CN104260828A - 一种超大型艏部总段的吊装方法 - Google Patents

一种超大型艏部总段的吊装方法 Download PDF

Info

Publication number
CN104260828A
CN104260828A CN201410463445.3A CN201410463445A CN104260828A CN 104260828 A CN104260828 A CN 104260828A CN 201410463445 A CN201410463445 A CN 201410463445A CN 104260828 A CN104260828 A CN 104260828A
Authority
CN
China
Prior art keywords
section
bow
complete cross
bow portion
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410463445.3A
Other languages
English (en)
Inventor
江创宏
孙剑
朱军
黄卫丰
陆伟中
王志浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yangzi Xinfu Shipbuilding Co Ltd
Original Assignee
Jiangsu Yangzi Xinfu Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yangzi Xinfu Shipbuilding Co Ltd filed Critical Jiangsu Yangzi Xinfu Shipbuilding Co Ltd
Priority to CN201410463445.3A priority Critical patent/CN104260828A/zh
Publication of CN104260828A publication Critical patent/CN104260828A/zh
Pending legal-status Critical Current

Links

Abstract

本发明涉及一种超大型艏部总段的吊装方法,包括以下组装步骤:各分段加强:艏部各分段的弱档用槽钢连接框架结构加强;a.分段吊马:在各分段上设计其吊装用吊马,兼顾各分段组装后艏部总段利用各分段吊马进行总段吊装;b.锚绞机安装:各分段组装成艏部总段,在艏部甲板上安装锚绞机 , 锚绞机后挡浪墙不安装;c.艏部总段吊装:艏部总段的下口处用槽钢连接总段纵壁上的强结构成一整体框架结构,艏部总段装焊后测量组装尺寸,艏部总段吊装至船体;d.挡浪墙吊装:艏部总段装焊船体后,将挡浪墙吊装至艏部总段甲板上安装。

Description

一种超大型艏部总段的吊装方法
技术领域
本发明涉及船舶建造领域,具体说是一种超大型艏部总段的吊装方法。
背景技术
超大型箱集装箱船的艏部总段重量较重,传统的建造工艺是在总组之前将分段全部组装结束,而将机电设备留在搭载后安装,机电设备安装不及时,造成水下出现工种交叉作业,不仅影响交船周期,而且对安全生产极为不利。特别是锚绞机的安装,其线路和管路的铺设、调试周期较长,如在搭载后安装,占用较多的交船周期。
发明内容
针对现有技术中的上述不足,本发明提供了一种工艺简单,能保证艏部总段的完整性,同时避免搭载后艏部总段工种与其他总段工种作业交叉,缩短建造周期的超大型艏部总段的吊装方法。
本发明采用的技术方案是:一种超大型艏部总段的吊装方法,包括以下组装步骤:
各分段加强:艏部各分段的弱档用槽钢连接框架结构加强;
分段吊马:在各分段上设计其吊装用吊马,兼顾各分段组装后艏部总段利用各分段吊马进行总段吊装;
锚绞机安装:各分段组装成艏部总段,在艏部甲板上安装锚绞机锚绞机后挡浪墙不安装;
艏部总段吊装:艏部总段的下口处用槽钢连接总段纵壁上的强结构成一整体框架结构,艏部总段装焊后测量组装尺寸,艏部总段吊装至船体;
挡浪墙吊装:艏部总段装焊船体后,将挡浪墙吊装至艏部总段甲板上安装。
进一步地,所述弱档为大开口处。
再进一步地,所述艏部总段测量采用激光经纬仪测量。
采用上述技术方案,本发明的有益效果是:艏部各分段组装及艏部总段采用槽钢加强连接成框架结构,提高整体结构强度,满足大型结构的吊装强度要求,有利于确保安全生产;挡浪墙在艏部总段组装时不安装,对艏部总段进度不会造成影响,并且将锚绞机在艏部总段上安装好后吊装与船体其他总段组装,在确保大型艏部总段安全吊装的前提下,避免了搭载后艏部总段安装锚绞机与其他总段工种作业交叉,减少搭载后的工作量,提高作业效率,缩短船只建造周期。
附图说明
图1为艏部结构示意图;
图2为弱档结构示意图。
图3为舷墙结构示意图;
图4为挡浪墙结构示意图。
图中:槽钢1,吊马2,挡浪墙3,锚绞机4,舷墙5。
具体实施方式
以下结合附图对本发明作进一步说明。
如图所示:一种超大型艏部总段的吊装方法,包括以下组装步骤:
各分段加强:艏部各分段的弱档大开口处用槽钢1连接框架结构加强;
分段吊马:在各分段上设计其吊装用吊马2,兼顾各分段组装后艏部总段利用各分段吊马进行总段吊装;
锚绞机安装:各分段组装成艏部总段,在艏部甲板上安装锚绞机4和舷墙5锚绞机后挡浪墙3不安装;
艏部总段吊装:艏部总段的下口处用槽钢连接总段纵壁上的强结构成一整体框架结构,艏部总段装焊后激光经纬仪测量组装尺寸,艏部总段吊装至船体;
挡浪墙吊装:艏部总段装焊船体后,将挡浪墙吊装至艏部总段甲板上安装。

Claims (3)

1.一种超大型艏部总段的吊装方法,包括以下组装步骤:
各分段加强:艏部各分段的弱档用槽钢连接框架结构加强;
分段吊马:在各分段上设计其吊装用吊马,兼顾各分段组装后艏部总段利用各分段吊马进行总段吊装;
锚绞机安装:各分段组装成艏部总段,在艏部甲板上安装锚绞机锚绞机后挡浪墙不安装;
艏部总段吊装:艏部总段的下口处用槽钢连接总段纵壁上的强结构成一整体框架结构,艏部总段装焊后测量组装尺寸,艏部总段吊装至船体;
挡浪墙吊装:艏部总段装焊船体后,将挡浪墙吊装至艏部总段甲板上安装。
2.根据权利要求1所述的一种超大型艏部总段的吊装方法,其特征是:所述弱档为大开口处。
3.根据权利要求1所述的一种超大型艏部总段的吊装方法,其特征是:所述艏部总段测量采用激光经纬仪测量。
CN201410463445.3A 2014-09-12 2014-09-12 一种超大型艏部总段的吊装方法 Pending CN104260828A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410463445.3A CN104260828A (zh) 2014-09-12 2014-09-12 一种超大型艏部总段的吊装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410463445.3A CN104260828A (zh) 2014-09-12 2014-09-12 一种超大型艏部总段的吊装方法

Publications (1)

Publication Number Publication Date
CN104260828A true CN104260828A (zh) 2015-01-07

Family

ID=52152463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410463445.3A Pending CN104260828A (zh) 2014-09-12 2014-09-12 一种超大型艏部总段的吊装方法

Country Status (1)

Country Link
CN (1) CN104260828A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105752268A (zh) * 2016-03-04 2016-07-13 江苏扬子鑫福造船有限公司 超大型船舶艉部分段总组吊装方法
CN105836595A (zh) * 2016-06-20 2016-08-10 上海江南长兴造船有限责任公司 一种用于分段、总段翻身的方法
CN107010171A (zh) * 2017-03-13 2017-08-04 沪东中华造船(集团)有限公司 一种用于超大型集装箱船横隔舱分段总段吊装的方法
CN110758674A (zh) * 2019-09-18 2020-02-07 沪东中华造船(集团)有限公司 一种船舶锚绞机总段阶段的安装方法
CN111409789A (zh) * 2020-03-13 2020-07-14 上海外高桥造船有限公司 散货船艏部总段的吊装组件及吊装方法
CN111792002A (zh) * 2020-07-24 2020-10-20 上海外高桥造船有限公司 一种散货船艏部总段的组装方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3875887A (en) * 1972-01-24 1975-04-08 Parsons Co Ralph M Apparatus and system for transporting and positioning prefabricated modules in the construction of seagoing ships
CN101181926A (zh) * 2007-09-07 2008-05-21 沪东中华造船(集团)有限公司 一种船舶艏舷部分段的总组方法
CN101570234A (zh) * 2008-04-29 2009-11-04 江南造船(集团)有限责任公司 一种机舱总段组装方法以及机舱总段的吊装方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3875887A (en) * 1972-01-24 1975-04-08 Parsons Co Ralph M Apparatus and system for transporting and positioning prefabricated modules in the construction of seagoing ships
CN101181926A (zh) * 2007-09-07 2008-05-21 沪东中华造船(集团)有限公司 一种船舶艏舷部分段的总组方法
CN101570234A (zh) * 2008-04-29 2009-11-04 江南造船(集团)有限责任公司 一种机舱总段组装方法以及机舱总段的吊装方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴仲其: "《船体分段吊装工艺》", 《江苏船舶》 *
张宏玲: "《船体分段吊装工艺研究》", 《哈尔滨工程大学硕士学位论文集》 *
李超: "《大型船舶艏部分段装配问题分析》", 《科技风》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105752268A (zh) * 2016-03-04 2016-07-13 江苏扬子鑫福造船有限公司 超大型船舶艉部分段总组吊装方法
CN105836595A (zh) * 2016-06-20 2016-08-10 上海江南长兴造船有限责任公司 一种用于分段、总段翻身的方法
CN107010171A (zh) * 2017-03-13 2017-08-04 沪东中华造船(集团)有限公司 一种用于超大型集装箱船横隔舱分段总段吊装的方法
CN107010171B (zh) * 2017-03-13 2019-04-23 沪东中华造船(集团)有限公司 一种用于超大型集装箱船横隔舱分段总段吊装的方法
CN110758674A (zh) * 2019-09-18 2020-02-07 沪东中华造船(集团)有限公司 一种船舶锚绞机总段阶段的安装方法
CN110758674B (zh) * 2019-09-18 2021-11-02 沪东中华造船(集团)有限公司 一种船舶锚绞机总段阶段的安装方法
CN111409789A (zh) * 2020-03-13 2020-07-14 上海外高桥造船有限公司 散货船艏部总段的吊装组件及吊装方法
CN111792002A (zh) * 2020-07-24 2020-10-20 上海外高桥造船有限公司 一种散货船艏部总段的组装方法

Similar Documents

Publication Publication Date Title
CN104260828A (zh) 一种超大型艏部总段的吊装方法
CN105151225A (zh) 一种顶边舱分段建造工艺
CN103661798B (zh) 船舶t型材分段吊运用可拆卸吊耳结构
CN203626261U (zh) 一种铝合金模板体系中混凝土布料机的施工结构
CN104310235B (zh) 海工生活平台上建整体吊运方法
CN104058333B (zh) 一种地下核电站反应堆厂房环形吊车大梁吊装方法
CN103640983A (zh) 一种手拉桥吊
CN201863994U (zh) 船舶吊篮悬挂机构
CN201907631U (zh) 舵叶吊装装置
CN107738978A (zh) 一种可拆式塔吊整体移运用吊梁及其工作原理
CN204714398U (zh) 一种起重机加高装置
CN204588443U (zh) 拆装自翻车车帮的专用工具
CN201914407U (zh) 可重复利用的吊装眼板结构
CN204727473U (zh) 一种起重机吊具防摆装置
CN205663224U (zh) 适用于建筑预制件的吊装连接件
CN204138148U (zh) 预制设备基础双机抬吊吊具
CN207699020U (zh) 一种用于打捞的连接器
CN202899022U (zh) 一种预埋横梁的桥墩
CN204737623U (zh) 一种适用于无缝钢管吊运的配重块
CN202729561U (zh) 一种万向柔性多功能吊排
CN202687746U (zh) 一种起重机用钢筋笼吊具
CN202783700U (zh) 一种浮式采油平台垂直旋转的超长燃气放空支架
CN203850142U (zh) 一种非晶合金干式变压器器身翻转装置
CN202865848U (zh) 一种用于海洋平台的水下结构件吊装装置
CN207166027U (zh) 一种用于输电线路修补引流线的检修平台

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150107

WD01 Invention patent application deemed withdrawn after publication