CN205443958U - Composite truss support of big cantilever bent cap - Google Patents
Composite truss support of big cantilever bent cap Download PDFInfo
- Publication number
- CN205443958U CN205443958U CN201620167768.2U CN201620167768U CN205443958U CN 205443958 U CN205443958 U CN 205443958U CN 201620167768 U CN201620167768 U CN 201620167768U CN 205443958 U CN205443958 U CN 205443958U
- Authority
- CN
- China
- Prior art keywords
- support
- pillar stand
- bent cap
- truss support
- modules
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种大悬臂盖梁的组合桁架支架,采用缀板格构式组合桁架支架,整个支架体系主要分为下支腿、组合桁架、分配梁、砂箱和三脚托架5个模块,安装时利用槽钢和螺栓将5个模块由下到上依次连接成一个整体,下面2个模块由承台上的4个格构式立柱组成,下立柱与上立柱间的横梁为下横梁,上横梁上按支架竖向杆件位置布设用于支撑盖梁三角托架及设置工作平台的分配梁;方形砂箱设置在分配梁和三角托架之间,斜撑将上横梁与下横梁端头以销子铰接,同时在前后斜撑之间均用横向横联连接,上横梁之间和下横梁之间焊接横梁横联及斜撑。本实用新型有效解决了支架支撑对于现场及基础的依赖,结构简单、拆装速度快、实际操作中安全性高、能够循环利用等特点。
A composite truss support for a large cantilever cover beam, which adopts a panel lattice composite truss support. The whole support system is mainly divided into five modules: lower legs, composite truss, distribution beam, sand box and tripod bracket. Channel steel and bolts connect the 5 modules sequentially from bottom to top to form a whole. The lower 2 modules are composed of 4 lattice columns on the platform. The beam between the lower column and the upper column is the lower beam, and the upper beam is upper According to the position of the vertical rods of the bracket, the distribution beam used to support the triangular bracket of the cover beam and set up the working platform is arranged; the square sand box is arranged between the distribution beam and the triangular bracket, and the diagonal brace connects the ends of the upper beam and the lower beam with pins. At the same time, the front and rear diagonal braces are connected by horizontal cross-links, and the cross-beam cross-links and diagonal braces are welded between the upper beams and the lower beams. The utility model effectively solves the dependence of the support on the site and the foundation, and has the characteristics of simple structure, fast disassembly and assembly speed, high safety in actual operation, and recyclable utilization.
Description
技术领域technical field
本实用新型涉及桥梁工程施工领域,具体来说是一种在软弱地基中施工的大悬臂盖梁的组合桁架支架设计及其施工方法。The utility model relates to the field of bridge engineering construction, in particular to a design of a combined truss support for a large cantilever cover beam constructed in a weak foundation and a construction method thereof.
背景技术Background technique
在日益发达的交通运输网络中,由于运输量的逐年增大,交通网络不断完善,新建线路日益增多。在城市高架桥总体线型设计中,为了克服地面复杂情况和桥下通行的影响,常常采用悬臂盖梁桥墩及预应力预制小箱梁相结合的结构形式。就高速公路而言,两端悬挑较小的圆柱墩相对较多,该种形式从设计到施工技术比较成熟。近年来,随之高速公路设计的不断完善,长悬臂预应力盖梁工程也越来越多,相关施工工艺在国内尚无成熟的经验可供借鉴,相关施工技术亟待研究,且在软弱地基上利用常规支架法施工必须对地基进行硬化处理,因而增加了施工成本。In the increasingly developed transportation network, due to the increase in transportation volume year by year, the transportation network is constantly improving, and the number of new lines is increasing. In the overall linear design of urban viaducts, in order to overcome the complex ground conditions and the influence of traffic under the bridge, the structural form combining cantilever cap girder piers and prestressed prefabricated small box girders is often used. As far as expressways are concerned, there are relatively many cylindrical piers with small overhangs at both ends, and this form is relatively mature in design and construction technology. In recent years, with the continuous improvement of expressway design, there are more and more long cantilever prestressed cap beam projects. There is no mature experience in the relevant construction technology in China for reference, and the relevant construction technology needs to be studied urgently. The foundation must be hardened for construction using the conventional support method, thus increasing the construction cost.
实用新型内容Utility model content
本实用新型提供一种在软弱地基中施工的大悬臂盖梁的组合桁架支架及其施工方法,有效解决了支架支撑对于现场及基础的依赖,该支架具有结构简单、拆装速度快、无需进行地基硬化处理、实际操作中安全性高、能够循环利用等特点,极大的节约了成本。The utility model provides a combined truss support for a large cantilever cover beam constructed in a weak foundation and a construction method thereof, which effectively solves the dependence of the support on the site and the foundation. The characteristics of ground hardening treatment, high safety in actual operation, and recyclability greatly save costs.
本实用新型所采取的技术方案:The technical scheme that the utility model takes:
一种大悬臂盖梁的组合桁架支架,采用缀板格构式组合桁架支架,整个支架体系主要分为下支腿、组合桁架、分配梁、砂箱和三脚托架5个模块,安装时利用槽钢和螺栓将5个模块由下到上依次连接成一个整体,下面2个模块由承台上的4个格构式立柱组成,立柱分下立柱和上立柱,下立柱与上立柱间的横梁为下横梁,上立柱上面的横梁为上横梁,上横梁采用40双工字钢组焊,上横梁上按支架竖向杆件位置布设用于支撑盖梁三角托架及设置工作平台的分配梁;方形砂箱设置在分配梁和三角托架之间,三角托架上方为盖梁底模,将上横梁与下横梁端头通过斜撑以销子铰接,同时在前后面斜撑之间均用横向横联连接,并设置剪刀撑,前后面上横梁之间和下横梁之间焊接横梁横联及斜撑。A composite truss support for a large cantilever cover beam, which adopts a panel lattice composite truss support. The whole support system is mainly divided into five modules: lower legs, composite truss, distribution beam, sand box and tripod bracket. Channel steel and bolts connect the 5 modules sequentially from bottom to top to form a whole. The lower 2 modules are composed of 4 lattice columns on the platform. The columns are divided into lower columns and upper columns. The beam is the lower beam, and the beam above the upper column is the upper beam. The upper beam is welded with 40 double I-beams. The upper beam is arranged according to the position of the vertical rod of the bracket to support the triangular bracket of the cover beam and set the distribution of the working platform. Beam; the square sand box is set between the distribution beam and the triangular bracket. Above the triangular bracket is the bottom formwork of the cover beam. The ends of the upper beam and the lower beam are hinged with pins through diagonal braces. At the same time, between the front and rear diagonal braces They are all connected by horizontal cross-links, and scissors braces are set, and cross-beam cross-links and diagonal braces are welded between the front and rear beams and between the lower beams.
所述的分配梁由18a工字钢制成The distribution beam is made of 18a I-beam
所述的下立柱采用32c槽钢组合焊接,上立柱采用22b槽钢组合焊接,前后面上立柱间和下立柱间用[14槽钢横向立柱横联连接。The lower column adopts 32c channel steel combination welding, and the upper column adopts 22b channel steel combination welding, and the front and rear columns and the lower column are connected with [14 channel steel horizontal column cross connection.
所述的砂箱平面尺寸为35cm×35cm,调节高度范围为22~32cm。The plane size of the sand box is 35cm×35cm, and the adjustable height range is 22-32cm.
所述的斜撑、横联及剪刀撑、下横梁和横梁横联及斜撑为[28双槽钢。Described diagonal brace, cross-link and scissors brace, lower beam and cross-beam cross-link and diagonal brace are [28 double channel steel.
一种大悬臂盖梁的组合桁架支架的施工方法,包括以下步骤:A construction method for a composite truss support of a large cantilever cap beam, comprising the following steps:
(1)清理承台:支架安装前将承台顶面杂物清理干净,保证支架下支腿可与承台直接接触并保证支架受力稳定;(1) Cleaning the platform: before installing the bracket, clean up the sundries on the top surface of the platform to ensure that the lower legs of the bracket can directly contact with the platform and ensure the stable force of the bracket;
(2)确定支架高度:根据墩柱设计高度确定需要安装支腿的组合方案,支腿有高度为2m、1m和0.3m三种型号;(2) Determining the height of the support: determine the combination scheme that needs to be installed with outriggers according to the design height of the pier column. The outriggers have three models with a height of 2m, 1m and 0.3m;
(3)下支腿安装:根据计算所确定的支腿组合方案,先安装2m高度的支腿,剩余高度小于2m时再安装1m和0.3m支腿,安装可利用汽车吊将支腿套装在墩柱上,再对其平面位置进行微调,位置确定后在支腿与墩柱之间用木楔塞进固定,上下两节支腿用螺栓连接;(3) Installation of lower outriggers: According to the outrigger combination plan determined by calculation, first install outriggers with a height of 2m, and then install outriggers with a height of 1m and 0.3m when the remaining height is less than 2m. On the pier column, fine-tune its plane position. After the position is determined, use wooden wedges to insert and fix between the outrigger and the pier column, and connect the upper and lower outriggers with bolts;
(4)组合桁架安装:将事先组装好的一片组合桁架整体利用汽车吊吊装至支腿上,用手拉葫芦将其与墩柱临时固定,待2片组合桁架全部吊装至支腿上以后,利用槽钢和剪刀撑将2片组合桁架连接固定。(4) Composite truss installation: hoist a piece of pre-assembled composite truss onto the outrigger with a truck crane, and temporarily fix it with the pier column with a chain hoist. Use channel steel and scissors braces to connect and fix the two combined trusses.
(5)分配梁安装:上横梁上的分配梁放置在三角托架每个竖向支撑处,并排3根,每根分配梁长4.5m,将分配梁与上横梁之间采用Φ25精轧螺纹钢配合[10槽钢压板进行锁定。(5) Distribution beam installation: The distribution beam on the upper beam is placed on each vertical support of the triangular bracket, 3 pieces are arranged side by side, each distribution beam is 4.5m long, and the Φ25 fine-rolled thread is used between the distribution beam and the upper beam The steel is matched with [10 channel steel platen for locking.
(6)安装砂箱:砂箱安装位置根据图纸设置,防止砂箱侧滑,分配梁上使用L50×50角钢焊接定位槽,将砂箱放入定位槽内。(6) Install the sand box: The installation position of the sand box is set according to the drawings to prevent the sand box from slipping. Use L50×50 angle steel welding positioning slots on the distribution beam, and put the sand box into the positioning slots.
(7)铺设操作平台:为施工方便,保证施工安全,在分配梁上横桥向铺设5cm厚木板作为施工平台,在分配梁两端焊接短钢筋,待分配梁铺设完毕后插上钢管,钢管高度为1.5m,横向每隔30cm设置横杆一道,栏杆外侧采用防护网围挡。(7) Laying operation platform: For the convenience of construction and to ensure the safety of construction, 5cm thick wooden boards are laid across the bridge on the distribution beam as a construction platform, and short steel bars are welded at both ends of the distribution beam. After the distribution beam is laid, insert steel pipes and steel pipes The height is 1.5m, and a horizontal bar is set every 30cm in the horizontal direction, and the outer side of the railing is surrounded by a protective net.
(8)安装三脚架:为加快施工速度,盖梁底模下支架采用[14槽钢双肢组合焊接桁架,因盖梁下锚槽张拉需要,每侧翼缘采用两片支架,中间预留张拉空间。安装时单片吊装,待两片全部就位后采用[14槽钢作为剪刀撑及横梁,位置设置在桁架立杆处,采用销子连接。(8) Install the tripod: In order to speed up the construction, the lower support of the bottom formwork of the cover beam adopts [14 channel steel double-leg combined welding trusses. Pull space. Single-piece hoisting during installation, after the two pieces are all in place, [14 channel steel is used as scissors brace and beam, and the position is set at the truss pole and connected by pins.
本实用新型的有益效果是:The beneficial effects of the utility model are:
(1)采用组合桁架施工,其下立柱直接立于承台之上,无需进行基础处理。(1) The composite truss is used for construction, and the lower column stands directly on the cap platform without foundation treatment.
(2)因无需地基处理,既节约成本,又缩短盖梁施工周期。(2) Because there is no need for foundation treatment, it not only saves costs, but also shortens the construction period of the cap beam.
(3)施工所用桁架组件可进行现场拼装后,进行模块化拆装,施工速度大大提高。(3) The truss components used in construction can be assembled on site, and then modularized and disassembled, which greatly improves the construction speed.
(4)支架与墩柱通过横联进行绑定,结构整体稳定性好、安全系数高。(4) The support and pier columns are bound through cross-connections, so the overall stability of the structure is good and the safety factor is high.
(5)整个支架体系均采用刚性材料且均为刚性连接,并支撑在承台之上,所以整个支架体系安装后无沉降。(5) The entire support system is made of rigid materials and is rigidly connected, and supported on the platform, so the entire support system has no settlement after installation.
(6)该支架加工成模块化,可针对不同高度墩柱调节支腿高度后都可应用。(6) The bracket is processed into a modular form, which can be applied after adjusting the height of the outriggers for pier columns of different heights.
(7)采用该支架体系施工时,只需配备一台25t汽车吊和2~4名工人,节省人工。(7) When using this bracket system for construction, it only needs to be equipped with a 25t truck crane and 2 to 4 workers, saving labor.
(8)该支架可循环使用,且周转方便。(8) The bracket can be recycled, and the turnover is convenient.
附图说明Description of drawings
图1是本实用新型的组合桁架支架体系搭设后整体正立面示意图。Figure 1 is a schematic diagram of the overall front elevation of the composite truss support system of the present invention after erection.
图2是本实用新型的组合桁架支架上横梁分配梁锁定安装示意图。Fig. 2 is a schematic diagram of locking and installation of the upper beam distribution beam of the composite truss support of the present invention.
图3是本实用新型的组合桁架支架体系支腿安装示意图。Fig. 3 is a schematic diagram of installation of legs of the combined truss support system of the present invention.
其中:1—承台;2—立柱横联;3—墩柱;4—盖梁底模;5—下立柱;6—下横梁;7—销子;8—横梁横联及斜撑;9—分配梁;10—斜撑;11—上立柱;12—横联;13—剪刀撑;14—上横梁;15—砂箱;16—三角托架;17—精轧螺纹钢;18—压板;:19—螺母;20—木楔子。Among them: 1—cap; 2—column cross connection; 3—pier column; 4—cover beam bottom mold; 5—lower column; 6—lower beam; 7—pin; 8—beam cross connection and diagonal brace; 9 — distribution beam; 10 — diagonal brace; 11 — upper column; 12 — cross connection; 13 — scissors brace; 14 — upper beam; 15 — sand box; 16 — triangular bracket; ;: 19—nut; 20—wooden wedge.
具体实施方式detailed description
下面结合附图和具体实施例对本实用新型加以详细说明。The utility model is described in detail below in conjunction with accompanying drawing and specific embodiment.
如附图1所示的本实用新型的一种在软弱地基中施工的大悬臂盖梁的组合桁架支架,该组合桁架支架体系采用缀板格构式组合桁架支架法,整个支架体系主要分为下支腿、组合桁架、分配梁9、砂箱15和三脚托架165个模块,安装时利用槽钢和螺栓将5个模块由下到上依次连接成一个整体,下面2个模块由承台1上的4个格构式立柱组成,立柱分下立柱5和上立柱11,下立柱5采用32c槽钢组合焊接,上立柱11采用22b槽钢组合焊接,立柱间用[14槽钢横向立柱横联2连接,下立柱5与上立柱11间的横梁为下横梁6,上立柱11上面的横梁为上横梁14,上横梁14采用40双工字钢组焊,上横梁14上按支架竖向杆件位置布设用于支撑盖梁三角托架16及设置工作平台的18a工字钢制成的分配梁9;为进行盖梁模板高度微调,在分配梁9和三角托架16之间设置方形砂箱15,砂箱15平面尺寸为35cm×35cm,调节高度范围为22~32cm;三角托架16上方为盖梁底模4,为防止上横梁14端头部分下挠过大,使用[28双槽钢斜撑10将上横梁14与[28双槽钢下横梁6端头以销子7铰接,同时在前后面斜撑10之间均用[28槽钢横向横联12连接,并设置剪刀撑13,前后面上横梁之间和下横梁之间焊接[28槽钢横梁横联及斜撑8。As shown in accompanying drawing 1, a composite truss support of a large cantilever cover beam of the utility model constructed in a weak foundation, the composite truss support system adopts the panel lattice type combined truss support method, and the whole support system is mainly divided into There are 165 modules including lower outriggers, composite trusses, distribution beams 9, sand boxes 15 and tripod brackets. When installing, use channel steel and bolts to connect the 5 modules from bottom to top to form a whole. 1 is composed of 4 lattice columns, the columns are divided into lower column 5 and upper column 11, the lower column 5 is welded by 32c channel steel combination, the upper column 11 is welded by 22b channel steel combination, and [14 channel steel horizontal column is used between the columns The horizontal connection 2 is connected, the beam between the lower column 5 and the upper column 11 is the lower beam 6, the beam above the upper column 11 is the upper beam 14, the upper beam 14 is welded with 40 double I-beams, and the upper beam 14 is vertically pressed by the bracket. Arrange the distribution beam 9 made of 18a I-beam for supporting the cover beam triangular bracket 16 and setting the working platform to the position of the bar; Square sand box 15, the plane size of sand box 15 is 35cm × 35cm, and the adjustable height range is 22 to 32cm; the top of the triangle bracket 16 is the cover beam bottom mold 4, in order to prevent the end part of the upper beam 14 from being too large, use [ 28 double-channel steel diagonal braces 10 hinge the upper beam 14 and [28 double-channel steel lower beam 6 ends with pins 7, and simultaneously connect the front and rear diagonal braces 10 with [28 channel steel horizontal cross-links 12, and Scissor braces 13 are set, and welding [28 channel steel beam cross-links and diagonal braces 8 between the beams on the front and rear surfaces and between the lower beams.
一种在软弱地基中施工的大悬臂盖梁的组合桁架支架的施工方法,包括以下步骤:A construction method for a composite truss support of a large cantilever cap beam constructed in a weak foundation, comprising the following steps:
(1)清理承台:支架安装前需将承台1顶面杂物清理干净,保证支架支腿可与承台1直接接触并保证支架受力稳定。(1) Cleaning the platform: Before the bracket is installed, the sundries on the top surface of the platform 1 must be cleaned to ensure that the legs of the bracket can directly contact with the platform 1 and ensure that the support is stable under force.
(2)确定支架高度:根据墩柱3设计高度确定需要安装支腿的组合方案,支腿有高度为2m、1m和0.3m三种型号。(2) Determining the height of the support: According to the design height of the pier column 3, determine the combination scheme that needs to be installed with outriggers. The outriggers have three models with a height of 2m, 1m and 0.3m.
(3)下支腿安装:根据计算所确定的支腿组合方案,先安装2m高度的支腿,剩余高度小于2m时再安装1m和0.3m支腿,安装,时利用汽车吊将支腿套装在墩柱3上,再对其平面位置进行微调,位置确定后在支腿与墩柱3之间用木楔子塞进固定,如图3所示,上下两节支腿用螺栓连接。(3) Installation of lower outriggers: According to the outrigger combination plan determined by calculation, first install outriggers with a height of 2m, and then install outriggers with a height of 1m and 0.3m when the remaining height is less than 2m. When installing, use a car crane to set the outriggers On the pier column 3, fine-tune its plane position. After the position is determined, use wooden wedges to insert and fix between the outrigger and the pier column 3. As shown in Figure 3, the upper and lower sections of the outriggers are connected with bolts.
(4)组合桁架安装:将事先组装好的一片组合桁架整体利用汽车吊吊装至支腿上,用手拉葫芦将其与墩柱3临时固定,待2片组合桁架全部吊装至支腿上以后,利用槽钢和剪刀撑13将2片组合桁架连接固定。(4) Composite truss installation: hoist a piece of pre-assembled composite truss onto the outrigger with a truck crane, temporarily fix it with the pier column 3 with a chain block, and wait until all the two composite trusses are hoisted to the outrigger , use channel steel and scissors support 13 to connect and fix the two composite trusses.
(5)分配梁安装:上横梁14上的分配梁9放置在三角托架16每个竖向支撑处,并排3根,每根分配梁9长4.5m,为保证支架整体稳定,将分配梁9与上横梁14之间采用Φ25精轧螺纹钢17配合[10槽钢压板18进行锁定,如图2所示。(5) Distribution beam installation: the distribution beam 9 on the upper beam 14 is placed on each vertical support of the triangular bracket 16, 3 in a row, and each distribution beam 9 is 4.5m long. In order to ensure the overall stability of the support, the distribution beam 9 and the upper beam 14 are locked with Φ25 finish-rolled rebar 17 and [10 channel steel platen 18, as shown in Figure 2.
(6)安装砂箱:砂箱15安装位置根据图纸设置,为防止砂箱15侧滑,分配梁9上使用L50×50角钢焊接定位槽,将砂箱15放入定位槽内。(6) Install the sand box: The installation position of the sand box 15 is set according to the drawings. In order to prevent the sand box 15 from sliding sideways, use L50×50 angle steel welding positioning slots on the distribution beam 9, and put the sand box 15 into the positioning slots.
(7)铺设操作平台:为施工方便,保证施工安全,在分配梁9上横桥向铺设5cm厚木板作为施工平台,在分配梁两端焊接短钢筋,待分配梁9铺设完毕后插上钢管,钢管高度为1.5m,横向每隔30cm设置横杆一道,栏杆外侧采用防护网围挡。(7) Lay the operation platform: for the convenience of construction and to ensure the safety of construction, a 5cm thick plank is laid on the distribution beam 9 as a construction platform, and short steel bars are welded at both ends of the distribution beam. After the distribution beam 9 is laid, the steel pipes are inserted. , the height of the steel pipe is 1.5m, and a horizontal bar is set every 30cm in the horizontal direction, and the outer side of the railing is surrounded by a protective net.
(8)安装三脚架:为加快施工速度,盖梁底模4下支架采用[14槽钢双肢组合焊接桁架,因盖梁下锚槽张拉需要,每侧翼缘采用两片支架,中间预留张拉空间。安装时单片吊装,待两片全部就位后采用[14槽钢作为剪刀撑及横梁,位置设置在桁架立杆处,采用销子7连接。(8) Install the tripod: In order to speed up the construction, the 4 lower brackets of the bottom formwork of the cover beam adopt [14 channel steel double-leg combined welding trusses. Due to the tension of the lower anchor groove of the cover beam, two pieces of brackets are used for each side flange, and the middle is reserved. Tensile space. Single-piece hoisting during installation, after the two pieces are all in place, [14 channel steel is used as scissors brace and beam, the position is set at the truss pole, and the pin 7 is used to connect.
Claims (5)
- null1. the composite roof truss support of a great cantilever bent cap,It is characterized in that,Use batten plate lattice composite roof truss support,Whole strutting system is broadly divided into lower supporting leg、Composite roof truss、Distribution beam (9)、Sandbox (15) and (16) 5 modules of three footrest framves,Utilize channel-section steel and bolt that 5 modules are in turn connected into an entirety from down to up during installation,2 modules are made up of 4 lattice columns on cushion cap (1) below,Column divides lower pillar stand (5) and upper pillar stand (11),Crossbeam between lower pillar stand (5) and upper pillar stand (11) is sill (6),Upper pillar stand (11) crossbeam above is entablature (14),Entablature (14) uses 40 pairs of I-steel assembly weldings,Lay for supporting bent cap shelf bracket and arranging the distribution beam (9) of work platforms by support vertical bar position on entablature (14);Square sandbox (15) is arranged between distribution beam (9) and shelf bracket (16), shelf bracket (16) is arranged above bent cap bed die (4), entablature (14) is hinged with pin (7) by diagonal brace (10) with sill (6) termination, all connect with horizontal horizontal-associate (12) between front-back diagonal brace (10) simultaneously, and bridging (13) is set, welding beam horizontal-associate and diagonal brace (8) between front-back entablature and between sill.
- The composite roof truss support of great cantilever bent cap the most according to claim 1, it is characterised in that described distribution beam (9) is made up of 18a I-steel.
- The composite roof truss support of great cantilever bent cap the most according to claim 1, it is characterized in that, described lower pillar stand (5) uses 32c channel-section steel Combination Welding, upper pillar stand (11) uses 22b channel-section steel Combination Welding, uses [14 channel-section steels transverse upright horizontal-associate (2) connections between front-back upper pillar stand and between lower pillar stand.
- The composite roof truss support of great cantilever bent cap the most according to claim 1, it is characterised in that described sandbox (15) planar dimension is 35cm × 35cm, regulation altitude range is 22~32cm.
- The composite roof truss support of great cantilever bent cap the most according to claim 1, it is characterized in that, described diagonal brace (10), horizontal-associate (12) and bridging (13), sill (6) and crossbeam horizontal-associate and diagonal brace (8) are [28 double flute steel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620167768.2U CN205443958U (en) | 2016-03-04 | 2016-03-04 | Composite truss support of big cantilever bent cap |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620167768.2U CN205443958U (en) | 2016-03-04 | 2016-03-04 | Composite truss support of big cantilever bent cap |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205443958U true CN205443958U (en) | 2016-08-10 |
Family
ID=56604967
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201620167768.2U Expired - Fee Related CN205443958U (en) | 2016-03-04 | 2016-03-04 | Composite truss support of big cantilever bent cap |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205443958U (en) |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107268967A (en) * | 2017-08-03 | 2017-10-20 | 北京城建六建设集团有限公司 | A kind of high-altitude English truss platform for construction |
| CN109208481A (en) * | 2018-09-11 | 2019-01-15 | 中国二十冶集团有限公司 | Sandbox and bent cap sectional shelf-unit mounting device |
| CN109267487A (en) * | 2018-10-15 | 2019-01-25 | 中建三局第二建设工程有限责任公司 | A kind of long big section bent cap bracket system of overhanging |
| CN110004832A (en) * | 2019-04-09 | 2019-07-12 | 宁波市政工程建设集团股份有限公司 | Long span cantilever truss formula bent cap strutting system and construction method |
| CN110184926A (en) * | 2019-05-14 | 2019-08-30 | 宁波市政工程建设集团股份有限公司 | A kind of public affairs rail is built together the overhead pier stud construction method of double-layer integrallyization |
| CN110512525A (en) * | 2019-08-23 | 2019-11-29 | 中交一航局第一工程有限公司 | A kind of detachable bent cap bed die bracket and its construction technology |
| CN113152283A (en) * | 2019-10-21 | 2021-07-23 | 宁波市政工程建设集团股份有限公司 | Construction method of cantilever or large-crotch-diameter support system of prefabricated small box girder type hidden cover beam of road bridge |
| CN114960433A (en) * | 2022-05-16 | 2022-08-30 | 中国十九冶集团有限公司 | Construction method for pouring working block at top of pier of steel bridge |
| CN115012309A (en) * | 2022-05-20 | 2022-09-06 | 中建八局第二建设有限公司 | Overhead supporting device for large cantilever bent cap and construction method |
| CN116180598A (en) * | 2023-02-09 | 2023-05-30 | 中铁大桥局集团有限公司 | Construction method for erecting ellipsoidal curtain wall outer frame by existing bridge tower top steel structure |
-
2016
- 2016-03-04 CN CN201620167768.2U patent/CN205443958U/en not_active Expired - Fee Related
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107268967A (en) * | 2017-08-03 | 2017-10-20 | 北京城建六建设集团有限公司 | A kind of high-altitude English truss platform for construction |
| CN109208481A (en) * | 2018-09-11 | 2019-01-15 | 中国二十冶集团有限公司 | Sandbox and bent cap sectional shelf-unit mounting device |
| CN109267487A (en) * | 2018-10-15 | 2019-01-25 | 中建三局第二建设工程有限责任公司 | A kind of long big section bent cap bracket system of overhanging |
| CN110004832A (en) * | 2019-04-09 | 2019-07-12 | 宁波市政工程建设集团股份有限公司 | Long span cantilever truss formula bent cap strutting system and construction method |
| CN110004832B (en) * | 2019-04-09 | 2024-03-05 | 宁波市政工程建设集团股份有限公司 | Large-span cantilever truss type bent cap bracket system and construction method |
| CN110184926A (en) * | 2019-05-14 | 2019-08-30 | 宁波市政工程建设集团股份有限公司 | A kind of public affairs rail is built together the overhead pier stud construction method of double-layer integrallyization |
| CN110512525A (en) * | 2019-08-23 | 2019-11-29 | 中交一航局第一工程有限公司 | A kind of detachable bent cap bed die bracket and its construction technology |
| CN113152283A (en) * | 2019-10-21 | 2021-07-23 | 宁波市政工程建设集团股份有限公司 | Construction method of cantilever or large-crotch-diameter support system of prefabricated small box girder type hidden cover beam of road bridge |
| CN113152283B (en) * | 2019-10-21 | 2022-06-10 | 宁波市政工程建设集团股份有限公司 | Construction method of large-crotch-diameter supporting system of small box girder type hidden cover beam prefabricated on road and bridge |
| CN114960433A (en) * | 2022-05-16 | 2022-08-30 | 中国十九冶集团有限公司 | Construction method for pouring working block at top of pier of steel bridge |
| CN115012309A (en) * | 2022-05-20 | 2022-09-06 | 中建八局第二建设有限公司 | Overhead supporting device for large cantilever bent cap and construction method |
| CN116180598A (en) * | 2023-02-09 | 2023-05-30 | 中铁大桥局集团有限公司 | Construction method for erecting ellipsoidal curtain wall outer frame by existing bridge tower top steel structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN205443958U (en) | Composite truss support of big cantilever bent cap | |
| CN215254604U (en) | Template support system encorbelments | |
| CN106939707B (en) | A kind of restricted clearance large-scale steel structure supporting platform from method for improving | |
| CN112411391A (en) | A single-column cover beam steel pipe column Bailey beam construction support system and construction method | |
| CN106677070A (en) | Construction support and method for overhead large-span heavy-duty cross beam | |
| JP7370626B2 (en) | Side span support structure for a continuous T-girder viaduct spanning the existing railway line | |
| CN113585075A (en) | Cast-in-place bridge deck formwork for steel-concrete composite beam | |
| CN110409624A (en) | A large-scale equipment installation and main structure reverse calculation and construction method | |
| CN207974601U (en) | A kind of large size earthing concrete tank dome steel support structure | |
| CN215482366U (en) | Double-line continuous beam bracket structure | |
| CN206607506U (en) | A kind of through type adds the capping construction support of passive stress trapezoid block | |
| CN112267369A (en) | Non-span upright post steel trestle structure, pushing installation device and construction method | |
| CN212925807U (en) | Cast-in-place continuous box girder side span straightway template support system | |
| CN103321155A (en) | Viaduct pier construction platform system and method for building system and pouring piers | |
| CN210049103U (en) | High-grade high-speed highway bracket spanned by large-span cast-in-place box girder | |
| CN112726411A (en) | Integral dragging construction method for single-hole large cantilever steel truss girder | |
| CN203307733U (en) | Construction platform system of concrete pier of viaduct | |
| CN102518041B (en) | Construction method of support system for overhead continuous beam form-erecting falsework | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN212426772U (en) | Suspended bracket system for cast-in-place bridge deck of steel plate composite beam | |
| CN112962427A (en) | Off-standard span cast-in-place beam support across valley and construction method | |
| CN119041304A (en) | Large cantilever bent cap lower chord reverse support bracket system and construction method thereof | |
| CN102797224B (en) | Paving method and template supporting device of bridge deck slab | |
| CN217810545U (en) | Construction system for steel truss girder bridge | |
| CN212452288U (en) | A steel-concrete composite beam concrete bridge deck construction support |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160810 Termination date: 20210304 |