CN203640291U - Height-difference adjustable double-layer operating platform for construction of building body and external ornaments - Google Patents
Height-difference adjustable double-layer operating platform for construction of building body and external ornaments Download PDFInfo
- Publication number
- CN203640291U CN203640291U CN201320861560.7U CN201320861560U CN203640291U CN 203640291 U CN203640291 U CN 203640291U CN 201320861560 U CN201320861560 U CN 201320861560U CN 203640291 U CN203640291 U CN 203640291U
- Authority
- CN
- China
- Prior art keywords
- platform
- stock
- building
- column
- operating platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Ladders (AREA)
Abstract
The utility model provides a height-difference adjustable double-layer operating platform for construction of a building body and external ornaments. The height-difference adjustable double-layer operating platform for the construction of the building body and the external ornaments comprises a stand column, a sleeve frame, a main platform and an auxiliary platform, wherein the stand column is connected and fixed to a building by adopting a wall attaching frame, the sleeve frame can move up and down along the stand column, the main platform is connected to the sleeve frame, and the auxiliary platform is suspended below the main platform through a connecting suspension rod with a height adjusting device.
Description
Technical field
The utility model relates to a kind of building operations operating platform, is specifically related to a kind of building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform.
Background technology
Building operations is divided into main body construction and internal and external ornament two stages of construction, and the facility operating for constructor in domestic construction work progress is at present comparatively backward.In the main body construction stage, multilayer and low-rise building generally adopt console mode scaffold, and highrise building generally adopts overhanging scaffold.Attached lift scaffold is owing to setting up complexity, and only more than 50 meters, in high-building construction, part adopts, and due to lifting action complicated operation, can not segmentation lifting etc. reason, can not be applied to building external decoration work progress.After main body construction binds, above-mentioned scaffold need to be removed, then adopt aerial work basket to carry out building external decoration construction.Therefore, current domestic a kind of safe and reliable operation facility or equipment that can be applicable to main body construction, can be applied to again building external decoration construction simultaneously that still do not have.Work progress need to be installed and used two kinds of different operation facilities, has caused the increase of manpower, waste of time and use cost.
Beijing XingHeRen building Technology Co.,Ltd has introduced electronic construction lifting platform from Spain, provides a people or many people to work thereon simultaneously.As shown in Figure 1: platform structure adopts individual layer platform, constructor can only be in of a building aspect operation; As shown in Figure 2: attended operation platform along the stock of column operation adopt that 6 rollers only contact with 2 main limbs of column, column power transmission point less, poor rigidity, cause going up most a cantilever height more than attachment point and be restricted; In addition, platform is larger apart from building distance, need to install expansion platform additional and could meet construction requirement, causes platform deadweight to strengthen; As shown in Figure 3: cantilever height has just exceeded 2 floor heights of building.The spacing of general operation platform wall-attached frame is 2 floor heights, in the time of building main body construction, concrete main body structure particularly, needs regular hour maintenance.If operating platform cantilever height has just exceeded 2 floor heights of building, just cannot in the agent structure that does not reach curing period, wall-attached frame be installed, so this type of electronic construction lifting platform can not adapt to the requirement in main body construction stage, can only be used at present building external decoration construction.Because cost is high, use and cannot compete with aerial work basket economy in the building external decoration stage separately simultaneously, in engineering, seldom use at present.
Utility model content
In order to overcome above-mentioned technical deficiency, the utility model provides a kind of building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and mounting method.
The utility model adopts following measures to realize:
Discrepancy in elevation adjustable double-layer operating platform for a kind of building body and outer decoration construction, comprises the column, the stock that can move up and down along column that adopt wall-attached frame to be connected and fixed with building, is connected to the main platform on stock and is suspended on the auxiliary platform below main platform by the suspension rod that is connected with arrangement for adjusting height.
Preferred version in aforesaid operations platform, stock four sides shroud ring is on column, and stock is provided with opening near the one side of building, and the upper and lower two ends of stock all adopt multiple rollers to contact with 4 main limbs of column.
Preferred version in aforesaid operations platform, is provided with U-shaped on the position of connecting platform and layout roller on stock and strengthens collar tie beam.
Preferred version in aforesaid operations platform, preferred version in aforesaid operations platform, the upper and lower both ends of the surface corner location of stock all adopts 2 rollers to contact with the main limb of column.
Preferred version in aforesaid operations platform, arrangement for adjusting height is multiple fitting structures that are set in together.
The utility model mainly contains following characteristics:
1) be not only applicable to building main body construction, but also can be applied to the operation of outer decoration construction simultaneously;
2) main platform and be arranged on the auxiliary platform of main platform below, is adapted to constructor simultaneously in upper and lower two-layer operation side operation;
3) adopt the structure that hangs one deck auxiliary platform at main platform, stressed more rationally, structure is lighter and handier, makes safety monitoring system more succinct reliably simultaneously;
4) difference in height of main platform and auxiliary platform can be according to different floor gaps apart from adjusting;
5) stock is together with column shroud ring, and is provided with opening, can avoid and wall-attached frame is interfered, and make operating platform more approach building, and constructability, needn't install expansion platform additional.
Accompanying drawing explanation
Fig. 1 is individual layer operating platform schematic diagram.
Fig. 2 is individual layer operating platform stock and the main limb contact structures of column schematic diagram.
Fig. 3 is that individual layer operating platform is gone up a cantilever height schematic diagram more than attachment point most.
Fig. 4 is double-deck operating platform stock and the main limb contact structures of column schematic diagram.
Fig. 5 is that double-deck operating platform is gone up a cantilever height schematic diagram more than attachment point most.
Fig. 6 is the selected example structure schematic diagram of the utility model.
Fig. 7 is arrangement for adjusting height schematic diagram.
In figure, 1-column, 2-stock, the main platform of 3-, 4-wall-attached frame, 5-building, 6-auxiliary platform, 7-arrangement for adjusting height, 8-strengthen collar tie beam, 9-roller.
the specific embodiment:
Below in conjunction with the drawings and specific embodiments, the utility model is described further.
With reference to accompanying drawing 5.6, discrepancy in elevation adjustable double-layer operating platform for a kind of building body and outer decoration construction, comprises the column 1, the stock 2 that can move up and down along column 1 that adopt wall-attached frame 4 to be connected and fixed with building 5, is connected to main platform 3 on stock 2 and by the auxiliary platform 6 that is connected suspension rod and is suspended on main platform 3 belows with arrangement for adjusting height 7.
With reference to accompanying drawing 4, stock 2 four sides shroud rings are on column 1, stock 2 is provided with opening near the one side of building 5, stock all adopts multiple rollers 9 to contact with 4 main limbs of column 1 in two ends Shang Xia 2, be equivalent to improve the rigidity of column 1, significantly increased column 1 at wall-attached frame more than 4 cantilever height, can exceed 3 building storey heights, guarantee the wall-attached frame spacing of 2 floor heights in main body construction process, make the more close building of operating platform, constructability, needn't install expansion platform additional.In order to guarantee opening portion rigidity, on stock 2, connect main platform 3 and arrange that on the position of roller 9, being provided with U-shaped strengthens collar tie beam 8.In reality stock Shang Xia 2 both ends of the surface corner location all adopt 2 rollers 9 to contact with the main limb of column 1.
With reference to accompanying drawing 7, arrangement for adjusting height 7 is multiple fitting structures that are set in together.
A mounting method for discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction, is characterized in that comprising the following steps:
1) column 1 is installed: according to using height, adopt wall-attached frame 4 that column 1 and building 5 are connected and fixed;
2) stock 2 is installed: adopt roller 9 to contact with 4 main limbs of column 1 stock 2;
3) major-minor operating desk is installed: main platform 3 is installed on column 1, on connection suspension rod, be provided with arrangement for adjusting height 7, according to the floor height of building 5, before installing, auxiliary platform 6 adjusts the spacing of main platform 3 and auxiliary platform 6, by connecting suspension rod, auxiliary platform 6 is suspended on to main platform 3 times;
4) install and can come into operation, stock 2 drives main platform 3 and auxiliary platform 6 to move up and down.
Below only described basic principle of the present utility model and preferred embodiment, those skilled in the art can make many changes and improvements according to foregoing description, and these changes and improvements should belong to protection domain of the present utility model.
