CN104266638A - Pit-in-pit fixed-point line laying method - Google Patents

Pit-in-pit fixed-point line laying method Download PDF

Info

Publication number
CN104266638A
CN104266638A CN201410429850.3A CN201410429850A CN104266638A CN 104266638 A CN104266638 A CN 104266638A CN 201410429850 A CN201410429850 A CN 201410429850A CN 104266638 A CN104266638 A CN 104266638A
Authority
CN
China
Prior art keywords
point
hole
reference mark
foundation ditch
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410429850.3A
Other languages
Chinese (zh)
Inventor
施立军
施群凯
岳志远
陈凯
张佳健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201410429850.3A priority Critical patent/CN104266638A/en
Publication of CN104266638A publication Critical patent/CN104266638A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00

Abstract

The invention relates to the field of civil engineering, and specifically relates to a pit-in-pit fixed-point line laying method. The method is characterized by comprising the following steps: step one, introducing a plurality of control point pile positions into a large basic pit; step two, finding an angular point, from which a small basic pit is dug, and two nearest control points, and marking the distance; step three, marking the distances of each angular point of the small basic pit and other small basic pits, and printing the map; step four, releasing a measuring line in the onsite pit; step five, by referring to the step four, finding other angular points of the same basic pit; step six, through the method mentioned above, finding all four angular points of all basic pits. The method is simple and easy to master, the operation is easy to perform, instrument measurement frequency is reduced, the lineation is precise and is not easy to lose, and the requirements on special instruments and operators are reduced.

Description

Fixed point line-putting method in hole in a kind of hole
Technical field
The present invention relates to field of civil engineering, be specially fixed point line-putting method in hole in a kind of hole.
Background technology
In civil engineering foundation pit construction, often run into the excavation comprising several foundation pits in a larger foundation ditch.After the generous amount earth excavation of foundation ditch completes, leave bottom 300mm dark, then the steel plate of welded bands sword on the tooth of digging machine, coordinates the little foundation pit be manually used in excavation pit, strikes off foundation ditch simultaneously.Some foundation pit is than comparatively dense, and workmen needs each angle point determining foundation pit with instrument, sprinkles lime line, but digging process scraping back and forth, and lime line does not see Chu soon.
Summary of the invention
The object of the invention is to, provide in a kind of simple, quick, stable hole and cheat line-putting method.
In order to achieve the above object, the present invention is achieved in that
In a kind of hole, hole fixed point line-putting method, is characterized in that: comprise the steps:
Step 1: in the large foundation ditch dug, at respective angle point and correct position place according to blueprint, by introducing stake position, several reference mark with the method for surveying setting-out, the reference point established is surveyed as follow-up little foundation ditch in this several reference mark;
Step 2, in Electronic Design figure, finds out angle point and nearest two reference mark of the little foundation ditch of required excavation, and marks out the distance at this angle point and these two reference mark;
Step 3, has marked distance by each angle point of this little foundation ditch and other little foundation ditches by step 2, and has been printed by drawing;
Step 4, at the scene in foundation ditch, release the lining rope of angle point length at nearest two reference mark to its place of one section of some little foundation ditch obtained by above step, lining rope one end is fixed on this stake position, reference mark, the other end draws one section of camber line on the ground of the general orientation of little foundation ditch angle point, just can obtain an intersection point of two arcs; Also the length that the free end of two cotton ropes is corresponding can be found respectively, then free end coincide point is pinched at finger tip, roughly direction simultaneously toward this little foundation ditch angle point is moved, until the position that two cotton ropes are all tightened, is the point that will look for immediately below finger correspondence position;
Step 5, with reference to step 4, finds out other several angle point in same foundation hole;
Step 6, just can find four angle points of all foundation pits by above method.
Fixed point line-putting method in hole in described hole, step 3 can also be: the carrier being loaded with Electronic Design figure is transported to operation field, needs which point can directly measure on Electronic Design figure to the distance of certain two point of fixity.
In described hole, hole fixed point line-putting method, lining rope has the sign point that spacing distance is 1 meter.
Fixed point line-putting method in hole in described hole, the reference mark of in earlier stage excavating large foundation ditch and introducing can be selected in selected reference mark.
Fixed point line-putting method in hole in described hole, the height of stake position, set reference mark in one plane.
This method adopts above-mentioned steps, and it has following advantage:
1, the method is easy to learn, and operating personnel grasps comparatively fast, easy to operate, comparatively fast can enter shoveling and bed course staged construction;
2, without the need to always checking complete foundation ditch corner points with instrument, surveying work amount is decreased;
3, decrease the spreading amount of lime line in classic method, decrease and repeat erection instrument, draw the surveying work amounts such as chi;
4, the method only needs two builders according to figure paper size, little foundation ditch angle point can be surveyed and set out, decrease the requirement to special instrument and operating personnel with lining rope.
Accompanying drawing explanation
Fig. 1 is operation schematic diagram of the present invention.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
As described in Figure 1, in a kind of hole, hole fixed point line-putting method, is characterized in that: comprise the steps:
Step 1: in the large foundation ditch dug, at its angle point and center position according to blueprint, by introducing the stake position at reference mark 1, reference mark 2, reference mark 3, reference mark 4, reference mark 5 with the method for surveying setting-out, the reference point established is surveyed as follow-up little foundation ditch in these five reference mark;
Step 2, in Electronic Design figure, finds out angle point and nearest two reference mark of the little foundation ditch of required excavation, and marks out the distance at this angle point and these two reference mark;
Step 3, has marked distance by each angle point of this little foundation ditch and other little foundation ditches by step 2, and has been printed by drawing;
Step 4, at the scene in foundation ditch, release the lining rope (in Fig. 1 L1, L2) of angle point length at nearest two reference mark to its place of one section of some little foundation ditch obtained by above step, lining rope one end is fixed on this stake position, reference mark, the other end draws one section of camber line on the ground of the general orientation of little foundation ditch angle point (in Fig. 1 A), just can obtain an intersection point of two arcs; (also can find the length that the free end of two cotton ropes is corresponding respectively, then free end coincide point is pinched at finger tip, roughly direction simultaneously toward this little foundation ditch angle point is moved, until the position that two cotton ropes are all tightened, is the point that will look for immediately below finger correspondence position);
Step 5, with reference to step 4, finds out other several angle point (in Fig. 1 B, C, D) in same foundation hole;
Step 6, just can find four angle points of all foundation pits by above method.
Fixed point line-putting method in hole in described hole, step 3 can also be: the carrier being loaded with Electronic Design figure is transported to operation field, needs which point can directly measure on Electronic Design figure to the distance of certain two point of fixity.
In described hole, hole fixed point line-putting method, lining rope has the sign point that spacing distance is 1 meter.
Fixed point line-putting method in hole in described hole, the reference mark of in earlier stage excavating large foundation ditch and introducing can be selected in selected reference mark.
Fixed point line-putting method in hole in described hole, the height of stake position, set reference mark in one plane.
This method adopts above-mentioned steps, and it has following advantage:
1, the method is easy to learn, and operating personnel grasps comparatively fast, easy to operate, comparatively fast can enter shoveling and bed course staged construction;
2, without the need to always checking complete foundation ditch corner points with instrument, surveying work amount is decreased;
3, decrease the spreading amount of lime line in classic method, decrease and repeat erection instrument, draw the surveying work amounts such as chi;
4, the method only needs two builders according to figure paper size, little foundation ditch angle point can be surveyed and set out, decrease the requirement to special instrument and operating personnel with lining rope.

