CN105887886B - A kind of strong karsts developing area stratum Curtain Grouting Construction method - Google Patents

A kind of strong karsts developing area stratum Curtain Grouting Construction method Download PDF

Info

Publication number
CN105887886B
CN105887886B CN201610434986.2A CN201610434986A CN105887886B CN 105887886 B CN105887886 B CN 105887886B CN 201610434986 A CN201610434986 A CN 201610434986A CN 105887886 B CN105887886 B CN 105887886B
Authority
CN
China
Prior art keywords
grouting
pressure
cement
filling
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610434986.2A
Other languages
Chinese (zh)
Other versions
CN105887886A (en
Inventor
潘龙龙
宋东旭
吕理军
严开义
李博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina 11th Bureau Engineering Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201610434986.2A priority Critical patent/CN105887886B/en
Publication of CN105887886A publication Critical patent/CN105887886A/en
Application granted granted Critical
Publication of CN105887886B publication Critical patent/CN105887886B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Soil Conditioners And Soil-Stabilizing Materials (AREA)

Abstract

The invention belongs to WR and hydropower construction engineering field, more particularly to a kind of strong karsts developing area stratum Curtain Grouting Construction method.Construction method of the present invention, high pressure washing replacement technique innovative technology is used in construction, the hole creating technology problem of Infra-karst development stratum grout curtain is solved, engineering is smoothly implemented;According to different geological conditions, the viscosity of slurries, shearing force and flow parameter are adjusted by filling various admixtures and chemical treatments in cement grout, it is subject to certain perfusion measure and means, so as to control the injection rate of slurries and diffusance, optimal grouting effect is not only can reach, can also reduce the unnecessary loss of slurries.

Description

A kind of strong karsts developing area stratum Curtain Grouting Construction method
Technical field
The invention belongs to WR and hydropower construction engineering field, more particularly to a kind of strong karsts developing area stratum Curtain Grouting Construction Method.
Background technology
China builds dam since the seventies in karst area, and it is big to build Facing Hydraulic Project two in karst area Problem, when applicable, efficient, the accurate investigation way of selection, to find out karst engineering geological condition;Second, selected according to condition Economical rationality, the ground of technical feasibility and based process method.By the solubility of particularity-carbonate of Karst Geological Landscape is made Into solution cavity, it is molten collapse body and complexity Buried Pipeline Network Systems, survey difficulty, funds and the cycle of work with not only increasing, more increase The big difficulty and complexity of basement process, have using displacement, grouting to karst strata processing, play bored concrete pile, rotary churning pile, steel pipe The methods of stake.
Strong karsts developing area stratum refers to there is major fault, the rock stratum of cavern development under normal circumstances, in strong corrosion section Occur rock stratum of the no pressure without the large seepage phenomenon such as overfall in grouting construction.Curtain Grouting Construction is mainly deposited on the stratum In following construction technology difficult point:(1) because grouting works amount is big, the grouting material of consumption is more, and construction is complicated, and construction lasts Long, therefore, the cost of curtain is high.(2) injection rate is big during the Curtain Grouting Construction on strong karsts developing area stratum, and hole section fills number again More, grouting lasts length, is constructed using bore hole-top-enclosed grouting method.The major defect of bore hole-top-enclosed grouting method is in perfusion underflow When time is long, grout pipe is easily clogged in hole by cement.Particularly when irrigating deep hole, grout pipe is very long, and slurries glue in hole Thick, careless slightly, grout pipe may be cast extremely by grout cures, cause hole event.(3) often met during strong karst curtain drilling construction To full-filling type solution cavity, charges are yellow mud sand.When shallow-layer meets full-filling type solution cavity, the punching of big flow water can be used to advance and rushed Wash, abrasive band most in hole is portalled outer, so as to reach the purpose of pore-forming.In deep layer, because the ratio of sand is great, using big When flow water is rinsed, the water flow pressure of pump output can only portal minimal amount of abrasive band outside, and substantial amounts of sand is remained in hole, So collapse can not pore-forming for the sand in trip-out metapore.And when carrying out deep layer full-filling solution cavity section drilling, because water pressure of cooling water is small, When down creeping into, the silt particle in hole can enter in drilling rod rig, block drilling rod, cause cooling water not circulate, burn The phenomenon of brill.(4) geological condition of karst area is changeable, and solution cavity, corrosion fissure are also frequently encountered during grouting construction, Occur when being mainly shown as drilling in work progress occurring when drilling depth quickening, collapse hole, leak, water burst and grouting in brill, drilling Injection rate is big and repeatedly multiple fill still is unable to reach the anomalies such as ending standard.
Application for a patent for invention Publication No. CN 103485345 discloses a kind of coating orifice closing high pressure grout curtain Construction method, it comprises the following steps:(1) non-grout compartment construction;(2) grout compartment pore-creating;(3) grout compartment length division;(4) it is in the milk Pressure determines;(5) grouting method determines.For the present invention using sleeve pipe with proceeding to non-grout compartment, slurry strengthened wall pore-creating can be greatly Penetration rate and one-tenth porosity are improved, the pore-forming difficult problem for solving deep covering layer stratum;In deep covering layer using high Grouting pressure, grouting injection rate substantially increase, dilation angle increase, and grouting effect is good;Orifice closing curtain is used in coating Curtain grouting construction engineering method, grouting quality is guaranteed, and has substantially solved thing in " holding tube " hole often occurred in filling process Therefore improve efficiency of construction.The patent only illustrates the pore-forming of coating high pressure grout curtain, grouting method, without reference to locating The karst treatment that drilling runs into is managed, also the no and specific grouting treatment method for different types of karst.
The content of the invention
In view of the shortcomings of the prior art, the present invention provides a kind of strong karsts developing area stratum Curtain Grouting Construction method, it includes Following steps:
(1) pore-forming
When filling-type Karst cave or corrosion fissure are run into filling process, by combine high pressure water washing replace pore-forming or Drilled using grouting pump injection cooling water, 1.5g/cm is backfilled after going out3Cement mortar;
(2) division grouting segment length
The a length of 5m of grout compartment, during rock crushing hole wall shakiness, grouting segment length foreshortens to 2~3m, concrete structure and basement rock The grout compartment segment length of contact position is 2m;
(3) controlled grouting pressure
Using aperture overfall pressure as standard, Stress control is in 3.0~5.0MPa;
(4) grouting method is determined
" orifice closing, from top to bottom stages cycle " grouting method is taken, it comprises the following steps:
1) grouting uses high-pressure grouting pump, is supported the use with grouting automatic recording instrument;
2) cement mortar converts step by step than level by dilute to dense, and water is 3 with grey mass ratio:1、2:1、1:1、0.8:1 and 0.5:1 Five than level, the water being in the milk and gray scale are 3:1.
Further, described in step (1) joint high pressure water washing displacement hole creating technology the step of be:Adjacent holes is equal The same elevation of solution cavity section is got into, holes carries out high pressure water washing processing simultaneously, gangs up holes, the sand content in water to be returned Terminate when less, without mud;The drilling rod in a hole is taken out, the aperture in another hole is closed, it is simultaneously right with two grouting pumps There is in the hole of drilling rod a progress high pressure water washing, the Stress control of the water under high pressure is in 3.0MPa, the hole of silt particle never drilling rod Inside go out.
Further, step (4) the determination grouting method, filling-type Karst cave or corrosion fissure grouting method are as follows:
(1) it is 3 by water and gray scale:1 cement mortar opens filling, and the value shown on the pressure gauge according to grouting pipe-line control valve is entered Row control, flow is more than 30L/min when slurries convert the ratio level reached big slurry filling or injection drying loss amount exceedes 500kg/m, irrigated using cement and flyash mixed serum, and handled by following measures:
1) the big duty pressure that shows declines 20% on the pressure gauge of grouting pipe-line control valve, irrigates l hours, if pressure or Injection rate is unchanged, then reduces the 20% of current pressure, after irrigating l hours, if pressure or injection rate are unchanged, that is, and 8h to be coagulated; Filled again after solidifying, the pressure or injection rate after multiple filling and treat it is solidifying before it is close, that is, use instead and wait that the cement before coagulating mixes with flyash Slurry filling;Pressure or injection rate after multiple filling change with waiting compared with before coagulating, then using 3:1 water and the cement of gray scale Slurry perfusion, by interval 0.5MPa classification boostings;Implement the pressure after multiple fill and be less than 1MPa, then sand perfusion is mixed using cement mortar, directly Reach to grouting pressure and l.0MPa wait to coagulate afterwards, time 8h to be coagulated;
2) the big duty pressure shown on the pressure gauge of grouting pipe-line control valve declines 20%, irrigates l hours, pressure occurs Rise or injection rate have the situation of reduction, continue to irrigate, until terminating, avoid waiting to coagulate.
Further, step (4) the determination grouting method, no filling or half packed type corrosion fissure grouting method are such as Under:
(1) if grouting when do not return slurry and corrosion fissure it is big, using grout pouring;If not returning slurry and corrosion fissure hour, Sand perfusion is mixed using cement mortar, until overfall and pressure >=1MPa, time to be coagulated are not less than 8h;
(2) if returning slurry and pressure >=1MPa, there is overfall, fully circulated beneficial in hole, open filling use water and gray scale for 3:1 cement mortar, slurries are carried out according to code requirement and are converted into the slurries bigger than level, when injection rate is more than 30L/min or list Position injection drying loss amount is irrigated using cement and flyash mixed serum more than 500kg/m, irrigates 7.5~10t dry ash amounts first Afterwards, the time to be coagulated is not less than 8h;
(3) filled again after solidifying, use water with gray scale for 3:1 cement mortar, the phase before pressure and injection rate occur and waiting to coagulate Closely, that is, use instead treat it is solidifying before cement irrigated with flyash mixed serum, irrigated in the case where there is overfall dry ash amount 7.5~ After l0t, waterglass perfusion is filled by the following method and the time to be coagulated is not less than 8h:
1) grout injection and waterglass mixed serum;
2) separately irrigated using waterglass and cement mortar, first irrigate 200L waterglass, Reperfu- sion is than level 0.5:1 cement mortar 400L;
(4) in filling process, in the case of pressure rise, it is classified and boosts by 0.5MPa.
Further, the grouting method of step (4) the determination grouting method, no filling or half filling-type Karst cave is as follows:
(1) solution cavity is small, falls to bore below 0.5m, mixes sand using cement mortar, using aperture plus sand, mixes sand amount by cement amount 50%th, 70%, l00% perfusions, handled using following methods after overfall to appear:
1) after there is overfall, irrigated using cement and flyash mixed serum, dry ash amount fills water glass up to after 7.5~10t Glass irrigates, and the time to be coagulated is not less than 8 hours;
2) filled again after solidifying, use water with gray scale for 3:1 cement mortar, occur pressure and injection rate with treat it is solidifying before it is close, i.e., Use the grout pouring for treating solidifying preceding water and gray scale instead;When there is overfall, irrigated with 7.5~10t of dry ash amount admixture waterglass, wait to coagulate Not less than 8 hours;
(2) solution cavity is big, falls and bores more than 0.5m, expands aperture, backfills self-compacting concrete or flowing concrete, or use Rubble exchanges backfill with concrete, after backfilling saturation, then is irrigated, and uses cement mortar or cement and flyash mixing slurry.
Further, the cement and flyash mixed serum, water:Concrete and coal ash=0.5:1~0.7:1;Flyash Volume is the 20%~30% of cement weight;Cement mortar mixes sand, mix sand amount generally by the 10% of cement amount, 20%, 30%, 40%th, 50%, 70% or 100%.
Compared with prior art, the beneficial effects of the present invention are:
Construction method of the present invention, using the innovation skill such as " high pressure washing replacement technique ", " sand return technology " in construction Art, solve the hole creating technology problem of Infra-karst development stratum grout curtain, engineering is smoothly implemented;According to different ground Matter condition, the viscosity of slurries, shearing force and modeling are adjusted by filling various admixtures and chemical treatments in cement mortar Variable element, it is subject to certain perfusion measure and means, so as to control the injection rate of slurries and diffusance, can not only reaches optimal Grouting effect, it can also reduce the unnecessary loss of slurries.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
The Specific construction technological process of pass reservoir is as follows
1st, overall construction technology process
Strong karsts developing area stratum grout curtain uses orifice closing, is circulated in hole, packer grouting from top to bottom, per work order The overall construction technology process of grouting in member is constructed according to the sequence of first downstream row → upstream row → intermediate row, with adjacent elder generation in row Sequence hole can construct postorder hole after having constructed.Operational procedure:Clear up the installation of job site → measurement discharge hole position → construction platform and → rig alignment leveling anchors → is checked and accepted (domatic) to lift hole drilling → installation and lift deformation observing device (and test) → guide Construct → III sequence hole construction → inspection hole construction in the sequence hole of hole → I → II sequence hole of constructing.
2nd, single hole construction technology process
Rig centering hole position → leveling fixation rig → first paragraph pore-creating → gaging hole depth, hole deviation → lower disabler → hole flushing → Press water → grouting → lower orifice tube, 72h coagulate → second segment pore-creating → gaging hole depth, hole deviation → hole flushing → pressure water → grouting →... the Water → whole hole section grouting → mechanical sealing of hole → artificial sealing of hole is pressed in five sections of pore-creating → odd number section deviational survey →... complete opening is checked and accepted →.
3rd, Mortar mix proportion
3.1st, the water of cement mortar and gray scale use 3:1、2:1、1:1、0.8:1、0.5:1 five, than level, are opened filling and use 3:1 The grout pouring of water and gray scale;
3.2nd, supplementary cementitious material, additive etc. need to be added being in the milk in slurries, grouting slurries are tests determined, using with It is as follows to close weight ratio:
Water:Concrete and coal ash=0.5:1~0.7:1;
Doping quantity of fly ash is the 20%~30% of cement weight;
Bentonite volume is the 1% of cement weight, and plasticiser volume is the 1.0~1.2% of cement weight;
Cement paste is prepared according to water burst traffic conditions in crack size and hole.
4th, grouting segment length and pressure
Grouting segment length is generally 5m, and during rock crushing hole wall shakiness, grouting segment length foreshortens to 2~3m, concrete structure with The grout compartment segment length of basement rock contact position is 2m.
Using aperture overfall pressure as standard, Stress control is in 3.0~5.0MPa.
5th, ending standard
5.1st, under design pressure, when grouting injection rate is not more than 1.0L/min, Continuous Perfusion 60min.
5.2nd, grout curtain end hole section permeability rate is more than the permeability rate standard of design requirement or unit injection rate is more than During 100kg/m, drilling should continue to deepen, and deepen segment length 5m every time, at most deepen 3 sections, count 15m.
6th, the grout construction method of abnormal type of karst or karst exception hole section
Mainly there is following type of karst or karst exception hole section in strong karsts developing area stratum grout curtain:(1), packed type Solution cavity or corrosion fissure;(2), without filling or half packed type corrosion fissure;(3), without filling or half filling-type Karst cave;(4), collapse hole Or water burst.
6.1st, the filling-type Karst cave or corrosion fissure grouting method are as follows:
(1) open filling and use 3:1 water and the grout pouring of gray scale, shown according to being in the milk on the pressure gauge of pipe-line control valve Value be controlled, flow is more than 30L/min during the ratio level that reaches of slurries conversion big slurry filling or injection drying loss amount surpasses 500kg/m is crossed, is irrigated using the mixed serum of cement and flyash, and handled by following measures:
1) the big duty pressure that shows declines 20% on the pressure gauge of grouting pipe-line control valve, irrigates l hours, if pressure or Injection rate is unchanged, then reduces the 20% of current pressure, after irrigating l hours, if pressure or injection rate are unchanged, that is, and 8h to be coagulated; Filled again after solidifying, the pressure or injection rate after multiple filling and treat it is solidifying before it is close, that is, use instead and wait that the cement before coagulating mixes with flyash Slurry filling;Pressure or injection rate after multiple filling change with waiting compared with before coagulating, then using 3:1 water and the cement of gray scale Slurry perfusion, by interval 0.5MPa classification boostings;Implement the pressure after multiple fill and be less than 1MPa, then sand perfusion is mixed using cement mortar, directly Reach to grouting pressure and l.0MPa wait to coagulate afterwards, time 8h to be coagulated;
2) the big duty pressure shown on the pressure gauge of grouting pipe-line control valve declines 20%, irrigates l hours, pressure occurs Rise or injection rate change, and continue to irrigate, until terminating, avoid waiting to coagulate.
6.2nd, it is described as follows without filling or half packed type corrosion fissure grouting method:
(1) if grouting when do not return slurry and corrosion fissure it is big, using grout pouring;If not returning slurry and corrosion fissure hour, Sand perfusion is mixed using cement mortar, until overfall and pressure >=1MPa, time to be coagulated are not less than 8h;
(2) if returning slurry and pressure >=1MPa, there is overfall, fully circulated beneficial in hole, be 3 by water and gray scale:1 water Mud opens filling, and carrying out slurries according to code requirement is converted into the slurries bigger than level, when injection rate is more than 30L/min or unit note Enter drying loss amount more than 500kg/m, irrigated using cement and flyash mixed serum, after irrigating 7.5~10t dry ash amounts first, treated The solidifying time is not less than 8h;
(3) filled again after solidifying, use water with gray scale for 3:1 cement mortar, the phase before pressure and injection rate occur and waiting to coagulate Closely, that is, use instead treat it is solidifying before cement irrigated with flyash mixed serum, irrigated in the case where there is overfall dry ash amount 7.5~ After l0t, waterglass perfusion is filled by the following method and the time to be coagulated is not less than 8h:
1) grout injection and waterglass mixed serum;
2) separately irrigated using waterglass and cement mortar, first irrigate 200L waterglass, Reperfu- sion is than level 0.5:1 cement mortar 400L;
(4) in filling process, in the case of having pressure rise, it is classified and boosts by 0.5MPa.
6.3rd, the grouting method without filling or half filling-type Karst cave is as follows:
(1) solution cavity is small, falls to bore below 0.5m, mixes sand using cement mortar, using aperture plus sand, mixes sand amount by cement amount 50%th, 70%, l00% perfusions, handled using following methods after overfall to appear:
1) after there is overfall, irrigated using cement and flyash mixed serum, dry ash amount fills water glass up to after 7.5~10t Glass irrigates, and the time to be coagulated is not less than 8 hours;
2) filled again after solidifying, use water with gray scale for 3:1 cement mortar, occur pressure and injection rate with treat it is solidifying before it is close, i.e., Use the grout pouring for treating solidifying preceding water and gray scale instead;When there is overfall, irrigated with 7.5~10t of dry ash amount admixture waterglass, wait to coagulate Not less than 8 hours;
(2) solution cavity is big, falls and bores more than 0.5m, expands aperture, backfills self-compacting concrete or flowing concrete, or use Rubble exchanges backfill with concrete, after backfilling saturation, then is irrigated, and uses cement mortar or cement and flyash mixing slurry.
6.4th, collapse hole, the construction method of water burst hole section are met
(1) collapse hole
Collapse hole section should shorten segment length's perfusion if soft stratum (such as clay), broken rock according to actual conditions.
Collapse hole section should determine segment length, usually 2m, is rushed using clear water if layer of sand according to collapse hole situation and sand layer thickness Wash, irrigated after returning water cleaning using neat slurry, avoid being fed into cement mortar.
(2) water burst hole section
1) there is the hole section of water burst, needing to survey note water burst pressure and flow before grouting, shortening segment length, increasing grouting by taking Slurry tail pipe tripping in hole section perfusion is penetrated in pressure, the perfusion of pure pressure type, pvc pipe replacement, admixture accelerator, is extended lasting grouting time and is treated The control measure such as time are coagulated to ensure the construction quality effect of such grout hole.
2) in filling process, a concentration of slurry is determined every 10~15min.When finding that overfall thickens, should strengthen starching The frequency of liquid Concentration Testing, and form record.When overfall thickens, grouting should use the new slurry that identical water is with gray scale instead and be filled Note, if DeGrain, continue perfusion 30min, that is, stop grouting.
3) grouting pressure is improved;Improve ending standard, it is necessary to screen slurry is carried out more than 4 hours, to check water burst;Water burst does not stop When only, using the means of supplementing out economy of the slurry as screen slurry are closed, close to starch and wait to coagulate 24~48 hours.
6.5th, the continuity of grouting is kept in work progress, avoids arbitrarily interrupting, once interrupting, to recover to be in the milk in time,
Pass Base of Dam of Reservoir belongs to typical karst landform, is excavated by adit, seepage proof curtain guide hole drilling and electromagnetism The means such as ripple CT detections are verified seepage prevention of dam founda line position stratum karst and extremely developed, and wherein right bank and riverbed line rate of karstification are high respectively Up to 20.90% and 31.32%, and based on being filled with silty clay.Wherein:The ∈ 3m stratum of river-bed section are developed the most, mainly Distribution elevation is 470~380m, and distributed depth is up to more than 100 meters, and with less than based on 3m height.Right bank develops multiple solution cavities or molten Hole group, maximum cavity volume are more than 40,000 m3.Pass reservoir arranges seepage proof curtain, antiseepage in three layers of grouting adit of left and right banks The curtain long 1383m of body, quantities is 150,000 m, maximum grouting pressure 3.5MPa, maximum hole depth 201.37m.Xiushan Mountain pass reservoir engineering Using above-mentioned construction method, engineering is possessed water storage condition on schedule, calculate and analyze by financial cost, reduce engineering cost 10000000 yuan, shorten 8 months completions time of project, remarkable in economical benefits.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should be included in the scope of the protection.

Claims (5)

1. a kind of strong karsts developing area stratum Curtain Grouting Construction method, it comprises the following steps:
(1) pore-forming
When filling-type Karst cave or corrosion fissure are run into filling process, pore-forming or use are replaced by combining high pressure water washing Grouting pump injection cooling water is drilled, and 1.5g/cm is backfilled after going out3Cement mortar;The joint high pressure water washing is replaced as The step of hole technology is:Adjacent holes is got into the same elevation of solution cavity section, holes carries out high pressure water washing processing simultaneously, made Holes is ganged up, wait return the sand content in water it is few, without mud when terminate;The drilling rod in a hole is taken out, the aperture in another hole is entered Row closing, high pressure water washing is carried out in the hole of drilling rod to having simultaneously with two grouting pumps, the Stress control of the water under high pressure exists 3.0MPa, go out in the hole silt particle never drilling rod;
(2) division grouting segment length
The a length of 5m of grout compartment, during rock crushing hole wall shakiness, grouting segment length foreshortens to 2~3m, and concrete structure contacts with basement rock The grout compartment segment length at place is 2m;
(3) controlled grouting pressure
Using aperture overfall pressure as standard, Stress control is in 3.0~5.0MPa;
(4) grouting method is determined
" orifice closing, from top to bottom stages cycle " grouting method is taken, it comprises the following steps:
1) grouting uses high-pressure grouting pump, is supported the use with grouting automatic recording instrument;
2) cement mortar converts step by step than level by dilute to dense, and water is 3 with grey mass ratio:1、2:1、1:1、0.8:1 and 0.5:1 five Than level, open filling and use water with grey mass ratio for 3:1 cement mortar.
2. according to construction method described in claim 1, it is characterised in that step (4) the determination grouting method, filling-type Karst cave Or corrosion fissure grouting method is as follows:
(1) it is 3 by water and grey mass ratio:1 cement mortar opens filling, and the value shown on the pressure gauge according to grouting pipe-line control valve is entered Row control, flow is more than 30L/min when slurries convert the ratio level reached big slurry filling or injection drying loss amount exceedes 500kg/m, irrigated using cement and flyash mixed serum, and handled by following measures:
1) the big duty pressure shown on the pressure gauge of grouting pipe-line control valve declines 20%, l hours is irrigated, if pressure or injection Rate is unchanged, then reduces the 20% of current pressure, after irrigating l hours, if pressure or injection rate are unchanged, that is, and 8h to be coagulated;Wait to coagulate Fill again afterwards, the pressure or injection rate after multiple filling with treat it is solidifying before it is close, that is, use instead treat it is solidifying before cement and flyash mixed serum Perfusion;Pressure or injection rate after multiple filling change with waiting compared with before coagulating, then using 3:The cement of 1 water and grey mass ratio Slurry perfusion, by interval 0.5MPa classification boostings;Implement the pressure after multiple fill and be less than 1MPa, then sand perfusion is mixed using cement mortar, directly Reach to grouting pressure and l.0MPa wait to coagulate afterwards, time 8h to be coagulated;
2) the big duty pressure shown on the pressure gauge of grouting pipe-line control valve declines 20%, irrigates l hours, pressure rise occurs Or injection rate has the situation of reduction, continue to irrigate, until terminating, avoid waiting to coagulate.
3. according to construction method described in claim 1, it is characterised in that step (4) the determination grouting method, no filling or half Packed type corrosion fissure grouting method is as follows:
(1) if grouting when do not return slurry and corrosion fissure it is big, using grout pouring;If not returning slurry and corrosion fissure hour, use Cement mortar mixes sand perfusion, until overfall and pressure >=1MPa, time to be coagulated are not less than 8h;
(2) if returning slurry and pressure >=1MPa, there is overfall, fully circulated beneficial in hole, open filling use water and grey mass ratio for 3:1 cement mortar, slurries are carried out according to code requirement and are converted into the slurries bigger than level, when injection rate is more than 30L/min or list Position injection drying loss amount is irrigated using cement and flyash mixed serum more than 500kg/m, irrigates 7.5~10t dry ash amounts first Afterwards, the time to be coagulated is not less than 8h;
(3) filled again after solidifying, use water with grey mass ratio for 3:1 cement mortar, the phase before pressure and injection rate occur and waiting to coagulate Closely, that is, use instead treat it is solidifying before cement irrigated with flyash mixed serum, irrigated in the case where there is overfall dry ash amount 7.5~ After l0t, waterglass perfusion is filled by the following method and the time to be coagulated is not less than 8h:
1) grout injection and waterglass mixed serum;
2) separately irrigated using waterglass and cement mortar, first irrigate 200L waterglass, Reperfu- sion is than level 0.5:1 cement mortar 400L;
(4) in filling process, in the case of pressure rise, it is classified and boosts by 0.5MPa.
4. according to construction method described in claim 1, it is characterised in that step (4) the determination grouting method, no filling or half The grouting method of filling-type Karst cave is as follows:
(1) solution cavity is small, falls to bore below 0.5m, mixes sand using cement mortar, using aperture plus sand, mix sand amount by cement amount 50%, 70%th, l00% is irrigated, and is handled after overfall to appear using following methods:
1) after there is overfall, irrigated using cement and flyash mixed serum, up to after 7.5~10t, admixture waterglass fills dry ash amount Note, time to be coagulated are not less than 8 hours;
2) filled again after solidifying, use water with grey mass ratio for 3:1 cement mortar, occur pressure and injection rate with treat it is solidifying before it is close, i.e., Use the grout pouring for treating solidifying preceding water and gray scale instead;When there is overfall, irrigated with 7.5~10t of dry ash amount admixture waterglass, wait to coagulate Not less than 8 hours;
(2) solution cavity is big, falls and bores more than 0.5m, expands aperture, backfills self-compacting concrete or flowing concrete, or using rubble Backfill is exchanged with concrete, after backfilling saturation, then is irrigated, uses cement mortar or cement and flyash mixing slurry.
5. according to any one of the claim 3-4 construction methods, it is characterised in that the cement and flyash mixed serum, Water:Concrete and coal ash=0.5:1~0.7:1;Doping quantity of fly ash is the 20%~30% of cement weight;Cement mortar mixes sand, mixes sand Amount is by 10%, 20%, 30%, 40%, 50%, 70% or the 100% of cement amount.
CN201610434986.2A 2016-06-16 2016-06-16 A kind of strong karsts developing area stratum Curtain Grouting Construction method Active CN105887886B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610434986.2A CN105887886B (en) 2016-06-16 2016-06-16 A kind of strong karsts developing area stratum Curtain Grouting Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610434986.2A CN105887886B (en) 2016-06-16 2016-06-16 A kind of strong karsts developing area stratum Curtain Grouting Construction method

Publications (2)

Publication Number Publication Date
CN105887886A CN105887886A (en) 2016-08-24
CN105887886B true CN105887886B (en) 2018-02-27

Family

ID=56729740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610434986.2A Active CN105887886B (en) 2016-06-16 2016-06-16 A kind of strong karsts developing area stratum Curtain Grouting Construction method

Country Status (1)

Country Link
CN (1) CN105887886B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107151956B (en) * 2016-11-24 2024-03-26 中铁第四勘察设计院集团有限公司 Grouting method for reinforcement and coverage type karst embankment with pressurized return grouting
CN106917401A (en) * 2017-02-28 2017-07-04 中国二十冶集团有限公司 Rubble, pebble layer high-pressure rotary jet grouting pile do not return the processing method of slurry
CN107387116A (en) * 2017-09-11 2017-11-24 中国矿业大学 Tunnel bottom plate concealed argillaceous filling karst replacement treatment method
CN108729438B (en) * 2018-05-28 2021-01-08 湖南宏禹工程集团有限公司 Treatment method for karst area channel
CN109183823B (en) * 2018-09-18 2021-02-26 贵州省水利水电勘测设计研究院有限公司 Method and device for dynamically designing lower limit of curtain
CN109930606A (en) * 2019-03-08 2019-06-25 中国水电建设集团十五工程局有限公司 Fast blockage impervious grouting construction method
CN110083868B (en) * 2019-03-26 2023-05-26 雅砻江流域水电开发有限公司 Cement filling quantity measuring method for slurry returning and concentration changing hole section of curtain grouting engineering
CN111648353A (en) * 2020-06-10 2020-09-11 深圳市市政工程总公司 Construction method of rotary excavating cast-in-place pile in karst area based on BIM three-dimensional geological model
CN113152412A (en) * 2021-04-30 2021-07-23 中国葛洲坝集团第一工程有限公司 Foundation pit slope karst seepage-proofing reinforcing treatment method
CN115162340B (en) * 2022-02-22 2024-06-14 中国水利水电建设工程咨询贵阳有限公司 Karst area reservoir curtain grouting construction method
CN115262555A (en) * 2022-08-26 2022-11-01 深圳市广汇源水利建筑工程有限公司 Water glass doped curtain grouting construction method for reservoir danger elimination and reinforcement

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7806631B2 (en) * 2007-04-17 2010-10-05 Smith Eric W Underground filling and sealing method
CN103485345A (en) * 2013-09-26 2014-01-01 葛洲坝集团基础工程有限公司 Construction method for covering layer closed porthole high-pressure curtain grouting
CN103866780A (en) * 2014-03-28 2014-06-18 中国水电顾问集团贵阳勘测设计研究院有限公司 Construction method for rapidly conducting impervious curtain grouting in karst pipeline leakage area
CN104131575A (en) * 2014-04-11 2014-11-05 中国水利水电第十一工程局有限公司 Plugging and drainage method for dam foundation on karst highly developed stratum
CN104594370A (en) * 2014-11-27 2015-05-06 中国电建集团贵阳勘测设计研究院有限公司 High-pressure combined washing grouting method and structure in karst region

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7806631B2 (en) * 2007-04-17 2010-10-05 Smith Eric W Underground filling and sealing method
CN103485345A (en) * 2013-09-26 2014-01-01 葛洲坝集团基础工程有限公司 Construction method for covering layer closed porthole high-pressure curtain grouting
CN103866780A (en) * 2014-03-28 2014-06-18 中国水电顾问集团贵阳勘测设计研究院有限公司 Construction method for rapidly conducting impervious curtain grouting in karst pipeline leakage area
CN104131575A (en) * 2014-04-11 2014-11-05 中国水利水电第十一工程局有限公司 Plugging and drainage method for dam foundation on karst highly developed stratum
CN104594370A (en) * 2014-11-27 2015-05-06 中国电建集团贵阳勘测设计研究院有限公司 High-pressure combined washing grouting method and structure in karst region

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
岩溶地区复杂地质条件下的堵漏防渗施工技术;杨忠兴;《四川水利发电》;20130430;第32卷(第2期);第20-25页 *
强岩溶地层深孔固结灌浆施工关键技术研究;孙晓英等;《中国西部科技》;20151025;第14卷(第10期);第12-15、20页 *
重庆隘口水库岩溶坝基灌浆试验;何英等;《大坝与安全》;20121008;第38-44页 *

Also Published As

Publication number Publication date
CN105887886A (en) 2016-08-24

Similar Documents

Publication Publication Date Title
CN105887886B (en) A kind of strong karsts developing area stratum Curtain Grouting Construction method
CN105201448B (en) Block water slip casting method for blocking in a kind of high-pressure high-flow water gushing channelway
CN103603689B (en) Curtain grouting construction method for treating mined-out areas
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN103266614B (en) Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum
CN103410119B (en) A kind of seepage inside concrete waterproof of man grouting method
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN105201001B (en) Composite seepage preventing structure for large karst cave in karst region and construction method thereof
CN101200897A (en) Construction method for grouting curtain combined with steel reinforced concrete guard ring
CN105625293A (en) Dissolution rock strong-development construction site filling-type geological processing structure and construction method thereof
CN104790419A (en) Dewatering construction method applicable to tunnel in water-rich quicksand stratum
CN106120797B (en) Hydrous fluids continuous steel frame aqueduct pier foundation grouting construction method
CN106759250A (en) Unfavorable geologic body grouting method under the conditions of a kind of pressure-bearing seepage flow
CN107130918A (en) Dam Heavy Curtain Grouting impact pore-forming construction method
CN108442378A (en) A kind of diversion tunnel reinforced concrete lining layer section consolidation grouting engineering method
CN109487777A (en) A method of a reinforcing deep soft soil foundation of filling the span of a man's arms is formed using slip casing by pressure
CN110241788A (en) A kind of reservoir dam body culvert pipe reconstruction structure and construction method
CN103174135B (en) Repair method of unqualified post-grouting bored concrete pile
CN110241837A (en) A kind of construction method for preventing basement bottom board from cracking under high artesian geological conditions
CN113266417A (en) Construction method of karst cave pile foundation
CN112523170A (en) Seepage-proofing treatment method for deep-buried karst seepage channel of reservoir
CN208364097U (en) It is a kind of to block the device for disclosing the drilling of coating artesian water
Adamo et al. Mystery of Mosul Dam the most dangerous dam in the world: problems encountered during and after impounding the reservoir
CN110130335A (en) A kind of basement fills out the construction method of gravel grouting anti-float anchor rod

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180820

Address after: 450000 59 Lianhua street, hi tech Zone, Zhengzhou, Henan

Patentee after: China Hydropower eleventh Engineering Bureau (Zhengzhou) Co., Ltd.

Address before: No. 147, the Yellow River Road, Sanmenxia, Henan, Henan

Patentee before: SINOHYDRO Bureau 11 Co., Ltd.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 450000 59 Lianhua street, hi tech Zone, Zhengzhou, Henan

Patentee after: China Power Construction Eleventh Bureau Engineering Co., Ltd.

Address before: 450000 59 Lianhua street, hi tech Zone, Zhengzhou, Henan

Patentee before: China Hydropower eleventh Engineering Bureau (Zhengzhou) Co., Ltd.

CP01 Change in the name or title of a patent holder