CN107190964A - A kind of construction method of prefabricated hoistway operation platform - Google Patents
A kind of construction method of prefabricated hoistway operation platform Download PDFInfo
- Publication number
- CN107190964A CN107190964A CN201710409593.0A CN201710409593A CN107190964A CN 107190964 A CN107190964 A CN 107190964A CN 201710409593 A CN201710409593 A CN 201710409593A CN 107190964 A CN107190964 A CN 107190964A
- Authority
- CN
- China
- Prior art keywords
- elevator
- platform
- hanger
- channel
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/24—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
- E04G3/246—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the inside contour of a building
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Types And Forms Of Lifts (AREA)
Abstract
A kind of construction method of prefabricated hoistway operation platform, belongs to operating platform technical field in architectural engineering.First by the channel-section steel support body made according to the actual length and width size of elevator and the height of floor, rack leg, hanger, steel platform, according to design drawing position firm welding, then the steel wire penetrating hanger on tower crane is passed through, it is hoisted to above elevator, vertically at the uniform velocity fall in completed elevator, its rack leg is seated on the floor for having completed elevator doorway, whole operation platform is support as the strong point.On inspection after safety, the steel wire rope of tower crane is released.Workman can construct in stable plate platform top-operation.It is to be onstructed to complete, i.e., again with the steel wire rope on tower crane by hanger after the dismounting of elevator inner side template, by prefabricated operating platform lifting to a upper floor.Repeat the above steps progress next step installment work.Advantage is, time saving and energy saving, and operating efficiency is high, saves construction cost.
Description
Technical field
The invention belongs to operating platform technical field in architectural engineering, a kind of prefabricated hoistway operation is in particular, provided
The construction method of platform.
Background technology
Scaffold is set up using wall box out more than hoistway operation platform in construction, this method has vertical rod missing
Caused by stress performance and stability difference shortcoming, there is certain potential safety hazard and set up scaffold and take a lot of work material.
The content of the invention
It is an object of the invention to provide a kind of construction method of prefabricated hoistway operation platform, wall box out is solved
The problems such as setting up stress performance and poor stability caused by scaffold.Made using channel-section steel, structure, making are simple, and installation is applied
Work is convenient, can have enough to meet the need, reuse, and improves efficiency, ensures safety, reduces construction cost.
The present invention includes:Channel-section steel support body 1, rack leg 2, hanger 3, plate platform 4.
First by the channel-section steel support body 1 made according to the actual length and width size of elevator and the height of floor, rack leg 2,
Hanger 3, steel platform 4, then by the steel wire penetrating hanger 3 on tower crane, are hoisted to electricity according to design drawing position firm welding
Above stair shaft, vertically at the uniform velocity fall in completed elevator, its rack leg 2 is seated in the building for having completed elevator doorway
On plate, whole operation platform is support as the strong point.On inspection after safety, the steel wire rope of tower crane is released.So far, it is complete
Into the installation overall process of a prefabricated operating platform, workman can construct in the stable top-operation of plate platform 4.It is to be onstructed
Complete, i.e., again with the steel wire rope on tower crane by hanger 3 after the dismounting of elevator inner side template, the lifting of prefabricated operating platform is arrived
A upper floor.Repeat the above steps progress next step installment work, and time saving and energy saving, operating efficiency is high, saves construction cost.
Channel-section steel support body 1 uses 14# channel-section steel welding productions, the actual length and width size and floor of specific size according to elevator
Highly design, rack leg 2 is made using 14# channel-section steels.Two outer lateral extents of rack leg 2 are less than the size of elevator door opening, with
Just above the platform for being seated in elevator door opening.Hanger 3 is made using the steel plate thick not less than 8mm, is arranged on channel-section steel support body
Above at four angles.Actual size of the plate platform 4 using steel plate thick 5mm according to elevator makes.Beneficial to being operated in platform
Top-operation is constructed.
The invention has the advantages that making simple, flexible and convenient operation, stress performance and stability are good, save safety time,
Time saving and energy saving, operating efficiency is high, saves construction cost.
Brief description of the drawings
Fig. 1 is composition structure fabrication schematic diagram of the invention.
Fig. 2 is the installation schematic diagram of prefabricated operating platform.
Fig. 3 is that hoistway operation layer construction is completed, schematic diagram after the form removable of elevator interior wall.
Fig. 4 is hoisted to last layer for the turnover of prefabricated operating platform and uses process schematic.
Embodiment
The present invention includes:Channel-section steel support body 1, rack leg 2, hanger 3, plate platform 4.
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing
Describe in detail as follows:
The first step:First by the channel-section steel support body 1 made according to the actual length and width size of elevator and the height of floor, branch
Frame leg 2, hanger 3, steel platform 4 are according to design drawing position firm welding.
Second step:Then by the steel wire penetrating hanger 3 on tower crane, it is hoisted to above elevator, vertically at the uniform velocity falls
In completed elevator, its rack leg 2 is seated on the floor for having completed elevator doorway, supported as the strong point
Whole operation platform.On inspection after safety, the steel wire rope of tower crane is released.
3rd step:Layer construction to be operated is completed, i.e., elevator inner side template is passed through with the steel wire rope on tower crane again after removing
Hanger 3, by prefabricated operating platform lifting to a upper floor.
Claims (2)
1. a kind of construction method of prefabricated hoistway operation platform, it is characterised in that:Including channel-section steel support body (1), rack leg
(2), hanger (3), plate platform (4);
(1) by the channel-section steel support body (1) made according to the actual length and width size of elevator and the height of floor, rack leg (2), hang
Ear (3), steel platform (4);According to design drawing position firm welding,
(2) by the steel wire penetrating hanger (3) on tower crane, it is hoisted to above elevator, vertically at the uniform velocity falls completed
In elevator, its rack leg (2) is seated on the floor for having completed elevator doorway, whole behaviour is support as the strong point
Make platform, on inspection after safety, release the steel wire rope of tower crane;So far, the installation for having completed a prefabricated operating platform is complete
Process, workman can construct in stable plate platform (4) top-operation;
(3) it is to be onstructed to complete, i.e., will be prefabricated again with the steel wire rope on tower crane by hanger (3) after the dismounting of elevator inner side template
Formula operating platform is lifted to a upper floor;
(4) repeat the above steps progress next step installment work.
2. prefabricated hoistway operation platform construction method according to claim 1, it is characterised in that:Channel-section steel support body (1)
Using 14# channel-section steel welding productions, specific size is according to the actual length and width size of elevator and the height design of floor, rack leg
(2) made using 14# channel-section steels;Two outer lateral extents of rack leg (2) are less than the size of elevator door opening, to be seated in elevator
Above the platform of well door opening;Hanger (3) is made using the steel plate thick not less than 8mm, is arranged on four angles above channel-section steel support body
Place;Actual size of the plate platform (4) using steel plate thick 5mm according to elevator makes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710409593.0A CN107190964A (en) | 2017-06-02 | 2017-06-02 | A kind of construction method of prefabricated hoistway operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710409593.0A CN107190964A (en) | 2017-06-02 | 2017-06-02 | A kind of construction method of prefabricated hoistway operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107190964A true CN107190964A (en) | 2017-09-22 |
Family
ID=59877511
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710409593.0A Pending CN107190964A (en) | 2017-06-02 | 2017-06-02 | A kind of construction method of prefabricated hoistway operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107190964A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107829553A (en) * | 2017-10-16 | 2018-03-23 | 中国十七冶集团有限公司 | A kind of elevator hoistways construction platform system |
CN108277970A (en) * | 2018-02-01 | 2018-07-13 | 温州市腾圣建设有限公司 | Elevator civil construction mobile platform |
CN108756197A (en) * | 2018-06-26 | 2018-11-06 | 中冶建工集团有限公司 | A kind of construction method of hoistway operation platform |
CN108756198A (en) * | 2018-06-26 | 2018-11-06 | 中冶建工集团有限公司 | A kind of hoistway operation platform |
CN109113321A (en) * | 2018-10-19 | 2019-01-01 | 中冶建工集团有限公司 | A kind of automatic leveling operating platform |
CN109113320A (en) * | 2018-10-19 | 2019-01-01 | 中冶建工集团有限公司 | Construction operation method in a kind of elevator |
CN110424710A (en) * | 2019-07-31 | 2019-11-08 | 云南省建设投资控股集团有限公司 | Elevator tool-type all steel operation platform construction |
CN112554579A (en) * | 2020-12-22 | 2021-03-26 | 中建四局第六建设有限公司 | Movable platform of unloading of assembled building utilization elevator well |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000070169A1 (en) * | 1999-05-13 | 2000-11-23 | Otis Elevator Company | Lift shaft working platform |
CN202850471U (en) * | 2012-10-19 | 2013-04-03 | 江苏南通二建集团有限公司 | Lifting type operation platform for elevator well |
CN203924657U (en) * | 2014-05-28 | 2014-11-05 | 中建一局集团第六建筑有限公司 | A kind of monolithic elevator hoistways platform |
CN204238537U (en) * | 2014-11-21 | 2015-04-01 | 中国建筑第四工程局有限公司 | A kind of elevated hoistway operation platform |
CN205955156U (en) * | 2016-05-24 | 2017-02-15 | 五冶集团上海有限公司 | Elevartor shaft steel platform |
-
2017
- 2017-06-02 CN CN201710409593.0A patent/CN107190964A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000070169A1 (en) * | 1999-05-13 | 2000-11-23 | Otis Elevator Company | Lift shaft working platform |
CN202850471U (en) * | 2012-10-19 | 2013-04-03 | 江苏南通二建集团有限公司 | Lifting type operation platform for elevator well |
CN203924657U (en) * | 2014-05-28 | 2014-11-05 | 中建一局集团第六建筑有限公司 | A kind of monolithic elevator hoistways platform |
CN204238537U (en) * | 2014-11-21 | 2015-04-01 | 中国建筑第四工程局有限公司 | A kind of elevated hoistway operation platform |
CN205955156U (en) * | 2016-05-24 | 2017-02-15 | 五冶集团上海有限公司 | Elevartor shaft steel platform |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107829553A (en) * | 2017-10-16 | 2018-03-23 | 中国十七冶集团有限公司 | A kind of elevator hoistways construction platform system |
CN108277970A (en) * | 2018-02-01 | 2018-07-13 | 温州市腾圣建设有限公司 | Elevator civil construction mobile platform |
CN108756197A (en) * | 2018-06-26 | 2018-11-06 | 中冶建工集团有限公司 | A kind of construction method of hoistway operation platform |
CN108756198A (en) * | 2018-06-26 | 2018-11-06 | 中冶建工集团有限公司 | A kind of hoistway operation platform |
CN108756198B (en) * | 2018-06-26 | 2020-06-02 | 中冶建工集团有限公司 | Elevator shaft operating platform |
CN109113321A (en) * | 2018-10-19 | 2019-01-01 | 中冶建工集团有限公司 | A kind of automatic leveling operating platform |
CN109113320A (en) * | 2018-10-19 | 2019-01-01 | 中冶建工集团有限公司 | Construction operation method in a kind of elevator |
CN109113321B (en) * | 2018-10-19 | 2020-09-29 | 中冶建工集团有限公司 | Automatic leveling operation platform |
CN110424710A (en) * | 2019-07-31 | 2019-11-08 | 云南省建设投资控股集团有限公司 | Elevator tool-type all steel operation platform construction |
CN112554579A (en) * | 2020-12-22 | 2021-03-26 | 中建四局第六建设有限公司 | Movable platform of unloading of assembled building utilization elevator well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107190964A (en) | A kind of construction method of prefabricated hoistway operation platform | |
CN105201195B (en) | One kind can lift supporting leg type elevator hoistway construction platform and construction method | |
CN206233576U (en) | For the hydraulic pressure lift turnover formwork construction device of bundled-tube structure chimney | |
CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
CN202850498U (en) | Hydraulic support system used for elevator shaft mold | |
CN204781927U (en) | Elevartor shaft formwork and elevartor shaft concrete placement operation platform | |
CN205296799U (en) | Construction of elevator well and protection platform | |
CN105952129B (en) | Elevator shaft combined type integral lifting operation platform and construction method thereof | |
CN206784891U (en) | A kind of prefabricated hoistway operation platform | |
CN204456816U (en) | One can promote supporting leg type elevator hoistway construction platform | |
CN206091283U (en) | Hydraulic pressure is from climbing formula elevartor shaft regularization operation platform | |
CN203475801U (en) | Telescopic steel platform for elevator shaft | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN106193586A (en) | Elevator Telescopic folding Integral lifting core | |
CN206174441U (en) | Elevator shaft operation platform | |
CN209723569U (en) | A kind of hoistway operation platform | |
CN205382718U (en) | Sparse passway for escaping of steel platform die carrier system | |
CN104806001B (en) | The sliding safe operation platform of elevator guide rail and construction method | |
CN107829553A (en) | A kind of elevator hoistways construction platform system | |
CN211714541U (en) | Special handling frame for installing shear wall template in elevator shaft | |
CN203924652U (en) | The operation platform of periphery shear wall between a kind of precast stair | |
CN204492173U (en) | Elevator shaft integral lifting template operation platform | |
CN203320922U (en) | Supporting device for forming of elevator shaft template | |
CN204491824U (en) | A kind of construction elevator basis conversion steel cushion cap | |
CN203594215U (en) | High-altitude large-area work platform semi-automatic lifting apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170922 |
|
WD01 | Invention patent application deemed withdrawn after publication |