Claims (5)

1. a fixed point line-putting method in hole in hole, is characterized in that: comprise the steps:
Step 1: in the large foundation ditch dug, at respective angle point and correct position place according to blueprint, by introducing stake position, several reference mark with the method for surveying setting-out, the reference point established is surveyed as follow-up little foundation ditch in this several reference mark;
Step 2, in Electronic Design figure, finds out angle point and nearest two reference mark of the little foundation ditch of required excavation, and marks out the distance at this angle point and these two reference mark;
Step 3, has marked distance by each angle point of this little foundation ditch and other little foundation ditches by step 2, and has been printed by drawing;
Step 4, at the scene in foundation ditch, release the lining rope of angle point length at nearest two reference mark to its place of one section of some little foundation ditch obtained by above step, lining rope one end is fixed on this stake position, reference mark, the other end draws one section of camber line on the ground of the general orientation of little foundation ditch angle point, just can obtain an intersection point of two arcs; Also the length that the free end of two cotton ropes is corresponding can be found respectively, then free end coincide point is pinched at finger tip, roughly direction simultaneously toward this little foundation ditch angle point is moved, until the position that two cotton ropes are all tightened, is the point that will look for immediately below finger correspondence position;
Step 5, with reference to step 4, finds out other several angle point in same foundation hole;
Step 6, just can find four angle points of all foundation pits by above method.
2. fixed point line-putting method in hole in hole according to claim 1, is characterized in that: step 3 can also be: the carrier being loaded with Electronic Design figure is transported to operation field, needs which point can directly measure on Electronic Design figure to the distance of certain two point of fixity.
3. fixed point line-putting method in hole in hole according to claim 1, is characterized in that: lining rope has the sign point that spacing distance is 1 meter.
4. fixed point line-putting method in hole in hole according to claim 1, is characterized in that: the reference mark of in earlier stage excavating large foundation ditch and introducing can be selected in selected reference mark.
5. fixed point line-putting method in hole in hole according to claim 1, is characterized in that: the height of stake position, set reference mark in one plane.
CN201410429850.3A 2014-08-28 2014-08-28 Pit-in-pit fixed-point line laying method Pending CN104266638A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410429850.3A CN104266638A (en) 2014-08-28 2014-08-28 Pit-in-pit fixed-point line laying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410429850.3A CN104266638A (en) 2014-08-28 2014-08-28 Pit-in-pit fixed-point line laying method

Publications (1)

Publication Number Publication Date
CN104266638A true CN104266638A (en) 2015-01-07

Family

ID=52158179

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410429850.3A Pending CN104266638A (en) 2014-08-28 2014-08-28 Pit-in-pit fixed-point line laying method

Country Status (1)

Country Link
CN (1) CN104266638A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10788322B2 (en) * 2012-09-25 2020-09-29 Trimble Jena Gmbh Method and apparatus for assigning measuring points to a set of fixed points
CN113073570A (en) * 2021-04-12 2021-07-06 平阳县政府投资项目建设中心 Construction method for controlling perpendicularity of equal-section thin-wall pier based on two-point distance method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101216306A (en) * 2008-01-07 2008-07-09 曹尔彬 Architectural engineering pit quick line-putting method
CN101349563A (en) * 2008-09-03 2009-01-21 武汉建工股份有限公司 Method of laying out line for building construction measurement
CN102022993A (en) * 2010-11-02 2011-04-20 河南省电力公司洛阳供电公司 Method for separated pits of single pole tower foundation of circuits
CN102776901A (en) * 2012-06-25 2012-11-14 中国华冶科工集团有限公司 Deep foundation pit delimitation method
US20140088915A1 (en) * 2012-09-25 2014-03-27 Trimble Jena Gmbh Method and apparatus for assigning measuring points to a set of fixed points
CN103866802A (en) * 2014-04-02 2014-06-18 江苏盐城二建集团有限公司 Ruler-free locating foundation pit tool and using method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101216306A (en) * 2008-01-07 2008-07-09 曹尔彬 Architectural engineering pit quick line-putting method
CN101349563A (en) * 2008-09-03 2009-01-21 武汉建工股份有限公司 Method of laying out line for building construction measurement
CN102022993A (en) * 2010-11-02 2011-04-20 河南省电力公司洛阳供电公司 Method for separated pits of single pole tower foundation of circuits
CN102776901A (en) * 2012-06-25 2012-11-14 中国华冶科工集团有限公司 Deep foundation pit delimitation method
US20140088915A1 (en) * 2012-09-25 2014-03-27 Trimble Jena Gmbh Method and apparatus for assigning measuring points to a set of fixed points
CN103866802A (en) * 2014-04-02 2014-06-18 江苏盐城二建集团有限公司 Ruler-free locating foundation pit tool and using method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋经纬: "建筑物定位和基础放线", 《价值工程》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10788322B2 (en) * 2012-09-25 2020-09-29 Trimble Jena Gmbh Method and apparatus for assigning measuring points to a set of fixed points
CN113073570A (en) * 2021-04-12 2021-07-06 平阳县政府投资项目建设中心 Construction method for controlling perpendicularity of equal-section thin-wall pier based on two-point distance method

Similar Documents

Publication Publication Date Title
CN102322853B (en) Tunnel back break control laser lofting device
CN102022993B (en) Method for separated pits of single pole tower foundation of circuits
CN102095401B (en) Long-distance shield tunnel breakthrough survey method
CN102409703A (en) Monitoring method for horizontal displacement of foundation pit pile top and monitoring device thereof
CN109900208B (en) Mine method tunnel excavation and primary support quality detection method
CN103603330B (en) Method for using total station instrument to measure horizontal displacement of deep soil
CN110513116A (en) A kind of monitoring device and monitoring method of tunnel jacking construction guiding
CN104251688A (en) Method for linear directional measurement by utilizing laser in pipe jacking engineering
CN101705814B (en) Advancing direction measurement method of vertical and slant orepasses
CN102778226A (en) Calibration method for waist line of underground long-distance tunnel
CN102620699A (en) Method for measuring deformation monitoring directional horizontal displacement by using directional vertical distance method
CN104266638A (en) Pit-in-pit fixed-point line laying method
CN103983148A (en) Full-automatic blast hole setting-out method for tunnel smooth surface blasting
CN106767703A (en) Soil-slope excavates domatic method for quick and device
CN108487253A (en) One kind facing rail and is long placed in bonus point hole and engineering method of removing obstacles after ultra-deep foundation pit
CN203811177U (en) Angle measurement pay-off instrument
CN207904918U (en) A kind of drilled pile casing locating rack
JP2023111937A (en) Tunnel face state display system and tunnel face state display method
CN204313844U (en) A kind of noncontact monitoring measurement controls flag-rod
CN106289164A (en) A kind of cavern section method for fast measuring
CN102645198A (en) Detection method and device for dynamic consolidation foundation material displacement
CN105544586A (en) Power transmission circuit foundation hole digging construction method
CN102636161B (en) Method for laying off plane control points by using wire suspension method
CN103487040B (en) The measuring method that a kind of steel column is installed
CN206450213U (en) A kind of triangular angles detection means

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150107

RJ01 Rejection of invention patent application after publication