CN104766155B - The management method and system of engineering project element based on BIM - Google Patents

The management method and system of engineering project element based on BIM Download PDF

Info

Publication number
CN104766155B
CN104766155B CN201510080209.8A CN201510080209A CN104766155B CN 104766155 B CN104766155 B CN 104766155B CN 201510080209 A CN201510080209 A CN 201510080209A CN 104766155 B CN104766155 B CN 104766155B
Authority
CN
China
Prior art keywords
bim model
bim
engineering project
model
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510080209.8A
Other languages
Chinese (zh)
Other versions
CN104766155A (en
Inventor
尹仕友
严国林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Is With Building Information Technology Co Ltd
Original Assignee
Shanghai Is With Building Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Is With Building Information Technology Co Ltd filed Critical Shanghai Is With Building Information Technology Co Ltd
Priority to CN201510080209.8A priority Critical patent/CN104766155B/en
Publication of CN104766155A publication Critical patent/CN104766155A/en
Application granted granted Critical
Publication of CN104766155B publication Critical patent/CN104766155B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The management method and system for the engineering project element based on BIM that the present invention provides a kind of, the attribute data A of the first BIM model is saved in server;First BIM model is simplified to obtain the 2nd BIM model and be issued, wherein being realized by component ID with the data correlation of attribute data A in server and being matched with the first BIM model in the end PC;The 2nd BIM model is loaded in the A of mobile terminal, to establishing incidence relation between collected engineering project element information and component ID, and it is shared by server.The present invention passes through the association of two sets of BIM models and component ID, realizes data interaction and virtual interactive interface.

Description

The management method and system of engineering project element based on BIM
Technical field
The present invention relates to the management methods based on BIM, more particularly to the management method of the engineering project element based on BIM And system, more particularly to the quality based on BIM, safety, environment, progress control method.
Background technique
BIM is the abbreviation of Building Information Modeling, domestic to be usually translated into architecture information mould Type.It is a kind of building Life cycle information system management technology, there is visualization, harmony, simulation, optimization property and can go out to scheme Five big features.BIM is that a kind of completely new architectural design, construction, management method will be advised based on three-dimensional digital information technology Draw, design, build, the data information in each stage such as operation is integrally incorporated among 3D model, allow building whole life cycle In any stage staff when using the model, effective, correct decision can be made according to accurate completely data.
Mobile Internet (Mobile Internet, abbreviation MI) is a kind of by intelligent mobile terminal, using mobile wireless Communication mode obtains the emerging service of business and service, comprising terminal, software and applies three levels.Terminating layer includes intelligent hand Machine, tablet computer, e-book, MID etc.;Software includes operating system, middleware, database and security software etc..Application layer packet Include different applications and the services such as amusement and recreation class, tool media class, commercial finance and economic.With the development of technology and industry, future, The network transmissions such as LTE (long term evolution, one of 4G communication technology standard) and NFC (near-field communication, the support technology of mobile payment) Layer key technology will be also included within the scope of mobile Internet.By the use to mobile Internet, can easily realize To the paperless management of building Life cycle, guarantee that the staff in any post of engineering can obtain complete, real-time work Journey information.
Have the defects that following several respects in the way to manage of the engineering projects element such as traditional operating condition and progress:
(1) information transfer connection.The unit and department being related to due to engineering management are numerous, traditional method such as meeting, hair The efficiency of the modes such as text, information transmitting is very low, and each side grasps multidate information more in time seems very difficult, to cause each side Information asymmetry causes to link up difficulty, or even delays project progress;
(2) in terms of Information procession.The data such as the related quality of operating condition, safety, environment, progress in engineering project, amount it is big and And ceaselessly changing, manual operations is difficult to summarize in time, and each side is made to be difficult to hold the situation of engineering.Also, the drawing of engineering, The information documents such as file, amount is big and saves generally in the form of paper, and as being in progress for engineering is continuous with all kinds of data Accumulation increases, and document is easily caused to lose, or even influences the maintenance work of later period building;
(3) information use aspect.The information for necessarily leading to magnanimity in architectural engineering construction and management process, especially confronts The management of the operating conditions such as amount, safety, environment and project progress is even more the most important thing, but traditional engineering management mode is not often because The various aspects factor such as it can record in time, link up and cause forgetting to operating condition, to influence the quality and normal progress of engineering.
Summary of the invention
For the defects in the prior art, the pipe for the engineering project element based on BIM that the object of the present invention is to provide a kind of Manage method and system.The features of the present invention includes:
(1) the real-time record of engineering information is realized using development of Mobile Internet technology, upload and download, it can be in the shortest time Site problems are reacted, and will not be lost.
(2) information includes text, voice, picture, video, and description problem is more accurate.
(3) all data are all stored in BIM model database, and by encryption and backup, ensure that data Safety and reliability.
(4) the open safe interface of data access, can be shared to other Management System Datas.
(5) BIM threedimensional model solid show is used, it is more intuitive than two-dimentional drawing.
A kind of management method of the engineering project element based on BIM provided according to the present invention, includes the following steps:
Step A: the first BIM model is saved in the end PC and is saved in the attribute data A of the first BIM model by the end PC In server, the attribute data includes component ID;Simplified to obtain the 2nd BIM model to the first BIM model, and by second The publication of BIM model uses for mobile terminal and/or WEB terminal, wherein after simplified, the attribute data B of the 2nd BIM model is only protected The component ID in the attribute data A of the first BIM model is stayed, to realize the number with attribute data A in server by component ID It is matched according to association, and with the first BIM model in the end PC;
Step B: loading the 2nd BIM model in the A of mobile terminal, to collected engineering project element information and component ID it Between establish incidence relation, and engineering project element information and incidence relation are sent to server and save and information sharing;
Step C: server is directed to the component ID in the request for carrying out user terminal, transferred according to the incidence relation and to Third party's terminal returns to corresponding engineering project element information, wherein the user terminal refers to not including the A of mobile terminal Mobile terminal, the end PC.
Preferably, the step A includes the following steps:
To caused in the first BIM model model face number be more than given threshold vertex remove;
To caused in the first BIM model moulded dimension be more than given threshold vertex remove;
Submodel in first BIM model is rebuild;
Race's example in first BIM model simplify and be replaced by MaxScript script;
The submodel of same material in first BIM model is merged.
Preferably, following steps are gone back:
In mobile terminal, user's operation is responded using the 2nd BIM model, and pass through component ID and engineering project element information Between incidence relation, returned to user and transfer component model or engineering project element information from server.
Preferably, the engineering project element information includes any one of quality, safety, environment, progress or multinomial letter Breath.
Preferably, the attribute data A in server only holding member ID and model name as the matched pass of unique information Key word.
A kind of management system of the engineering project element based on BIM provided according to the present invention, including the following end PC, service Device, mobile terminal;
The first BIM model is saved in the end PC, and the attribute data A of the first BIM model is saved in by server by the end PC In, the attribute data includes component ID;Simplified to obtain the 2nd BIM model to the first BIM model, and by the 2nd BIM mould Type publication uses for mobile terminal and/or WEB terminal, wherein after simplified, the attribute data B of the 2nd BIM model only remains the Component ID in the attribute data A of one BIM model, to realize the data correlation with attribute data A in server by component ID, And it is matched with the first BIM model in the end PC;
The 2nd BIM model is loaded in the A of mobile terminal, is established between collected engineering project element information and component ID Incidence relation, and engineering project element information and incidence relation are sent to server and carry out preservation and information sharing;
Server is directed to the component ID in the request for carrying out user terminal, is transferred according to the incidence relation and to third party Terminal returns to corresponding engineering project element information, wherein the user terminal refers to the not movement including the A of mobile terminal End, the end PC.
Preferably, following steps are executed in the end PC:
To caused in the first BIM model model face number be more than given threshold vertex remove;
To caused in the first BIM model moulded dimension be more than given threshold vertex remove;
Submodel in first BIM model is rebuild;
Race's example in first BIM model simplify and be replaced by MaxScript script;
The submodel of same material in first BIM model is merged.
Preferably, in mobile terminal, user's operation is responded using the 2nd BIM model, and pass through component ID and engineering project Incidence relation between element information returns to the component model or engineering project element information transferred from server to user.
Preferably, the engineering project element information includes any one of quality, safety, environment, progress or multinomial letter Breath.
Preferably, the attribute data A in server only holding member ID and model name as the matched pass of unique information Key word.
Compared with prior art, the present invention have it is following the utility model has the advantages that
1) three-dimensional visualization technique of BIM model, more intuitive carry out engineering management are combined;
2) using the fast development of Internet technology and Intelligent mobile equipment, computer terminal platform, mobile terminal are realized Multi-platform, the comprehensive Engineering Management Patterns such as platform, enrich management means and tool, realize the informationization of engineering management And diversification;
3) mobile Internet and data cloud are used, realizes the multi-platform Real-Time Sharing of information data in engineering management, Eliminate each party information asymmetry problem in engineering management;
4) specific each platform terminal purposes, simplifies process of engineering management, reduces cost payout, makes the thing in engineering management Part manages sharpening, responsibility distribution is made clear, progress monitoring digitization.
Detailed description of the invention
Upon reading the detailed description of non-limiting embodiments with reference to the following drawings, other feature of the invention, Objects and advantages will become more apparent upon:
Fig. 1 to Fig. 4 shows the topological diagram of the management method provided by the present invention jointly.
Specific embodiment
The present invention is described in detail combined with specific embodiments below.Following embodiment will be helpful to the technology of this field Personnel further understand the present invention, but the invention is not limited in any way.It should be pointed out that the ordinary skill of this field For personnel, without departing from the inventive concept of the premise, various modifications and improvements can be made.These belong to the present invention Protection scope.
A kind of management method of the engineering project element based on BIM provided according to the present invention, includes the following steps:
Step A: the first BIM model is saved in the end PC and is saved in the attribute data A of the first BIM model by the end PC In server, the attribute data includes component ID;Simplified to obtain the 2nd BIM model to the first BIM model, and by second The publication of BIM model uses for mobile terminal and/or WEB terminal, wherein after simplified, the attribute data B of the 2nd BIM model is only protected The component ID in the attribute data A of the first BIM model is stayed, to realize the number with attribute data A in server by component ID It is matched according to association, and with the first BIM model in the end PC.For example, the end C/S on PC will be as the first BIM model The attribute data A of detailed BIM model is saved in server database, is used for subsequent data real-time, interactive, the attribute number According to A as can not preferably be edited after in the confirmed typing server database of initial data;To also at the end C/S on PC Detailed BIM model is simplified, and the simplification BIM model as the 2nd BIM model is obtained, in the attribute data B for simplifying BIM model By holding member ID, to realize data correlation with the attribute data A in server database.
Step B: the 2nd BIM model is loaded in A (such as PAD) in mobile terminal, to collected engineering project element information Establish incidence relation between component ID, and by engineering project element information and incidence relation be sent to server save and Information sharing.Simplify BIM model for example, loading on PAD, carry out the information collection of quality, safety, environment, progress, and passes through Component ID is interacted with detailed BIM model data.
Step C: server is directed to the component ID in the request for carrying out user terminal, transferred according to the incidence relation and to Third party's terminal returns to corresponding engineering project element information, wherein the user terminal refers to not including the A of mobile terminal Mobile terminal, the end PC.
Wherein, the step A includes the following steps:
To caused in the first BIM model model face number be more than given threshold vertex remove;
To caused in the first BIM model moulded dimension be more than given threshold vertex remove;
Submodel in first BIM model is rebuild;
Race's example in first BIM model simplify and be replaced by MaxScript script;
The submodel of same material in first BIM model is merged.
Preferably, the engineering project element information includes any one of quality, safety, environment, progress or multinomial letter Breath.Attribute data A in server only holding member ID and model name as the matched keyword of unique information.In mobile terminal It is interior, user's operation is responded using the 2nd BIM model, and pass through the incidence relation between component ID and engineering project element information, The component model or engineering project element information transferred from server are returned to user.For example, (such as more in multiple users A mobile terminal or WEB terminal) on the quality of acquisition, safety, environment, progress msg are checked according to user role permission and Comment is replied, and by clicking component extraction component ID and location information in simplifying BIM model, by these quality, safety, Environment, progress, comment, return information are associated by component ID with the data of detailed BIM model, realize that each engineering participant exists Real-time quick exchange in engineering management.Mobile terminal and WEB terminal can using the 2nd BIM model according to the construction of component, tear open The process that building is completed in entire construction is simulated except time attribute.
The step B includes the following steps:
The 2nd BIM model (simplifying BIM model) is shown using Unity3D on the A of mobile terminal;
According to operating condition instruction is created on the A of mobile terminal, quality, safety, environment, progress are added by the 2nd BIM model Newly-built operating condition is associated with to component ID, and the following attribute information of newly-built operating condition is arranged:
Operating condition type, wherein operating condition type includes safety, quality, environment etc.;
Operating condition founder, wherein the login user of the mobile terminal of newly-built operating condition instruction will be issued as operating condition founder;
Creation time, wherein the time of operating condition creation is subject to time at WEB service end;
Deadline, wherein deadline is used to record the final date of operating condition processing, if reaching in the final date When operating condition operating condition situation or new problem when, then reminder message and operating condition are pushed by WEB service end forward end intelligent platform Attribute information;
Alarm interval, wherein alarm interval is used to record the interval time of the adjacent reminder message push alarmed twice;
Operating condition situation, wherein operating condition situation include new problem, in processing, processing completes, closes this four situations;
Operating condition title, wherein operating condition title is used to record the brief introduction of operating condition content;
Operating condition content, wherein operating condition content is used to record the practical illustration of operating condition;
Operating condition attachment, wherein operating condition attachment includes picture, voice, video;
It is associated with component, wherein the component ID in association BIM model is used for recording component ID associated by operating condition It bubble and is highlighted;
Newly-built work information is issued on the A of mobile terminal, passes through component ID on the back-end data cloud of server The shared interaction of information data is realized as association, and is pushed on other mobile terminals by the end Web.
Further, correspondingly with the management method of the engineering project element based on BIM, the present invention also provides one The management system of engineering project element of the kind based on BIM, including the following end PC, server, mobile terminal;
The first BIM model is saved in the end PC, and the attribute data A of the first BIM model is saved in by server by the end PC In, the attribute data includes component ID;Simplified to obtain the 2nd BIM model to the first BIM model, and by the 2nd BIM mould Type publication uses for mobile terminal and/or WEB terminal, wherein after simplified, the attribute data B of the 2nd BIM model only remains the Component ID in the attribute data A of one BIM model, to realize the data correlation with attribute data A in server by component ID, And it is matched with the first BIM model in the end PC;
The 2nd BIM model is loaded in the A of mobile terminal, is established between collected engineering project element information and component ID Incidence relation, and engineering project element information and incidence relation are sent to server and carry out preservation and information sharing;
Server is directed to the component ID in the request for carrying out user terminal, is transferred according to the incidence relation and to third party Terminal returns to corresponding engineering project element information, wherein the user terminal refers to the not movement including the A of mobile terminal End, the end PC.
Preferably, following steps are executed in the end PC:
To caused in the first BIM model model face number be more than given threshold vertex remove;
To caused in the first BIM model moulded dimension be more than given threshold vertex remove;
Submodel in first BIM model is rebuild;
Race's example in first BIM model simplify and be replaced by MaxScript script;
The submodel of same material in first BIM model is merged.
Preferably, in mobile terminal, user's operation is responded using the 2nd BIM model, and pass through component ID and engineering project Incidence relation between element information returns to the component model or engineering project element information transferred from server to user.
Preferably, the engineering project element information includes any one of quality, safety, environment, progress or multinomial letter Breath.
Preferably, the attribute data A in server only holding member ID and model name as the matched pass of unique information Key word.
The mobile terminal (including mobile terminal A) includes work information management module, wherein the work information manages mould Block, including following device:
Newly-built operating condition managing device: for adding quality, safety, ring by the 2nd BIM model according to operating condition instruction is created Border, progress newly-built operating condition be associated with to component ID, and the following attribute information of newly-built operating condition is set:
Operating condition type, wherein operating condition type includes safety, quality, environment;
Operating condition founder, wherein the login user of the mobile terminal of newly-built operating condition instruction will be issued as operating condition founder;
Creation time, wherein the time of operating condition creation is subject to time at WEB service end;
Deadline, wherein deadline is used to record the final date of operating condition processing, if reaching in the final date When operating condition operating condition situation or new problem when, then reminder message and operating condition are pushed by WEB service end forward end intelligent platform Attribute information;
Alarm interval, wherein alarm interval is used to record the interval time of the adjacent reminder message push alarmed twice;
Operating condition situation, wherein operating condition situation include new problem, in processing, processing completes, closes this four situations;
Operating condition title, wherein operating condition title is used to record the brief introduction of operating condition content;
Operating condition content, wherein operating condition content is used to record the practical illustration of operating condition;
Operating condition attachment, wherein operating condition attachment includes picture, voice, video;
It is associated with component, wherein association component using bubble and is highlighted for recording component associated by operating condition;
Operating condition comments on managing device: adding for receiving foreground intelligent platform to the comment information of operating condition, and by comment information It is added in operating condition content, it is then synchronous between foreground intelligent platform, WEB service end, background data base end by WEB service end Update operating condition content;
Operating condition replys managing device: for receiving other mobile terminals or WEB terminal to the return information of operating condition comment information, and Return information is added in operating condition content, then by WEB service end mobile terminal, WEB service end, server rear number of units According to synchronized update operating condition content between the end of library;
The driving means of work information: for that will be more than the work in deadline and operating condition situation or new problem or processing The operating condition attribute information of condition is pushed to the specified mobile terminal of user instruction by WEB service end.
Schedule management apparatus: management valid data: searching associated progress msg according to the date range of selection, as long as into The plan of degree starts, terminates;Actually start, Close Date and the date selected as valid data in relation to showing;Manage into The expression of degree and the time difference.
More specifically, the management method and system of the engineering project element provided by the invention based on BIM: all or Partial data can be associated by component ID and be saved in WEB service end and server, nothing using development of Mobile Internet technology Need manual intervention, front end and backstage can be analyzed and determined according to data the duration whether in predetermined period, in time remind it is untreated Safety, quality, environmental problem;Using local buffer technology, it can be achieved that without the data transmit-receive under network;It will using Unity3D Mobile terminal, detailed BIM model, three-dimensional real-time, interactive combined technology are on the leading domestic level.Wherein, of the invention main Feature is that by BIM model real-time, interactive, specifically includes:
A. it is associated by simplifying the database in the component ID and server that save in BIM model;
B. will simplify BIM model and detailed BIM model to match by component ID;
C. to information such as structure attribute, the model absolute altitudes of detailed BIM model, by the C/S Program extraction at the end PC, store to In server database, the keyword of holding member ID and model name as these information of unique match realizes information exchange;
D. to simplify BIM model mobile terminal realize rotation, scaling, component choose, construction progress simulation etc. user's operations, And by model component ID and engineering project element it is newly-increased, the operations such as to modify associated, both engineering can be checked by model Project elements can also check model information, the virtual interactive interface of implementation model and data by checking engineering project element.
It can be realized following application using the present invention
1 using the personnel of collection in worksite, material, machinery real work situation compare in ready-made planned management of project into Degree plan, automatically generates the three-dimensional visualization model of working report and model interaction, to carry out subsequent more specific progress peace Row and optimization.
2 are done pair using real data and the National Technical specification or related sample project of live each side staff acquisition Than being derived automatically from related final report.Time that each event occurs and geographical location are associated with three-dimensional visible with space coordinate The BIM model of change carries out concealed work the record and product of data so that the quality to construction carries out reasonable control It is tired.
3 show the associated event data being consistent with actual conditions in the BIM model of three-dimensional visible, existing using each side The abundant information of field personnel's acquisition is managed to the safety problem of architectural engineering in the construction process and control, for hidden work Journey, which is carried out, keeps on file in advance and takes precautions against.
4 using scene Real-time Monitoring Data the work progress of architectural engineering is monitored, automatic data collection and Real-time exhibition in threedimensional model.The warning value for concurrently setting active forewarning, active forewarning of finding the problem, and according to the weight of event Emergency judges automatically monitoring frequency.
Specific embodiments of the present invention are described above.It is to be appreciated that the invention is not limited to above-mentioned Particular implementation, those skilled in the art can make various deformations or amendments within the scope of the claims, this not shadow Ring substantive content of the invention.

Claims (8)

1. a kind of management method of the engineering project element based on BIM, which comprises the steps of:
Step A: the first BIM model is saved in the end PC, the attribute data A of the first BIM model is saved in by service by the end PC In device, the attribute data includes component ID;Simplified to obtain the 2nd BIM model to the first BIM model, and by the 2nd BIM Model publication uses for mobile terminal and/or WEB terminal, wherein after simplified, the attribute data B of the 2nd BIM model is only remained Component ID in the attribute data A of first BIM model is closed with being realized by component ID with the data of attribute data A in server Connection, and matched with the first BIM model in the end PC;
Step B: the 2nd BIM model is loaded in the A of mobile terminal, is built between collected engineering project element information and component ID Vertical incidence relation, and engineering project element information and incidence relation are sent to server and carry out preservation and information sharing;
Step C: server is directed to the component ID in the request for carrying out user terminal, is transferred according to the incidence relation and to third Square terminal returns to corresponding engineering project element information, wherein the user terminal refers to the not movement including the A of mobile terminal End, the end PC;
The step A includes the following steps:
To caused in the first BIM model model face number be more than given threshold vertex remove;
To caused in the first BIM model moulded dimension be more than given threshold vertex remove;
Submodel in first BIM model is rebuild;
Race's example in first BIM model simplify and be replaced by MaxScript script;
The submodel of same material in first BIM model is merged.
2. the management method of the engineering project element according to claim 1 based on BIM, which is characterized in that also following step It is rapid:
In mobile terminal, user's operation is responded using the 2nd BIM model, and by between component ID and engineering project element information Incidence relation, returned to user and transfer component model or engineering project element information from server.
3. the management method of the engineering project element according to claim 1 based on BIM, which is characterized in that the engineering Project elements information includes any one of quality, safety, environment, progress or multinomial information.
4. the management method of the engineering project element according to claim 1 based on BIM, which is characterized in that in server Attribute data A only holding member ID and model name as the matched keyword of unique information.
5. a kind of management system of the engineering project element based on BIM, which is characterized in that including the following end PC, server, movement End;
The first BIM model is saved in the end PC the attribute data A of the first BIM model is saved in server by the end PC, The attribute data includes component ID;First BIM model is simplified to obtain the 2nd BIM model, and the 2nd BIM model is sent out Cloth uses for mobile terminal and/or WEB terminal, wherein after simplified, the attribute data B of the 2nd BIM model only remains first Component ID in the attribute data A of BIM model, to realize the data correlation with attribute data A in server by component ID, and It is matched with the first BIM model in the end PC;
The 2nd BIM model is loaded in the A of mobile terminal, is associated with to establishing between collected engineering project element information and component ID Relationship, and engineering project element information and incidence relation are sent to server and carry out preservation and information sharing;
Server is directed to the component ID in the request for carrying out user terminal, is transferred according to the incidence relation and to third party's terminal Return to corresponding engineering project element information, wherein the user terminal refers to the not mobile terminal including the A of mobile terminal, PC End;
Following steps are executed in the end PC:
To caused in the first BIM model model face number be more than given threshold vertex remove;
To caused in the first BIM model moulded dimension be more than given threshold vertex remove;
Submodel in first BIM model is rebuild;
Race's example in first BIM model simplify and be replaced by MaxScript script;
The submodel of same material in first BIM model is merged.
6. the management system of the engineering project element according to claim 5 based on BIM, which is characterized in that in mobile terminal It is interior, user's operation is responded using the 2nd BIM model, and pass through the incidence relation between component ID and engineering project element information, The component model or engineering project element information transferred from server are returned to user.
7. the management system of the engineering project element according to claim 5 based on BIM, which is characterized in that the engineering Project elements information includes any one of quality, safety, environment, progress or multinomial information.
8. the management system of the engineering project element according to claim 5 based on BIM, which is characterized in that in server Attribute data A only holding member ID and model name as the matched keyword of unique information.
CN201510080209.8A 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM Active CN104766155B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510080209.8A CN104766155B (en) 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510080209.8A CN104766155B (en) 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM

Publications (2)

Publication Number Publication Date
CN104766155A CN104766155A (en) 2015-07-08
CN104766155B true CN104766155B (en) 2018-12-04

Family

ID=53647969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510080209.8A Active CN104766155B (en) 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM

Country Status (1)

Country Link
CN (1) CN104766155B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105335558A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering circle establishment method and system on basis of BIM (building information modeling)
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106204745B (en) * 2016-08-31 2023-01-03 中国电建集团昆明勘测设计研究院有限公司 Monitoring BIM model rapid loading interaction method and system based on standard atlas management
CN107146065A (en) * 2017-03-20 2017-09-08 中国铁道科学研究院电子计算技术研究所 Railway engineering management platform system
CN107423886A (en) * 2017-06-29 2017-12-01 中国建筑局(集团)有限公司 Engineering data synchronous management system and method based on tracking table
CN108376376B (en) * 2018-02-02 2021-11-09 北京筑业志远软件开发有限公司 BIM model-based construction engineering quality management standardization method
CN108256831B (en) * 2018-02-02 2021-07-30 北京筑业志远软件开发有限公司 Method for managing engineering data based on visual BIM model
CN109214068B (en) * 2018-08-17 2023-03-10 徐州中煤百甲重钢科技股份有限公司 BIM-based bottom assembled building information extraction method
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
CN112215939A (en) * 2019-06-24 2021-01-12 华建数创(上海)科技有限公司 Collaborative management method and system for building data
CN111680970A (en) * 2020-05-25 2020-09-18 中亿丰建设集团股份有限公司 Foundation pit monitoring intelligent management system based on BIM
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102884532A (en) * 2010-03-09 2013-01-16 欧特克公司 Systems and methods for construction field management and operations with building information modeling
CN103246951A (en) * 2012-12-11 2013-08-14 中建三局第一建设工程有限责任公司 Intelligent electromechanical equipment management system and method based on BIM (building information modeling)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5325286B2 (en) * 2008-05-13 2013-10-23 サイアンディア インコーポレイテッド Apparatus and method for interacting with multiple forms of information between multiple types of computing devices

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102884532A (en) * 2010-03-09 2013-01-16 欧特克公司 Systems and methods for construction field management and operations with building information modeling
CN103246951A (en) * 2012-12-11 2013-08-14 中建三局第一建设工程有限责任公司 Intelligent electromechanical equipment management system and method based on BIM (building information modeling)

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
BIM在工程施工中的应用;张建平,等;《施工技术》;20120831;第41卷(第371期);第10-17页 *
基于BIM的工程项目管理系统及其应用;张建平,等;《土木建筑工程信息技术》;20121231;第4卷(第4期);第1-6页 *

Also Published As

Publication number Publication date
CN104766155A (en) 2015-07-08

Similar Documents

Publication Publication Date Title
CN104766155B (en) The management method and system of engineering project element based on BIM
CN104680320A (en) BIM-based project management system and method
CN104504497B (en) BIM engineering information management system and method
CN111160869A (en) Intelligent early warning care system based on community meshing
CN117391640B (en) Engineering construction project construction period management method and system based on BIM and GIS
CN109214784A (en) A kind of method, client, server and the system of fire-fighting inspection management
CN112070861A (en) Multi-user real-time synchronous collaborative map editing method and system considering geographic features
CN108629552A (en) BIM cooperative design platforms based on cloud
Guerrero et al. Selecting computing devices to support mobile collaboration
CN109615700B (en) Three-dimensional virtual reality tunnel monitoring system and operation method thereof
CN114037097A (en) BIM model-based equipment operation and maintenance management method
JP2023001002A (en) Data for 3d object management, computer program, and method for distributedly managing 3d object
CN110599116A (en) Power grid decentralized collaborative design method and system based on cloud data center
Lu et al. Open3D: crowd-sourced distributed curation of city models
CN109063223B (en) BIM model light weight method and device and BIM model processing method and system
Liu et al. An IoT‐Based Intelligent Geological Disaster Application Using Open‐Source Software Framework
CN109559085A (en) The measures and procedures for the examination and approval and terminal device based on BIM light weighed model
CN117407951A (en) BIM model processing method, server and storage medium
CN104468788A (en) Multi-net and multi-terminal data synchronization method
Kevany GIS in the World Trade Center response: 10 years after
Dulishkovych et al. Business Process Management of Virtual Enterprise based on Augmented Reality.
Jia et al. [Retracted] Construction of Heritage Digital Resource Platform Based on Digital Twin Technology
CN112507053A (en) Method for establishing visualization system and application method
CN110780737A (en) ERP enterprise information management and panoramic VR combined system
CN110782218A (en) Rail transit design contact method, system, device and storage medium

Legal Events

Date Code Title Description