CN104746860A - 一种倒锥壳水塔斜拉模架的水箱空中现浇方法 - Google Patents

一种倒锥壳水塔斜拉模架的水箱空中现浇方法 Download PDF

Info

Publication number
CN104746860A
CN104746860A CN201310730263.3A CN201310730263A CN104746860A CN 104746860 A CN104746860 A CN 104746860A CN 201310730263 A CN201310730263 A CN 201310730263A CN 104746860 A CN104746860 A CN 104746860A
Authority
CN
China
Prior art keywords
water tank
support
internal
water tower
external double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310730263.3A
Other languages
English (en)
Inventor
张卫财
曲成平
王卫国
郁有升
魏兴友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Installation & Construction Co Ltd
Qingdao University of Technology
Original Assignee
Qingdao Installation & Construction Co Ltd
Qingdao University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Installation & Construction Co Ltd, Qingdao University of Technology filed Critical Qingdao Installation & Construction Co Ltd
Priority to CN201310730263.3A priority Critical patent/CN104746860A/zh
Publication of CN104746860A publication Critical patent/CN104746860A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种倒锥壳水塔斜拉模架的水箱空中现浇方法,首先安装内外双环形钢管支座,并在两节内外双环形钢管支座中间的连接部位焊接立柱端支撑钢梁,然后将中心立柱底端焊接在立柱端支撑钢梁上,并在水塔混凝土支筒顶端与中心立柱之间焊接立柱侧支撑;安装液压提升设备体系后液压提升斜桁架;然后将支撑牛腿焊接在内外双环形钢管支座上,然后将斜桁架落在支撑牛腿上,并进行焊接固定;最后安装钢丝绳钢绞线。本发明的安装方法操作简单,采用液压整体提升斜桁架,安装效率高,安全性好。

Description

一种倒锥壳水塔斜拉模架的水箱空中现浇方法
技术领域
本发明属于土木工程领域,具体涉及一种倒锥壳水塔斜拉模架的水箱空中现浇方法。 
背景技术
目前很多国家水塔均采用预制水箱,而预制水箱因为渗水、漏水现象比较普遍,国外业主方和监理方提出水塔水箱必须采用现浇混凝土施工,水塔其高度大,如果采用落地式满堂扣件钢管支撑架方案,要达到支撑架的强度和刚度要求,靠近水箱根部的立杆间距太密,其方案的施工难度太大,且造价高,工期长。 
发明内容
本发明的目的是针对上述现有技术中的不足,提供一种倒锥壳水塔斜拉模架的水箱空中现浇方法。 
本发明的技术方案是:一种倒锥壳水塔斜拉模架的水箱空中现浇方法,包括以下步骤: 
(1) 在水塔混凝土支筒上安装第一节内外双环形钢管支座,混凝土浇筑后,在第一节内外双环形钢管支座上方安装立柱端支撑钢梁,然后在立柱端支撑钢梁上方安装第二节内外双环形钢管支座,然后进行混凝土浇筑;
(2)将中心立柱底端焊接在立柱端支撑钢梁上,然后在水塔混凝土支筒顶端与中心立柱之间焊接立柱侧支撑;
(3)安装液压提升设备体系;
(4)液压提升斜桁架;
(5)将支撑牛腿焊接在内外双环形钢管支座上,然后将斜桁架落在支撑牛腿上,并进行焊接固定;
(6)安装水平钢丝绳;
(7)安装钢绞线;
(8)绑水箱下底壳钢筋,支下底壳内模,浇筑水箱下底壳混凝土。
步骤(1)中所述内外双环形钢管支座包括内钢筒、外钢筒,所述内钢筒和外钢筒之间焊接肋板,所述肋板上设有三列通孔,所述支座上设有一个开孔口,所述开孔口穿通内钢筒和外钢筒,所述开孔口上下各设有一个加强板,所述加强板分别与内钢筒、外钢筒和肋板焊接,所述加强板上设有3个通筋孔。 
本发明的有益效果是:操作简单,采用液压整体提升斜桁架,安装效率高,安全性高,并且可以将水箱下底壳模板和部分钢筋与模架同时液压提升,模架拆除模板后还可以做水箱装饰脚手架使用,具有较好的技术经济效果和较高的推广应用价值。 
附图说明
图1为本发明的工艺流程图; 
图2为本发明安装完成后的主剖视图;
图3为图2中A的放大图。
图4为实施例1中内外双环形钢管支座的俯视图; 
图5为实施例1中内外双环形钢管支座主剖视图;
图6为实施例1中肋板的主视图;
图7为图4中A-A向的主视图;
图8为实施例1中加强板的俯视图。
具体实施方式
以下结合附图对本发明作进一步披露。 
实施例1 
一种倒锥壳水塔斜拉模架的水箱空中现浇方法,包括以下步骤:
(1) 在内外双环形钢管支座1的上下两侧穿环向钢筋15,然后起吊内外双环形钢管支座1,提升至略高于水塔混凝土支筒5的预留竖向钢筋顶部后,找正钢筋和内外双环形钢管支座1的洞口关系,边下落边穿竖向钢筋,然后进行混凝土浇筑;浇筑完成后,安装立柱端支撑钢梁9,利用内外双环形钢管支座1顶面的水平来控制立柱端支撑钢梁9的水平;然后以上述同样的方法在立柱端支撑钢梁9上方安装第二节内外双环形钢管支座1,并进行混凝土浇筑;
所述内外双环形钢管支座1包括内钢筒11、外钢筒12,所述内钢筒11和外钢筒12之间焊接肋板13,所述肋板13上设有三列通孔14,所述支座上设有一个开孔口16,所述开孔口16穿通内钢筒11和外钢筒12,所述开孔口16上下各设有一个加强板17,所述加强板17分别与内钢筒11、外钢筒12和肋板13焊接,所述加强板17上设有3个通筋孔18;在靠近内钢筒11和外钢筒12的两列通孔14穿上述环向钢筋15,相邻两个肋板13之间穿上述竖向钢筋,所述开孔口16用于水塔混凝土支筒5的窗洞预留口;
(2)将中心立柱2底端焊接在立柱端支撑钢梁9上,然后在水塔混凝土支筒5顶端与中心立柱2之间焊接立柱侧支撑10;
(3)安装液压提升设备体系;
(4)液压提升斜桁架4,以及砼水箱的下底壳模板和部分钢筋,首先启动油泵,使千斤顶同步顶升10~12mm,将下锚具卡紧后,油泵回油,使提升设备带载进行12小时观察,无异常情况后进入正常提升;正常提升时,开动油泵使千斤顶顶升一个行程,即18cm,此时,上锚具锁紧,下锚具已自动脱锚;检查下锚具然后千斤顶回油下降,使下锚具自锚,松开上锚具,千斤顶继续下降至复位,将上锚具锁紧进入下一循环;如此循环直至将斜桁架4提升到位;在提升至斜桁架4底部离地面2米左右时,安装吊脚手架41,做为吊装中观察施工时使用;在斜桁架提升至略高于设计工作面时停止;
(5)将支撑牛腿3焊接在内外双环形钢管支座1上,然后将斜桁架4落在支撑牛腿3上,并进行焊接固定;
(6)安装水平钢丝绳7,其两端分别固定在斜桁架4和中心立柱2上,然后连接相应的花篮螺栓6进行紧固,以控制钢丝绳7的长度从而控制钢丝绳7的拉力;
(7)安装钢绞线8;其一端连接斜桁架4,另一端连接中心立柱2,安装完成后在中心立柱2顶部集中对称张拉;
(8)绑水箱下底壳钢筋,支下底壳内模,浇筑水箱下底壳混凝土。
上述说明并非是对本发明的限制,本发明也并不限于上述举例,在相关领域的普通技术人员,在本发明的实质范围内,作出的变化、改型、添加或替换,都应属于本发明的保护范围。 

Claims (2)

1.一种倒锥壳水塔斜拉模架的水箱空中现浇方法,其特征在于:包括以下步骤:
(1)在水塔混凝土支筒上安装第一节内外双环形钢管支座,混凝土浇筑后,在第一节内外双环形钢管支座上方安装立柱端支撑钢梁,然后在立柱端支撑钢梁上方安装第二节内外双环形钢管支座,然后进行混凝土浇筑;
(2)将中心立柱底端焊接在立柱端支撑钢梁上,然后在水塔混凝土支筒顶端与中心立柱之间焊接立柱侧支撑;
(3)安装液压提升设备体系;
(4)液压提升斜桁架;
(5)将支撑牛腿焊接在内外双环形钢管支座上,然后将斜桁架落在支撑牛腿上,并进行焊接固定;
(6)安装水平钢丝绳;
(7)安装钢绞线;
(8)绑水箱下底壳钢筋,支下底壳内模,浇筑水箱下底壳混凝土。
2.根据权利要求1所述的一种倒锥壳水塔斜拉模架的水箱空中现浇方法,其特征在于:步骤(1)中所述内外双环形钢管支座包括内钢筒、外钢筒,所述内钢筒和外钢筒之间焊接肋板,所述肋板上设有三列通孔,所述支座上设有一个开孔口,所述开孔口穿通内钢筒和外钢筒,所述开孔口上下各设有一个加强板,所述加强板分别与内钢筒、外钢筒和肋板焊接,所述加强板上设有3个通筋孔。
CN201310730263.3A 2013-12-26 2013-12-26 一种倒锥壳水塔斜拉模架的水箱空中现浇方法 Pending CN104746860A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310730263.3A CN104746860A (zh) 2013-12-26 2013-12-26 一种倒锥壳水塔斜拉模架的水箱空中现浇方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310730263.3A CN104746860A (zh) 2013-12-26 2013-12-26 一种倒锥壳水塔斜拉模架的水箱空中现浇方法

Publications (1)

Publication Number Publication Date
CN104746860A true CN104746860A (zh) 2015-07-01

Family

ID=53587056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310730263.3A Pending CN104746860A (zh) 2013-12-26 2013-12-26 一种倒锥壳水塔斜拉模架的水箱空中现浇方法

Country Status (1)

Country Link
CN (1) CN104746860A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119654A (zh) * 2017-06-14 2017-09-01 中国葛洲坝集团机电建设有限公司 突扩体顶降和滑移牛腿支撑结构及顶降滑移方法
CN107313591A (zh) * 2017-09-05 2017-11-03 吕洁 千吨级水塔施工方法
CN114892966A (zh) * 2022-06-27 2022-08-12 中交二公局第七工程有限公司 一种倒锥壳水塔水箱整体浇注砼支撑组件及支撑方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3858866A (en) * 1973-03-06 1975-01-07 Ernie R Armstrong Adjustable template for supporting and aligning tower footings
CN201321746Y (zh) * 2008-12-19 2009-10-07 鞍钢集团设计研究院 一种高位大容积钢结构水塔
CN103195287A (zh) * 2013-04-09 2013-07-10 中国十九冶集团有限公司 钢筋砼水塔倒锥形水箱液压提升防坠落装置及方法
CN203308165U (zh) * 2013-05-20 2013-11-27 中国十五冶金建设集团有限公司 用于倒锥形水塔塔顶水箱施工的网架式模板支撑操作平台

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3858866A (en) * 1973-03-06 1975-01-07 Ernie R Armstrong Adjustable template for supporting and aligning tower footings
CN201321746Y (zh) * 2008-12-19 2009-10-07 鞍钢集团设计研究院 一种高位大容积钢结构水塔
CN103195287A (zh) * 2013-04-09 2013-07-10 中国十九冶集团有限公司 钢筋砼水塔倒锥形水箱液压提升防坠落装置及方法
CN203308165U (zh) * 2013-05-20 2013-11-27 中国十五冶金建设集团有限公司 用于倒锥形水塔塔顶水箱施工的网架式模板支撑操作平台

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
曲成平等: "安哥拉某倒锥壳水塔高空现浇水箱施工技术", 《施工技术》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119654A (zh) * 2017-06-14 2017-09-01 中国葛洲坝集团机电建设有限公司 突扩体顶降和滑移牛腿支撑结构及顶降滑移方法
CN107119654B (zh) * 2017-06-14 2022-12-02 中国葛洲坝集团股份有限公司 突扩体顶降和滑移牛腿支撑结构及顶降滑移方法
CN107313591A (zh) * 2017-09-05 2017-11-03 吕洁 千吨级水塔施工方法
CN107313591B (zh) * 2017-09-05 2019-08-13 温州焕宏纺织品有限公司 千吨级水塔施工方法
CN114892966A (zh) * 2022-06-27 2022-08-12 中交二公局第七工程有限公司 一种倒锥壳水塔水箱整体浇注砼支撑组件及支撑方法

Similar Documents

Publication Publication Date Title
CN102661054B (zh) 平面钢桁架整体提升中的侧向加固结构及整体提升方法
CN105971271B (zh) 单侧自爬升悬臂模板及其施工方法
CN105201195B (zh) 一种可提升支腿式电梯井施工平台及施工方法
CN106437130A (zh) 一种用于超高层建筑施工的内顶外爬式模架施工平台
CN102535845A (zh) 一种连廊结构承重架的施工方法
CN108033367B (zh) 一种钢柱筒架交替支撑式钢平台与塔吊同步提升装置及其提升方法
CN103422668A (zh) 超厚大斜率剪力墙施工方法及所用液压自顶升倾斜爬模
CN106812328B (zh) 带吊挂层的张弦预应力钢结构网架整体二步提升施工方法
CN108979131B (zh) 一种高层建筑施工钢模板及操作架整体提升平台装置
CN102444271B (zh) 现浇混凝土结构悬吊脚手架
CN102733608B (zh) 一种造粒塔喷头层施工方法
CN106150057B (zh) 一种分片式液压提升爬架
CN104746860A (zh) 一种倒锥壳水塔斜拉模架的水箱空中现浇方法
CN109881585B (zh) 一种用于高墩施工的装配式作业平台
CN208280592U (zh) 自动爬升式井道筒模板装置
CN203452375U (zh) 一种液压自顶升倾斜爬模
CN110158675A (zh) 改建工程中地下室外墙抗侧支撑加固系统及其施工方法
CN105347142A (zh) 一种施工升降机安装在地下室顶板上的穿板安装方法
CN203034799U (zh) 塔吊标准节支承高空支模钢平台结构
CN102691267A (zh) 一种外置整体操作平台高墩施工方法
CN104989092B (zh) 一种高空悬挑叠合式钢桁架承重平台的施工方法
CN111705677A (zh) 一种用于高墩柱翻模施工的滑升架
CN108277817B (zh) 高桩承台塔吊基础加固结构的施工方法
CN106522542B (zh) 一种单机位液压爬模系统及其爬升方法
CN201943350U (zh) 高空大跨度悬挑结构模架的支撑钢架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150701