Claims (5)
1. a discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction, is characterized in that: comprise the column, the stock that can move up and down along column that adopt wall-attached frame to be connected and fixed with building, be connected to the main platform on stock and be suspended on the auxiliary platform below main platform by the suspension rod that is connected with arrangement for adjusting height.
2. discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction according to claim 1, it is characterized in that: stock four sides shroud ring is on column, stock is provided with opening near the one side of building, and the upper and lower two ends of stock all adopt multiple rollers to contact with 4 main limbs of column.
3. discrepancy in elevation adjustable double-layer operating platform for building body and outer decoration construction according to claim 2, is characterized in that: on stock, connect main platform and arrange that on the position of roller, being provided with U-shaped strengthens collar tie beam.
4. according to building body described in claim 2 or 3 and outer decoration construction discrepancy in elevation adjustable double-layer operating platform, it is characterized in that: the upper and lower both ends of the surface corner location of stock all adopts 2 rollers to contact with the main limb of column.
5. according to building body described in claim 2 or 3 and outer decoration construction discrepancy in elevation adjustable double-layer operating platform, it is characterized in that: arrangement for adjusting height is multiple fitting structures that are set in together.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320861560.7U CN203640291U (en) | 2013-12-25 | 2013-12-25 | Height-difference adjustable double-layer operating platform for construction of building body and external ornaments |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320861560.7U CN203640291U (en) | 2013-12-25 | 2013-12-25 | Height-difference adjustable double-layer operating platform for construction of building body and external ornaments |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203640291U true CN203640291U (en) | 2014-06-11 |
Family
ID=50871547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320861560.7U Expired - Fee Related CN203640291U (en) | 2013-12-25 | 2013-12-25 | Height-difference adjustable double-layer operating platform for construction of building body and external ornaments |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203640291U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669867A (en) * | 2013-12-25 | 2014-03-26 | 山东省建筑科学研究院 | Altitude difference adjustable double-layer operating platform used for building body and outer decoration construction and installing method |
CN108398961A (en) * | 2017-02-05 | 2018-08-14 | 钱浙滨 | A kind of suspended working platform control method, apparatus and system |
-
2013
- 2013-12-25 CN CN201320861560.7U patent/CN203640291U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669867A (en) * | 2013-12-25 | 2014-03-26 | 山东省建筑科学研究院 | Altitude difference adjustable double-layer operating platform used for building body and outer decoration construction and installing method |
CN108398961A (en) * | 2017-02-05 | 2018-08-14 | 钱浙滨 | A kind of suspended working platform control method, apparatus and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103979383B (en) | Building operation multiple layer up-down plateform system | |
CN103711323B (en) | Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing | |
CN103603504B (en) | The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction | |
CN103206074B (en) | Elevator shaft template construction method, platform and support | |
CN202248941U (en) | Integral lifting, positioning and mounting device for large-scale steel members | |
CN107700719A (en) | A kind of hanging method of high-rise building glass curtain wall | |
CN103899093A (en) | Step-by-step hoisting construction method of mega-frame steel truss beam | |
CN203640291U (en) | Height-difference adjustable double-layer operating platform for construction of building body and external ornaments | |
CN103896127A (en) | Connecting structure of construction hoist and building climbing formwork frame | |
CN102493666A (en) | High-altitude translation installation and construction method for super-large super-heavy member | |
CN204662951U (en) | High tower hydraulic climbing scaffold | |
CN205637622U (en) | Perpendicular unit glass curtain wall hoist and mount system | |
CN103669867B (en) | Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method | |
CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method | |
CN103741939B (en) | The outside climbing type CONSTRUCTION OPERATIONS platform of building and mounting method | |
CN103726449B (en) | Automatically fall Liangping table apparatus and the construction method for changing railway beam thereof | |
CN102807178A (en) | Chamfered hanging basket device with slide rail | |
CN102587601A (en) | Multistage connection cage-type staircase | |
CN208981745U (en) | Multifunction scaffold | |
CN204754150U (en) | Dish -type node formula scaffold | |
CN203640251U (en) | Climbing type building construction operating platform outside building | |
CN205421883U (en) | Suspension type operation platform | |
CN103334592B (en) | Step-type sliding installation construction method for convex structure of high-rise building | |
CN202139007U (en) | Single hanging seat for overhead work |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |