CN104179365B - 整体铁塔位移施工方法 - Google Patents
整体铁塔位移施工方法 Download PDFInfo
- Publication number
- CN104179365B CN104179365B CN201410401151.8A CN201410401151A CN104179365B CN 104179365 B CN104179365 B CN 104179365B CN 201410401151 A CN201410401151 A CN 201410401151A CN 104179365 B CN104179365 B CN 104179365B
- Authority
- CN
- China
- Prior art keywords
- tower
- steel
- wire
- sole
- steel tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 55
- 239000010959 steel Substances 0.000 title claims abstract description 55
- 238000006073 displacement reaction Methods 0.000 title claims abstract description 21
- 238000000034 method Methods 0.000 title claims abstract description 18
- 241001669679 Eleotris Species 0.000 claims abstract description 18
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 239000010687 lubricating oil Substances 0.000 claims description 3
- 230000000246 remedial effect Effects 0.000 claims description 3
- 230000001360 synchronised effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 7
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种施工简单、操作安全、整体将铁塔移动,可缩短施工时间及停电时间,省时省力,节约施工费用的整体铁塔位移施工方法,包括以下步骤:1、由工作人员登塔将塔上导、地线附件拆除放入导线滑车,采用四根平衡拉线固定铁塔2、将新塔位与原塔位之间的地面修理平整夯实形成位移通道,垫设枕木,在枕木上铺设钢轨,铁塔的四个塔角之间采用加强横梁加强,采用四个千斤将其顶在加强横梁上;3、拆除塔脚螺丝,用千斤顶支起铁塔,将塔脚板安装在塔脚上再落入钢轨上,通过牵引机牵引;4、牵引至新塔位,再次顶起铁塔,拆下塔脚板,移除钢轨和枕木,使铁塔下落至新塔位位置,紧固好地脚螺栓并将导、地线附件工具安装完好。
Description
技术领域
本发明涉及一种整体铁塔位移施工方法。
背景技术
电力系统中对于靠近河套边的铁塔,由于河水冲刷塔位基础,经过几年的运行,塔位基础容易外露,因此,必须将此塔向送电侧移动一定距离(10米左右)。目前,整体铁塔位移施工方法是将36米高的大型铁塔拆除,由于地处河套边,施工场地受限制,施工进度慢,将其移动到适当位置,在进行组装,这种方法施工繁琐复杂、难度大,拆组铁塔环节多,存在的危险因素较多,施工时工器具用量较多,同时需要用25吨吊车2台,操作人员60人,拆除需用2.5-3天,重新组立铁塔也需用2-3天,停电作业时间长,如果遇到恶劣天气或雷雨天气等工期还得需要延长。
发明内容
本发明要解决的技术问题是提供一种施工简单、操作安全、可缩短施工时间及停电时间,省时省力,节约施工费用的整体铁塔位移施工方法。
本发明的技术解决方案是:
一种整体铁塔位移施工方法,其特殊之处包括以下步骤:
1)、由工作人员登塔将塔上导、地线附件拆除,将导、地线放入导线滑车,滑车门封固好后,采用4根平衡拉线,平衡拉线一端固定在横担下平面,另一端与地面上新塔位和原塔位两侧位置设有的地锚连接,塔上工作人员进行一次全面的检查,发现问题及时处理,确无问题后塔上工作人员撤离至地面,在新塔位前面和原塔位之间两侧分别立一根抱杆并将塔两侧的导线落在抱杆的顶部,支撑所述导线;
2)、将新塔位与原塔位之间的地面修理平整夯实形成位移通道,位移通道上对应新塔位与原塔位的两侧塔脚连线位置垫设枕木,并在枕木上铺设钢轨,铁塔的四个塔脚之间采用加强横梁加强,采用四个千斤顶放在枕木的上面并将其顶在加强横梁上;
3)、拆除塔脚螺丝,用千斤顶支起铁塔,铁塔支起时,四个千斤顶同步顶起,当顶升300mm-350mm时,将底部设有滑槽的塔脚板安装在塔脚上实现塔脚板与铁塔的固接,待4个塔脚板全部安装好后,在塔脚板下铺设枕木和与原钢轨相接的短钢轨,反向操作千斤顶使塔脚板底部的滑槽座落在短钢轨上,将钢丝绳系在铁塔两侧采用牵引设备两点平行牵引,牵引过程中牵引速度为≤0.5米/分钟,塔脚板的滑槽内涂好润滑油,同时调整四根平衡拉线,使四根平衡拉线受力均匀,如果平衡拉线发现变形或地锚不牢固状况立即停止牵引,并采取补救措施,恢复正常后,各受力点无异常,四根平衡拉线可以正常使用后再继续牵引;
4)、牵引至新塔位,然后利用千斤顶再次顶起铁塔,顶升高度控制在200mm-250mm,将塔脚板拆下,并将垫设在位移通道上的枕木及对应的钢轨移除,反向操作千斤顶使铁塔下落至新塔位位置,紧固好地脚螺栓,检查铁塔受力正常安装后,将所有辅助设备拆除,并将导、地线附件工具安装完好。
所述塔脚板是由板体和垂直固设在板体底面中部两侧的两个支撑板构成,所述两个支撑板平行设置形成滑槽,所述板体上设有与塔脚上螺孔相对应的板体螺孔。
本发明的有益效果是:
该整体铁塔位移施工方法施工简单、操作安全、整体将铁塔移动,避免了将铁塔拆卸再组装的麻烦,可缩短施工时间及停电时间,省时省力,节约施工费用。
附图说明
图1是本发明的施工布置图:
图2是本发明的平衡拉线及抱杆的架设示意图;
图3是千斤顶顶升铁塔状态示意图;
图4是本发明的塔脚板、塔脚及钢轨连接状态示意图;
图5是图4中的塔脚板的仰视图。
图中:1-板体,2-支撑板,3-板体螺孔,4-塔脚。
具体实施方式
如图所示,本发明涉及的整体铁塔位移施工方法,包括以下步骤:
1)、由工作人员登塔将塔上导、地线附件拆除,将导、地线放入导线滑车,滑车门封固好后,采用4根平衡拉线,平衡拉线一端固定在横担下平面,另一端与地面上新塔位和原塔位两侧位置设有的地锚连接,塔上工作人员进行一次全面的检查,发现问题及时处理,确无问题后塔上工作人员撤离至地面,在新塔位前面和原塔位之间两侧分别立一根抱杆并将塔两侧的导线落在抱杆的顶部,支撑所述导线;
2)、将新塔位与原塔位之间的地面修理平整夯实形成位移通道,位移通道上对应新塔位与原塔位的两侧塔脚连线位置垫设枕木,并在枕木上铺设钢轨,铁塔的四个塔脚之间采用加强横梁加强,采用四个千斤顶放在枕木的上面并将其顶在加强横梁上;
3)、拆除塔脚螺丝,用千斤顶支起铁塔,铁塔支起时,四个千斤顶同步顶起,当顶升300mm时,将底部设有滑槽的塔脚板安装在塔脚上实现塔脚板与铁塔的固接,待4个塔脚板全部安装好后,在塔脚板下铺设枕木和与原钢轨相接的短钢轨,反向操作千斤顶使塔脚板底部的滑槽座落在短钢轨上,将钢丝绳系在铁塔两侧采用牵引设备两点平行牵引,牵引过程中牵引速度为≤0.5米/分钟,塔脚板的滑槽内涂好润滑油,同时调整四根平衡拉线,使4根平衡拉线受力均匀,如果平衡拉线发现变形或地锚不牢固状况立即停止牵引,并采取补救措施,恢复正常后,各受力点无异常,四根平衡拉线可以正常使用后再继续牵引;
4)、牵引至新塔位,然后利用千斤顶再次顶起铁塔,顶升高度控制在200mm,将塔脚板拆下,并将垫设在位移通道上的枕木及对应的钢轨移除,反向操作千斤顶使铁塔下落至新塔位位置,紧固好地脚螺栓,检查铁塔受力正常安装后,将所有辅助设备拆除,并将导、地线附件工具安装完好。
所述塔脚板是由板体1和垂直固设在板体1底面中部两侧的两个支撑板2构成,所述两个支撑板2平行设置形成滑槽,所述板体1上设有与塔脚4上螺孔相对应的板体螺孔3。
Claims (2)
1.一种整体铁塔位移施工方法,其特征包括以下步骤:
1)、由工作人员登塔将塔上导、地线附件拆除,将导、地线放入导线滑车,滑车门封固好后,采用4根平衡拉线,平衡拉线一端固定在横担下平面,另一端与地面上新塔位和原塔位两侧位置设有的地锚连接,塔上工作人员进行一次全面的检查,发现问题及时处理,确无问题后塔上工作人员撤离至地面,在新塔位前面和原塔位之间两侧分别立一根抱杆并将塔两侧的导线落在抱杆的顶部,支撑所述导线;
2)、将新塔位与原塔位之间的地面修理平整夯实形成位移通道,位移通道上对应新塔位与原塔位的两侧塔脚连线位置垫设枕木,并在枕木上铺设钢轨,铁塔的四个塔脚之间采用加强横梁加强,采用四个千斤顶放在枕木的上面并将其顶在加强横梁上;
3)、拆除塔脚螺丝,用千斤顶支起铁塔,铁塔支起时,四个千斤顶同步顶起,当顶升300mm-350mm时,将底部设有滑槽的塔脚板安装在塔脚上实现塔脚板与铁塔的固接,待四个塔脚板全部安装好后,在塔脚板下铺设枕木和与原钢轨相接的短钢轨,反向操作千斤顶使塔脚板底部的滑槽座落在短钢轨上,将钢丝绳系在铁塔两侧采用牵引设备两点平行牵引,牵引过程中牵引速度为≤0.5米/分钟,塔脚板的滑槽内涂好润滑油,同时调整四根平衡拉线,使四根平衡拉线受力均匀,如果平衡拉线发现变形或地锚不牢固状况立即停止牵引,并采取补救措施,恢复正常后,各受力点无异常,四根平衡拉线可以正常使用后再继续牵引;
4)、牵引至新塔位,然后利用千斤顶再次顶起铁塔,顶升高度控制在200mm-250mm,将塔脚板拆下,并将垫设在位移通道上的枕木及对应的钢轨移除,反向操作千斤顶使铁塔下落至新塔位位置,紧固好地脚螺栓,检查铁塔受力正常安装后,将所有辅助设备拆除,并将导、地线附件工具安装完好。
2.根据权利要求1所述的整体铁塔位移施工方法,其特殊之处在于:所述塔脚板是由板体和垂直固设在板体底面中部两侧的两个支撑板构成,所述两个支撑板平行设置形成滑槽,所述板体上设有与塔脚上螺孔相对应的板体螺孔。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410401151.8A CN104179365B (zh) | 2014-08-15 | 2014-08-15 | 整体铁塔位移施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410401151.8A CN104179365B (zh) | 2014-08-15 | 2014-08-15 | 整体铁塔位移施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104179365A CN104179365A (zh) | 2014-12-03 |
CN104179365B true CN104179365B (zh) | 2016-06-01 |
Family
ID=51960682
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410401151.8A Active CN104179365B (zh) | 2014-08-15 | 2014-08-15 | 整体铁塔位移施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104179365B (zh) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105089292A (zh) * | 2015-08-21 | 2015-11-25 | 顾雍舟 | 带土基房屋整体平移施工法 |
CN107269024A (zh) * | 2016-04-08 | 2017-10-20 | 五冶集团上海有限公司 | 塔更换施工中消除塔底板与基础之间吸力方法 |
CN109441197B (zh) * | 2018-12-18 | 2020-05-01 | 温州电力设计有限公司 | 一种轨道式铁塔平移施工方法 |
CN111576919B (zh) * | 2020-04-02 | 2022-01-14 | 国网浙江省电力有限公司湖州供电公司 | 一种输电塔整塔移动装置和方法 |
CN111910951A (zh) * | 2020-08-28 | 2020-11-10 | 衡阳嵘昇生物颗粒有限公司 | 一种板材及木料转运装置 |
CN114592715A (zh) * | 2022-04-19 | 2022-06-07 | 青海送变电工程有限公司 | 一种输电角钢塔同步位移施工方法 |
CN114809782A (zh) * | 2022-04-25 | 2022-07-29 | 国网山西省电力公司朔州供电公司 | 一种电力线路铁塔位移的应急处理方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002147063A (ja) * | 2000-11-10 | 2002-05-22 | Kaihatsu Denki Kk | 鉄塔中間嵩上げ装置及び鉄塔中間嵩上げ方法 |
JP2005133417A (ja) * | 2003-10-30 | 2005-05-26 | Jukankyo Sekkeishitsu:Kk | 建築物基礎の引き上げ装置、並びにこれを用いた建築物基礎の引き上げ工法、及び沈下した建築物基礎の修正工法 |
CN201268960Y (zh) * | 2008-08-28 | 2009-07-08 | 张华� | 一种高压铁塔带电顶升装置 |
CN102493701A (zh) * | 2011-11-30 | 2012-06-13 | 河南省电力公司郑州供电公司 | 双回路终端塔整体悬浮移位方法 |
CN103132710A (zh) * | 2011-12-01 | 2013-06-05 | 吉林省电力有限公司辽源供电公司 | 500kV输电线路带电整体移铁塔的方法 |
CN103216114A (zh) * | 2013-04-18 | 2013-07-24 | 朱奎 | 建筑物的平移施工方法 |
-
2014
- 2014-08-15 CN CN201410401151.8A patent/CN104179365B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002147063A (ja) * | 2000-11-10 | 2002-05-22 | Kaihatsu Denki Kk | 鉄塔中間嵩上げ装置及び鉄塔中間嵩上げ方法 |
JP2005133417A (ja) * | 2003-10-30 | 2005-05-26 | Jukankyo Sekkeishitsu:Kk | 建築物基礎の引き上げ装置、並びにこれを用いた建築物基礎の引き上げ工法、及び沈下した建築物基礎の修正工法 |
CN201268960Y (zh) * | 2008-08-28 | 2009-07-08 | 张华� | 一种高压铁塔带电顶升装置 |
CN102493701A (zh) * | 2011-11-30 | 2012-06-13 | 河南省电力公司郑州供电公司 | 双回路终端塔整体悬浮移位方法 |
CN103132710A (zh) * | 2011-12-01 | 2013-06-05 | 吉林省电力有限公司辽源供电公司 | 500kV输电线路带电整体移铁塔的方法 |
CN103216114A (zh) * | 2013-04-18 | 2013-07-24 | 朱奎 | 建筑物的平移施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104179365A (zh) | 2014-12-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104179365B (zh) | 整体铁塔位移施工方法 | |
CN204370830U (zh) | 一种电杆扶正器 | |
CN106760903A (zh) | 一种输电铁塔不均匀沉降调节装置 | |
CN103938663A (zh) | 一种单拼角钢主材的倾斜输电铁塔纠偏装置 | |
CN107386244B (zh) | 桁架式液压插销升降装置 | |
CN208150850U (zh) | 一种手摇式开关平台升降装置 | |
CN103669882A (zh) | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 | |
CN105952160A (zh) | 一种预应力双索同步张拉工装 | |
CN203977421U (zh) | 电力拉线盘 | |
CN204675726U (zh) | 檩条吊装辅助装置 | |
CN203361170U (zh) | 一种建筑基坑围护用的支撑立柱桩 | |
CN102642482B (zh) | 一种接触网锚柱抢修工法 | |
CN201102869Y (zh) | 空中拆卸水平吊臂类塔式起重机大臂的装置 | |
CN106639322B (zh) | 一种利用电梯导轨的自升式混凝土布料塔及安装方法 | |
CN202090346U (zh) | 一种移动组合式地锚 | |
CN203701282U (zh) | 一种预埋槽道及与其相匹配的支架结构 | |
CN203499575U (zh) | 一种石油钻机的液压起升井架 | |
CN205218474U (zh) | 一种活塞式接力器移出装置 | |
CN207210970U (zh) | 一种桥梁贝雷架吊装装置 | |
CN206873629U (zh) | 一种用于建筑框架中的钢结构 | |
CN106677137B (zh) | 液压启闭机油缸的安装装置及安装方法 | |
CN203903819U (zh) | 发电机定子抬吊装置 | |
CN209177412U (zh) | 一种用于大坡度胶带输送机的夹带装置 | |
CN221001088U (zh) | 混凝土预制模板结构 | |
CN104453253B (zh) | 一种限制被提升结构水平位移的施工装置及施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |