CN104047214A - 采用风积沙填筑的路基施工方法 - Google Patents

采用风积沙填筑的路基施工方法 Download PDF

Info

Publication number
CN104047214A
CN104047214A CN201410326223.7A CN201410326223A CN104047214A CN 104047214 A CN104047214 A CN 104047214A CN 201410326223 A CN201410326223 A CN 201410326223A CN 104047214 A CN104047214 A CN 104047214A
Authority
CN
China
Prior art keywords
pressure
water
aeolian sand
sand
roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410326223.7A
Other languages
English (en)
Inventor
付宗波
杨小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201410326223.7A priority Critical patent/CN104047214A/zh
Publication of CN104047214A publication Critical patent/CN104047214A/zh
Pending legal-status Critical Current

Links

Abstract

本发明涉及公路路基施工方法,具体是一种采用风积沙填筑的路基施工方法。其步骤是:每层风积沙填筑完成打格筑埂,然后进行洒水;洒水量按上层饱水、下层半饱水状态控制,饱和水状态时的含水量控制在16-20%之间,佳含水量控制在8-12%之间;风积沙上层洒水至饱和状态后进行施压,施压分稳压、振压和终压三个阶段,稳压:用推土机或静压设备静压一遍;振压:用振动压路机振动压实4-6遍;终压:用静压设备静压两遍。本发明以水为结合料,在风积沙饱水状态下,通过机械施压,使风积沙的颗粒重新排列,小颗粒紧密地嵌入大颗粒之间,从而达到密实,形成稳定、可靠的路基,解决了风积沙地区缺乏筑路材料问题,为风积沙资源利用提供了途径。

Description

采用风积沙填筑的路基施工方法
技术领域
本发明涉及公路路基施工方法,具体是一种采用风积沙填筑的路基施工方法。
背景技术
路基填料问题一直制约着我国西部、北部等边远地区的公路建设,而这些地区广泛存在着风积沙,将风积沙利用起来作为路基填料,不仅能够治理沙害,更是解决填料短缺这一问题的有效途径。但风积沙材料具有级配不良、抗剪强度低和无粘聚性等特点,碾压过程中不易形成密实的结构,施工质量难以控制,施工周期较长,一定程度上制约了风积沙路基施工的发展前景。
发明内容
本发明针对上述问题,提供一种采用风积沙填筑的路基施工方法,该方法施工速度快、工期短、减少施工成本,风积沙材料能够达到固定的密实度,保证路基填筑施工质量。
本发明解决所述问题采用的技术方案是:
一种采用风积沙填筑的路基施工方法,按以下步骤进行:
(1)每层风积沙填筑完成后用人工将填料打格筑埂,路基两侧间隔设置水井,利用水泵及水管直接将水抽至路基上进行洒水;
(2)洒水过程中控制水压及喷洒速度,使喷水均匀,呈散射状,使水有充分的渗透时间;洒水量按上层饱水、下层半饱水状态控制,风积沙达到饱和水状态时的含水量控制在16-20%之间,风积沙的最佳含水量控制在8-12%之间;
(3)风积沙上层洒水至饱和状态后进行施压,施压在2-3小时内完成;施压前,先检查含水量,含水量控制在比最佳含水量高1-2%,施压分稳压、振压和终压三个阶段:
稳压:用推土机或静压设备静压一遍;
振压:用振动压路机振动压实4-6遍,碾压时,压路机由慢到快,直线段由两边向中间,小半径曲线段由内侧向外侧,纵向进退式进行,轮迹重叠宽度不            
小于1/3,前后相邻两区段纵向重叠2m以上,应达到无漏压、无死角,碾压均匀;
终压:用静压设备静压两遍。
采用上述技术方案的本发明,与现有技术相比,其突出的效果是:
本发明利用水为结合料,对无塑性级配不良的风积沙在饱水状态下,通过机械施压,使风积沙的颗粒重新排列,小颗粒紧密地嵌入大颗粒之间,从而达到密实,形成稳定、可靠的路基,解决了沙漠地区缺乏筑路材料问题,为风积沙资源利用找到了很好的途径,使之变废为宝,同时减少沙害,保护植被地貌。其次,采用此方法,在保证施工质量的前提下,增加了松铺厚度,减少了压实遍数,扣除使用的施工用水等消耗,降低了路基填料的材料成本。本发明有广阔的推广使用价值。
附图说明
图1为本发明实施例所述的筑埂洒水平面布置示意图。
图2为本发明实施例所述的碾压振动立面布置示意图。
图中:1-水井,2-水泵及水管,3-筑埂,4-静压设备,5-振动压路机。
具体实施方式
以下结合附图及实施例详述本发明,目的仅在于更好的理解本发明内容。
本实施例所述的这种采用风积沙填筑的路基施工方法,按以下步骤进行:
(1)如图1所示,每层风积沙填筑完成后用人工将填料打格筑埂3,埂高15cm左右,面积20-30m2,再进行洒水。由于水车在路基上不能行走,因此,洒水主要利用水泵及水管2直接将水抽至路基上。路基两侧间隔设置水井1,水井间距一般约100-150m。
(2)洒水区段长度控制在50-100m为宜,过长的区段会使水的蒸发过程持续时间长,造成反复洒水从而浪费水资源。洒水量以上层饱水、下层半饱水状态控制为宜。洒水过程中水压不可过大,喷洒速度不可太急。尽量使喷水均匀,呈散射状,使水有充分的渗透时间。
(3)根据试验数据,风积沙的最佳含水量约为8-12%,而使风积沙达到饱和水状态时的含水量在16-20%之间,再根据填筑长度、宽度和厚度,计算出每段风积沙填料所需洒水的大致数量。最后,根据洒水设备功效,确定打格培埂的尺寸面积,并计算和控制好每个方格内洒水时间,避免洒水不到位造成返工或洒水过量造成水资源及机械使用的浪费。试验路段以50-100m路段计算洒水量,每段配备两台3-5.5Kw水泵,一般在2-3小时内将该区段上层风积沙洒水至饱和状态,则可进行下步施压工序。
(4)施压工序:
施压前,先检查含水量,含水量控制在比最佳含水量高1-2%,压实区域以50-80m作为一个施压段,施压分稳压、振压和终压三个阶段。
稳压:用静压设备4或推土机静压一遍;
振压:用振动压路机5振动压实4-6遍,碾压时,压路机由慢到快,直线段由两边向中间,小半径曲线段由内侧向外侧,纵向进退式进行,轮迹重叠宽度不            
小于1/3,前后相邻两区段纵向重叠2m以上,应达到无漏压、无死角,碾压均匀。
终压:用静压设备4静压两遍。
在保证路基各项质量要求的前提下,通过优化控制上述施工工艺,能够确保施工质量的提高、减少用水量,达到降本增效的目的。

Claims (1)

1.一种采用风积沙填筑的路基施工方法,其特征在于,按以下步骤进行:
(1)每层风积沙填筑完成后用人工将填料打格筑埂,路基两侧间隔设置水井,利用水泵及水管直接将水抽至路基上进行洒水;
(2)洒水过程中控制水压及喷洒速度,使喷水均匀,呈散射状,使水有充分的渗透时间;洒水量按上层饱水、下层半饱水状态控制,风积沙达到饱和水状态时的含水量控制在16-20%之间,风积沙的最佳含水量控制在8-12%之间;
(3)风积沙上层洒水至饱和状态后进行施压,施压在2-3小时内完成;施压前,先检查含水量,含水量控制在比最佳含水量高1-2%,施压分稳压、振压和终压三个阶段:
稳压:用推土机或静压设备静压一遍;
振压:用振动压路机振动压实4-6遍,碾压时,压路机由慢到快,直线段由两边向中间,小半径曲线段由内侧向外侧,纵向进退式进行,轮迹重叠宽度不            
小于1/3,前后相邻两区段纵向重叠2m以上,应达到无漏压、无死角,碾压均匀;
终压:用静压设备静压两遍。
CN201410326223.7A 2014-07-10 2014-07-10 采用风积沙填筑的路基施工方法 Pending CN104047214A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410326223.7A CN104047214A (zh) 2014-07-10 2014-07-10 采用风积沙填筑的路基施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410326223.7A CN104047214A (zh) 2014-07-10 2014-07-10 采用风积沙填筑的路基施工方法

Publications (1)

Publication Number Publication Date
CN104047214A true CN104047214A (zh) 2014-09-17

Family

ID=51500587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410326223.7A Pending CN104047214A (zh) 2014-07-10 2014-07-10 采用风积沙填筑的路基施工方法

Country Status (1)

Country Link
CN (1) CN104047214A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452507A (zh) * 2014-11-28 2015-03-25 中铁二十三局集团有限公司 使用风积沙填筑路基施工方法
CN105544335A (zh) * 2016-02-03 2016-05-04 中交第一公路勘察设计研究院有限公司 厚层风积沙路基填筑压实施工方法
CN106012732A (zh) * 2016-06-12 2016-10-12 中国十七冶集团有限公司 一种风积沙填料路基的施工方法
CN107653758A (zh) * 2017-08-18 2018-02-02 中交第四公路工程局有限公司 红土包边风积沙路基填筑施工方法
CN107938453A (zh) * 2016-10-12 2018-04-20 新疆铁道勘察设计院有限公司 采用粉细砂作为路基填料的施工工艺
CN113882222A (zh) * 2021-11-19 2022-01-04 中国化学工程第七建设有限公司 一种用于沙漠地区道路填前原地面的压实方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101608419A (zh) * 2009-07-21 2009-12-23 中铁二十一局集团有限公司 沙漠地区流动沙丘地带铁路路基施工方法
CN101962928A (zh) * 2010-08-12 2011-02-02 中铁二十二局集团第一工程有限公司 冲击碾压处理风积沙路基基底的施工工法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101608419A (zh) * 2009-07-21 2009-12-23 中铁二十一局集团有限公司 沙漠地区流动沙丘地带铁路路基施工方法
CN101962928A (zh) * 2010-08-12 2011-02-02 中铁二十二局集团第一工程有限公司 冲击碾压处理风积沙路基基底的施工工法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘刚等: "浅谈风积沙填筑路基施工工艺", 《黑龙江交通科技》 *
喻江武: "风积沙路基施工技术浅析", 《交通科技》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452507A (zh) * 2014-11-28 2015-03-25 中铁二十三局集团有限公司 使用风积沙填筑路基施工方法
CN105544335A (zh) * 2016-02-03 2016-05-04 中交第一公路勘察设计研究院有限公司 厚层风积沙路基填筑压实施工方法
CN105544335B (zh) * 2016-02-03 2017-12-05 中交第一公路勘察设计研究院有限公司 厚层风积沙路基填筑压实施工方法
CN106012732A (zh) * 2016-06-12 2016-10-12 中国十七冶集团有限公司 一种风积沙填料路基的施工方法
CN107938453A (zh) * 2016-10-12 2018-04-20 新疆铁道勘察设计院有限公司 采用粉细砂作为路基填料的施工工艺
CN107653758A (zh) * 2017-08-18 2018-02-02 中交第四公路工程局有限公司 红土包边风积沙路基填筑施工方法
CN113882222A (zh) * 2021-11-19 2022-01-04 中国化学工程第七建设有限公司 一种用于沙漠地区道路填前原地面的压实方法

Similar Documents

Publication Publication Date Title
CN104047214A (zh) 采用风积沙填筑的路基施工方法
JP4808241B2 (ja) 地盤改良工法および地盤改良装置
CN104452507A (zh) 使用风积沙填筑路基施工方法
CN105220590A (zh) 多溶洞塌陷路基注浆处理法
CN106835884A (zh) 一种高填方段永久路基施工方法
CN104179105B (zh) 一种逆作法刚性桩复合地基施工方法
CN108999058A (zh) 一种人造草坪的施工方法
CN105951672B (zh) 一种新型堤岸与护坡的施工工艺
CN206815127U (zh) 软基区临时便道铺设结构
CN108570909A (zh) 一种粉细砂路基的填筑压实方法
CN205591066U (zh) 细粒土收坡路堤填筑结构
CN107151960A (zh) 软基区临时便道铺设结构及铺设方法
CN106436523A (zh) 一种利用再生骨料生产的新结构植草砖
CN107503370B (zh) 一种沙井复合式加筋土高挡墙及制作方法
CN109137659A (zh) 渣土类建筑废弃物填筑高速公路路基的施工方法
CN109537385A (zh) 粉砂土填筑路基施工工艺
CN105484230A (zh) 桩土混凝一体化复合桩及其施工方法
CN206157760U (zh) 一种具有生态恢复功能的蜂窝土工格室挡土墙
CN111893828A (zh) 一种机制砂改良高液限土路基填筑施工方法
CN107447617A (zh) 一种临时施工道路的防尘固化工艺
CN203625741U (zh) 一种填筑尾矿砂的路基
CN103806434B (zh) 一种级配建渣土工袋处理钻前工程饱和过湿土地基的方法
CN103195077B (zh) 一种坝基加固框架结构和坝基加固方法
CN109610244A (zh) 细粉砂物理改良的路基填筑方法
CN105603842A (zh) 路堤大厚度填砂施工工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140917