CN105544586A - Power transmission circuit foundation hole digging construction method - Google Patents

Power transmission circuit foundation hole digging construction method Download PDF

Info

Publication number
CN105544586A
CN105544586A CN201510902141.7A CN201510902141A CN105544586A CN 105544586 A CN105544586 A CN 105544586A CN 201510902141 A CN201510902141 A CN 201510902141A CN 105544586 A CN105544586 A CN 105544586A
Authority
CN
China
Prior art keywords
hole
rig
foundation
foundation ditch
drill bit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510902141.7A
Other languages
Chinese (zh)
Inventor
王喜俊
徐静
程安民
李鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Huaxing Electric Power Engineering Design Co Ltd
State Grid Corp of China SGCC
Original Assignee
Luoyang Huaxing Electric Power Engineering Design Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Huaxing Electric Power Engineering Design Co Ltd, State Grid Corp of China SGCC filed Critical Luoyang Huaxing Electric Power Engineering Design Co Ltd
Priority to CN201510902141.7A priority Critical patent/CN105544586A/en
Publication of CN105544586A publication Critical patent/CN105544586A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/002Survey of boreholes or wells by visual inspection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/04Measuring depth or liquid level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/08Measuring diameters or related dimensions at the borehole
    • E21B47/085Measuring diameters or related dimensions at the borehole using radiant means, e.g. acoustic, radioactive or electromagnetic
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/28Enlarging drilled holes, e.g. by counterboring

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Electromagnetism (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention relates to a power transmission circuit foundation hole digging construction method in the field of construction of power transmission circuits. The method comprises the implementation flow of place arrangement-assembly and debugging-drilling rig adjustment-straight hole drilling-bottom expanding operation-quality inspection-hole position transfer-foundation pit finishing-place transfer. The method not only can effectively prevent the safety risk in underground manual operation, but also can effectively shorten the construction period, and improves the whole construction efficiency.

Description

A kind of transmission line foundation is drawn and is scraped out hole construction method
[technical field]
The present invention relates to transmission line construction field, especially relating to a kind of by drawing the construction method scraping out hole formation transmission line foundation.
[background technology]
Known, a kind of foundation pattern generally adopted when digging hole pile foundation is transmission line construction, it not only can give full play to the advantage of undisturbed soil, improves the load-carrying properties on basis, but also eliminate the operation of underground formwork and pit backfill, the corresponding efficiency that improve construction; At present, the method for hand excavation's foundation ditch is all adopted traditionally, namely first by manually stake holes being dug, corresponding reinforcing cage is placed again in hole, and concrete perfusion forms pile-type, find in prolonged application, hand excavated pile has following defect: the lower operating condition in hole is poor, bad environments, safety is poor, and construction period is longer, and constructor operating space is limited, labour intensity is large, easily casualty accident occurs.
[summary of the invention]
In order to overcome the deficiency in background technology, the invention discloses a kind of transmission line foundation to draw and scrape out hole construction method, described method not only effectively can evade the security risk of artificial lower hole operation, but also effectively can shorten construction period, improves integral construction efficiency.
For achieving the above object, the present invention adopts following technical scheme:
A kind of transmission line foundation is drawn and is scraped out hole construction method, described method implementing procedure is as follows: Ground arrangement → assembly and adjustment → rig adjustment → straight hole creeps into → expands end operation → quality examination → transfer hole position → foundation ditch and completes → shift place, and its particular content is:
One, Ground arrangement: to open according to job site operating condition, basic root, the factor such as drill configuration size, rig approach course, concrete construction flow process, carry out rig operating position, dregs is stacked, cage of reinforcement is processed and the design of placing of material position, require spot plane connection and reasonable arrangement, guarantee smooth implementation and operation;
Two, assembly and adjustment: rig is transported to place, utilizes drilling machine mast straight hole drill bit and bottom expanding drill to be moved to need that to draw the foundation ditch dug near coal-mine, requires that the size of straight hole drill bit and the diameter-enlarging drill bit be equipped with can meet foundation ditch aperture, hole depth and expanding requirement; First straight hole drill bit is installed, makes the pin-and-hole bottom the corresponding drilling rod of straight hole drill bit, then insert pin by straight hole drill bit and drilling rod locking, require to guarantee that each system of rig all can normally work simultaneously;
Three, rig adjustment: excavate out the foundation ditch open test pit of the 200mm degree of depth according to design aperture by artificial, and repetition measurement root is opened, diagonal and aperture size, and driller insertion is operated after condition meets designing requirement;
Four, straight hole creeps into: after driller insertion centering, starts drilling construction, requires that rig zero load runs up, and starts to creep into hourly velocity and wants, slowly to protect near coal-mine shape, when drilling depth reaches a drilling bucket height, to revolve according to the corresponding quickening of actual soil property situation the speed of digging;
Five, end operation is expanded: when after excavation of foundation pit to design hole depth, be diameter-enlarging drill bit by straight hole bit change-over, carry out at the bottom of expansion; After foundation ditch is drawn and scraped out hole, use laser measuring apparatus to carry out total quality inspection to foundation ditch, require that laser measurement instrument probe possesses illumination and shoot function, measurement result and one-tenth hole shape directly can be transferred to chart display and show line item of going forward side by side;
Six, shift position, hole: when first foundation ditch draw dug and by quality examination after, rig moves to next Foundation Pit position according to mobile alignment planned in advance, and the verticality of borer drill rod is checked again, repeat the excavation operation that above-mentioned steps carries out next foundation ditch after meeting the requirements; Require that rig crawler belt and near coal-mine edge when mobile keep the spacing of more than 1.5m;
Seven, shift place: after all foundation ditches are all drawn and dug in basis, will draw and dig rig and ancillary service is transferred to next construction plant, and before requiring to shift place, air ferry route should be planned in advance;
Further, in work flow at the bottom of described expansion, the all controls of laser measuring apparatus in measuring process all pass through conputer controlled, and laser measuring apparatus supporting have can launch infrared rays by infrared camera and receive reverberation to calculate diameter and the degree of depth of foundation ditch pore-forming, possess illumination and the laser range finder of shoot function simultaneously.
Further, in described transfer place flow process, when being shifted by highway, should trailer transportation being taked, when not possessing the condition of trailer transportation, requiring below crawler belt, to lay straw mattress or take other can avoid damaging by pressure the safeguard procedures of highway.
Owing to adopting technical scheme as above, the present invention has following beneficial effect:
Transmission line foundation of the present invention is drawn and is scraped out hole construction method and be applicable to geological conditions is common soil, hard soil, groundwater level depth are greater than embedded depth of foundation foundation ditch and draw and dig operation; Compared with digging with traditional manually drawing, described method apply time not only place take little, orographic condition requires low, environment pollution can be reduced, reduce construction cost, accelerating construction progress, effective raising efficiency of construction and shortening construction period, and its hole quality is better, hole wall finishing process amount is less, the security risk of artificial lower hole operation can be evaded, thus reach and effectively reduce project management department's construction organization pressure, for digging foundation widelys popularize the object creating better condition in transmission line construction from now on.
[detailed description of the invention]
Can explain the present invention in more detail by the following examples, disclose object of the present invention and be intended to protect all changes and improvements in the scope of the invention, the present invention is not limited to the following examples:
Described transmission line foundation is drawn and is scraped out hole construction method, described method implementing procedure is as follows: Ground arrangement → assembly and adjustment → rig adjustment → straight hole creeps into → expands end operation → quality examination → transfer hole position → foundation ditch and completes → shift place, and its particular content is:
One, Ground arrangement: to open according to job site operating condition, basic root, the factor such as drill configuration size, rig approach course, concrete construction flow process, carry out rig operating position, dregs is stacked, cage of reinforcement is processed and the design of placing of material position, require spot plane connection and reasonable arrangement, guarantee smooth implementation and operation;
Two, assembly and adjustment: rig is transported to place, utilizes drilling machine mast straight hole drill bit and bottom expanding drill to be moved to need that to draw the foundation ditch dug near coal-mine, requires that the size of straight hole drill bit and the diameter-enlarging drill bit be equipped with can meet foundation ditch aperture, hole depth and expanding requirement; First straight hole drill bit is installed, makes the pin-and-hole bottom the corresponding drilling rod of straight hole drill bit, then insert pin by straight hole drill bit and drilling rod locking, require to guarantee that each system of rig all can normally work simultaneously;
Three, rig adjustment: excavate out the foundation ditch open test pit of the 200mm degree of depth according to design aperture by artificial, and repetition measurement root is opened, diagonal and aperture size, and driller insertion is operated after condition meets designing requirement;
Four, straight hole creeps into: after driller insertion centering, starts drilling construction, requires that rig zero load runs up, and starts to creep into hourly velocity and wants, slowly to protect near coal-mine shape, when drilling depth reaches a drilling bucket height, to revolve according to the corresponding quickening of actual soil property situation the speed of digging;
Five, end operation is expanded: when after excavation of foundation pit to design hole depth, be diameter-enlarging drill bit by straight hole bit change-over, carry out at the bottom of expansion; After foundation ditch is drawn and scraped out hole, use laser measuring apparatus to carry out total quality inspection to foundation ditch, require that laser measurement instrument probe possesses illumination and shoot function, measurement result and one-tenth hole shape directly can be transferred to chart display and show line item of going forward side by side; As required, the all controls of laser measuring apparatus in measuring process all can pass through conputer controlled, and laser measuring apparatus supporting have can launch infrared rays by infrared camera and receive reverberation to calculate diameter and the degree of depth of foundation ditch pore-forming, possess illumination and the laser range finder of shoot function simultaneously;
Six, shift position, hole: when first foundation ditch draw dug and by quality examination after, rig moves to next Foundation Pit position according to mobile alignment planned in advance, and the verticality of borer drill rod is checked again, repeat the excavation operation that above-mentioned steps carries out next foundation ditch after meeting the requirements; Require that rig crawler belt and near coal-mine edge when mobile keep the spacing of more than 1.5m, thus to avoid the stability having influence on hole wall, cause landslide phenomenon;
Seven, shift place: after all foundation ditches are all drawn and dug in basis, will draw and dig rig and ancillary service is transferred to next construction plant, and before requiring to shift place, air ferry route should be planned in advance; Should note when shifting place: should trailer transportation being taked when being shifted by highway, when not possessing the condition of trailer transportation, requiring below crawler belt, to lay straw mattress or take other can avoid damaging by pressure the safeguard procedures of highway.
Part not in the detailed description of the invention is prior art, therefore the present invention is not described in detail.

Claims (3)

1. a transmission line foundation is drawn and is scraped out hole construction method, it is characterized in that: described method implementing procedure is as follows: Ground arrangement → assembly and adjustment → rig adjustment → straight hole creeps into → expands end operation → quality examination → transfer hole position → foundation ditch and completes → shift place, and its particular content is:
One, Ground arrangement: to open according to job site operating condition, basic root, the factor such as drill configuration size, rig approach course, concrete construction flow process, carry out rig operating position, dregs is stacked, cage of reinforcement is processed and the design of placing of material position, require spot plane connection and reasonable arrangement, guarantee smooth implementation and operation;
Two, assembly and adjustment: rig is transported to place, utilizes drilling machine mast straight hole drill bit and bottom expanding drill to be moved to need that to draw the foundation ditch dug near coal-mine, requires that the size of straight hole drill bit and the diameter-enlarging drill bit be equipped with can meet foundation ditch aperture, hole depth and expanding requirement; First straight hole drill bit is installed, makes the pin-and-hole bottom the corresponding drilling rod of straight hole drill bit, then insert pin by straight hole drill bit and drilling rod locking, require to guarantee that each system of rig all can normally work simultaneously;
Three, rig adjustment: excavate out the foundation ditch open test pit of the 200mm degree of depth according to design aperture by artificial, and repetition measurement root is opened, diagonal and aperture size, and driller insertion is operated after condition meets designing requirement;
Four, straight hole creeps into: after driller insertion centering, starts drilling construction, requires that rig zero load runs up, and starts to creep into hourly velocity and wants, slowly to protect near coal-mine shape, when drilling depth reaches a drilling bucket height, to revolve according to the corresponding quickening of actual soil property situation the speed of digging;
Five, end operation is expanded: when after excavation of foundation pit to design hole depth, be diameter-enlarging drill bit by straight hole bit change-over, carry out at the bottom of expansion; After foundation ditch is drawn and scraped out hole, use laser measuring apparatus to carry out total quality inspection to foundation ditch, require that laser measurement instrument probe possesses illumination and shoot function, measurement result and one-tenth hole shape directly can be transferred to chart display and show line item of going forward side by side;
Six, shift position, hole: when first foundation ditch draw dug and by quality examination after, rig moves to next Foundation Pit position according to mobile alignment planned in advance, and the verticality of borer drill rod is checked again, repeat the excavation operation that above-mentioned steps carries out next foundation ditch after meeting the requirements; Require that rig crawler belt and near coal-mine edge when mobile keep the spacing of more than 1.5m;
Seven, shift place: after all foundation ditches are all drawn and dug in basis, will draw and dig rig and ancillary service is transferred to next construction plant, and before requiring to shift place, air ferry route should be planned in advance.
2. transmission line foundation according to claim 1 is drawn and is scraped out hole construction method, it is characterized in that: in work flow at the bottom of described expansion, the all controls of laser measuring apparatus in measuring process all pass through conputer controlled, and laser measuring apparatus supporting have can launch infrared rays by infrared camera and receive reverberation to calculate diameter and the degree of depth of foundation ditch pore-forming, possess illumination and the laser range finder of shoot function simultaneously.
3. transmission line foundation according to claim 1 is drawn and is scraped out hole construction method, it is characterized in that: in described transfer place flow process, trailer transportation should be taked when being shifted by highway, when not possessing the condition of trailer transportation, require below crawler belt, to lay straw mattress or take other can avoid damaging by pressure the safeguard procedures of highway.
CN201510902141.7A 2015-12-09 2015-12-09 Power transmission circuit foundation hole digging construction method Pending CN105544586A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510902141.7A CN105544586A (en) 2015-12-09 2015-12-09 Power transmission circuit foundation hole digging construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510902141.7A CN105544586A (en) 2015-12-09 2015-12-09 Power transmission circuit foundation hole digging construction method

Publications (1)

Publication Number Publication Date
CN105544586A true CN105544586A (en) 2016-05-04

Family

ID=55824107

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510902141.7A Pending CN105544586A (en) 2015-12-09 2015-12-09 Power transmission circuit foundation hole digging construction method

Country Status (1)

Country Link
CN (1) CN105544586A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812135A (en) * 2017-03-15 2017-06-09 高歌 A kind of circuit column foot continuous-flow type mechanical execution engineering method
CN106836225A (en) * 2017-03-24 2017-06-13 长春工程学院 A kind of artificial digging pile laser alignment device
CN108978741A (en) * 2018-09-12 2018-12-11 浙江三凯工程管理有限公司 A kind of foundation pit displacement automated watch-keeping facility

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03267492A (en) * 1990-03-15 1991-11-28 Ishioka Kensetsu Kk Underground hole excavator
CN201802310U (en) * 2010-02-03 2011-04-20 国家电网公司直流建设分公司 Excavation drilling machine

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03267492A (en) * 1990-03-15 1991-11-28 Ishioka Kensetsu Kk Underground hole excavator
CN201802310U (en) * 2010-02-03 2011-04-20 国家电网公司直流建设分公司 Excavation drilling machine

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘振亚: "《2009年特高压直流输电技术研究成果专辑》", 31 October 2011 *
司基建部: "《家电网公司输变电工程标准工艺(四)-典型施工方法(第二辑)》", 31 July 2012 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812135A (en) * 2017-03-15 2017-06-09 高歌 A kind of circuit column foot continuous-flow type mechanical execution engineering method
CN106836225A (en) * 2017-03-24 2017-06-13 长春工程学院 A kind of artificial digging pile laser alignment device
CN108978741A (en) * 2018-09-12 2018-12-11 浙江三凯工程管理有限公司 A kind of foundation pit displacement automated watch-keeping facility

Similar Documents

Publication Publication Date Title
CN106369223B (en) A kind of silt stratum pipe jacking construction method
CN101457853B (en) Non-digging tube-pulling construction method
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN109723443B (en) Tunnel construction method
CN112103852B (en) Method for crossing river channel and laying cable by using horizontal directional drilling technology
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN102605772A (en) Construction method for revolving digging cast-in-place pile
CN106761776B (en) Construction method for ultra-shallow tunnel shield to penetrate existing pipeline downwards
CN105178291A (en) Large pile foundation construction method
CN104060615B (en) Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN103851257A (en) Paired cable duct bank laying-based support pipe construction process
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN105064336A (en) Hole forming construction method for three-section type pedestal pile
CN110593753A (en) Mechanical rapid hole forming construction method for rectangular slide-resistant pile
CN107130592A (en) A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction
CN108193671A (en) For the weight dangerous region super-large diameter pile foundation drilling construction method of alpine terrain landforms
CN106988305A (en) A kind of pile-column pier construction method of underground integrated molding
CN105544586A (en) Power transmission circuit foundation hole digging construction method
CN111560958A (en) Construction method of water-rich deep foundation pit in silty clay stratum
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN113931637A (en) Shallow-buried water-rich softer rock tunnel construction method
CN107237338B (en) Double-Wall Steel Boxed Cofferdam piecemeal transfers construction method
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160504