CN103669867A - Altitude difference adjustable double-layer operating platform used for building body and outer decoration construction and installing method - Google Patents

Altitude difference adjustable double-layer operating platform used for building body and outer decoration construction and installing method Download PDF

Info

Publication number
CN103669867A
CN103669867A CN201310724991.3A CN201310724991A CN103669867A CN 103669867 A CN103669867 A CN 103669867A CN 201310724991 A CN201310724991 A CN 201310724991A CN 103669867 A CN103669867 A CN 103669867A
Authority
CN
China
Prior art keywords
platform
stock
column
building
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310724991.3A
Other languages
Chinese (zh)
Other versions
CN103669867B (en
Inventor
王乔
钟士宪
李恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Construction Engineering Quality Inspection And Testing Center Co ltd
Shandong Provincial Academy of Building Research
Original Assignee
Shandong Provincial Academy of Building Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Provincial Academy of Building Research filed Critical Shandong Provincial Academy of Building Research
Priority to CN201310724991.3A priority Critical patent/CN103669867B/en
Publication of CN103669867A publication Critical patent/CN103669867A/en
Application granted granted Critical
Publication of CN103669867B publication Critical patent/CN103669867B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明提供了一种建筑主体和外装饰施工用高差可调双层操作平台及安装方法。一种建筑主体和外装饰施工用高差可调双层操作平台,包括采用附墙架与建筑物连接固定的立柱、能够沿立柱上下移动的套架、连接在套架上的主平台和通过带有高度调节装置的连接吊杆悬挂在主平台下方的副平台。一种高差可调双层操作平台的安装方法,包括以下步骤:安装立柱;安装套架;安装主副操作台;安装完毕即可投入使用,套架带动主平台及副平台上下运行。

Figure 201310724991

The invention provides a two-layer operating platform with adjustable height difference for building main body and exterior decoration construction and an installation method. A two-layer operating platform with adjustable height difference for building main body and exterior decoration construction, including a column fixed to the building by using a wall frame, a sleeve frame that can move up and down along the column, a main platform connected to the sleeve frame and through A connecting boom with a height adjustment device is suspended from the sub-platform below the main platform. A method for installing a height-difference-adjustable double-layer operating platform includes the following steps: installing a column; installing a sleeve frame; installing a main and auxiliary operating platform;

Figure 201310724991

Description

Discrepancy in elevation adjustable double-layer operating platform and mounting method for building body and outer decoration construction
Technical field
The present invention relates to a kind of building operations operating platform, be specifically related to discrepancy in elevation adjustable double-layer operating platform and mounting method for a kind of building body and outer decoration construction.
Background technology
Building operations is divided into main body construction and internal and external ornament two stages of construction, and the facility operating for constructor in domestic construction work progress is at present comparatively backward.In the main body construction stage, multilayer and low-rise building generally adopt console mode scaffold, and highrise building generally adopts overhanging scaffold.Attached lift scaffold is owing to setting up complexity, and only in more than 50 meters high-building construction, part adopts, and due to lifting action complicated operation, can not segmentation lifting etc. reason, can not be applied to building external decoration work progress.After main body construction binds, above-mentioned scaffold need to be removed, then adopt aerial work basket to carry out building external decoration construction.Therefore, current domestic a kind of safe and reliable operation facility or equipment that can be applicable to main body construction, can be applied to again building external decoration construction simultaneously that still do not have.Work progress need to be installed and used two kinds of different operation facilities, has caused the increase of manpower, waste of time and use cost.
Beijing XingHeRen building Technology Co.,Ltd has introduced electronic construction lifting platform from Spain, provides a people or many people to work thereon simultaneously.As shown in Figure 1: platform structure adopts individual layer platform, constructor can only be in an aspect operation of building; As shown in Figure 2: attended operation platform along the stock of column operation adopt that 6 rollers only contact with 2 main limbs of column, column power transmission point less, poor rigidity, cause going up most a cantilever height more than attachment point and be restricted; In addition, platform is larger apart from building distance, need to install expansion platform additional and could meet construction requirement, causes platform deadweight to strengthen; As shown in Figure 3: cantilever height has just surpassed 2 floor heights of building.The spacing of general operation platform wall-attached frame is 2 floor heights, when building main body construction, concrete main body structure particularly, needs regular hour maintenance.If operating platform cantilever height has just surpassed 2 floor heights of building, just cannot in the agent structure that does not reach curing period, wall-attached frame be installed, so this type of electronic construction lifting platform can not adapt to the requirement in main body construction stage, can only construct for building external decoration at present.Because cost is high, in the building external decoration stage, use and cannot compete with aerial work basket economy separately simultaneously, in engineering, seldom use at present.
Summary of the invention
In order to overcome above-mentioned technical deficiency, the invention provides discrepancy in elevation adjustable double-layer operating platform and mounting method for a kind of building body and outer decoration construction.
The present invention adopts following measures to realize:
A discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction, comprises the column, the stock that can move up and down along column that adopt wall-attached frame to be connected and fixed with building, is connected to main platform on stock and is suspended on the auxiliary platform below main platform with the suspension rod that is connected by with arrangement for adjusting height.
Preferred version in aforesaid operations platform, stock four sides shroud ring is on column, and stock is provided with opening near the one side of building, and the upper and lower two ends of stock all adopt a plurality of rollers to contact with 4 main limbs of column.
Preferred version in aforesaid operations platform, is provided with U-shaped on the position of connecting platform and layout roller on stock and strengthens collar tie beam.
Preferred version in aforesaid operations platform, preferred version in aforesaid operations platform, the upper and lower both ends of the surface corner location of stock all adopts 2 rollers to contact with the main limb of column.
Preferred version in aforesaid operations platform, arrangement for adjusting height is a plurality of fitting structures that are set in together.
A mounting method for discrepancy in elevation adjustable double-layer operating platform for described building body and outer decoration construction, comprises the following steps:
1) column is installed: according to using height, adopt wall-attached frame that column and building are connected and fixed;
2) stock is installed: adopt roller to contact with 4 main limbs of column stock;
3) major-minor operating desk is installed: main platform is installed on column, on connection suspension rod, is provided with arrangement for adjusting height, according to the floor height of building, before auxiliary platform is installed, adjust the spacing of main platform and auxiliary platform, by connecting suspension rod, auxiliary platform is suspended under main platform;
4) install and can come into operation, stock drives main platform and auxiliary platform to move up and down.
The present invention mainly contains following characteristics:
1) be not only applicable to building main body construction, but also can be applied to the operation of outer decoration construction simultaneously;
2) main platform and be arranged on the auxiliary platform of main platform below, is adapted to constructor simultaneously in upper and lower two-layer operation side operation;
3) adopt the structure that hangs one deck auxiliary platform at main platform, stressed more rationally, structure is lighter and handier, makes safety monitoring system more succinct reliably simultaneously;
4) difference in height of main platform and auxiliary platform can be according to different floor gaps apart from adjusting;
5) stock is together with column shroud ring, and is provided with opening, can avoid and wall-attached frame is interfered, and make operating platform more approach building, and constructability, needn't install expansion platform additional.
Accompanying drawing explanation
Fig. 1 is individual layer operating platform schematic diagram.
Fig. 2 is individual layer operating platform stock and the main limb contact structures of column schematic diagram.
Fig. 3 is that individual layer operating platform is gone up a cantilever height schematic diagram more than attachment point most.
Fig. 4 is double-deck operating platform stock and the main limb contact structures of column schematic diagram.
Fig. 5 is that double-deck operating platform is gone up a cantilever height schematic diagram more than attachment point most.
Fig. 6 is the selected example structure schematic diagram of the present invention.
Fig. 7 is arrangement for adjusting height schematic diagram.
In figure, 1-column, 2-stock, the main platform of 3-, 4-wall-attached frame, 5-building, 6-auxiliary platform, 7-arrangement for adjusting height, 8-strengthen collar tie beam, 9-roller.
the specific embodiment:
Below in conjunction with the drawings and specific embodiments, the present invention is described further.
With reference to accompanying drawing 5 and accompanying drawing 6, a discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction, comprise the column 1, the stock 2 that can move up and down along column 1 that adopt wall-attached frame 4 to be connected and fixed with building 5, be connected to main platform 3 on stock 2 with by the auxiliary platform 6 that suspension rod is suspended on main platform 3 belows that is connected with arrangement for adjusting height 7.
With reference to accompanying drawing 4, stock 2 four sides shroud rings are on column 1, stock 2 is provided with opening near the one side of building 5, stock all adopts a plurality of rollers 9 to contact with 4 main limbs of column 1 in two ends Shang Xia 2, be equivalent to improve the rigidity of column 1, significantly increased column 1 at wall-attached frame more than 4 cantilever height, can surpass 3 building storey heights, guarantee the wall-attached frame spacing of 2 floor heights in main body construction process, make the more close building of operating platform, constructability, needn't install expansion platform additional.In order to guarantee opening portion rigidity, on stock 2, connect main platform 3 and arrange that on the position of roller 9, being provided with U-shaped strengthens collar tie beam 8.In reality stock Shang Xia 2 both ends of the surface corner location all adopt 2 rollers 9 to contact with the main limb of column 1.
With reference to accompanying drawing 7, arrangement for adjusting height 7 is a plurality of fitting structures that are set in together.
A mounting method for discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction, is characterized in that comprising the following steps:
1) column 1 is installed: according to using height, adopt wall-attached frame 4 that column 1 and building 5 are connected and fixed;
2) stock 2 is installed: adopt roller 9 to contact with 4 main limbs of column 1 stock 2;
3) major-minor operating desk is installed: main platform 3 is installed on column 1, on connection suspension rod, be provided with arrangement for adjusting height 7, according to the floor height of building 5, before installing, auxiliary platform 6 adjusts the spacing of main platform 3 and auxiliary platform 6, by connecting suspension rod, auxiliary platform 6 is suspended on to main platform 3 times;
4) install and can come into operation, stock 2 drives main platform 3 and auxiliary platform 6 to move up and down.
Below only described basic principle of the present invention and preferred embodiment, those skilled in the art can make many changes and improvements according to foregoing description, and these changes and improvements should belong to protection scope of the present invention.

Claims (6)

1. a discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction, is characterized in that: comprise the column, the stock that can move up and down along column that adopt wall-attached frame to be connected and fixed with building, be connected to main platform on stock and be suspended on the auxiliary platform below main platform with the suspension rod that is connected by with arrangement for adjusting height.
2. discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction according to claim 1, it is characterized in that: stock four sides shroud ring is on column, stock is provided with opening near the one side of building, and the upper and lower two ends of stock all adopt a plurality of rollers to contact with 4 main limbs of column.
3. discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction according to claim 2, is characterized in that: on stock, connect main platform and arrange that on the position of roller, being provided with U-shaped strengthens collar tie beam.
4. according to building body described in claim 2 or 3 and outer decoration construction discrepancy in elevation adjustable double-layer operating platform, it is characterized in that: the upper and lower both ends of the surface corner location of stock all adopts 2 rollers to contact with the main limb of column.
5. according to building body described in claim 2 or 3 and outer decoration construction discrepancy in elevation adjustable double-layer operating platform, it is characterized in that: arrangement for adjusting height is a plurality of fitting structures that are set in together.
6. a mounting method for discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction described in claim 2 or 3 any one, is characterized in that comprising the following steps:
1) column is installed: according to using height, adopt wall-attached frame that column and building are connected and fixed;
2) stock is installed: adopt roller to contact with 4 main limbs of column stock;
3) major-minor operating desk is installed: main platform is installed on stock, on connection suspension rod, is provided with arrangement for adjusting height, according to the floor height of building, before auxiliary platform is installed, adjust the spacing of main platform and auxiliary platform, by connecting suspension rod, auxiliary platform is suspended under main platform;
4) install and can come into operation, stock drives main platform and auxiliary platform to move up and down.
CN201310724991.3A 2013-12-25 2013-12-25 Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method Expired - Fee Related CN103669867B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310724991.3A CN103669867B (en) 2013-12-25 2013-12-25 Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310724991.3A CN103669867B (en) 2013-12-25 2013-12-25 Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method

Publications (2)

Publication Number Publication Date
CN103669867A true CN103669867A (en) 2014-03-26
CN103669867B CN103669867B (en) 2016-09-28

Family

ID=50308576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310724991.3A Expired - Fee Related CN103669867B (en) 2013-12-25 2013-12-25 Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method

Country Status (1)

Country Link
CN (1) CN103669867B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103883113A (en) * 2014-03-27 2014-06-25 王乔 Building construction operation platform statically determinate combination system and existing building renovation construction method
CN103979383A (en) * 2014-04-29 2014-08-13 山东腾飞建设机械工程有限公司 Multi-layer lifting platform for building construction
CN114080923A (en) * 2021-11-12 2022-02-25 长江勘测规划设计研究有限责任公司 Depend on showy afforestation equipment of aquatic building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4293054A (en) * 1980-05-19 1981-10-06 Piat Impalcature Automatiche S.P.A. Scaffolding for supporting lifting working bridges and platforms
CN1285450A (en) * 1999-08-23 2001-02-28 弗拉科产品制造有限公司 Scaffold
CN201268937Y (en) * 2008-09-05 2009-07-08 高智鹏 Double-layer hanging cradle for working aloft
CA2618183A1 (en) * 2008-01-15 2009-07-15 Bennu Parts And Service, Inc. Liftable scaffold
CN101586392A (en) * 2009-04-13 2009-11-25 许树根 Mast climbing type aerial working platform
CN203640291U (en) * 2013-12-25 2014-06-11 山东省建筑科学研究院 Height-difference adjustable double-layer operating platform for construction of building body and external ornaments

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4293054A (en) * 1980-05-19 1981-10-06 Piat Impalcature Automatiche S.P.A. Scaffolding for supporting lifting working bridges and platforms
CN1285450A (en) * 1999-08-23 2001-02-28 弗拉科产品制造有限公司 Scaffold
CA2618183A1 (en) * 2008-01-15 2009-07-15 Bennu Parts And Service, Inc. Liftable scaffold
CN201268937Y (en) * 2008-09-05 2009-07-08 高智鹏 Double-layer hanging cradle for working aloft
CN101586392A (en) * 2009-04-13 2009-11-25 许树根 Mast climbing type aerial working platform
CN203640291U (en) * 2013-12-25 2014-06-11 山东省建筑科学研究院 Height-difference adjustable double-layer operating platform for construction of building body and external ornaments

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103883113A (en) * 2014-03-27 2014-06-25 王乔 Building construction operation platform statically determinate combination system and existing building renovation construction method
CN103883113B (en) * 2014-03-27 2016-01-06 王乔 CONSTRUCTION OPERATIONS platform static determinacy combined system and reconstruction of existing building construction method
CN103979383A (en) * 2014-04-29 2014-08-13 山东腾飞建设机械工程有限公司 Multi-layer lifting platform for building construction
CN114080923A (en) * 2021-11-12 2022-02-25 长江勘测规划设计研究有限责任公司 Depend on showy afforestation equipment of aquatic building

Also Published As

Publication number Publication date
CN103669867B (en) 2016-09-28

Similar Documents

Publication Publication Date Title
CN103243926B (en) Construction method for hoisting pipe well vertical pipe in high-rise building engineering
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
CN205077885U (en) Hydraulic intelligent climbing protection platform for core tube of building
CN103603504B (en) The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction
CN107700719A (en) A kind of hanging method of high-rise building glass curtain wall
CN107190964A (en) A kind of construction method of prefabricated hoistway operation platform
CN103669867A (en) Altitude difference adjustable double-layer operating platform used for building body and outer decoration construction and installing method
CN103896127A (en) Connecting structure of construction hoist and building climbing formwork frame
CN205654127U (en) Portable operation protective platform of assembly type structure stairwell
CN103291083A (en) Repair method for old wooden tower
CN204662951U (en) High tower hydraulic climbing scaffold
CN106906966B (en) Flexible connecting device for stair railing
CN208981745U (en) Multifunction scaffold
CN106401206B (en) Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project
CN203640291U (en) Height-difference adjustable double-layer operating platform for construction of building body and external ornaments
CN205712818U (en) A kind of lightweight integrally assembling staircase
CN103741939A (en) Climbing type building construction operating platform on outer portion of building and installing method
CN205575520U (en) Installation device of super high -rise building elevator
CN108569629A (en) A self-elevating high-rise modular building hoisting equipment and construction method
CN203647250U (en) Track type window cleaning machine for complex inner court curtain wall
CN206360391U (en) A kind of architectural stair temporary guard rail
CN103720427B (en) A kind of complicated Neiting curtain wall rail mounted window cleaning equipment
CN205421883U (en) Suspension type operation platform
CN202139007U (en) Single hanging seat for overhead work
CN206397107U (en) Armored concrete construction of lift well operating platform bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20140326

Assignee: SHANDONG TENGFEI CONSTRUCTION MECHANICAL ENGINEERING CO.,LTD.

Assignor: SHANDONG PROVINCIAL ACADEMY OF BUILDING RESEARCH

Contract record no.: 2017370000072

Denomination of invention: Altitude difference adjustable double-layer operating platform used for building body and outer decoration construction and installing method

Granted publication date: 20160928

License type: Common License

Record date: 20171106

EE01 Entry into force of recordation of patent licensing contract
TR01 Transfer of patent right

Effective date of registration: 20200820

Address after: 250031 Shandong Province Flyover District of Ji'nan City Road 29.

Co-patentee after: Shandong construction engineering quality inspection and Testing Center Co.,Ltd.

Patentee after: Shandong Academy of Building Science Co.,Ltd.

Address before: 250031 Shandong Province Flyover District of Ji'nan City Road 29.

Patentee before: SHANDONG PROVINCIAL ACADEMY OF BUILDING RESEARCH

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160928

Termination date: 20211225

CF01 Termination of patent right due to non-payment of annual fee