CN103352581B - 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法 - Google Patents

采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法 Download PDF

Info

Publication number
CN103352581B
CN103352581B CN201310288583.8A CN201310288583A CN103352581B CN 103352581 B CN103352581 B CN 103352581B CN 201310288583 A CN201310288583 A CN 201310288583A CN 103352581 B CN103352581 B CN 103352581B
Authority
CN
China
Prior art keywords
prestressed reinforcement
wall
anchor pole
reinforcement anchor
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310288583.8A
Other languages
English (en)
Other versions
CN103352581A (zh
Inventor
董有
鞠树森
赵恩平
谢建明
万兆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Advocating Creation Shanghai Consulting Management Firm
Original Assignee
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201310288583.8A priority Critical patent/CN103352581B/zh
Publication of CN103352581A publication Critical patent/CN103352581A/zh
Application granted granted Critical
Publication of CN103352581B publication Critical patent/CN103352581B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及一种采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法,属于抗震加固技术领域。包括墙体以及预应力钢筋锚杆,所述墙体由烧结粘土砖构成,所述预应力钢筋锚杆横向均匀穿设于墙体中,其预应力钢筋锚杆的两端由垫板和锚栓预应力锚固,然后预应力钢筋锚杆与烧结粘土砖的孔洞之间灌注砂浆。本发明有效地改善了墙体抗裂、抗剪性能,抑制了墙体开裂和裂缝发展,提高了砌体结构的抗震性能。

Description

采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法
技术领域
本发明涉及一种采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法,属于抗震加固技术领域。
背景技术
国内外研究表明,对砌体结构施加预应力,可以改善砌体结构材料的特性,提高砌体结构的抗裂、抗震性能及抗剪承载力,而且可以使既有建筑经过预应力加固及改造后满足后续安全使用要求和抗震、节能和环保要求。我国是世界上砌体结构应用最多的国家,尤其是烧结粘土砖专但对预应力砌体研究与国际相比相对滞后。1995年至1998年间,重庆建筑大学骆万康教授对砖砌体墙片进行了配置预应力钢筋的试验研究,试验结果表明,即使施加了很低的预应力σ0=0.0852Mpa(σ0为预应力对墙体的初始压应力),无窗洞的实墙比非预应力墙的开裂荷载提高了30%,极限荷载提高25%。对于开窗洞的预应力墙,在施加预应力为σ0=0.141MPa和σ0=0.282MPa的两种情况下与非预应力开窗洞墙相比,开裂荷载分别提高了27%和40%,极限荷载分别提高了18%和60%,延性比提高了8%和25%。
但是与国外相比,中国关于预应力砌体结构还处在研究阶段,还没有编入相应的规范进行实际应用阶段。国外自80年代预应力砌体结构系统研究起步,英国和新西兰等国做了大量工作,参照预应力混凝土结构设计原则建造了许多预应力砌体砖房和挡土墙,在总结试验和工程实践的基础上,把设计方法纳入了砌体结构设计规范。1999年美国砌体标准联合会(MSJC),将预应力砌体列入了新修订的《砌体结构建筑规范》(ACI530/ASCE5/TMS402)中。
我国对砌体的加固合理的计算方法、预应力的张拉、锚固、最佳预应力度以及防止预应力松弛的方法等问题还需要进一步地研究、试验及工程实践,为推广和应用这一技术创造条件。
发明内容
本发明针对上述问题,提出了一种采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法,主要是通过在烧结粘土砖墙中置入预应力钢筋锚杆,并进行压力灌浆,再张拉钢筋进行锚固,形成预应力砂浆锚杆对烧结粘土砖结构进行抗震加固,其中预应力钢筋锚杆采用横向均匀布置的形式。其有效的解决了墙体开裂以及提高抗震承载力的问题。
为了实现上述目的,本发明采取了如下技术方案:
一种采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法,包括墙体以及预应力钢筋锚杆,所述墙体由烧结粘土砖构成,所述预应力钢筋锚杆横向均匀穿设于墙体中,所述预应力钢筋锚杆的两端由垫板和锚栓施加预应力锚固,所述预应力钢筋锚杆与烧结粘土砖的孔洞之间灌注有砂浆,其特征在于:包括如下步骤:
步骤一:根据设计图纸对需加固的墙体进行放线并沿横墙向上下均匀布置孔洞;
步骤二:清理需要加固的墙体的侧面,沿孔洞两端的横截面方向各开150mm×150mm的洞口用于设置垫板和锚栓;
步骤三:预应力钢筋锚杆涂油后套上薄壁钢管或塑料管,插入步骤一的孔洞中,将预应力钢筋锚杆布置在墙体内;
步骤四:调整预应力钢筋锚杆的长度,使其两端露出上述步骤二中的洞口,在预应力钢筋锚杆的两端设置垫板和锚栓,预应力钢筋锚杆两端的锚固长度均不小于60mm,并用C30混凝土将上述一端洞口填实,使预应力钢筋锚杆的一端与墙体锚固;
步骤五:待砂浆强度达到设计强度后,采用气动推进注浆机进行压力注浆,将烧结粘土砖与薄壁钢管或塑料管之间的缝隙用砂浆灌实;
步骤六:采用扭矩扳手拧紧预应力钢筋锚杆另一端的锚栓,对预应力钢筋锚杆施加预应力张拉并锚固。
其中,所述墙体中每隔1~2匹砌块设置有竖直钢筋网片。
所述竖直钢筋网片采用φ6钢筋焊接而成。
所述预应力钢筋锚杆采用φ16~φ18的预应力钢筋。
所述预应力钢筋锚杆的纵向间距为400mm~600mm。
为防止钻孔对墙体的削弱,破坏结构,施工中应按墙体分段施工,选择的孔钻为施压钻,避免采用冲击钻。
有益效果:本发明能够有效地改善墙体抗裂、抗剪性能,抑制墙体开裂、抑制裂缝发展,提高砌体结构的抗震性能,特别是对既有砌体建筑抗震加固能有效地提高抗震承载力。
附图说明
图1为本发明采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构布置样图;
图2为图1中预应力钢筋锚杆锚固端详图;
图中,1:垫板;2:墙体;3:预应力钢筋锚杆;4:锚栓。
具体实施方式
如图1~图2所示,本发明的具体实施方式如下:
一种内部预应力烧结粘土砖砖砌体结构,包括墙体2以及预应力钢筋锚杆3,墙体2由烧结粘土砖构成,预应力钢筋锚杆3采用φ16~φ18的预应力钢筋并横向均匀穿设于墙体2中,纵向间距为400mm~600mm。预应力钢筋锚杆3的两端由垫板1和锚栓4预应力锚固,两端锚固长度不小于60mm。预应力钢筋锚杆3上套设有薄壁钢管或塑料管,其与烧结粘土砖的孔洞之间灌注有砂浆。墙体2中每隔1~2匹砌块设置有竖直钢筋网片,竖直钢筋网片采用φ6钢筋焊接而成。
采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的具体方法如下:
步骤一:根据设计图纸对需加固的墙体2进行放线并沿横墙向上下均匀布置孔洞;
步骤二:清理需要加固的墙体2的侧面,沿孔洞两端的横截面方向各开150mm×150mm的洞口用于设置垫板1和锚栓4;
步骤三:预应力钢筋锚杆3涂油后套上薄壁钢管或塑料管,插入步骤一的孔洞中,将预应力钢筋锚杆3布置在墙体2内;
步骤四:调整预应力钢筋锚杆3的长度,使其两端露出上述步骤二中的洞口,在预应力钢筋锚杆3的两端设置垫板1和锚栓4,预应力钢筋锚杆3两端的锚固长度均不小于60mm,并用C30混凝土将上述~端洞口填实,使预应力钢筋锚杆3的一端与墙体2锚固;
步骤五:待砂浆强度达到设计强度后,采用气动推进注浆机进行压力注浆,将烧结粘土砖与薄壁钢管或塑料管之间的缝隙用砂浆灌实;
步骤六:采用扭矩扳手拧紧预应力钢筋锚杆3另一端的锚栓4,对预应力钢筋锚杆3施加预应力张拉并锚固。
其中,为防止钻孔对墙体2的削弱,破坏结构,施工中应按墙体2分段施工,选择的孔钻为施压钻,避免采用冲击钻。
以上是本发明的一典型实施例,本发明的实施不限于此。

Claims (1)

1.一种采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法,包括墙体(2)以及预应力钢筋锚杆(3),所述墙体(2)由烧结粘土砖构成,所述预应力钢筋锚杆(3)横向均匀穿设于墙体(2)中,所述预应力钢筋锚杆(3)的两端由垫板(1)和锚栓(4)施加预应力锚固,所述预应力钢筋锚杆(3)与烧结粘土砖的孔洞之间灌注有砂浆,其特征在于:包括如下步骤:
步骤一:根据设计图纸对需加固的墙体(2)进行放线并沿横墙向上下均匀布置孔洞;
步骤二:清理需要加固的墙体(2)的侧面,沿孔洞两端的横截面方向各开150mm×150mm的洞口用于设置垫板(1)和锚栓(4);
步骤三:预应力钢筋锚杆(3)涂油后套上薄壁钢管或塑料管,插入步骤一的孔洞中,将预应力钢筋锚杆(3)布置在墙体(2)内;
步骤四:调整预应力钢筋锚杆(3)的长度,使其两端露出上述步骤二中的洞口,在预应力钢筋锚杆(3)的两端设置垫板(1)和锚栓(4),预应力钢筋锚杆(3)两端的锚固长度均不小于60mm,并用C30混凝土将上述步骤二中的洞口的一端填实,使预应力钢筋锚杆(3)的一端与墙体(2)锚固;
步骤五:待混凝土强度达到设计强度后,采用气动推进注浆机进行压力注浆,将步骤一中的孔洞用砂浆灌实;
步骤六:采用扭矩扳手拧紧预应力钢筋锚杆(3)另一端的锚栓(4),对预应力钢筋锚杆(3)施加预应力张拉并锚固;
其中,所述墙体(2)中每隔1~2匹砌块设置有竖直钢筋网片;所述竖直钢筋网片采用φ6钢筋焊接而成;所述预应力钢筋锚杆(3)采用φ16~φ18的预应力钢筋;所述预应力钢筋锚杆(3)的纵向间距为400mm~600mm;为防止钻孔对墙体(2)的削弱,破坏结构,施工中应按墙体(2)分段施工,选择的孔钻为施压钻,避免采用冲击钻。
CN201310288583.8A 2013-07-09 2013-07-09 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法 Active CN103352581B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310288583.8A CN103352581B (zh) 2013-07-09 2013-07-09 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310288583.8A CN103352581B (zh) 2013-07-09 2013-07-09 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法

Publications (2)

Publication Number Publication Date
CN103352581A CN103352581A (zh) 2013-10-16
CN103352581B true CN103352581B (zh) 2015-12-09

Family

ID=49308989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310288583.8A Active CN103352581B (zh) 2013-07-09 2013-07-09 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法

Country Status (1)

Country Link
CN (1) CN103352581B (zh)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758361B (zh) * 2014-01-06 2015-12-09 北京筑福国际工程技术有限责任公司 既有建筑后增短肢墙和钢拉杆的抗震加固施工方法
CN104058780B (zh) * 2014-06-30 2016-02-03 佛山市东鹏陶瓷有限公司 一种无洞洞石瓷质砖
CN105275222B (zh) * 2015-11-24 2017-06-30 郑州大学 生土填芯型传统民居墙体加固结构及加固方法
CN107227860B (zh) * 2016-02-17 2019-06-11 朱奎 砖墙预应力加固结构
CN105604344B (zh) * 2016-02-28 2018-01-30 叶香竹 一种有裂缝内墙的加固方法
CN105672690B (zh) * 2016-03-02 2017-11-28 叶香竹 承重墙洞口加固方法
CN107916797B (zh) * 2016-05-21 2020-05-15 叶长青 一种提升旧建筑物承载性能的构造方法
JP6921536B2 (ja) * 2017-01-06 2021-08-18 公益財団法人文化財建造物保存技術協会 既存の組積造に設けるアンカーの施工方法及びあと施工アンカー
CN107700700A (zh) * 2017-11-01 2018-02-16 西安建筑科技大学 一种预应力砌体窗间墙及加固方法
CN108222539B (zh) * 2018-01-12 2020-07-24 江苏筑镹营造科技有限公司 砌体构件锚杆加固的方法
CN108412081A (zh) * 2018-01-30 2018-08-17 天津城建大学 施加有水平预应力的砌体结构及砌体的砌筑施工方法
CN110924997A (zh) * 2019-12-09 2020-03-27 中铁十六局集团有限公司 一种隧道二次衬砌裂缝修整加固方法
CN111502322B (zh) * 2020-04-12 2022-06-24 汪方勇 一种砌体加固锚杆结构及其施工方法
CN111794554A (zh) * 2020-08-06 2020-10-20 天津城建大学 一种新型砖砌体墙加固技术
CN113863539B (zh) * 2021-08-25 2023-06-23 东南大学 一种低干预的砖砌体墙抗震加固装置及施工方法
CN114016765B (zh) * 2021-12-20 2022-12-06 江苏筑镹营造科技有限公司 砌体墙横缝加强结构方法
CN114753668B (zh) * 2022-04-14 2023-06-06 江苏海洋大学 一种无粘结预应力钢丝绳加固砖砌体墙的施工方法
CN115199076A (zh) * 2022-07-21 2022-10-18 东南大学 基于Fe-SMA自预应力的砌体结构整体加固方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2440531B (en) * 2006-08-01 2008-07-02 Pyramid Builders Ltd Reinforced Masonry Panel Structure
CN101899839A (zh) * 2010-03-30 2010-12-01 山东大学 一种预应力悬臂对拉式置筋挡墙
CN101818530A (zh) * 2010-04-07 2010-09-01 湖南大学 可再生砌体墙体系及其施工方法
CN102864945B (zh) * 2012-10-11 2016-08-17 北京筑福国际工程技术有限责任公司 一种砂浆锚杆砌体加固结构及其加固方法

Also Published As

Publication number Publication date
CN103352581A (zh) 2013-10-16

Similar Documents

Publication Publication Date Title
CN103352581B (zh) 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法
CN103352582B (zh) 内部预应力钢筋锚杆加固混凝土空心砌块砌体结构的方法
CN206681751U (zh) 一种用于破碎围岩巷道锚注一体化支护系统
CN105201514B (zh) 一种含水岩层井壁结构及施工方法
CN201704689U (zh) 用于岩质边坡加固的四角加筋式预应力锚索锚头
CN2878511Y (zh) 拉压组合自锚型岩石锚杆
CN104005567A (zh) 一种纤维增强聚合物缠绕钢管超高性能混凝土加固混凝土柱
CN2830645Y (zh) 一种带防腐套管的注浆锚杆
CN103758552A (zh) 扩孔型锚杆及其施工工艺
CN1712670A (zh) 一种带防腐套管的注浆锚杆
CN101994315B (zh) 全长粘结预应力锚杆及其施工方法
CN102051880A (zh) 一种可拆卸锚杆
CN102808635B (zh) 一种胀壳式内锚头预应力锚杆及其安装使用方法
CN102828761A (zh) 全螺纹玻璃纤维复合中空注浆锚杆
CN201924356U (zh) 一种可拆卸锚杆
CN210562163U (zh) 一种预制预应力锚杆杆件
CN105714678B (zh) 一种复合式重力锚碇
CN106930436B (zh) 一种内置预应力钢斜撑的钢筋混凝土剪力墙
CN202936792U (zh) 一种胀壳式内锚头预应力锚杆
CN203393865U (zh) 一种内部预应力烧结粘土砖砖砌体结构
CN203394092U (zh) 一种采用内部预应力加固的混凝土空心砌块砌体结构
AU2020273364B2 (en) A new type of mining rooting-anchoring double-layer shaft lining
CN105201525B (zh) 一种可修复的防治底鼓方法
CN201714304U (zh) 可加长的双向螺旋挤扩钻头
CN215716274U (zh) 一种采用预应力锚杆压力灌浆加固空心砌块结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Du Lihong

Inventor before: Dong You

Inventor before: Ju Shusen

Inventor before: Zhao Enping

Inventor before: Xie Jianming

Inventor before: Wan Zhao

TR01 Transfer of patent right

Effective date of registration: 20171031

Address after: 102600, room 2, building 2212, center 3, 2 Xinghua street, Daxing District, Beijing

Patentee after: Beijing Yong Bo Science and Technology Ltd.

Address before: 100043, Beijing, Shijingshan District, 166 Fu Shi Road, two floor, Chak Yang Building

Patentee before: Beijing Aeido International Engineering Technology Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171207

Address after: No. 13, Taizhou, Yongan, Jiangsu, Jiangsu Province

Patentee after: Du Lihong

Address before: 102600, room 2, building 2212, center 3, 2 Xinghua street, Daxing District, Beijing

Patentee before: Beijing Yong Bo Science and Technology Ltd.

CP02 Change in the address of a patent holder

Address after: 225300 room 104, Pearl Road, Yongan Town, Yongan, Taizhou, Jiangsu

Patentee after: Du Lihong

Address before: 225300 No. 13, North Sha Village, Yongan Town, Taizhou, Jiangsu

Patentee before: Du Lihong

CP02 Change in the address of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190520

Address after: 202172 Room 1260, No. 495 Yuejin South Road, Xinhai Town, Chongming District, Shanghai (Guangming Rice Industry Economic Park)

Patentee after: Advocating Creation (Shanghai) Consulting Management Firm

Address before: 225300 room 104, Pearl Road, Yongan Town, Yongan, Taizhou, Jiangsu

Patentee before: Du Lihong

TR01 Transfer of patent right