institute passed through The operation done is included in PriKeys field, and the operation increase, delete, changing is included in CRUD field, and the time of single record creation is charged to CreateTime field is finally completed the record to server-side database change.
(4) after each sync database data of local client, a Txt file is created in the machine, stores the last item The modification time of record.Per the subsynchronous preceding SynchronousDBTime table of reading first, whether field CreateTime is judged The time is emptied greater than the machine Txt file record, empties time, explanation if it is greater than the machine Txt file record SynchronousDB table has null clear operation, needs backup database again;The time is emptied if it is less than the machine Txt record, is said Bright SynchronousDB table does not empty, then read SynchronousDBTime.CreateTime the machine Txt record the time it All records of Flag=0 in interim concordance list SynchronousDB afterwards, according to every record corresponding data library name (DBName), data table name (TableName), major key set (PriKeys), in corresponding this in query service device end record Hold, then executes that CRUD value is corresponding to be increased, delete, changes operation in local data base.After completing this time synchronized update of all data, The record change that Flag=1 is done to the server data specifically read, illustrates that this record has been synchronized to local data base.
It should be understood by those skilled in the art that, embodiments herein can provide as method, system or computer program Product.Therefore, complete hardware embodiment, complete software embodiment or reality combining software and hardware aspects can be used in the application Apply the form of example.Moreover, it wherein includes the computer of computer usable program code that the application, which can be used in one or more, The computer program implemented in usable storage medium (including but not limited to magnetic disk storage, CD-ROM, optical memory etc.) produces The form of product.
The application is referring to method, the process of equipment (system) and computer program product according to the embodiment of the present application Figure and/or block diagram describe.It should be understood that every one stream in flowchart and/or the block diagram can be realized by computer program instructions The combination of process and/or box in journey and/or box and flowchart and/or the block diagram.It can provide these computer programs Instruct the processor of general purpose computer, special purpose computer, Embedded Processor or other programmable data processing devices to produce A raw machine, so that being generated by the instruction that computer or the processor of other programmable data processing devices execute for real The device for the function of being specified in present one or more flows of the flowchart and/or one or more blocks of the block diagram.
These computer program instructions, which may also be stored in, is able to guide computer or other programmable data processing devices with spy Determine in the computer-readable memory that mode works, so that it includes referring to that instruction stored in the computer readable memory, which generates, Enable the manufacture of device, the command device realize in one box of one or more flows of the flowchart and/or block diagram or The function of being specified in multiple boxes.
These computer program instructions also can be loaded onto a computer or other programmable data processing device, so that counting Series of operation steps are executed on calculation machine or other programmable devices to generate computer implemented processing, thus in computer or The instruction executed on other programmable devices is provided for realizing in one or more flows of the flowchart and/or block diagram one The step of function of being specified in a box or multiple boxes.
The aforementioned description to specific exemplary embodiment of the invention is in order to illustrate and illustration purpose.These descriptions It is not wishing to limit the invention to disclosed precise forms, and it will be apparent that according to the above instruction, can much be changed And variation.The purpose of selecting and describing the exemplary embodiment is that explaining specific principle of the invention and its actually answering With so that those skilled in the art can be realized and utilize a variety of different exemplary implementation schemes of the invention and Various chooses and changes.The scope of the present invention is intended to be limited by claims and its equivalents.

Claims (9)

1. a kind of three-dimension virtual reality tunnel monitoring system, which is characterized in that the three-dimension virtual reality tunnel monitoring system packet Include system client, three-dimensional emulation platform, database and two-dimentional Tunnel Excavation Monitoring system, wherein the system users End offer system starting operation and user's logentry and operation interface, the system client are emulated by three-dimension virtual reality Platform client and two-dimentional Tunnel Excavation Monitoring system client composition, the three-dimensional emulation platform include that three-dimensional is existing Real emulation platform client, the three-dimension virtual reality emulation platform client are provided to the three-dimension virtual reality emulation platform Login and operating parameter setting operation, and the data source of local data base is configured and is connected, the two dimension tunnel Construction monitoring system client provides the login and system parameter setting to two-dimentional Tunnel Excavation Monitoring system, to the hardware of binding The input function of emergency preplan after the running parameter setting of equipment and calamity.
2. three-dimension virtual reality tunnel monitoring system as described in claim 1, which is characterized in that the three-dimensional emulation is flat Stylobate is realized in the 3D engine technique of OPENGL.
3. three-dimension virtual reality tunnel monitoring system as claimed in claim 2, which is characterized in that the three-dimensional emulation is flat Platform is for providing modeling, the 3D visualization display of Tunnel Design survey data, construction monitoring of tunnel three-dimensional simulation model Data real-time update is shown and the animated walk-through of virtual channel model and 3D browsing function.
4. three-dimension virtual reality tunnel monitoring system as claimed in claim 3, which is characterized in that the database is by local number Constituted according to library and remote network data library, the local data base by the three-dimension virtual reality emulation platform management and use, The relayed surveillanced network database is then by the two-dimentional Tunnel Excavation Monitoring system administration, the local data base and telecommunication network number The synchronization and update of data are carried out by internet according to library.
5. three-dimension virtual reality tunnel monitoring system as claimed in claim 4, which is characterized in that the two dimension constructing tunnel prison Examining system has automatic collection, wireless transmission, early warning and the safety management function of multiple information during constructing tunnel.
6. three-dimension virtual reality tunnel monitoring system as claimed in claim 5, which is characterized in that the two dimension constructing tunnel prison Examining system is able to carry out tunnel construction tunnel face image real-time acquisition, face STABILITY MONITORING, personnel and vehicle location in hole Automatic data collection and comprehensive analysis, the starting level Four early warning and emergency preplan of the various sensors of section are surveyed in management to choosing.
7. three-dimension virtual reality tunnel monitoring system as claimed in claim 6, which is characterized in that the three-dimensional emulation is flat Platform can be used in the modeling of tunnel threedimensional model, tunnel three-dimensional cross-sections are drawn, tunnel three-dimensional line style is drawn, Tunnel Design information three-dimensional Display, tunnel surveying information three-dimensional is shown, Tunnel Construction Schedule information is shown, tunnel three-dimensional virtual environment roaming browsing, tunnel Construction monitoring data real-time display and work progress forecasting and warning information alert.
8. three-dimension virtual reality tunnel monitoring system as claimed in claim 7, which is characterized in that wherein, the local data It is synchronous that library is based on following steps progress data:
An interim concordance list is established in server-side database, the interim concordance list increases for storage server client database The index for the data revised;
Server end timing empties the interim concordance list, and creates and empty record sheet, will empty in described empty in record sheet Time insertion empty the creation time field of record sheet;
Server by the increasing of database, delete and change operation and be all recorded in the interim concordance list, when needing to synchronize When local data base and server database, the needs recorded in the interim concordance list in reading service device client database are repaired The data changed execute corresponding data manipulation on local data base;And
After each sync database data of local client, a text file is created in the machine, to store the last item record Modification time.
9. a kind of operating method of three-dimension virtual reality tunnel monitoring system as described in one of claim 1-8, feature exist In the operating method includes the following steps:
Two-dimentional Tunnel Excavation Monitoring system is logged in by webpage client, and the design information in tunnel and investigation information etc. are recorded Enter;Three-dimension virtual reality emulation platform is logged in by client, and to the related operating parameter of three-dimension virtual reality emulation platform It is configured;
Information acquisition module is acquired to monitoring and measurement data and handles and send it to server, and data management provides money Expect input function, data are carried out by visualization model and are checked;
Keeper's location information, audio and video information and prospective design data, the measurement data of various kinds of sensors, tunnel in database Survey design, advance geologic prediction data and relevant early-warning and predicting information and emergency preplan;
Preservation and management are carried out in design information and investigation information and monitoring data write-in relayed surveillanced network data to tunnel, and Newest data are updated;
After the setting of virtual reality emulation platform, local data base and the progress of relayed surveillanced network database are synchronous for the first time, and virtual reality is drawn It holds up starting and reads tunneling data from local data base and establish three-dimensional tunnel model;And
Local data base timing is synchronous with the progress data holding of remote network data library according to presetting condition, realizes number According to real-time update, two-dimentional Tunnel Excavation Monitoring system will issue when having detected data update to three-dimensional emulation platform Data update notification assigns data more new command by three-dimensional emulation platform, completes a data and updates.
CN201811563806.6A 2018-12-20 2018-12-20 Three-dimensional virtual reality tunnel monitoring system and operation method thereof Active CN109615700B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811563806.6A CN109615700B (en) 2018-12-20 2018-12-20 Three-dimensional virtual reality tunnel monitoring system and operation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811563806.6A CN109615700B (en) 2018-12-20 2018-12-20 Three-dimensional virtual reality tunnel monitoring system and operation method thereof

Publications (2)

Publication Number Publication Date
CN109615700A true CN109615700A (en) 2019-04-12
CN109615700B CN109615700B (en) 2023-02-28

Family

ID=66009605

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811563806.6A Active CN109615700B (en) 2018-12-20 2018-12-20 Three-dimensional virtual reality tunnel monitoring system and operation method thereof

Country Status (1)

Country Link
CN (1) CN109615700B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110717986A (en) * 2019-10-11 2020-01-21 中国电建集团铁路建设有限公司 Shield tunnel construction system based on virtual reality technology
CN110830331A (en) * 2019-12-06 2020-02-21 中国交通建设股份有限公司 Physical model test process data transmission system and method
CN110847963A (en) * 2019-10-08 2020-02-28 中国铁建重工集团股份有限公司 Data interaction system for railway tunnel construction
CN111966670A (en) * 2020-07-08 2020-11-20 成都星时代宇航科技有限公司 Remote sensing data distribution method and device based on mosaic data set and management platform

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201689455U (en) * 2009-12-01 2010-12-29 北京市市政工程研究院 Tunnel construction disaster planning and preventing response system based on network platform
CN104680579A (en) * 2015-03-02 2015-06-03 北京工业大学 Tunnel construction informatization monitoring system based on three-dimensional scanning point cloud
CN106384191A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model
CN106572325A (en) * 2015-10-13 2017-04-19 上海宝信软件股份有限公司 Virtual-reality-technology-based tunnel monitoring equipment inspection system
CN108268986A (en) * 2016-12-30 2018-07-10 上海大学 Cross-river tunnel engineering construction simulation system based on BIM

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201689455U (en) * 2009-12-01 2010-12-29 北京市市政工程研究院 Tunnel construction disaster planning and preventing response system based on network platform
CN104680579A (en) * 2015-03-02 2015-06-03 北京工业大学 Tunnel construction informatization monitoring system based on three-dimensional scanning point cloud
CN106572325A (en) * 2015-10-13 2017-04-19 上海宝信软件股份有限公司 Virtual-reality-technology-based tunnel monitoring equipment inspection system
CN106384191A (en) * 2016-08-31 2017-02-08 铁道第三勘察设计院集团有限公司 Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model
CN108268986A (en) * 2016-12-30 2018-07-10 上海大学 Cross-river tunnel engineering construction simulation system based on BIM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张玥: "隧道施工智能管理系统研究及形象进度系统实现", 《中国优秀硕士学位论文数据库信息科技辑》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847963A (en) * 2019-10-08 2020-02-28 中国铁建重工集团股份有限公司 Data interaction system for railway tunnel construction
CN110847963B (en) * 2019-10-08 2021-11-30 中国铁建重工集团股份有限公司 Data interaction system for railway tunnel construction
CN110717986A (en) * 2019-10-11 2020-01-21 中国电建集团铁路建设有限公司 Shield tunnel construction system based on virtual reality technology
CN110830331A (en) * 2019-12-06 2020-02-21 中国交通建设股份有限公司 Physical model test process data transmission system and method
CN111966670A (en) * 2020-07-08 2020-11-20 成都星时代宇航科技有限公司 Remote sensing data distribution method and device based on mosaic data set and management platform
CN111966670B (en) * 2020-07-08 2021-09-10 成都星时代宇航科技有限公司 Remote sensing data distribution method and device based on mosaic data set and management platform

Also Published As

Publication number Publication date
CN109615700B (en) 2023-02-28

Similar Documents

Publication Publication Date Title
CN109615700A (en) Three-dimension virtual reality tunnel monitoring system and its operating method
CN102750618B (en) A kind of comprehensive pipeline of metro construction aided management system and implementation method
CN110689705A (en) Comprehensive application system for mine geological environment management
WO2022048156A1 (en) Pumped storage power station comprehensive management method, platform and system, device and medium
CN104680320A (en) BIM-based project management system and method
CN106779417A (en) The collection of engineering investigation information digitalization, management and integrated application method
CN111931278A (en) Building method and system of cloud platform based on BIM and GIS cooperative work
CN113722797A (en) Lightweight BIM prefabricated part full life cycle comprehensive information management system
CN114037097A (en) BIM model-based equipment operation and maintenance management method
US20240144576A1 (en) 3d object management data, computer program, and distributed management method for 3d object
CN112069580A (en) Digital delivery method, platform, system, equipment and medium for pumped storage power station
CN116304152A (en) Intelligent investigation result display system based on GIS and BIM
CN116091039A (en) Power transmission and transformation project acceptance result visualization method and system based on south network intelligent aerial view
CN114092648A (en) Digital twin application framework and method for application scene of station equipment
CN115131498A (en) Method for quickly constructing intelligent water conservancy digital twin model of reservoir
CN115905650A (en) Coal mine production three-dimensional visual information system based on Internet of things and sensor technology
CN110599116A (en) Power grid decentralized collaborative design method and system based on cloud data center
CN114781827A (en) Environment sample investigation cloud management method based on geographic spatial information
CN103150348B (en) A kind of GIS database increment updating method and its system
CN117171862B (en) Bridge engineering land investigation drilling point position checking method and equipment
CN109726916A (en) A method of suitable for highway life cycle management intelligent health monitoring
CN117056284A (en) Management system for drilling achievements of water transport engineering
CN116681847A (en) Management and service system for urban three-dimensional geological data
CN116109783A (en) Open-pit mine three-dimensional mining planning system and method
CN115062940A (en) Intelligent visual inspection method and system for launching pad based on digital twins

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant