CN106812065A - A kind of concrete freely-supported pre-stressed box girder construction process - Google Patents

A kind of concrete freely-supported pre-stressed box girder construction process Download PDF

Info

Publication number
CN106812065A
CN106812065A CN201510858602.5A CN201510858602A CN106812065A CN 106812065 A CN106812065 A CN 106812065A CN 201510858602 A CN201510858602 A CN 201510858602A CN 106812065 A CN106812065 A CN 106812065A
Authority
CN
China
Prior art keywords
scaffold
concrete
box girder
installation
girder construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510858602.5A
Other languages
Chinese (zh)
Inventor
廖志伟
谭庆华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hengyang Xindeli Prestress Co Ltd
Original Assignee
Hengyang Xindeli Prestress Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hengyang Xindeli Prestress Co Ltd filed Critical Hengyang Xindeli Prestress Co Ltd
Priority to CN201510858602.5A priority Critical patent/CN106812065A/en
Publication of CN106812065A publication Critical patent/CN106812065A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a kind of concrete freely-supported pre-stressed box girder construction process, it is characterised in that described construction technology step is:Basement process → full hall scaffold is set up and precompressed → bed die and side form installations → colligation beam body bottom web reinforcement → installation bottom web prestressing force bellows → installation internal model → installation end mould → colligation roof steel bar → installation top board prestressing force bellows → beam body filling concrete → maintenance → take off side form → tensioning → mud jacking → remove scaffold and bed die.A kind of the problems such as present invention is directed to existing prestress box beam complicated construction technique, production cost is higher, there is provided the concrete freely-supported pre-stressed box girder construction process of construction quality of raising box beam, accelerating construction progress and reduction engineering cost.

Description

A kind of concrete freely-supported pre-stressed box girder construction process
Technical field
The invention belongs to technical field of building construction, and in particular to a kind of concrete freely-supported pre-stressed box girder construction process.
Background technology
With developing rapidly for Chinese national economy and high-speed railway communication, increasing High-speed Passenger Dedicated Lines constantly build up and go into operation.By the end of in December, 2011, China is completed and the speed per hour that has been open to traffic has a series of circuits such as Beijing-Shanghai express railway, military wide high ferro, Zheng Xi high ferros, Shanghai-Hangzhou high ferro, Shanghai and Nanjing high ferro, the wide depth section of wide Shenzhen and Hong Kong high ferro, stone force high ferro Henan Section, Harbin-to-Dalian high ferro, Beijing-Tianjin inter-city in the Line for Passenger Transportation of 300km and the above;Have in the Line for Passenger Transportation of 300km and the above building or debugging speed per hour:Big western high ferro, Beijing-to-Shijiazhuang high ferro, stone force high ferro Hebei Section etc..And in these high-speed railway circuits, because high ferro settlement request standard is high, to account for bridge ratio is very big, wherein in Beijing-Shanghai express railway, circuit overall length 1318km, bridge line length 1060km, accounts for total line 80.7%, military wide high ferro Bridge account for ratio is then higher, hence in so that the concrete freely-supported prestress box beam construction technology that the most high-speed rail bridge of China is used has been studied into necessity.Although concrete freely-supported prestress box beam has rigidity big, anti-impact force is strong, good stability, noise is small, the advantages of being easy to maintaining, but also there is complex structure simultaneously, new technology, it is with high content of technology, own vol is big, weight weight, the features such as width is big is therefore, the prefabricated difficulty of this box beam is larger, used with new material wide, new technology requirement is high, the characteristics of construction is complicated, construction technology has direct and great influence to construction quality, improve the construction quality of box beam, the construction technology that accelerating construction progress and reduction engineering cost must just have, and make its constantly improve, obtain good economic benefit and social benefit.
The content of the invention
A kind of the problems such as technical problems to be solved by the invention are directed to existing prestress box beam complicated construction technique, production cost is higher, there is provided the concrete freely-supported pre-stressed box girder construction process of construction quality of raising box beam, accelerating construction progress and reduction engineering cost.
The technical scheme that present invention solution above-mentioned technical problem is used is as follows:
There is provided a kind of concrete freely-supported pre-stressed box girder construction process, it is characterised in that described construction technology step is:
Basement process → full hall scaffold is set up and precompressed → bed die and side form installations → colligation beam body bottom web reinforcement → installation bottom web prestressing force bellows → installation internal model → installation end mould → colligation roof steel bar → installation top board prestressing force bellows → beam body filling concrete → maintenance → take off side form → tensioning → mud jacking → remove scaffold and bed die, it is first bottom web chamfering that the beam body concrete irrigates technique detailed process, bottom web again, base plate again, epiplastron, last top board again.
This technique is in addition to the requirement of general railroad bridge is met, also meet some special requirements, because under bullet train service condition, the dynamic response aggravation of structure so that the security of train operation, passenger take comfort level, load impact, the fatigue of material, train operation when noise, the durability of structure etc. the problems such as it is all different from common railway.So, bridge structure must have enough strength and stiffness, it is necessary to assure the smooth-going state high of reliable stability and holding bridge upper rail, the bridge structure of high-speed railway is born.This construction technology improves construction quality, accelerating construction progress and the reduction engineering cost of box beam simultaneously.
Further, the mud jacking is vacuum grouting.
Further, the vacuum grouting detailed process is preparation → vacuumize and to configure slurries → mud jacking → stop vacuumizing and cleaning → sealing off and covering anchorage after pressurize → work before mud jacking.
Further, the basement process process is for before scaffold in-situ beam casting, levelling of the land first is carried out to job site, place to setting up scaffold carries out consolidation process, changed in soft base location rubble and fill out or do concrete foundation, ensure that foundation bearing capacity reaches the requirement for being abound with load, sedimentation is not produced after making beam body concreting.Construction site to handling well carries out unwrapping wire, and periphery sets gutter, meets the drainage sunk well requirement on ground.
Further, the full hall scaffold sets up process for bowl buckle scaffold is assembled using external diameter standard member, every vertical rod lower end is all provided with shape disk support or sheeting caps, bridging is set, rod end installs Adjustable U rest, the horizontal lumps of wood is first installed in rest, then longitudinal lumps of wood and stow-wood cushion block are installed by design spacing and absolute altitude, the resistance to overturning of steel pipe is differential settlement, the stability control of supporting structure by basis.Direction across bridge strictly controls the perpendicularity of montant and the quantity and spacing of sweep the floor bar and Crossing brace according to the assembly requirement of support.Connected to scaffold and pier shaft along bridge, with offset along bridge to horizontal force total sub-semigroup be connected with military pier scaffold by steel pipe, the intensity and resistance to overturning of guarantor's combined support.
Further, after the full hand hall scaffold building is good, bed die is laid; carry out preloading pressure testing; to check the bearing capacity of support, reduce and eliminate inelastic deformation and uneven settlement of foundation, the adjustment camber of support, so that it is guaranteed that the pouring quality of beams of concrete.Loading sequence is to be carried out successively to span centre from bearing, and the lotus time is held after being fully loaded with not less than 24h, and the deformation values of scaffold under loads at different levels are measured respectively, is then unloaded step by step again, when the settling amount deviation of scaffold is larger, scaffold is adjusted.
Specific embodiment
In order that technical problem solved by the invention, technical scheme and beneficial effect become more apparent, with reference to embodiments, the present invention is described in further detail.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.All any modification, equivalent and improvement made within the spirit and principles in the present invention etc., should be included within the scope of the present invention.
Embodiment 1
A kind of concrete freely-supported pre-stressed box girder construction process, it is characterised in that described construction technology step is:
Basement process,Detailed process is for before scaffold in-situ beam casting,Levelling of the land first is carried out to job site,Place to setting up scaffold carries out consolidation process,Changed in soft base location rubble and fill out or do concrete foundation,Construction site to handling well carries out unwrapping wire,Periphery sets gutter → full hall scaffold and sets up and precompressed,Full hall scaffold sets up process for bowl buckle scaffold is assembled using external diameter standard member,Every vertical rod lower end is all provided with shape disk support or sheeting caps,Bridging is set,Rod end installs Adjustable U rest,The horizontal lumps of wood is first installed in rest,Longitudinal lumps of wood and stow-wood cushion block are installed by design spacing and absolute altitude again,Connected to scaffold and pier shaft along bridge,Total sub-semigroup is connected by steel pipe with military pier scaffold,After full hand hall scaffold building is good,Laying bed die,Carry out preloading pressure testing,Loading sequence is to be carried out successively to span centre from bearing,Lotus time 25h is held after fully loaded,The deformation values of scaffold under loads at different levels are measured respectively,Then unload step by step again,When the settling amount deviation of scaffold is larger,Scaffold is adjusted → bed die and side form installations → colligation beam body bottom web reinforcement → installations bottom web prestressing force bellows → installation internal model → installation end mould → colligation roof steel bar → installation top board prestressing force bellows → beam body filling concrete → maintenance → take off side form → tensioning → vacuum grouting detailed process is preparation before mud jacking,Vacuumize and configure slurries,Mud jacking,Stop vacuumizing and pressurize,Cleared up after work,Sealing off and covering anchorage → remove scaffold and bed die,It is first bottom web chamfering that the beam body concrete irrigates technique detailed process,Bottom web again,Base plate again,Epiplastron again,Last top board.
Embodiment 2
Basement process,Detailed process is for before scaffold in-situ beam casting,Levelling of the land first is carried out to job site,Place to setting up scaffold carries out consolidation process,Changed in soft base location rubble and fill out or do concrete foundation,Construction site to handling well carries out unwrapping wire,Periphery sets gutter → full hall scaffold and sets up and precompressed,Full hall scaffold sets up process for bowl buckle scaffold is assembled using external diameter standard member,Every vertical rod lower end is all provided with shape disk support or sheeting caps,Bridging is set,Rod end installs Adjustable U rest,The horizontal lumps of wood is first installed in rest,Longitudinal lumps of wood and stow-wood cushion block are installed by design spacing and absolute altitude again,Connected to scaffold and pier shaft along bridge,Total sub-semigroup is connected by steel pipe with military pier scaffold,After full hand hall scaffold building is good,Laying bed die,Carry out preloading pressure testing,Loading sequence is to be carried out successively to span centre from bearing,Lotus time 30h is held after fully loaded,The deformation values of scaffold under loads at different levels are measured respectively,Then unload step by step again,When the settling amount deviation of scaffold is larger,Scaffold is adjusted → bed die and side form installations → colligation beam body bottom web reinforcement → installations bottom web prestressing force bellows → installation internal model → installation end mould → colligation roof steel bar → installation top board prestressing force bellows → beam body filling concrete → maintenance → take off side form → tensioning → vacuum grouting detailed process is preparation before mud jacking,Vacuumize and configure slurries,Mud jacking,Stop vacuumizing and pressurize,Cleared up after work,Sealing off and covering anchorage → remove scaffold and bed die,It is first bottom web chamfering that the beam body concrete irrigates technique detailed process,Bottom web again,Base plate again,Epiplastron again,Last top board.
Embodiment 3
Basement process,Detailed process is for before scaffold in-situ beam casting,Levelling of the land first is carried out to job site,Place to setting up scaffold carries out consolidation process,Changed in soft base location rubble and fill out or do concrete foundation,Construction site to handling well carries out unwrapping wire,Periphery sets gutter → full hall scaffold and sets up and precompressed,Full hall scaffold sets up process for bowl buckle scaffold is assembled using external diameter standard member,Every vertical rod lower end is all provided with shape disk support or sheeting caps,Bridging is set,Rod end installs Adjustable U rest,The horizontal lumps of wood is first installed in rest,Longitudinal lumps of wood and stow-wood cushion block are installed by design spacing and absolute altitude again,Connected to scaffold and pier shaft along bridge,Total sub-semigroup is connected by steel pipe with military pier scaffold,After full hand hall scaffold building is good,Laying bed die,Carry out preloading pressure testing,Loading sequence is to be carried out successively to span centre from bearing,Lotus time 36h is held after fully loaded,The deformation values of scaffold under loads at different levels are measured respectively,Then unload step by step again,When the settling amount deviation of scaffold is larger,Scaffold is adjusted → bed die and side form installations → colligation beam body bottom web reinforcement → installations bottom web prestressing force bellows → installation internal model → installation end mould → colligation roof steel bar → installation top board prestressing force bellows → beam body filling concrete → maintenance → take off side form → tensioning → vacuum grouting detailed process is preparation before mud jacking,Vacuumize and configure slurries,Mud jacking,Stop vacuumizing and pressurize,Cleared up after work,Sealing off and covering anchorage → remove scaffold and bed die,It is first bottom web chamfering that the beam body concrete irrigates technique detailed process,Bottom web again,Base plate again,Epiplastron again,Last top board.

Claims (6)

1. a kind of concrete freely-supported pre-stressed box girder construction process, it is characterised in that described construction technology step is:
Basement process → full hall scaffold is set up and precompressed → bed die and side form installations → colligation beam body bottom web reinforcement → installation bottom web prestressing force bellows → installation internal model → installation end mould → colligation roof steel bar → installation top board prestressing force bellows → beam body filling concrete → maintenance → take off side form → tensioning → mud jacking → remove scaffold and bed die, it is first bottom web chamfering that the beam body concrete irrigates technique detailed process, bottom web again, base plate again, epiplastron, last top board again.
2. concrete freely-supported pre-stressed box girder construction process according to claim 1, it is characterised in that the mud jacking is vacuum grouting.
3. concrete freely-supported pre-stressed box girder construction process according to claim 2, it is characterised in that the vacuum grouting detailed process is preparation before mud jacking → vacuumize and configures slurries → mud jacking → stop vacuumizing and cleaning → sealing off and covering anchorage after pressurize → work.
4. concrete freely-supported pre-stressed box girder construction process according to claim 1, it is characterized in that, the basement process process is for before scaffold in-situ beam casting, levelling of the land first is carried out to job site, place to setting up scaffold carries out consolidation process, changed in soft base location rubble and fill out or do concrete foundation, the construction site to handling well carries out unwrapping wire, periphery sets gutter.
5. concrete freely-supported pre-stressed box girder construction process according to claim 1, it is characterized in that, the full hall scaffold sets up process for bowl buckle scaffold is assembled using external diameter standard member, every vertical rod lower end is all provided with shape disk support or sheeting caps, bridging is set, rod end installs Adjustable U rest, the horizontal lumps of wood is first installed in rest, longitudinal lumps of wood and stow-wood cushion block are installed by design spacing and absolute altitude again, connected to scaffold and pier shaft along bridge, total sub-semigroup is connected by steel pipe with military pier scaffold.
6. concrete freely-supported pre-stressed box girder construction process according to claim 1, it is characterized in that, after the full hand hall scaffold building is good, bed die is laid, carry out preloading pressure testing, loading sequence is to be carried out successively to span centre from bearing, the lotus time is held after fully loaded not less than 24h, the deformation values of scaffold under loads at different levels are measured respectively, then unloaded step by step again, when the settling amount deviation of scaffold is larger, scaffold is adjusted.
CN201510858602.5A 2015-12-01 2015-12-01 A kind of concrete freely-supported pre-stressed box girder construction process Pending CN106812065A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510858602.5A CN106812065A (en) 2015-12-01 2015-12-01 A kind of concrete freely-supported pre-stressed box girder construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510858602.5A CN106812065A (en) 2015-12-01 2015-12-01 A kind of concrete freely-supported pre-stressed box girder construction process

Publications (1)

Publication Number Publication Date
CN106812065A true CN106812065A (en) 2017-06-09

Family

ID=59155695

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510858602.5A Pending CN106812065A (en) 2015-12-01 2015-12-01 A kind of concrete freely-supported pre-stressed box girder construction process

Country Status (1)

Country Link
CN (1) CN106812065A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374004A (en) * 2019-07-10 2019-10-25 江苏镇江路桥工程有限公司 A kind of presstressed reinforcing steel mud-jacking technology
CN112832112A (en) * 2021-01-14 2021-05-25 中铁四局集团第二工程有限公司 Pouring and vibrating process for railway machine-made sand concrete box girder
CN113430942A (en) * 2021-06-25 2021-09-24 中铁十九局集团第五工程有限公司 Construction method for pouring box girder concrete

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102797223A (en) * 2012-08-22 2012-11-28 中铁十九局集团第七工程有限公司 Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
KR101249285B1 (en) * 2011-10-05 2013-04-01 주식회사 동성엔지니어링 Bridge with prestressed concrete box girder of cantilever support structure by precast bracket, and it`s construction method
CN104372890A (en) * 2014-11-07 2015-02-25 成龙建设集团有限公司 Construction method of bare concrete prefabricated box beam with complicated structure
CN104963290A (en) * 2015-07-08 2015-10-07 杭州江润科技有限公司 Mold supporting structure for variable cross-section cast-in-place box girder at section combining horizontal and longitudinal curves, and construction method of the mold supporting structure
CN107119574A (en) * 2017-06-27 2017-09-01 中交第三航务工程局有限公司 A kind of Cantilever Construction Method of arch rib bridge girder

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101249285B1 (en) * 2011-10-05 2013-04-01 주식회사 동성엔지니어링 Bridge with prestressed concrete box girder of cantilever support structure by precast bracket, and it`s construction method
CN102797223A (en) * 2012-08-22 2012-11-28 中铁十九局集团第七工程有限公司 Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN104372890A (en) * 2014-11-07 2015-02-25 成龙建设集团有限公司 Construction method of bare concrete prefabricated box beam with complicated structure
CN104963290A (en) * 2015-07-08 2015-10-07 杭州江润科技有限公司 Mold supporting structure for variable cross-section cast-in-place box girder at section combining horizontal and longitudinal curves, and construction method of the mold supporting structure
CN107119574A (en) * 2017-06-27 2017-09-01 中交第三航务工程局有限公司 A kind of Cantilever Construction Method of arch rib bridge girder

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374004A (en) * 2019-07-10 2019-10-25 江苏镇江路桥工程有限公司 A kind of presstressed reinforcing steel mud-jacking technology
CN112832112A (en) * 2021-01-14 2021-05-25 中铁四局集团第二工程有限公司 Pouring and vibrating process for railway machine-made sand concrete box girder
CN113430942A (en) * 2021-06-25 2021-09-24 中铁十九局集团第五工程有限公司 Construction method for pouring box girder concrete

Similar Documents

Publication Publication Date Title
CN102888815B (en) The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam
CN100464026C (en) Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process
CN101230563B (en) Method for replacing bridge bearing without traffic interruption and special device thereof
CN205443958U (en) Composite truss support of big cantilever bent cap
CN104047236B (en) The restorative procedure on bumping at bridge-head road surface
CN101368371A (en) Cast-in-situ continuous beam construction method for special railway line stands
CN103726450B (en) Supported Slab Bridge rises method and adjustable height combination mat stone structure thereof
CN210134291U (en) Broad structure of side of existing passenger dedicated line road bed
CN107905114A (en) A kind of construction method of large span Successive interference cancellation
CN112854008A (en) Prefabricated bridge pier and beam integrated bridge girder erection machine and construction method thereof
CN102587282B (en) Large-section simply-supported box girder precasting and assembly process under conditions of strong wind and high altitude
CN106812065A (en) A kind of concrete freely-supported pre-stressed box girder construction process
CN102797223B (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN105201107A (en) Construction method for stacked plate type shear wall of underground garage
CN106381810B (en) With the cast-in-place outstanding method for filling beam of beam-column type bracket
CN104047213B (en) A kind of method for repairing road surface that can solve hard stratum and Soft Soil Layer sinking speed difference
CN104047237B (en) A kind of method for repairing road surface
CN101838967B (en) Construction technology of ballast bed of bridge double-block ballastless track
CN104047235B (en) The Bridge back wall place of road pavement carries out the method for repairing
CN107988854B (en) Later-stage reservation structure of subway upper cover vehicle base parking train inspection warehouse
CN206052565U (en) A kind of beam-column type bracket
CN205259051U (en) Railway existing line large -span crossbeam system of making somebody a mere figurehead
CN101736693B (en) Construction process for casting large-tonnage box beam in site by support pier method
CN209227616U (en) A kind of inspection well cover support of high bearing capacity
CN209066195U (en) Railway high-filled embankment vertically in iris type box-structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170609