CN104594370B - High-pressure combined flushing grouting method and structure in karst region - Google Patents

High-pressure combined flushing grouting method and structure in karst region Download PDF

Info

Publication number
CN104594370B
CN104594370B CN201410695167.4A CN201410695167A CN104594370B CN 104594370 B CN104594370 B CN 104594370B CN 201410695167 A CN201410695167 A CN 201410695167A CN 104594370 B CN104594370 B CN 104594370B
Authority
CN
China
Prior art keywords
grouting
karst
flushing
pressure
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410695167.4A
Other languages
Chinese (zh)
Other versions
CN104594370A (en
Inventor
屈昌华
郭维祥
余波
朱代强
昝廷东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201410695167.4A priority Critical patent/CN104594370B/en
Publication of CN104594370A publication Critical patent/CN104594370A/en
Application granted granted Critical
Publication of CN104594370B publication Critical patent/CN104594370B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a karst area high-pressure combined flushing grouting method and a structure thereof, wherein when filling type karst caves or corrosion cracks are met in the grouting process, cement mortar or cement paste with the ratio of 0.5:1 is backfilled after fillers are flushed out by high-pressure water or high-pressure wind and water, and the conventional cement grouting method is adopted for grouting after the cement mortar is solidified for 24-72 hours. The high-pressure combined flushing grouting method is an economical and efficient grouting treatment technology aiming at geological defect sites such as karst caves, corrosion cracks and the like, and has the advantages of simple method (no need of adding special construction equipment and operators), remarkable flushing effect, capability of greatly improving construction efficiency, grouting quality guarantee and the like. When the grouting flushing and grouting method is adopted to perform grouting flushing and grouting in geological defect sections such as karst caves, corrosion cracks and the like in karst regions, the design requirements can be effectively and quickly met, the construction efficiency can be greatly improved, and the waste of grouting raw materials can be reduced.

Description

Karst high pressure joint rinses grouting method and its structure
Technical field
The present invention relates to karst geological disposal method, and in particular to a kind of karst high pressure combines douche can Paste-making method and its structure.
Background technology
Karst topography refer to the water with corrosion power solublerock is carried out the formed earth's surface of the effect such as corrosion and The general name of underground form.Water includes the mechanical erosion processes such as erosion, the shallow erosion of flowing water, and collapse based on corrosion.
In the Hydraulic and Hydro-Power Engineering impervious grouting processing procedure of karst, filling-type Karst cave or corrosion are frequently encountered Crack, or strong corrosion area, charges are generally clay, dauk, are not often reached with grouting method using conventional flushing and set Meter is required, and influences anti-seepage effect.
By current specifications(DL/T5148-2012)It is required that, grout hole(Section)Crack is carried out before grouting to rinse and simple Press water(Maximum pressure is not more than 1MPa), whether entered according to design requirement for regulation in the Special zone specification such as solution cavity, tomography Row is special to be rinsed.At present, general requirement of the designing unit to Special zones such as solution cavity, tomographies is carried out often in Hydraulic and Hydro-Power Engineering Rule are rinsed, and this normal developing method well can neither go out charges in solution cavity, construction speed and quality are influenceed again, also Have to be handled using the method such as " encrypting grout hole between former grout hole ", make quantities and investment increasing degree it is larger, Construction period significantly extends.
Karst Hydraulic and Hydro-Power Engineering impervious grouting《Construction technical requirement》In simple packer permeability test is rinsed to crack Typically there are clear stipulaties, mostly normal developing, it is rare special when running into the Special zones such as solution cavity, corrosion fissure, shear-zone The purpose for not reaching flushing not only is rinsed before rinsing requirement, this conventional grout, can be deteriorated on the contrary by the performance of filling rock mass, influence Grouting quality.
Therefore, for the project seepage controlling grouting treatment of casta region, in the prior art still without preferable skill Art scheme.
The content of the invention
It is an object of the invention to solve in the prior art to the project seepage controlling grouting treatment of casta region Problem rinses grouting method there is provided a kind of karst high pressure joint.
The technical scheme is that such:
It is that a kind of karst high pressure joint rinses grouting method first, and this method runs into filling in filling process When type solution cavity or corrosion fissure, cement mortar or 0.5 is backfilled after charges are gone out by water under high pressure or high-pressure blast, water:1 water Mud, after taking traditional cements grouting method to be irrigated again after solidifying 24h~72h.This method comprises the following steps:
1)Find out that solution cavity develops scale, the property of charges, roof and floor hole depth or elevation by drilling or geophysical prospecting method;This Item work is general to utilize the pilot hole that is in the milk(It is not further added by drilled grout hole)Carry out.
2)According to the solution cavity developmental state found out, the grout hole in the Geological Defects location such as reasonable Arrangement solution cavity, corrosion fissure As flushing hole, these grout holes are filled after the hole depth being drilled into residing for corresponding solution cavity or corrosion fissure using two conventional high-pressures Stock pump(Parallel connection, Stress control maximum pressure in 3~6MPa, hole depth 40m~100m is no more than 25MPa)Or press pneumatics in joint Machine(The MPa of Stress control 3~4)High pressure water washing or wind and water combined flushing are carried out, charges in solution cavity are gone out from drilling, directly To aperture backwater it is peace and quiet when stop.
3)Quickly stuffing 0.5 is answered after the completion of flushing:1 cement mortar or cement mortar, and 24h~72h to be coagulated.
4)Reach after cleaning bottom of hole after the solidifying time and carry out conventional strengthening grouting, until reaching design requirement.
In order to realize such method, present invention employs a kind of such grouting structure suitable for karst: It is the Geological Defects section for handling karst, and Geological Defects section is located at the lower section of basement rock, and the structure is provided with least Three drillings, drilling is vertically goed deep into basement rock, and the bottom of drilling is into Geological Defects section;At least two be geomantic omen in three drillings Import, one is flushing outlet.It is preferred that, two geomantic omen imports are located at the both sides of flushing outlet respectively.
It is a kind of warp for Geological Defects locations such as solution cavity, corrosion fissures that the high pressure joint of the present invention, which rinses grouting method, Ji, efficient grouting treatment technology are simple with method(Special construction equipment and operating personnel need not be increased), developing result Significantly, the advantages of construction efficiency can be increased substantially, ensure grouting quality.The present invention is with a kind of brand-new thinking, with simply, just Prompt, efficient mode solves the problems, such as that the Geological Defects such as the solution cavity of karst, corrosion fissure location is rinsed and grouting.Using The present invention, can effectively, soon when the progress grouting of the Geological Defects locations such as solution cavity, the corrosion fissure of karst is rinsed with grouting Fast reaches design requirement, and can increase substantially construction efficiency and reduce grouting waste of raw materials.
Brief description of the drawings
Fig. 1 rinses grouting structural representation for the joint of the present invention.
Description of reference numerals:1- basement rock, 2- drillings, 3- Geological Defects section, the import of 4- geomantic omens, 5- flushing outlets.
Embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
Referring initially to Fig. 1, the joint that Fig. 1 illustrates the present invention rinses the laying structure being in the milk, from the figure, it can be seen that this hair It is bright it is to be processed be Geological Defects section 3, the Geological Defects section 3 be located at basement rock 1 in, in the lower section of built in advance engineering.For each Processing unit engineering, the present invention needs to be drilled with the drilling 2 of more than three, and two of which drilling 2 is as geomantic omen import 4, for rushing Hole flushing hole is the import of wind and water, and another drilling 2 is as flushing outlet 5, the passage of emerging for washings.Geomantic omen in figure Import 4 is located at the right and left, and flushing outlet 5 is located at centre.
Embodiment 1:The present invention is applied to the situation of large-scale filling-type Karst cave:The solution-cavity filling thing is mainly clay, clay Burning into sand etc., hole depth is 45m~67m.Grouting pressure is extremely difficult to design requirement 3.5MPa in filling process, and porous repeatedly multiple filling is still Not up to design requirement.After present invention construction, design requirement is reached on inspection.
Embodiment 2:The present invention is in the situation in strong corrosion area applied to engineering curtain grouting area:Such case solution cavity Charges are based on sand and yellow mud, because trial zone scope is smaller, and single hole processing is carried out when running into solution cavity, using dividing from top to bottom Floor height presses douche, that is, creeps into solution cavity, and then segment length carries out high pressure washing using energy pore-forming as principle(Stress control 4~ 7MPa), flushing is returned to aperture is in the milk again after clear water(Based on grout injection, injection rate is big and is filled with a certain amount of slurries Can mix the additives such as waterglass in proportion afterwards, Reperfu- sion cement mortar, at the end of cement injection-waterglass slurries), reach limit Wait to coagulate after amount standard(Time to be coagulated is generally 24h~72h), shorten segment length during cleaning bottom of hole, it is impossible to punch hole depth of last time when coagulating, Then it is in the milk, so handles repeatedly again, until this section, which reaches, carries out next section of processing after design requirement.After construction terminates, through inspection Look into, above karst cave treatment position construction quality reaches design requirement.
Certainly, it is the concrete application example of the present invention above, the present invention also has other embodiments, all using equivalent Replacement or the technical scheme of equivalent transformation formation, all fall within protection domain of the presently claimed invention.

Claims (2)

1. a kind of karst high pressure joint rinses grouting method, it is characterised in that:This method runs into filling process and filled When filling out type solution cavity or corrosion fissure, cement mortar or 0.5 is backfilled after charges are gone out by water under high pressure or high-pressure blast, water:1 Cement mortar, after taking traditional cements grouting method to be irrigated again after solidifying 24h~72h;
Comprise the following steps that:
1)Find out that solution cavity develops scale, the property of charges, roof and floor hole depth or elevation by drilling or geophysical prospecting method;
2)The grout hole in Geological Defects location is arranged as flushing hole, these grout holes are being drilled into corresponding solution cavity or corrosion fissure institute After the hole depth at place, high pressure water washing or wind and water combined punching are carried out using pressure air compressor machine in two conventional high-pressure grouting pumps or joint Wash, charges in solution cavity are gone out from drilling, stop when aperture backwater is peace and quiet;
(3)Quickly stuffing 0.5 is answered after the completion of flushing:1 cement mortar or cement mortar, and 24h~72h to be coagulated;
(4)Reach after cleaning bottom of hole after the solidifying time and carry out conventional strengthening grouting, until reaching design requirement;
The step 2)Described in two conventional high-pressure grouting pumps according to being arranged in parallel, Stress control is in 3~6MPa, hole depth 40m Maximum pressure is no more than 25MPa during~100m;The MPa of Stress control 3~4 of air compressor machine is pressed in the joint;
The grouting structure that karst high pressure joint rinses grouting method application is:Ground for handling karst Matter defective section(3), Geological Defects section(3)Positioned at basement rock(1)Lower section, the structure provided with least three drilling(2), drilling (2)Vertically go deep into basement rock(1)In, drilling(2)Bottom to Geological Defects section(3)In;Three drillings(2)In at least two be wind Water inlet(4), one is flushing outlet(5).
2. high pressure joint in karst according to claim 1 rinses grouting method, it is characterised in that:Two geomantic omens are entered Mouthful(4)It is located at flushing outlet respectively(5)Both sides.
CN201410695167.4A 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region Active CN104594370B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410695167.4A CN104594370B (en) 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410695167.4A CN104594370B (en) 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region

Publications (2)

Publication Number Publication Date
CN104594370A CN104594370A (en) 2015-05-06
CN104594370B true CN104594370B (en) 2017-10-10

Family

ID=53120397

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410695167.4A Active CN104594370B (en) 2014-11-27 2014-11-27 High-pressure combined flushing grouting method and structure in karst region

Country Status (1)

Country Link
CN (1) CN104594370B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862725A (en) * 2016-03-31 2016-08-17 大连久鼎祥瑞特种工程技术研究院有限公司 Underground construction preliminary grouting waterproof and anti-seepage supporting technology
CN105887886B (en) * 2016-06-16 2018-02-27 中国水利水电第十一工程局有限公司 A kind of strong karsts developing area stratum Curtain Grouting Construction method
CN106088094B (en) * 2016-07-31 2018-09-28 中水东北勘测设计研究有限责任公司 High mountain strid Method of Arch Dam Foundation is segmented stage grouting method
CN106498965A (en) * 2016-12-05 2017-03-15 广西大学 A kind of karst area water sealing consolidation construction method
CN113152412A (en) * 2021-04-30 2021-07-23 中国葛洲坝集团第一工程有限公司 Foundation pit slope karst seepage-proofing reinforcing treatment method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509264B (en) * 2009-03-25 2011-12-07 李旺雷 One-step pore-creating, segmenting high pressure cement grout construction method
CN102493403A (en) * 2011-12-07 2012-06-13 长江勘测规划设计研究有限责任公司 Rock-fill dam deformation control technology
CN204266221U (en) * 2014-11-27 2015-04-15 中国电建集团贵阳勘测设计研究院有限公司 grouting structure suitable for karst region

Also Published As

Publication number Publication date
CN104594370A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN104594370B (en) High-pressure combined flushing grouting method and structure in karst region
CN103510957B (en) A kind of combined type coal uncovering method
CN107620312A (en) High hydraulic pressure precipitation well construction and hydrostatic slip casting method for blocking in a kind of Metro station excavation
CN104278667A (en) Underground karst cave filling treatment method
CN104481063B (en) Grouting waterproof sealing strip and water proof structure of pre-cast wall panel vertical seam and construction method of water proof structure
CN105804410A (en) Sub-cabin pressure grouting method for vertical connection of prefabricated concrete structure
CN105887886A (en) Strong karst development stratum curtain grouting construction method
CN109538295A (en) Seal groundwater in mining area library system
CN102011591A (en) Grouting process for working surface of deep well
CN108756945A (en) The device and construction method administered for multilayer goaf grouting
CN108708768A (en) Slip casting tube head, grouting device and its construction method
CN102720176B (en) Foundation strengthening treatment method
CN204266221U (en) grouting structure suitable for karst region
CN104032713B (en) A kind of pressure diversion tunnel composite lining concrete anti-seepage structure and construction technology thereof
CN105604163A (en) Sewage pipeline internal plugging and external grouting construction method
CN103615014B (en) A kind of dewatering device of soft soil foundation pit and using method thereof
CN104594369B (en) Karst region high-pressure group hole replacement grouting method and structure thereof
CN203891785U (en) Special joint pipe assembly for throwing of gravels in pipe of hydrogeological water well
CN101205766B (en) Waterproof treatment method for joint of new station and old station
CN106939619A (en) A kind of anti-vibration for underground engineering disturbs the leak stopping reinforcement means of voids and pits
CN104529339A (en) Polypropylene crosslinking copolymer fiber concrete leaking stoppage paste
CN115142852A (en) Treatment method for deep pore water-containing stratum of vertical shaft working face
CN205171501U (en) I -steel connects formula underground continuous wall and streams processing apparatus
CN105220683B (en) A kind of I-shaped steel joint formula diaphram wall is around current processing device and method
CN103541679A (en) Method for sealing underground hydraulic fracture drilled hole of coal mine in combined manner

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant