CN103215969A - 一种用龙门架吊装风机基础环的方法 - Google Patents
一种用龙门架吊装风机基础环的方法 Download PDFInfo
- Publication number
- CN103215969A CN103215969A CN2013101375908A CN201310137590A CN103215969A CN 103215969 A CN103215969 A CN 103215969A CN 2013101375908 A CN2013101375908 A CN 2013101375908A CN 201310137590 A CN201310137590 A CN 201310137590A CN 103215969 A CN103215969 A CN 103215969A
- Authority
- CN
- China
- Prior art keywords
- discharge ring
- portal frame
- ring
- portal
- foundation ring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Wind Motors (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明是一种用龙门架吊装风机基础环的方法。采用两个与风机基础环相关尺寸相配的龙门架,两个龙门架垂直交叉安装,在两个龙门架上安装四个葫芦吊,对风机基础环精确调平。通过工程实践表明,利用该方法和装置吊装风机基础环,最大的优点是可全方位的移动,精确调平简单,可快速拆卸安装,占地面积小,可用小型载货汽车就可转移到另一个场地安装使用,安装精度满足要求,安装操作可不受风力的影响,施工安全,施工费用得到降低。
Description
技术领域
本发明属于风电土建工程技术领域,具体涉及一种用龙门架吊装风机基础环的方法。
背景技术
在风力发电场建设过程中,基础环水平度要求高,基础环安装,固定要求相当精确可靠,风机基础环安装是一个极其关键的工序,其安装精度直接关系到塔筒连接的垂直度、风机的安全性和可靠性。在安装过程中如单独采用吊车安装,由于吊车工作半径及现场条件影响,难以达到,需要大吨位的吊车才能满足吊装要求,在基础环完全调平、安装完成后吊车才能撤走,而且基础环调平只能靠配套的螺栓。这样一来,风机基础环安装费时、费力,而且会使螺栓扭坏,对工程进度和成本都造成了极其不利的影响,且造成了资源的浪费。
有些风电项目风机基础半径较大,一些施工单位在风机基础环安装过程中采用拉槽的方式,将吊车直接开进风机基坑进行基础环吊装施工。上述措施会造成开挖、回填工程量增加、影响施工进度,无法推广运用。
发明内容
本发明的目的是克服风机基础环吊装单独使用吊车的不足之处,提供一种构造简单、就地取材、操作方便、施工安全、施工成本低的龙门架吊装风机基础环的方法。
本发明的技术方案为:采用两个与风机基础环相关尺寸相配的龙门架,两个龙门架垂直交叉安装,在两个龙门架上安装四个葫芦吊,对风机基础环精确调平。
两个龙门架为外龙门架和内龙门架在空间上垂直交叉,龙门架由门架和支撑脚连接构成,内龙门架顶部有固定钢槽。可以采用四点起吊,同时可以任意起吊抬高其中的一个角,对基础环精确调平较为方便。
龙门架吊装风机基础环施工方法如下:
1)龙门架组装完成后采用四点起吊,分别由安装在两个龙门架上的四个葫芦吊来完成,固定好基础环后起吊,待基础环空中稳定后,将事先连接好的基础环支座迅速与基础环进行可靠连接,吊至规定部位,两侧校正,轴线位置合格后做最后固定;
2)基础环的精确调平:将水平尺放置在基础环上法兰面上,调节四个葫芦,第一次精确将基础环调水平,固定基础环的四个螺栓固定,再采用精密水准仪对基础环进行二次精确调整,对基础环上法兰表面各个部位进行检查,保证各部位的安装误差都达到设计和规范要求。
以上能够保证基础环的精确调平,而不用花费更多时间,通过调整基础环螺栓来进行精确调平。
通过工程实践表明,利用该方法和装置吊装风机基础环,最大的优点是可全方位的移动,精确调平简单,可快速拆卸安装,占地面积小,可用小型载货汽车就可转移到另一个场地安装使用,安装精度满足要求,安装操作可不受风力的影响,施工安全,施工费用得到降低。
附图说明
图1为本发明的龙门架吊装基础环装置结构示意图。
图2为图1的俯视图。
图中,1―固定钢槽,2―基础环,3―基础环角钢,4―支撑脚,5―外龙门架,6―内龙门架,7―基础环连接螺栓。
具体实施方式
本发明用龙门架吊装基础环的方法是:采用两个与风机基础环相关尺寸相配的龙门架,两个龙门架空间上垂直交叉安装(平面上组成十字架,如图2所示),在两个龙门架上安装四个葫芦吊,对风机基础环精确调平。两个龙门架为外龙门架5和内龙门架6在空间上垂直交叉,龙门架由门架和支撑脚连接构成,内龙门架6顶部有固定钢槽,如图1所示。可以采用四点起吊,同时可以任意起吊抬高其中的一个角,对基础环精确调平较为方便。
龙门架吊装的施工方法如下:
(1)基础环吊装到基坑:基础环吊入基坑由汽车吊完成,基础环吊装采用四点起吊,先试吊,离地面高度200毫米左右,各项性能合格后再正式起吊。基础环起吊至1.5米高度,待基础环空中稳定后,缓慢旋转进入基坑。吊车缓慢起吊综绳牵引,吊至规定位置,卸掉基础环。
(2)龙门架的组装:先将内龙门架置于基础环的安装位置上,保证龙门架的两只脚与基础环安装钢板在一条直线上,便可安装外龙门架,外龙门架保证与内龙门架空间上垂直,将外龙门架置于内龙门架的固定钢槽内,这时龙门架的四个支撑脚的位置刚好是基础环的四个工字钢与四个垫层钢板连接的位置。
(3)基础环精确吊装:基础环的精确吊装采用四点起吊,分别由安装在两个龙门架上的四个葫芦来完成,基础环起吊,待基础环空中稳定后,将事先连接好的基础环支座迅速与基础环进行可靠连接。吊至规定位置,撬棍两侧校正,轴线位置合格后做最后固定。
Claims (3)
1.一种用龙门架吊装风机基础环的方法,其特征在于采用两个与风机基础环相关尺寸相配的龙门架,两个龙门架垂直交叉安装,在两个龙门架上安装四个葫芦吊,对风机基础环精确调平。
2.根据权利要求1所述的用龙门架吊装风机基础环的方法,其特征在于所述的两个龙门架为外龙门架和内龙门架在空间上垂直交叉,龙门架由门架和支撑脚连接构成,内龙门架顶部有固定钢槽。
3.根据权利要求1所述的用龙门架吊装风机基础环的方法,其特征在于龙门架吊装风机基础环的施工方法如下:
1)龙门架组装完成后采用四点起吊,分别由安装在两个龙门架上的四个葫芦吊来完成,固定好基础环后起吊,待基础环空中稳定后,将事先连接好的基础环支座迅速与基础环进行可靠连接,吊至规定部位,两侧校正,轴线位置合格后做最后固定;
2)基础环的精确调平:将水平尺放置在基础环上法兰面上,调节四个葫芦,第一次精确将基础环调水平,固定基础环的四个螺栓固定,再采用精密水准仪对基础环进行二次精确调整,对基础环上法兰表面各个部位进行检查,保证各部位的安装误差都达到设计和规范要求。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310137590.8A CN103215969B (zh) | 2013-04-19 | 2013-04-19 | 一种用龙门架吊装风机基础环的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310137590.8A CN103215969B (zh) | 2013-04-19 | 2013-04-19 | 一种用龙门架吊装风机基础环的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103215969A true CN103215969A (zh) | 2013-07-24 |
CN103215969B CN103215969B (zh) | 2015-06-10 |
Family
ID=48814094
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310137590.8A Active CN103215969B (zh) | 2013-04-19 | 2013-04-19 | 一种用龙门架吊装风机基础环的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103215969B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108331007A (zh) * | 2018-05-17 | 2018-07-27 | 中能电力科技开发有限公司 | 一种用于海上风电大功率机组的基础结构及安装方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56108690A (en) * | 1980-01-29 | 1981-08-28 | Shiyunyuu So | Crosssshaped both end craning and cargo gear |
WO2011154110A1 (de) * | 2010-06-08 | 2011-12-15 | Wader-Wittis Gmbh | Hubvorrichtung für turmsegmente |
CN202829273U (zh) * | 2012-06-18 | 2013-03-27 | 中交二公局第一工程有限公司 | 钢筋笼吊具 |
CN202864665U (zh) * | 2012-11-16 | 2013-04-10 | 重庆钢铁(集团)有限责任公司 | 筒体专用吊具 |
-
2013
- 2013-04-19 CN CN201310137590.8A patent/CN103215969B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56108690A (en) * | 1980-01-29 | 1981-08-28 | Shiyunyuu So | Crosssshaped both end craning and cargo gear |
WO2011154110A1 (de) * | 2010-06-08 | 2011-12-15 | Wader-Wittis Gmbh | Hubvorrichtung für turmsegmente |
CN202829273U (zh) * | 2012-06-18 | 2013-03-27 | 中交二公局第一工程有限公司 | 钢筋笼吊具 |
CN202864665U (zh) * | 2012-11-16 | 2013-04-10 | 重庆钢铁(集团)有限责任公司 | 筒体专用吊具 |
Non-Patent Citations (1)
Title |
---|
高继峰等: "风机基础施工关键点的控制", 《甘肃科技》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108331007A (zh) * | 2018-05-17 | 2018-07-27 | 中能电力科技开发有限公司 | 一种用于海上风电大功率机组的基础结构及安装方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103215969B (zh) | 2015-06-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
ES2595231T3 (es) | Método de construcción de torre híbrida para un generador eólico | |
CN101619630B (zh) | 钢烟囱的安装方法及其实施的顶升装置 | |
EP2982862A1 (en) | Method and device for blade replacement in wind turbines | |
CN102251486B (zh) | 一种用于桥塔分节段安装的顶升支架系统及其施工工艺 | |
CN107311051B (zh) | 自爬升起重机及风力发电机安装设备 | |
CN103437589B (zh) | 一种钢烟囱筒体的倒装施工方法 | |
CN205772984U (zh) | 一种单片钢桁架的吊装装置 | |
CN106996214A (zh) | 一种设有预制桩基础的通信塔 | |
CN103266779A (zh) | 一种越过水平障碍物的提升滑移施工设备及其方法 | |
CN102493666A (zh) | 一种超大超重构件高空平移安装施工方法 | |
CN207046724U (zh) | 自爬升起重机及风力发电机安装设备 | |
CN103215969B (zh) | 一种用龙门架吊装风机基础环的方法 | |
CN205444867U (zh) | 一种新型电梯井自翻式操作架 | |
CN207158647U (zh) | 一种用于声屏障板的吊装系统 | |
CN203229331U (zh) | 一种用于风机基础环的吊装装置 | |
CN205312922U (zh) | 1000kV串补设备修试专用起吊工具 | |
CN102383613B (zh) | 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置 | |
CN206319628U (zh) | 一种建筑装配式墙板安装机 | |
CN211169496U (zh) | 一种带配重的pc墙板快速吊装装置 | |
CN110847616B (zh) | 大体积钢架烟道安装方法 | |
CN204281114U (zh) | 风力发电塔自爬升维修机器人 | |
CN108677749B (zh) | 一种桥梁转体施工的plc变频控制系统 | |
CN107700854B (zh) | 一种超高层核心筒的钢板墙滑移安装装置和安装方法 | |
CN102733612B (zh) | 电动葫芦轨道安装方法 | |
CN204530491U (zh) | 一种高墩液压爬模施工架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20160825 Address after: Yunnan Yunling Avenue 671099 Autonomous Prefecture in Dali province Dali city Dali Economic Development Zone Patentee after: Hydropower fourteen Bureau Dali shaped Investment Co., Ltd. Address before: 650041 Ring Road in Yunnan city of Kunming province No. 395 Patentee before: Sino Hydro Bureau 14 Co., Ltd. |