CN104140037A - 墙板吊装系统 - Google Patents

墙板吊装系统 Download PDF

Info

Publication number
CN104140037A
CN104140037A CN201410368142.3A CN201410368142A CN104140037A CN 104140037 A CN104140037 A CN 104140037A CN 201410368142 A CN201410368142 A CN 201410368142A CN 104140037 A CN104140037 A CN 104140037A
Authority
CN
China
Prior art keywords
girder
lift
wallboard
executive device
displacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410368142.3A
Other languages
English (en)
Other versions
CN104140037B (zh
Inventor
吴秋冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING AOJIE WALL MATERIAL Co Ltd
Original Assignee
NANJING AOJIE WALL MATERIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING AOJIE WALL MATERIAL Co Ltd filed Critical NANJING AOJIE WALL MATERIAL Co Ltd
Priority to CN201410368142.3A priority Critical patent/CN104140037B/zh
Publication of CN104140037A publication Critical patent/CN104140037A/zh
Application granted granted Critical
Publication of CN104140037B publication Critical patent/CN104140037B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种墙板吊装系统,包括中部设置有吊装点的工字梁,设置于工字梁一端并可沿其纵向滑动的吊钩组件,固定于工字梁上的用于移动吊钩组件的第一位移执行装置,设置于工字梁另一端并可沿其纵向滑动的配重组件,固定于工字梁上的用于移动配重组件的第二位移执行装置,一端连接于吊装点、另一端连接于吊机的绳体,以及与第一位移执行装置和第二位移执行装置电连接的控制装置。采用本发明吊装墙板,基本不会受到现场作业面的限制,效率高,成本低,而且墙板在吊装过程中不会受到碰撞,导致损坏。

Description

墙板吊装系统
技术领域
本发明属于墙板施工领域,尤其是一种墙板吊装系统。 
背景技术
现有的墙板吊装方法有多种,例如,在大板最终位置的顶部安装葫芦,然后用人工抬或者小车推的方法,将大板运到安装位置,最后用葫芦吊装。又如,在建筑物的外壁上设置导轨和电动葫芦,电动葫芦与吊架连接,以此将墙板沿导轨运到规定位置。 
上述方法效率低,成本高,而且不便作业,在很多情况下难以开展工作,由于运输和现场作业面的限制,对大板的尺寸和重量有相当的要求,大板在运输和吊装的过程中很容易受损。 
发明内容
发明目的:提供一种墙板吊装系统,以解决现有技术的至少部分问题。 
技术方案:一种墙板吊装系统,包括中部设置有吊装点的工字梁,设置于工字梁一端并可沿其纵向滑动的吊钩组件,固定于工字梁上的用于移动吊钩组件的第一位移执行装置,设置于工字梁另一端并可沿其纵向滑动的配重组件,固定于工字梁上的用于移动配重组件的第二位移执行装置,一端连接于吊装点、另一端连接于吊机的绳体,以及与第一位移执行装置和第二位移执行装置电连接的控制装置。 
在进一步的实施例中,还包括与控制装置电连接的无线信号收发装置,其接收到的控制信号送至控制装置,由控制装置驱动第一位移执行装置或第二位移执行装置。所述吊装点为2个或2个以上,沿工字梁的纵向排列。所述工字梁为两个或两个以上,相互平行;每个工字梁上对应设置吊钩组件、第一位移执行装置、配重组件、第二位移执行装置和绳体。 
所述工字梁的底部设有斜齿齿条,所述配重组件包括托架,设置在托架上的配重,固定于托架上并沿工字梁纵向移动的滚轮,以及固定于托架上的电机,电机输出轴联接一与斜齿齿条啮合的斜齿齿轮。 
有益效果:采用本发明吊装墙板,基本不会受到现场作业面的限制,效率高,成本低,而且墙板在吊装过程中不会受到碰撞,导致损坏。 
附图说明
图1是本发明一种实施例的示意图。 
图2是本发明又一实施例的示意图。 
图3是本发明刹车结构的主视图。 
图4是本发明刹车结构的侧视图。 
具体实施方式
如图1和图2所示,本发明的墙板吊装系统主要包括工字梁1、吊钩组件13、第一位移执行装置15、配重组件3、第二位移执行装置16、绳体和控制装置14。工字梁的中部设置有多个纵向排列的吊装点11,吊钩组件13设置于工字梁一端并可沿其纵向滑动,第一位移执行装置15固定于工字梁1上,用于移动吊钩组件,吊钩组件移动方式可采用现有的多种方式,例如,设置一滑轮,工字梁上对应设置轨道等。 
配重组件3设置于工字梁另一端并可沿其纵向滑动,第二位移执行装置16固定于工字梁上,用于移动配重组件。绳体一端连接于吊装点、另一端连接于吊机。第一位移执行装置和第二位移执行装置与控制装置电连接。 
本发明的实施过程如下:根据所需的吊臂长度选择合适的吊装点;根据墙板重量和悬臂的长度,计算并确定可移动配重组件的重量和位置;启动吊机,将工字梁、墙板和配重等装置一起吊起,移动配重,是系统平衡。将墙板吊运到合适的位置,卸下墙板,移动配重,使系统平衡,降落,重复上述步骤即可。 
当吊钩为多个时,可以进行群吊。需要注意的是:在卸下每块墙板的同时,移动配重,使系统平衡即可。 
在进一步的实施例中,与控制装置电连接的无线信号收发装置,其接收到的控制信号送至控制装置,由控制装置驱动第一位移执行装置或第二位移执行装置。通过无线控制的方式,可以在吊机的操作室对吊装过程进行控制。在其他的实施例中,还可以将控制装置设置在控制室中,通过有线或者无线的方式控制位移执行装置的工作状态。位移执行装置可以为电控卷线机、液压推杆或类似的装置。 
在进一步的实施例中,工字梁为两个或两个以上,相互平行;每个工字梁上对应设置吊钩组件、第一位移执行装置、配重组件、第二位移执行装置和绳体。在该实施例中,墙板具有多个受力点,在吊装的过程中不能发生摇摆或晃动,更加安全。 
如图3和图4所示,在进一步的实施例中,工字梁的底部设有斜齿齿条18,配重组件包括托架32,设置在托架上的配重33,固定于托架上并沿工字梁纵向移动的滚轮31,以及固定于托架上的电机34,电机输出轴联接一与斜齿齿条啮合的斜齿齿轮35。工字梁的端部设有挡板17。 
电机转动时,带动斜齿齿轮沿着斜齿齿条移动,从而使托架及配重沿工字梁的纵向移动,到达指定位置后,制动电机,可移动的配重系统便停止在预定的位置。通过齿轮齿条副的配合,配重的移动非常稳定,不易发生偏离。在其他实施例中,齿轮齿条副可以替换成其他移动副或导轨副。 
在吊装时,吊机的钢缆只承受竖直向下的拉力,调节可移动配重的位置,是整个系统的重心位置和吊机钢缆在同一垂直线上。当系统的重心和吊机的钢缆不在同一垂线上时,整个吊装系统将会通过摆动来自动复位,使重心和吊机钢缆重新处于同一垂直线上。 
在工程实践中,无需将可移动配重调节重心准确地和钢缆处于同一垂直线上,基本重合即可,摆动的幅度不大实际上不影响吊装。 
以上结合附图详细描述了本发明的优选实施方式,但是,本发明并不限于上述实施方式中的具体细节,在本发明的技术构思范围内,可以对本发明的技术方案进行多种等同变换,这些等同变换均属于本发明的保护范围。 
另外需要说明的是,在上述具体实施方式中所描述的各个具体技术特征,在不矛盾的情况下,可以通过任何合适的方式进行组合。为了避免不必要的重复,本发明对各种可能的组合方式不再另行说明。 
此外,本发明的各种不同的实施方式之间也可以进行任意组合,只要其不违背本发明的思想,其同样应当视为本发明所公开的内容。 

Claims (5)

1.一种墙板吊装系统,其特征在于,包括中部设置有吊装点(11)的工字梁(1),设置于工字梁一端并可沿其纵向滑动的吊钩组件(13),固定于工字梁上的用于移动吊钩组件的第一位移执行装置,设置于工字梁另一端并可沿其纵向滑动的配重组件(3),固定于工字梁上的用于移动配重组件的第二位移执行装置,一端连接于吊装点、另一端连接于吊机的绳体(2),以及与第一位移执行装置和第二位移执行装置电连接的控制装置。
2.如权利要求1所述的墙板吊装系统,其特征在于,还包括与控制装置电连接的无线信号收发装置,其接收到的控制信号送至控制装置,由控制装置驱动第一位移执行装置或第二位移执行装置。
3.如权利要求1所述的墙板吊装系统,其特征在于,所述吊装点为2个或2个以上,沿工字梁的纵向排列。
4.如权利要求1所述的墙板吊装系统,其特征在于,所述工字梁为两个或两个以上,相互平行;每个工字梁上对应设置吊钩组件、第一位移执行装置、配重组件、第二位移执行装置和绳体。
5.如权利要求1所述的墙板吊装系统,其特征在于,所述工字梁的底部设有斜齿齿条,所述配重组件包括托架(32),设置在托架上的配重(33),固定于托架上并沿工字梁纵向移动的滚轮(31),以及固定于托架上的电机(34),电机输出轴联接一与斜齿齿条啮合的斜齿齿轮(35)。
CN201410368142.3A 2014-07-29 2014-07-29 墙板吊装系统 Active CN104140037B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410368142.3A CN104140037B (zh) 2014-07-29 2014-07-29 墙板吊装系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410368142.3A CN104140037B (zh) 2014-07-29 2014-07-29 墙板吊装系统

Publications (2)

Publication Number Publication Date
CN104140037A true CN104140037A (zh) 2014-11-12
CN104140037B CN104140037B (zh) 2016-06-08

Family

ID=51849395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410368142.3A Active CN104140037B (zh) 2014-07-29 2014-07-29 墙板吊装系统

Country Status (1)

Country Link
CN (1) CN104140037B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104803276A (zh) * 2015-04-28 2015-07-29 中国水利水电第八工程局有限公司 用于工程设备的吊装装置及吊装方法
CN106395651A (zh) * 2016-11-11 2017-02-15 许昌学院 一种悬臂吊装平衡装置
CN106672800A (zh) * 2017-01-10 2017-05-17 吴光明 一种用于大型设备吊装的起吊装置
CN107265280A (zh) * 2017-08-14 2017-10-20 西山煤电(集团)有限责任公司 重心移动吊梁
CN108910672A (zh) * 2018-08-03 2018-11-30 中国十九冶集团有限公司 吊装梁及其吊装方法
CN109356196A (zh) * 2018-11-21 2019-02-19 中铁十局集团城市轨道工程有限公司 一种半盖挖地铁车站基坑钢支撑并撑架设方法及结构
CN109502474A (zh) * 2018-12-22 2019-03-22 吉林大学 一种远距离单吊车单独吊装装置
CN110182684A (zh) * 2019-06-24 2019-08-30 中国水电四局(阳江)海工装备有限公司 塔筒附件卧式安装用辅助设备及塔筒附件卧式安装方法
WO2021109932A1 (zh) * 2019-12-02 2021-06-10 中建三局第二建设工程有限责任公司 一种带配重的pc墙板快速吊装装置

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0769578A (ja) * 1993-09-06 1995-03-14 Ohbayashi Corp クレーン用吊荷装置
CN1765727A (zh) * 2005-11-18 2006-05-03 沈阳重型机械集团有限责任公司 半体齿轮专用吊具
CN101468777A (zh) * 2007-12-28 2009-07-01 中建三局建设工程股份有限公司 牵引式平衡吊具
CN202481915U (zh) * 2012-01-13 2012-10-10 北京东方泰洋装饰工程有限公司 幕墙板块吊装装置
CN103832936A (zh) * 2013-12-17 2014-06-04 朝阳凌云建筑机械有限公司 塔机的起重力矩平衡系统
CN103910277A (zh) * 2014-04-23 2014-07-09 北京卫星环境工程研究所 一种航天器用一维平衡自动调节吊具
CN203938366U (zh) * 2014-07-29 2014-11-12 南京奥捷墙体材料有限公司 墙板吊装系统

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0769578A (ja) * 1993-09-06 1995-03-14 Ohbayashi Corp クレーン用吊荷装置
CN1765727A (zh) * 2005-11-18 2006-05-03 沈阳重型机械集团有限责任公司 半体齿轮专用吊具
CN101468777A (zh) * 2007-12-28 2009-07-01 中建三局建设工程股份有限公司 牵引式平衡吊具
CN202481915U (zh) * 2012-01-13 2012-10-10 北京东方泰洋装饰工程有限公司 幕墙板块吊装装置
CN103832936A (zh) * 2013-12-17 2014-06-04 朝阳凌云建筑机械有限公司 塔机的起重力矩平衡系统
CN103910277A (zh) * 2014-04-23 2014-07-09 北京卫星环境工程研究所 一种航天器用一维平衡自动调节吊具
CN203938366U (zh) * 2014-07-29 2014-11-12 南京奥捷墙体材料有限公司 墙板吊装系统

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104803276A (zh) * 2015-04-28 2015-07-29 中国水利水电第八工程局有限公司 用于工程设备的吊装装置及吊装方法
CN106395651A (zh) * 2016-11-11 2017-02-15 许昌学院 一种悬臂吊装平衡装置
CN106672800A (zh) * 2017-01-10 2017-05-17 吴光明 一种用于大型设备吊装的起吊装置
CN107265280A (zh) * 2017-08-14 2017-10-20 西山煤电(集团)有限责任公司 重心移动吊梁
CN108910672A (zh) * 2018-08-03 2018-11-30 中国十九冶集团有限公司 吊装梁及其吊装方法
CN109356196A (zh) * 2018-11-21 2019-02-19 中铁十局集团城市轨道工程有限公司 一种半盖挖地铁车站基坑钢支撑并撑架设方法及结构
CN109502474A (zh) * 2018-12-22 2019-03-22 吉林大学 一种远距离单吊车单独吊装装置
CN110182684A (zh) * 2019-06-24 2019-08-30 中国水电四局(阳江)海工装备有限公司 塔筒附件卧式安装用辅助设备及塔筒附件卧式安装方法
WO2021109932A1 (zh) * 2019-12-02 2021-06-10 中建三局第二建设工程有限责任公司 一种带配重的pc墙板快速吊装装置

Also Published As

Publication number Publication date
CN104140037B (zh) 2016-06-08

Similar Documents

Publication Publication Date Title
CN104140037A (zh) 墙板吊装系统
CN104276484A (zh) 升降传动装置
CN106986263A (zh) 设有压力传感器的建筑用建材运输设备
CN103863938B (zh) 用于搬运风洞实验车的安全吊装装置
CN103264952A (zh) 一种采用导杆吊装就位转炉塔楼汽包的施工方法
CN203247031U (zh) 遮板运输吊装装置
CN205023761U (zh) 一种车间挂壁式悬臂起重机
CN107792806A (zh) 一种混凝土运输调度装置
CN103086276B (zh) 一种吊装高层井塔型建筑物内桥式起重机的施工方法
CN202245865U (zh) 烧结机头轮吊装装置
CN203938366U (zh) 墙板吊装系统
CN102704725A (zh) 两层斜放升降横移停车设备
CN204079171U (zh) 升降传动装置
CN103058059B (zh) 双平臂塔式起重机及其起重小车同步控制装置
CN204980736U (zh) 一种工地施工专用的双吊笼电梯
CN204702448U (zh) 高空作业平台用上料系统
CN103287986A (zh) 遮板运输吊装装置及用该装置进行遮板安装的方法
CN202913360U (zh) 一种桥面回转吊装装置
CN202465196U (zh) 一种巷道堆垛起重机
CN204549724U (zh) 一种施工升降机的吊杆式连接机构
CN107288354B (zh) 一种龙门吊整体移位的施工方法
CN104444183A (zh) 输送升降一体机
CN205419582U (zh) 一种楼层起重机
CN205187648U (zh) 快速对箱用吊具结构
CN202465195U (zh) 一种可移动式巷道堆垛起重机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant