CN103922232A - 一种自升式塔机降塔工艺 - Google Patents

一种自升式塔机降塔工艺 Download PDF

Info

Publication number
CN103922232A
CN103922232A CN201410147142.0A CN201410147142A CN103922232A CN 103922232 A CN103922232 A CN 103922232A CN 201410147142 A CN201410147142 A CN 201410147142A CN 103922232 A CN103922232 A CN 103922232A
Authority
CN
China
Prior art keywords
tower
tower crane
fulcrum
center
distance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410147142.0A
Other languages
English (en)
Other versions
CN103922232B (zh
Inventor
丁华
顾龙
顾建华
张卫东
黄金保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd
Original Assignee
NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd filed Critical NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd
Priority to CN201410147142.0A priority Critical patent/CN103922232B/zh
Publication of CN103922232A publication Critical patent/CN103922232A/zh
Application granted granted Critical
Publication of CN103922232B publication Critical patent/CN103922232B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

本发明涉及一种自升式塔机降塔工艺,包括以下步骤:将塔机起重臂旋转到反向降塔的位置;计算旋转180°后的塔机配平,使塔机结构平衡的条件为塔机各结构对顶升支点的力矩和为零;计算塔机配平后,观察顶升爬架导向轮与标准节主弦杆的距离是否一致来判断是否配平,如有不平时,通过移动载重小车的位置来调整塔机的配平;降节;吊运:在塔机的平衡臂底部安装一台电动葫芦,用以吊运引进平台上的标准节,直至吊运至地面。本发明具有保证钢丝绳不会脱槽,使用方便,保证塔机安全运行的优点。

Description

一种自升式塔机降塔工艺
技术领域
本发明涉及一种自升式塔机降塔工艺。
背景技术
自升式塔机,在顶升和降节时起重臂的方向必须是一致的。也就是说在塔机安装时就已经决定了起重臂的方向,在以后的顶升和降节时起重臂的方向不能进行变化。
在建筑施工现场,塔机的安装往往比较容易,但是,在建筑物施工完成,在塔机安装前因疏漏,可能会造成塔机大臂与建筑物有干涉,从而造成塔机拆卸时无法按正常操作过程进行降节。
发明内容
本发明的目的是为了克服以上的不足,提供一种通过将起重臂旋转180度,这样平衡臂比起重臂短,不容易碰到建筑物,起重臂也不会碰到建筑物,就可以进行降节操作的自升式塔机降塔工艺。
本发明的目的通过以下技术方案来实现:一种自升式塔机降塔工艺,包括以下步骤:
A、将塔机起重臂旋转到反向降塔的位置;
B、计算旋转180°后的塔机配平,使塔机结构平衡的条件为塔机各结构对顶升支点的力矩和为零;
C、计算塔机配平后,观察顶升爬架导向轮与标准节主弦杆的距离是否一致来判断是否配平,如有不平时,通过移动载重小车的位置来调整塔机的配平;
D、降节;
E、吊运:在塔机的平衡臂底部安装一台电动葫芦,用以吊运引进平台上的标准节,直至吊运至地面。
本发明的进一步改进在于:步骤C中的计算配平具体为:
a、计算支点左侧力矩和:起重臂的重量×(起重臂重心到塔吊中心之间的距离-顶升支点到塔吊中心之间的距离)+载重小车及吊物力矩;
b、计算支点右侧力矩和:支点右侧荷载有塔身部分的重量×顶升支点到塔吊中心之间的距离+平衡臂重量×(平衡臂重心+顶升支点到塔吊中心之间的距离)+平衡重重量×(配重重心到塔吊中心之间的距离+顶升支点到塔吊中心之间的距离);
c、判断支点左侧力矩和与支点右侧力矩和是否相等,在左右支点力矩不相等时,通过改变载重小车及吊物的力矩或者改变塔机平衡重重量。
本发明的进一步改进在于:步骤F中的电动葫芦为2吨的电动葫芦。
本发明与现有技术相比具有以下优点:通过将起重臂旋转180度,这样平衡臂比起重臂短,不容易碰到建筑物,起重臂也不会碰到建筑物,就可以进行降节操作。
附图说明:
图1为塔机正常状态下的结构示意图;
图2为起重臂旋转180°后的结构示意图;
具体实施方式
为了加深对本发明的理解,下面将结合实施例和附图对本发明作进一步详述,该实施例仅用于解释本发明,并不构成对本发明保护范围的限定。
如图1和图2示出了本发明一种自升式塔机降塔工艺的具体实施方式,包括以下步骤:
A、将塔机起重臂旋转到反向降塔的位置即将起重臂旋转到与正常状态相比的反方向;
B、计算旋转180°后的塔机配平,使塔机结构平衡的条件为塔机各结构对顶升支点的力矩和为零;
C、计算塔机配平后,观察顶升爬架导向轮与标准节主弦杆的距离是否一致来判断是否配平,如有不平时,通过移动载重小车的位置来调整塔机的配平;
D、降节;
E、吊运:在塔机的平衡臂底部安装一台电动葫芦,用以吊运引进平台上的标准节,直至吊运至地面。
步骤C中的计算配平具体为:
a、计算支点左侧力矩和:起重臂的重量×(起重臂重心到塔吊中心之间的距离-顶升支点到塔吊中心之间的距离)+载重小车及吊物力矩;
b、计算支点右侧力矩和:支点右侧荷载有塔身部分的重量×顶升支点到塔吊中心之间的距离+平衡臂重量×(平衡臂重心+顶升支点到塔吊中心之间的距离)+平衡重重量×(配重重心到塔吊中心之间的距离+顶升支点到塔吊中心之间的距离);
c、判断支点左侧力矩和与支点右侧力矩和是否相等,在左右支点力矩不相等时,通过改变载重小车及吊物的力矩或者改变塔机平衡重重量。
如图2所示,支点左侧的荷载有起重臂的重量G1和载重小车及所吊重物的重量,G1为6.25吨。支点右侧的荷载有塔身部分的重量G2、平衡臂重量G3及平衡重重量G4,G2为9.38吨、G3为4.5吨、G4为15.3吨。设平衡臂重心到塔吊重心之间的距离为S1,顶升支点到塔吊重心之间的距离为S2,S1为20.59m,S2为0.8m,配重重心到塔吊重心之间的距离S3,S3为11.29m,这样支点左侧力矩和为:6.25×(20.59-0.8)+载重小车及吊物力矩,支点右侧力矩和为:9.38×0.8+4.5×(7.12+0.8)+15.3×(11.29+0.8)=228.121吨·米
这样:载重小车及吊物力矩=228.121-6.25×(20.59-0.8)=104.434吨·米。
如载重小车运行到20.59米的位置需吊5.28吨的重物才可以使塔机上部构件重心移到顶升支点位置。
降节时标准节按操作会留驻在引进平台上,引进平台只可以安放一节标准节,所以在降节操作完毕,回转固定在塔身标准节上后,常规操作由载重小车吊运到地面。在这儿,引进平台在平衡臂下方,无法利用载重小车将引进平台上的标准节吊运到地面。考虑在平衡臂底部安装一台2吨的电动葫芦,用以吊运标准节,这样通过以上的改变,塔机起重臂旋转180度的情况下可进行降节操作。

Claims (3)

1.一种自升式塔机降塔工艺,其特征在于,包括以下步骤:
A、将塔机起重臂旋转到反向降塔的位置;
B、计算旋转180°后的塔机配平,使塔机结构平衡的条件为塔机各结构对顶升支点的力矩和为零;
C、计算塔机配平后,观察顶升爬架导向轮与标准节主弦杆的距离是否一致来判断是否配平,如有不平时,通过移动载重小车的位置来调整塔机的配平;
D、降节;
E、吊运:在塔机的平衡臂底部安装一台电动葫芦,用以吊运引进平台上的标准节,直至吊运至地面。
2.根据权利要求1所述自升式塔机降塔工艺,其特征在于:步骤C中的计算配平具体为:
a、计算支点左侧力矩和:起重臂的重量×(起重臂重心到塔吊中心之间的距离-顶升支点到塔吊中心之间的距离)+载重小车及吊物力矩;
b、计算支点右侧力矩和:支点右侧荷载有塔身部分的重量×顶升支点到塔吊中心之间的距离+平衡臂重量×(平衡臂重心+顶升支点到塔吊中心之间的距离)+平衡重重量×(配重重心到塔吊中心之间的距离+顶升支点到塔吊中心之间的距离);
c、判断支点左侧力矩和与支点右侧力矩和是否相等,在左右支点力矩不相等时,通过改变载重小车及吊物的力矩或者改变塔机平衡重重量。
3.根据权利要求1所述自升式塔机降塔工艺,其特征在于:步骤F中的电动葫芦为2吨的电动葫芦。
CN201410147142.0A 2014-04-14 2014-04-14 一种自升式塔机降塔工艺 Active CN103922232B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410147142.0A CN103922232B (zh) 2014-04-14 2014-04-14 一种自升式塔机降塔工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410147142.0A CN103922232B (zh) 2014-04-14 2014-04-14 一种自升式塔机降塔工艺

Publications (2)

Publication Number Publication Date
CN103922232A true CN103922232A (zh) 2014-07-16
CN103922232B CN103922232B (zh) 2016-09-14

Family

ID=51140672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410147142.0A Active CN103922232B (zh) 2014-04-14 2014-04-14 一种自升式塔机降塔工艺

Country Status (1)

Country Link
CN (1) CN103922232B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108128712A (zh) * 2017-11-22 2018-06-08 中国二十冶集团有限公司 附着液压顶升系统的塔吊施工方法
CN109941897A (zh) * 2019-04-23 2019-06-28 广东大汉建设机械有限公司 一种塔机顶升方法
CN110094101A (zh) * 2018-01-31 2019-08-06 中国二十冶集团有限公司 受限空间下塔吊拆除标准节的方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101264850A (zh) * 2008-04-21 2008-09-17 湖南省第六工程公司 用于建筑物干涉塔机上部构件正常下落的塔机下降方法
RU2333883C1 (ru) * 2006-12-15 2008-09-20 Карл Вульфович Меркин Башенный кран и способ его монтажа и демонтажа
JP2010265727A (ja) * 2009-05-18 2010-11-25 Shimizu Corp フロアクライミング型タワークレーンを用いた建物解体方法
CN201670670U (zh) * 2010-05-12 2010-12-15 中建七局第三建筑有限公司 塔吊加、降节导向装置
CN202390113U (zh) * 2011-12-16 2012-08-22 西安市第四建筑工程公司 一种建筑用塔吊附着的起吊拆除装置
CN103523683A (zh) * 2013-10-16 2014-01-22 温州建设集团有限公司 利用小型起重机具拆卸塔机施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2333883C1 (ru) * 2006-12-15 2008-09-20 Карл Вульфович Меркин Башенный кран и способ его монтажа и демонтажа
CN101264850A (zh) * 2008-04-21 2008-09-17 湖南省第六工程公司 用于建筑物干涉塔机上部构件正常下落的塔机下降方法
JP2010265727A (ja) * 2009-05-18 2010-11-25 Shimizu Corp フロアクライミング型タワークレーンを用いた建物解体方法
CN201670670U (zh) * 2010-05-12 2010-12-15 中建七局第三建筑有限公司 塔吊加、降节导向装置
CN202390113U (zh) * 2011-12-16 2012-08-22 西安市第四建筑工程公司 一种建筑用塔吊附着的起吊拆除装置
CN103523683A (zh) * 2013-10-16 2014-01-22 温州建设集团有限公司 利用小型起重机具拆卸塔机施工方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
无: "塔式起重机基本知识培训", 《HTTP://WWW.DOCIN.COM/P-465876326.HTML》 *
栾晓成: "塔机逆向顶升分析研究", 《建设机械技术管理》 *
韩贵林: "塔机塔身加节与降节的安全因素", 《大众标准化》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108128712A (zh) * 2017-11-22 2018-06-08 中国二十冶集团有限公司 附着液压顶升系统的塔吊施工方法
CN110094101A (zh) * 2018-01-31 2019-08-06 中国二十冶集团有限公司 受限空间下塔吊拆除标准节的方法
CN109941897A (zh) * 2019-04-23 2019-06-28 广东大汉建设机械有限公司 一种塔机顶升方法
CN109941897B (zh) * 2019-04-23 2020-09-15 广东大汉建设机械有限公司 一种塔机顶升方法

Also Published As

Publication number Publication date
CN103922232B (zh) 2016-09-14

Similar Documents

Publication Publication Date Title
CN201228206Y (zh) 自制小型吊车
RU2709322C2 (ru) Кран, а также способ контроля устройства предохранения от перегрузок указанного крана
CN102259792B (zh) 一种改进型正交式水平自动调节吊具及其水平调节方法
CN203295034U (zh) 吊钩、卷扬装置、起重机和起重机偏摆预警装置
CN103883129B (zh) 一种钢结构屋面梁安装方法
CN102587288B (zh) 一种斜拉桥钢箱梁节段的吊装方法
CN104045006B (zh) 塔式起重机及其顶升自平衡控制系统和控制方法
CN102556835A (zh) 钢桁架桥杆件空间角度可调节吊具
CN103264952B (zh) 一种采用导杆吊装就位转炉塔楼汽包的施工方法
CN104140037A (zh) 墙板吊装系统
CN101934989A (zh) 动态平衡建筑塔式起重机
CN103922232A (zh) 一种自升式塔机降塔工艺
CN104495622A (zh) 一种风载控制系统、方法、装置及起重设备
CN103086276B (zh) 一种吊装高层井塔型建筑物内桥式起重机的施工方法
CN102992203B (zh) 一种钢结构桥梁安装用简易吊装装置
CN101660295A (zh) 拱桥的拱肋或梁体的顺桥向吊装方法及使用的扣索平衡轮
CN104234636B (zh) 自升式平台井架安装方法
CN104627849B (zh) 一种用于内天井管道吊装的吊装设备及吊装方法
CN105040592B (zh) 一种平拉索桥及其架设方法
RU143959U1 (ru) Мобильный стенд для испытаний грузоподъемных установок
CN202046786U (zh) 桩基础超长钢筋笼整体吊装臂
KR20050032069A (ko) 안전 타워 크레인
CN108408667A (zh) 折线型桁架梁杆件快速翻转装置及其翻转方法
CN106861882A (zh) 建筑物内球磨机倒运吊装的方法
JP5580721B2 (ja) 固定式ケーブルクレーンの運転方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant