CN104047235A - Method for repairing bridgehead abutment position of road surface - Google Patents

Method for repairing bridgehead abutment position of road surface Download PDF

Info

Publication number
CN104047235A
CN104047235A CN201410223493.5A CN201410223493A CN104047235A CN 104047235 A CN104047235 A CN 104047235A CN 201410223493 A CN201410223493 A CN 201410223493A CN 104047235 A CN104047235 A CN 104047235A
Authority
CN
China
Prior art keywords
injected hole
nothing
slurry
soil layer
injected holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410223493.5A
Other languages
Chinese (zh)
Other versions
CN104047235B (en
Inventor
张腊花
何伟兴
陈云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU DINGTAI ENGINEERING MATERIALS Co Ltd
Original Assignee
JIANGSU DINGTAI ENGINEERING MATERIALS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU DINGTAI ENGINEERING MATERIALS Co Ltd filed Critical JIANGSU DINGTAI ENGINEERING MATERIALS Co Ltd
Priority to CN201410223493.5A priority Critical patent/CN104047235B/en
Priority to CN201610199179.7A priority patent/CN105862560B/en
Publication of CN104047235A publication Critical patent/CN104047235A/en
Application granted granted Critical
Publication of CN104047235B publication Critical patent/CN104047235B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/06Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
    • E01C23/10Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for raising or levelling sunken paving; for filling voids under paving; for introducing material into substructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Road Repair (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to a method for repairing a bridgehead abutment position of a road surface. The method comprises the steps that a detecting radar is used for detecting the void position in a damaged bridge approach slab, the positions of first injected holes are marked in the surface of the approach slab and are drilled, the first injected holes reach a hard soil layer, the first injected holes are arranged in an array way, the central distance of the adjacent first injected holes is 10-20cm, the void position drops in the array range, second injected holes communicate a soft soil layer and are intersected with the first injected holes, the two ends of each second injected hole are provided with an exhaust single-way valve respectively, the first injected holes are grouted, a three-dimensional detecting radar is used for detecting the void position and the slurry filling condition inside the first injected holes and the second injected holes in time, and when the void position, the first injected holes and the second injected holes are filled with the slurry, the grouting is stopped; the detecting radar is used again for detecting and re-checking the filling position after the grouting is finished, and the positions which are not filled with the slurry are drilled and grouted again. The method solves the problem that the hard soil layer and the soft soil layer are different in sinking speed.

Description

The method that repair at the end of the bridge platform back of the body place of road pavement
Technical field
The present invention relates to a kind of method that repair at end of the bridge platform back of the body place of road pavement, can repair end of the bridge platform back of the body place, eliminate vehicle bump at bridge ends.
Background technology
Along with the continuous increase of highway in China and railway mileage, it is increasing that the highway such as bridge, culvert is constructed shared proportion, back filling behind abutment place ubiquity " bumping at bridge-head " phenomenon of a lot of these class formations, so-called " bumping at bridge-head " refers to that the structure such as bridge, culvert itself and the platform back of the body are because the effect of driving load and deadweight continues sedimentation, inconsistent and the differential settlement that produces of tectonic subsidence and platform back of the body sedimentation, cause the platform back of the body and the road surface of structure junction to occur step, the vehicle of running at high speed produces the phenomenon of jolting and jumping by back filling behind abutment place.
Occur that the vertical of above-mentioned phenomenon want reason to be, general bridge floor will be connected with roadbed (hardpan) higher than road surface and by bridge pier, therefore have between the bridge floor of difference in height and road surface and be connected by attachment strap, need on the existing roadbed below attachment strap, pile the artificial soil horizon's (Soft Soil Layer) who establishes compacting in order to support this attachment strap, therefore to compare former roadbed (hardpan) softer for the later stage forms for this artificial soil horizon, bridge in later stage operation process due to natural subsidence effect, the height on its bridge floor and road surface all can decline, but the infall process of above-mentioned Soft Soil Layer is faster than hardpan, therefore between bridge floor and attachment strap, occur that difference in height causes vehicle bump at bridge ends, between while Soft Soil Layer and attachment strap, meeting forms to come to nothing and make and misplaces between bridge floor and attachment strap, thereby has aggravated vehicle bump at bridge ends.
China Patent No. is that the document of CN102051861 has proposed to utilize high polymer material to be injected into the interior attachment strap that comes to nothing, promotes depression of eliminating of coming to nothing of attachment strap bottom to eliminate vehicle bump at bridge ends, but the method fails the settling rate difference of the different soil that causes vehicle bump at bridge ends to take measures, therefore fail fundamentally to solve the problem of bumping at bridge-head.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of method that repair at end of the bridge platform back of the body place of road pavement, can solve the problem of hardpan and Soft Soil Layer settling rate difference.
In order to solve the problems of the technologies described above, the invention provides a kind of method that repair at end of the bridge platform back of the body place of road pavement, it comprises the steps:
A. utilize detection radar to detect to come to nothing in the attachment strap of impaired bridge position, the position that goes out to come to nothing in the surface markers of attachment strap is also measured this and is come to nothing and the degree of depth of hardpan;
B. mark position the boring of injected hole one on attachment strap surface, injected hole one reaches hardpan deeply, and injected hole one is with array way layout, and making to come to nothing falls within the scope of array;
C. mark position the boring of injected hole two in the side of Soft Soil Layer, each injected hole two connects this Soft Soil Layer crossing with injected hole one;
D. injected hole one is carried out to slip casting and utilize instant detection of three-dimensional detection radar to come to nothing and the slurry of each injected hole one, injected hole two inside is filled situation, come to nothing and stop slip casting when each injected hole one, injected hole two when slurry is full of this;
E. slip casting utilizes detection radar to filling location detection check, to not re-started boring, slip casting by slurry filling place again after stopping;
F. slip casting finished after 10 minutes, and each injected hole one, injected hole two are carried out to sealing of hole.
Described injected hole one is 3-15cm with the diameter of injected hole two, and the center distance of adjacent injected hole one is 8-25cm.
Described injected hole two levels connect this Soft Soil Layer and perpendicular to attachment strap center line, each injected hole one is crossing with multiple injected holes two of the below of coming to nothing respectively.
The present invention also provides a kind of slurry of repairing, the slip casting process of the method that this slurry is repaired for the end of the bridge platform back of the body place of above-mentioned road pavement.
This slurry is high strength foam-type resin.
The elative free swelling ratio of this slurry reaches 20:1, can fill and come to nothing after 3 minutes in injection, injects and reaches final strength after 10 minutes.
The machine viscosity that goes out of this slurry is 100 ± 45mPas, and its final strength meets compressive strength >=20MPa, bending strength >=15MPa
With respect to prior art, the technique effect that the present invention has is:
1) method that repair at the end of the bridge platform back of the body place of road pavement of the present invention, detect and boring by detection radar, slip casting combines, the also lifting attachment strap that comes to nothing of not only having filled up attachment strap below makes end of the bridge smooth-going, also by crossing injected hole one and injected hole two make solidify after the slurry bodily form reticulate structure, by attachment strap, Soft Soil Layer and hardpan link into an integrated entity, thereby the settling rate of Soft Soil Layer and hardpan is consistent, the settling rate of attachment strap will be consistent with hardpan, prevent from forming and coming to nothing between Soft Soil Layer and attachment strap, thereby avoid bridge floor and attachment strap because of settling rate difference causes separately vehicle bump at bridge ends,
2) come to nothing position inject slurry curing after form a pulp layer, this pulp layer top connects attachment strap, below is connected with hardpan by slurry column, injected hole one and slurry column diameter are 5-10cm, fractional load on attachment strap directly can be passed to hardpan by slurry column, thereby reduce the settling amount after Soft Soil Layer pressurized; Injected hole two and slurry crossbeam diameter are 5-10cm, can make part conduct to slurry column through the attachment strap load of Soft Soil Layer conduction through slurry crossbeam, conduct to hardpan through slurry column again, thereby reduce the load through Soft Soil Layer conduction, further reduce the settling amount of Soft Soil Layer; The center distance of adjacent injected hole one is 10-20cm, not only can make slurry column arrange closely but also be beneficial to injected hole one is holed;
3) injected hole two levels connect this Soft Soil Layer and perpendicular to attachment strap center line, be convenient to the mobile and filling of slurry in boring and slip casting process, multiple injected holes two crossing with injected hole one are set in the Soft Soil Layer below coming to nothing, can strengthen the bonding strength between Soft Soil Layer and hardpan, attachment strap, also be conducive to more load through Soft Soil Layer conduction to be directly conducted to hardpan by slurry crossbeam, slurry column simultaneously;
4) the water-free high strength foam-type resin of this slurry, can not produce drying shrinkage phenomenon, can closely knit filling come to nothing; After slurry curing, have pliability and elasticity, be not easy to ftracture, this resin material has good impermeability simultaneously, can stop rainwater infiltration to enter in attachment strap, and fracture and seam have good sealing function;
5) this slurry injects after 3 minutes and can fill and come to nothing, and injects and reaches its final strength after 10 minutes, and hardening time is short, engineering time and the impact on traffic are reduced, after slurry curing, form foaming shape solid, its density is cement paste 20%, can be to the larger load of structure generation;
6) elative free swelling ratio of this slurry can reach 20:1, can come to nothing by Fast Filling, and the further soil layer of compacting around coming to nothing in expansion process;
7) solidify after Stability of Slurry strong, be difficult for aging distortion, its durability can reach a century;
8), after slurry curing, each chemical composition can not dissolved or decompose in rainwater and be run off, environmentally safe;
9) the attachment strap structure after this slurry is repaired, the later stage, without periodic maintenance, maintenance, has reduced maintenance cost.
Brief description of the drawings
In order to clearly demonstrate innovative principle of the present invention and the technical advantage than existing product thereof, by applying the limiting examples of described principle, possible embodiment is described by means of accompanying drawing below.In the drawings:
Fig. 1 is the profile of impaired bridge in the present invention;
Fig. 2 is the profile of the bridge after boring in the present invention;
Fig. 3 is the top view that is provided with the attachment strap of injected hole one in the present invention;
Fig. 4 is the left view of the slurry body after solidifying in the present invention.
Detailed description of the invention
Embodiment 1
As shown in Figure 1, impaired bridge generally comprises: the face 1 of mating formation, attachment strap 2, comes to nothing 3, bridge floor 4, road surface 5, Soft Soil Layer 6, hardpan 7.
Come to nothing and generally appear between attachment strap 2 and Soft Soil Layer 6, along with the sedimentation of the Soft Soil Layer volume that comes to nothing can increase gradually, because Soft Soil Layer 6 exceeds roadbed, be convenient to from the side Soft Soil Layer 6 be holed.
As shown in Fig. 1-3, the method that repair at the end of the bridge platform back of the body place of road pavement of the present invention, comprises the following steps:
(1) utilize 3 positions of coming to nothing in the attachment strap of the impaired bridge of three-dimensional detection detections of radar, in the surface markers of attachment strap 2 go out to come to nothing 3 position measure this and come to nothing 3 and the degree of depth of hardpan 7;
(2) mark position the boring of each injected hole 1 on attachment strap 2 surfaces of coming to nothing above 3, the diameter of injected hole 1 is 5-10cm and deeply reaches hardpan 7, all injected holes 1 arrange in square array mode, and the center distance of adjacent injected hole 1 is 10-20cm and coming to nothing of above-mentioned mark 3 fallen within the scope of the array of described injected hole 1;
(3) mark the position of injected hole 29 in the side of Soft Soil Layer 6 and hole, each injected hole 29 levels connect this Soft Soil Layer and intersect at injected hole 1, each injected hole 1 is crossing with three injected holes 29 being located at 3 belows of coming to nothing, and each injected hole 29 is 5-10cm perpendicular to attachment strap center line and diameter;
(4) in the position of each injected hole 1, Grouting Pipe 11 is installed, Grouting Pipe 11 stretches to the bottom of injected hole 1, in each Grouting Pipe 11, filling adaptor is installed, debugging grouting equipment is also connected with filling adaptor, inspection injecting paste material also adds in grouting equipment, is provided with at each injected hole 29 two ends the one way valve that only can discharge air;
(5) injected hole 1 is carried out to slip casting and utilize three-dimensional detection radar instant detect come to nothing 3 and the slurry of each injected hole 1, injected hole 29 inside fill situation, come to nothing 3 and stop slip casting when each injected hole 1, injected hole 29 when slurry is full of this;
(6) slip casting after stopping, again utilizing detection radar detect this come to nothing 3 and each injected hole 1, injected hole 29 in whether also have and do not filled position by slurry, to existing the position of above-mentioned situation to re-start boring, slip casting;
(7) after waiting for 10 minutes, the slurry curing of filling also reaches final strength, takes off one way valve and each injected hole 1, injected hole 29 are carried out to sealing of hole.
Slurry after solidifying forms slurry body 10 as shown in Figure 4, comprise the net structure that many rows are made up of the slurry crossbeam 103 of multiple vertical slurry columns 101, level and be full of 3 the pulp layer 102 of coming to nothing, this slurry body 10 is fixedly connected with attachment strap 2, Soft Soil Layer 6 and hardpan 7.
Embodiment 2
Slurry described in the present invention adopts a kind of high strength foam-type resin, its model is SZ3, when slip casting, this resin is added in above-mentioned grouting equipment, the resin viscosity (going out machine viscosity) flowing out from this grouting equipment is 100 ± 45mPas, this resin slurry volume in flowing constantly increases, its penetrating power is strong, be suitable for arriving fast the position or enter in gap of coming to nothing, be suitable under pressure squeezing ponding, after above-mentioned slurry injects 3 minutes, can fill and come to nothing, inject and reach its final strength after 10 minutes, its compressive strength >=20MPa, bending strength >=15MPa.
This slurry has following characteristics:
(1) this slurry is not moisture, can not produce drying shrinkage phenomenon, can closely knit filling come to nothing; After slurry curing, have pliability and elasticity, be not easy to ftracture, this resin material has good impermeability simultaneously, can stop rainwater infiltration to enter Soft Soil Layer, and fracture and seam have good sealing function;
(2) after slurry curing, form foaming shape solid, its density is cement paste 20%, can be to the larger load of structure generation;
(3) elative free swelling ratio of this slurry can reach 20:1, can come to nothing by Fast Filling, and the further soil layer of compacting around coming to nothing in expansion process;
(4) solidify after Stability of Slurry strong, be difficult for aging distortion, its durability can reach a century;
(5), after slurry curing, each chemical composition can not dissolved or decompose in rainwater and be run off, environmentally safe;
(6) the attachment strap structure after this slurry is repaired, the later stage, without periodic maintenance, maintenance, has reduced maintenance cost.
Obviously, above-described embodiment is only for example of the present invention is clearly described, and is not the restriction to embodiments of the present invention.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Here without also giving exhaustive to all embodiments.And these belong to apparent variation that spirit of the present invention extended out or variation still among protection scope of the present invention.

Claims (3)

1. the method that repair at the end of the bridge platform back of the body place of road pavement, is characterized in that comprising the steps:
A. utilize detection radar to detect to come to nothing in the attachment strap of impaired bridge (3) position, the surface markers of attachment strap (2) go out to come to nothing (3) position and measure this and come to nothing (3) and the degree of depth of hardpan (7);
B. mark position the boring of injected hole one (8) on attachment strap (2) surface, injected hole one reaches hardpan (7) deeply, and injected hole one (8) is with array way layout, and make to come to nothing (3) fall within the scope of array;
C. mark position the boring of injected hole two (9) in the side of Soft Soil Layer (6), each injected hole two (9) connects this Soft Soil Layer crossing with injected hole one (8);
D. injected hole one (8) is carried out to slip casting and utilize instant detection of three-dimensional detection radar to come to nothing (3) and each injected hole one (8), the inner slurry of injected hole two (9) are filled situation, when slurry is full of this and comes to nothing (3) and stops slip casting when each injected hole one (8), injected hole two (9);
E. slip casting utilizes detection radar to filling location detection check, to not re-started boring, slip casting by slurry filling place again after stopping;
F. slip casting finished after 10 minutes, and each injected hole one (8), injected hole two (9) are carried out to sealing of hole.
2. the method that repair at the end of the bridge platform back of the body place of road pavement according to claim 1, is characterized in that: described injected hole one is 3-15cm with the diameter of injected hole two, and the center distance of adjacent injected hole one (8) is 8-25cm.
3. the method that repair at the end of the bridge platform back of the body place of road pavement according to claim 1, it is characterized in that: described injected hole two (9) levels connect this Soft Soil Layer and perpendicular to attachment strap center line, each injected hole one (8) is crossing with multiple injected holes two (9) of (3) below of coming to nothing respectively.
CN201410223493.5A 2014-05-26 2014-05-26 The Bridge back wall place of road pavement carries out the method for repairing Active CN104047235B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201410223493.5A CN104047235B (en) 2014-05-26 2014-05-26 The Bridge back wall place of road pavement carries out the method for repairing
CN201610199179.7A CN105862560B (en) 2014-05-26 2014-05-26 The method repaired at the Bridge back wall of environmentally safe road pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410223493.5A CN104047235B (en) 2014-05-26 2014-05-26 The Bridge back wall place of road pavement carries out the method for repairing

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201610199179.7A Division CN105862560B (en) 2014-05-26 2014-05-26 The method repaired at the Bridge back wall of environmentally safe road pavement

Publications (2)

Publication Number Publication Date
CN104047235A true CN104047235A (en) 2014-09-17
CN104047235B CN104047235B (en) 2016-04-27

Family

ID=51500606

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201410223493.5A Active CN104047235B (en) 2014-05-26 2014-05-26 The Bridge back wall place of road pavement carries out the method for repairing
CN201610199179.7A Active CN105862560B (en) 2014-05-26 2014-05-26 The method repaired at the Bridge back wall of environmentally safe road pavement

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610199179.7A Active CN105862560B (en) 2014-05-26 2014-05-26 The method repaired at the Bridge back wall of environmentally safe road pavement

Country Status (1)

Country Link
CN (2) CN104047235B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108330848A (en) * 2018-03-10 2018-07-27 林光琴 A kind of bridge pavement repairing construction technology

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252111A (en) * 2020-08-25 2021-01-22 徐州成瑞建筑科技研究院有限公司 Desilting and grouting reinforcement method for slab bottom void pavement crack
CN112627168A (en) * 2020-12-23 2021-04-09 河南长安交通科技发展有限公司 High-density polymer grouting reinforcement method for roadbed at sunken part of bridge and culvert butt strap

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0456331A1 (en) * 1990-05-10 1991-11-13 Voorbij Groep B.V. Method for the displacement of a slab-shaped carrier, and seal therefor
CN2793158Y (en) * 2005-03-04 2006-07-05 铁道科学研究院铁道建筑研究所 Porous pipe for cement casting at transitting section of present bridge
CN101168957A (en) * 2007-10-01 2008-04-30 于心然 Bridge brow plate emptying shallow layer grouting reinforcement technique
CN102051861A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 Bridgehead vehicle bump prevention and control high polymer grouting technique and construction method thereof
CN102409598A (en) * 2011-09-29 2012-04-11 河海大学 Method for processing vehicle bump at bridge head of existing highway
CN102888796A (en) * 2012-09-13 2013-01-23 山西路众道桥有限公司 Method for quickly repairing cavity disease of cement concrete pavement
CN203334152U (en) * 2013-07-09 2013-12-11 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure at deep layer yielding ground area
CN103669385A (en) * 2013-12-30 2014-03-26 中铁二十四局集团有限公司 Method for improving pile group bearing capacity by means of reticular pile foundations

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU977789A1 (en) * 1981-04-28 1982-11-30 Научно-исследовательский институт строительства угольных и горнорудных предприятий Method for plugging rocks
JP2000204554A (en) * 1999-01-08 2000-07-25 Tenox Corp Reinforcing structure for embankment
CN102052081A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 High polymer grouting technology for treating tunnel void and construction method thereof
FR3017398B1 (en) * 2014-02-07 2017-06-23 Electricite De France METHOD FOR STABILIZING A TECHNICAL FILLER

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0456331A1 (en) * 1990-05-10 1991-11-13 Voorbij Groep B.V. Method for the displacement of a slab-shaped carrier, and seal therefor
CN2793158Y (en) * 2005-03-04 2006-07-05 铁道科学研究院铁道建筑研究所 Porous pipe for cement casting at transitting section of present bridge
CN101168957A (en) * 2007-10-01 2008-04-30 于心然 Bridge brow plate emptying shallow layer grouting reinforcement technique
CN102051861A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 Bridgehead vehicle bump prevention and control high polymer grouting technique and construction method thereof
CN102409598A (en) * 2011-09-29 2012-04-11 河海大学 Method for processing vehicle bump at bridge head of existing highway
CN102888796A (en) * 2012-09-13 2013-01-23 山西路众道桥有限公司 Method for quickly repairing cavity disease of cement concrete pavement
CN203334152U (en) * 2013-07-09 2013-12-11 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure at deep layer yielding ground area
CN103669385A (en) * 2013-12-30 2014-03-26 中铁二十四局集团有限公司 Method for improving pile group bearing capacity by means of reticular pile foundations

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108330848A (en) * 2018-03-10 2018-07-27 林光琴 A kind of bridge pavement repairing construction technology
CN108330848B (en) * 2018-03-10 2019-05-31 青海省恒立公路勘测设计有限公司 A kind of bridge pavement repairing construction technology

Also Published As

Publication number Publication date
CN104047235B (en) 2016-04-27
CN105862560B (en) 2018-02-02
CN105862560A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN104047236B (en) The restorative procedure on bumping at bridge-head road surface
CN104033164B (en) Come to nothing and the harmful method repaired that seeps water to what encircle in tunnel
CN104695343B (en) Long-distance jacking construction method based on back wall pushing technology
CN104047217A (en) Rapid pavement restoration method
CN104047213B (en) A kind of method for repairing road surface that can solve hard stratum and Soft Soil Layer sinking speed difference
CN104047237B (en) A kind of method for repairing road surface
CN104746390A (en) Foam lightweight concrete railroad bed structure
CN105735151B (en) A kind of method for repairing road surface
KR20100097337A (en) Speedy recovering method for concrete track
CN203295966U (en) Structure for reducing bumping of bridge abutment based on flexible piles
CN104033165B (en) Tunnel defect restorative procedure and reparation slurry
CN104047235B (en) The Bridge back wall place of road pavement carries out the method for repairing
CN105926391A (en) Method for widening shoulder of existing railway subgrade
CN113737624A (en) Bridge head bump bag type grouting repair construction method
CN109704656A (en) A kind of bridge joint hillside fields polymer grouting strengthening method
CN104047305A (en) Fast repairing method of house sinking
CN204875495U (en) No abutment body seat formula abutment
CN105780673B (en) Solve the hard, restorative procedure on the bumping at bridge-head road surface of Soft Soil Layer differential settling velocity
CN204715136U (en) A kind of road-bridge transition section road structure
CN106812065A (en) A kind of concrete freely-supported pre-stressed box girder construction process
CN210946334U (en) Soft foundation reinforcement and butt strap jacking repair system for sunk bridge head butt strap
CN109033714B (en) Design method for controlling coordinated deformation of roadbed and pavement
CN104047306A (en) Method for lifting and centralizing sinking house
CN203160089U (en) Anti-settling bridgehead slope structure
CN206127853U (en) Adopt integral foundation structure's of grit stake dark bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Chen Zan

Inventor before: Zhang Lahua

Inventor before: He Weixing

Inventor before: Chen Yun

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: The method of repairing the bridge head and back of the road surface

Granted publication date: 20160427

Pledgee: Industrial and Commercial Bank of China Danyang Branch

Pledgor: JIANGSU DINGTAI ENGINEERING MATERIAL CO.,LTD.

Registration number: Y2024980002806