CN103138206A - Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes - Google Patents

Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes Download PDF

Info

Publication number
CN103138206A
CN103138206A CN2013100874932A CN201310087493A CN103138206A CN 103138206 A CN103138206 A CN 103138206A CN 2013100874932 A CN2013100874932 A CN 2013100874932A CN 201310087493 A CN201310087493 A CN 201310087493A CN 103138206 A CN103138206 A CN 103138206A
Authority
CN
China
Prior art keywords
ground wire
power transmission
ppr
overhead
overhead ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100874932A
Other languages
Chinese (zh)
Inventor
张啸
许超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIHE ELECTRIC POWER BUREAU
State Grid Corp of China SGCC
Original Assignee
BEIHE ELECTRIC POWER BUREAU
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIHE ELECTRIC POWER BUREAU, State Grid Corp of China SGCC filed Critical BEIHE ELECTRIC POWER BUREAU
Priority to CN2013100874932A priority Critical patent/CN103138206A/en
Publication of CN103138206A publication Critical patent/CN103138206A/en
Pending legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

利用PPR管垂吊进行高压架空送电线路更换架空地线装置及方法,它涉及高压架空送电线路更换架空地线装置及方法,具体涉及利用PPR管垂吊进行高压架空送电线路更换架空地线装置及方法。本发明为了解决现有更换架空地线换线施工中施工时间长、所需人员多、投资巨大的问题。本发明包括两个PPR管、两根绝缘绳和四个钢钎地锚,每根绝缘绳的中部分别各套装一个PPR管,每跟绝缘绳的一端分别各与一个钢钎地锚连接。本发明用于架空地线更换。

Figure 201310087493

A device and method for replacing an overhead ground wire with a high-voltage overhead power transmission line by using a PPR pipe hanging, which relates to a device and a method for replacing an overhead ground wire for a high-voltage overhead power transmission line, and specifically relates to using a PPR pipe for hanging a high-voltage overhead power transmission line to replace an overhead ground Line devices and methods. The invention aims to solve the problems of long construction time, many required personnel and huge investment in the existing construction of replacing overhead ground wires. The invention comprises two PPR pipes, two insulating ropes and four steel ground anchors. The middle part of each insulating rope is fitted with a PPR pipe respectively, and one end of each insulating rope is respectively connected with a steel ground anchor. The invention is used for replacement of overhead ground wires.

Figure 201310087493

Description

利用PPR管垂吊进行高压架空送电线路更换架空地线装置及方法Device and method for replacing overhead ground wires of high-voltage overhead power transmission lines using PPR pipe hanging

技术领域technical field

本发明涉及高压架空送电线路更换架空地线装置及方法,具体涉及利用PPR管垂吊进行高压架空送电线路更换架空地线装置及方法。The invention relates to a device and a method for replacing an overhead ground wire for a high-voltage overhead power transmission line, in particular to a device and a method for replacing an overhead ground wire for a high-voltage overhead power transmission line by using a PPR pipe for hanging.

背景技术Background technique

随着我国综合国力的提升和电力网的发展,尤其在稳定经济拉动内需的方针政策出台后,在铁路、高等级公路和电力线路的基础设施建设方面投入了巨资,辐射面遍及全国各地。高压送电线路架空地线更换改造施工经常遇到与铁路、公路和电力线路交叉跨越的问题。通常更换架空地线换线施工中,多采用搭跨越架或使用吊车绑扎羊角杆及张力放紧线的方法。搭跨越架的方法的不足之处在于准备材料复杂、耗时长,所需人员多,运输困难,耗时费力;使用吊车绑扎羊角杆的方法,虽然简便,但也存在着受地形影响大,遇有跨越点多、施工时日较长时,吊车使用台次、台班过多成本资金支出过高的缺点;张力放紧线要求机械设备先进,投资巨大,地形也要适合机械设备的展开。遇到特殊地段跨越铁路、公路、电力线时,受地形所限制吊车跨越无法使用且不能完全搭设跨越架及使用张力放紧线方法跨越施工。而铁路运输频繁,不可能因跨越施工而停运;公路车流量大,封道施工影响交通且难以实现;被跨电力线路停电,直接影响用户的生产生活,同时也降低了供电的可靠率,影响供电企业的经济效益。With the improvement of my country's comprehensive national strength and the development of power grids, especially after the introduction of policies to stabilize the economy and stimulate domestic demand, huge sums of money have been invested in the infrastructure construction of railways, high-grade highways and power lines, which radiate all over the country. The replacement and reconstruction of overhead ground wires of high-voltage power transmission lines often encounters the problem of crossing with railways, highways and power lines. Usually, in the construction of replacing the overhead ground wire, the method of taking a span frame or using a crane to bind the horn pole and tension the wire is often used. The disadvantages of the method of building a spanning frame are that the preparation of materials is complicated, time-consuming, requires a large number of personnel, and transportation is difficult, time-consuming and laborious; although the method of using a crane to bind the poles is simple, it is also greatly affected by the terrain. When there are many crossing points and long construction time, the number of cranes used and the cost of too many shifts are too high; the tension release line requires advanced mechanical equipment, huge investment, and the terrain must be suitable for the deployment of mechanical equipment. When crossing railways, highways, and power lines in special areas, the crane cannot be used due to terrain restrictions, and the crossing frame cannot be fully erected and the tension and tension line method can be used for crossing construction. The railway transportation is frequent, and it is impossible to stop due to crossing construction; the traffic volume of the road is large, and the road closure construction affects traffic and is difficult to realize; the power outage of the crossed power line directly affects the production and life of users, and also reduces the reliability of power supply. Affect the economic benefits of power supply enterprises.

发明内容Contents of the invention

本发明为解决现有更换架空地线换线施工中施工时间长、所需人员多、投资巨大的问题,进而提出利用PPR管垂吊进行高压架空送电线路更换架空地线装置及方法。In order to solve the problems of long construction time, many required personnel and huge investment in the existing construction of replacing overhead ground wires, the present invention further proposes a device and method for replacing overhead ground wires with high-voltage overhead power transmission lines using PPR pipe hanging.

本发明为解决上述问题采取的技术方案是:本发明所述装置包括两个PPR管、两根绝缘绳和四个钢钎地锚,每根绝缘绳的中部分别各套装一个PPR管,每跟绝缘绳的一端分别各与一个钢钎地锚连接。The technical scheme adopted by the present invention for solving the above-mentioned problems is: the device described in the present invention comprises two PPR pipes, two insulating ropes and four steel ground anchors, and a PPR pipe is respectively set in the middle of each insulating rope, and each heel One end of the insulating rope is respectively connected with a steel drill ground anchor.

本发明所述方法的具体步骤如下:The concrete steps of method of the present invention are as follows:

步骤一、在被跨越物两侧的上方的平行导线上分别各吊挂一根PPR管;Step 1. Hang a PPR pipe on the parallel wires on both sides of the spanned object;

步骤二、牵引每根绝缘绳的两端使两根PPR管平行;Step 2. Pull both ends of each insulating rope to make the two PPR pipes parallel;

步骤三、将每根绝缘绳拉紧,并将每根绝缘绳两端的钢钎地锚夯入地面,每个钢钎地锚距离被跨越物的距离为10米;Step 3. Tighten each insulating rope, and ram the steel ground anchors at both ends of each insulating rope into the ground. The distance between each steel ground anchor and the object to be spanned is 10 meters;

步骤四、在两个PPR管上进行架空地线的放线和紧线操作,被跨越物两侧杆塔线夹安装完毕后即完成架空地线的更换;Step 4. Perform the setting-out and tightening operation of the overhead ground wire on the two PPR pipes, and complete the replacement of the overhead ground wire after the installation of the pole and tower wire clips on both sides of the spanned object;

步骤五、将更换架空地线装置拆除。Step 5. Remove the replacement overhead ground wire device.

本发明的有益效果是:使用本发明更换架空地线仅需要两人即可,减少了劳动力的投入,节约了施工时间,本发明结构简单,操作方便,资金投入少,节约了大量的成本;减少了因长时间停电造成的居民生活不变,以及工厂企业等用电单位的经济损失,还可以提高供电企业的供电可靠率,同时也降低了因施工时对公路、铁路等交通线路的出行和安全影响。The beneficial effects of the present invention are: only two people are needed to replace the overhead ground wire by using the present invention, which reduces labor input and saves construction time. The present invention has simple structure, convenient operation, less capital investment, and saves a lot of cost; It reduces the life of residents caused by long-term power outages, as well as the economic losses of power consumers such as factories and enterprises. and security implications.

附图说明Description of drawings

图1是本发明的工作示意图。Fig. 1 is the working schematic diagram of the present invention.

具体实施方式Detailed ways

具体实施方式一:结合图1说明本实施方式,本实施方式所述利用PPR管垂吊进行高压架空送电线路更换架空地线装置包括两个PPR管1、两根绝缘绳2和四个钢钎地锚3,每根绝缘绳2的中部分别各套装一个PPR管1,每跟绝缘绳2的一端分别各与一个钢钎地锚3连接。Specific Embodiment 1: This embodiment is described in conjunction with FIG. 1. The device for replacing overhead ground wires with high-voltage overhead power transmission lines by using PPR pipes to hang down in this embodiment includes two PPR pipes 1, two insulating ropes 2 and four steel wires. Brazed ground anchor 3, the middle part of each insulating rope 2 is equipped with a PPR pipe 1 respectively, and one end of each insulating rope 2 is connected with a steel brazed ground anchor 3 respectively.

具体实施方式二:结合图1说明本实施方式,本实施方式所述利用PPR管垂吊进行高压架空送电线路更换架空地线装置的每个PPR管1的两端的绝缘绳2上分别各设有一个绳结2-1。Specific embodiment two: This embodiment is described in conjunction with Fig. 1, and the insulating ropes 2 at both ends of each PPR pipe 1 of the high-voltage overhead power transmission line described in this embodiment are used to hang and replace the overhead ground wire device. There is a knot 2-1.

本实施方式的技术效果是:每个PPR管1两端绝缘绳2上的绳结2-1可防止PPR管1在绝缘绳2上窜动,避免更换架空地线过程中发生地线脱落伤及工作人员。The technical effect of this embodiment is: the knot 2-1 on the insulating rope 2 at both ends of each PPR pipe 1 can prevent the PPR pipe 1 from moving on the insulating rope 2, and avoid the ground wire from falling off during the replacement of the overhead ground wire. and staff.

其它组成及连接关系与具体实施方式一相同。Other components and connections are the same as those in the first embodiment.

具体实施方式三:结合图1说明本实施方式,本实施方式所述利用PPR管垂吊进行高压架空送电线路更换架空地线装置的每个钢钎地锚3是直径为22mm的螺纹钢钎制作的钢钎地锚3。其它组成及连接关系与具体实施方式一相同。Specific embodiment three: This embodiment is described in conjunction with Fig. 1. In this embodiment, each steel braze ground anchor 3 of the overhead ground wire device using PPR pipe hanging to replace the overhead ground wire device is a threaded steel braze with a diameter of 22mm. The steel brazing ground anchor 3 made. Other components and connections are the same as those in the first embodiment.

具体实施方式四:结合体图1说明本实施方式,本实施方式所述利用PPR管垂吊进行高压架空送电线路更换架空地线装置的每根绝缘绳2的直径为16mm~20mm。其它组成及连接关系与具体实施方式一相同。Specific Embodiment 4: Combination Fig. 1 illustrates this embodiment. The diameter of each insulating rope 2 of the overhead ground wire replacement device for high-voltage overhead power transmission lines using PPR pipe hanging in this embodiment is 16mm-20mm. Other components and connections are the same as those in the first embodiment.

具体实施方式五:结合图1说明本实施方式,本实施方式所述利用PPR管垂吊进行高压架空送电线路更换架空地线装置的每个PPR管1的壁厚为10mm~14mm。其它组成及连接关系与具体实施方式一相同。Embodiment 5: This embodiment is described with reference to FIG. 1 . In this embodiment, the wall thickness of each PPR pipe 1 of the high-voltage overhead power transmission line replacement overhead ground wire device using PPR pipe hanging is 10 mm to 14 mm. Other components and connections are the same as those in the first embodiment.

具体实施方式六:结合图1说明本实施方式,本实施方式所述一种利用具体实施方式一所述装置进行高压架空送电线路更换架空地线的方法的具体步骤如下:Specific embodiment six: This embodiment is described in conjunction with FIG. 1. The specific steps of a method for replacing an overhead ground wire with a high-voltage overhead power transmission line using the device described in Embodiment 1 described in this embodiment are as follows:

步骤一、在被跨越物两侧的上方的平行导线上分别各吊挂一根PPR管1;Step 1. Hang a PPR pipe 1 respectively on the parallel wires above the two sides of the spanned object;

步骤二、牵引每根绝缘绳2的两端使两根PPR管1平行;Step 2, pulling both ends of each insulating rope 2 to make the two PPR pipes 1 parallel;

步骤三、将每根绝缘绳2拉紧,并将每根绝缘绳2两端的钢钎地锚3夯入地面,每个钢钎地锚3距离被跨越物的距离为10米;Step 3, tighten each insulating rope 2, and ram the steel ground anchor 3 at both ends of each insulating rope 2 into the ground, and the distance between each steel ground anchor 3 and the object to be crossed is 10 meters;

步骤四、在两个PPR管1上进行架空地线的放线和紧线操作,被跨越物两侧杆塔线夹安装完毕后即完成架空地线的更换;Step 4: Carry out the setting-out and tightening operations of the overhead ground wires on the two PPR pipes 1, and complete the replacement of the overhead ground wires after the installation of the pole and tower wire clips on both sides of the spanned object;

步骤五、将更换架空地线装置拆除。Step 5. Remove the replacement overhead ground wire device.

Claims (6)

1. utilize the hanging of PPR pipe to carry out the high voltage overhead power transmission sequence and change the overhead ground wire device: it is characterized in that: the hanging of the described PPR of utilization pipe is carried out high voltage overhead power transmission sequence replacing overhead ground wire device and is comprised two PPR pipes (1), two insulating cords (2) and four drill rod earth anchors (3), the middle part of every insulating cord (2) is set with respectively a PPR pipe (1), and often the end with insulating cord (2) respectively is connected with a drill rod earth anchor (3) respectively.
2. utilize according to claim 1 the hanging of PPR pipe to carry out the high voltage overhead power transmission sequence and change the overhead ground wire device, it is characterized in that: respectively be provided with respectively a knot (2-1) on the insulating cord (2) at the two ends of each PPR pipe (1).
3. utilize according to claim 1 the hanging of PPR pipe to carry out the high voltage overhead power transmission sequence and change the overhead ground wire device, it is characterized in that: each drill rod earth anchor (3) is that diameter is the drill rod earth anchor (3) of the screw thread drill rod making of 22mm.
4. utilize according to claim 1 the hanging of PPR pipe to carry out the high voltage overhead power transmission sequence and change the overhead ground wire device, it is characterized in that: the diameter of every insulating cord (2) is 16mm~20mm.
5. utilize according to claim 1 the hanging of PPR pipe to carry out the high voltage overhead power transmission sequence and change the overhead ground wire device, it is characterized in that: the wall thickness of each PPR pipe (1) is 10mm~14mm.
6. one kind is utilized the described device of claim 1 to carry out the method that the high voltage overhead power transmission sequence is changed overhead ground wire, it is characterized in that: the high voltage overhead power transmission sequence is carried out in the hanging of the described PPR of utilization pipe, and to change the concrete steps of method of overhead ground wire as follows:
Step 1, crossed over thing both sides above parallel wire on respectively hang respectively a PPR pipe (1);
The two ends of step 2, every insulating cord of traction (2) make two PPR pipes (1) parallel;
Step 3, with every insulating cord (2) tension, and will every insulating cord (2) the drill rod earth anchor (3) at two ends ram ground, each drill rod earth anchor (3) distance is 10 meters by the distance of leap thing;
The replacing of namely completing overhead ground wire after thing both sides shaft tower wire clamp installs is crossed in step 4, the unwrapping wire that carries out overhead ground wire on two PPR pipes (1) and stringing operation;
Step 5, will change the overhead ground wire device and remove.
CN2013100874932A 2013-03-19 2013-03-19 Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes Pending CN103138206A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100874932A CN103138206A (en) 2013-03-19 2013-03-19 Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100874932A CN103138206A (en) 2013-03-19 2013-03-19 Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes

Publications (1)

Publication Number Publication Date
CN103138206A true CN103138206A (en) 2013-06-05

Family

ID=48497683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100874932A Pending CN103138206A (en) 2013-03-19 2013-03-19 Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes

Country Status (1)

Country Link
CN (1) CN103138206A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104377591A (en) * 2014-11-20 2015-02-25 国家电网公司 Method for replacing overhead wire of crossing electrified railway without building crossing frame
CN104410005B (en) * 2014-10-24 2017-08-04 国家电网公司 A working method for replacing overhead wires and ground wires
CN107196229A (en) * 2017-05-15 2017-09-22 天津送变电工程公司 Application process of the PVC protection pipes in extra-high voltage crossing construction
CN112242666A (en) * 2020-09-29 2021-01-19 浙江大有实业有限公司带电作业分公司 Method for replacing outgoing cable of line with radial structure
CN113572117A (en) * 2021-06-11 2021-10-29 国网山东省电力公司烟台供电公司 Device and method for realizing overhead drilling by adopting single-loop-trunk-shaped terminal tower

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2765352Y (en) * 2005-01-22 2006-03-15 广西送变电建设公司 Double-post combined suspension cable type crossover rack
CN2927428Y (en) * 2006-04-24 2007-07-25 俞云飞 Assembled insulated spanning rack
JP2008154438A (en) * 2006-12-15 2008-07-03 Michio Takaoka Removal of snow and ice accretion on overhead transmission line
CN202285309U (en) * 2011-10-28 2012-06-27 湖北省输变电工程公司 Lifting energized spanning frame
CN203086060U (en) * 2013-03-19 2013-07-24 黑河电业局 Device for replacing overhead ground wires of high-voltage overhead power transmission line by using PPR (polypropylene random) pipe suspension

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2765352Y (en) * 2005-01-22 2006-03-15 广西送变电建设公司 Double-post combined suspension cable type crossover rack
CN2927428Y (en) * 2006-04-24 2007-07-25 俞云飞 Assembled insulated spanning rack
JP2008154438A (en) * 2006-12-15 2008-07-03 Michio Takaoka Removal of snow and ice accretion on overhead transmission line
CN202285309U (en) * 2011-10-28 2012-06-27 湖北省输变电工程公司 Lifting energized spanning frame
CN203086060U (en) * 2013-03-19 2013-07-24 黑河电业局 Device for replacing overhead ground wires of high-voltage overhead power transmission line by using PPR (polypropylene random) pipe suspension

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104410005B (en) * 2014-10-24 2017-08-04 国家电网公司 A working method for replacing overhead wires and ground wires
CN104377591A (en) * 2014-11-20 2015-02-25 国家电网公司 Method for replacing overhead wire of crossing electrified railway without building crossing frame
CN107196229A (en) * 2017-05-15 2017-09-22 天津送变电工程公司 Application process of the PVC protection pipes in extra-high voltage crossing construction
CN112242666A (en) * 2020-09-29 2021-01-19 浙江大有实业有限公司带电作业分公司 Method for replacing outgoing cable of line with radial structure
CN112242666B (en) * 2020-09-29 2022-04-19 浙江大有实业有限公司带电作业分公司 Method for replacing outgoing cable of line with radial structure
CN113572117A (en) * 2021-06-11 2021-10-29 国网山东省电力公司烟台供电公司 Device and method for realizing overhead drilling by adopting single-loop-trunk-shaped terminal tower

Similar Documents

Publication Publication Date Title
CN203645249U (en) Hook-net-plane-type charged crossing device
CN103138206A (en) Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes
CN102354926A (en) Large-section conductor tension stringing construction method
CN102324712A (en) A construction method for live spanning of high-voltage power transmission and transformation lines
CN207098456U (en) A kind of crossover tower auxiliary cross-arm block component for being used to live across operation
CN204424793U (en) A kind of block crossing frame of power circuit
CN203352049U (en) Overhead line pulling-up assisting device
CN104577875A (en) Construction method of block crossover frame cable of power circuit
CN203367865U (en) Auxiliary bracket for maintaining power transmission line
CN102661057B (en) Power angle tower pull leg main material changing method and special main material clamp
CN204481391U (en) A kind of replacing double bundle conductor conductor spacer specific purpose tool
CN203086060U (en) Device for replacing overhead ground wires of high-voltage overhead power transmission line by using PPR (polypropylene random) pipe suspension
CN103236656A (en) Column suspension type crossing structure and operating method thereof
CN201252365Y (en) Construction charged crossover device of ultra-high and special-high voltage transmission line
CN106532557B (en) Across 10KV line construction platform tools devices
CN206401811U (en) A spanning net for striding construction across live lines
CN103683098A (en) Method of replacing strain poles without laying down lines
CN101966823A (en) Carrier cable crossing frame and erecting method thereof
CN102738732A (en) Construction method for 500kV line to span highly intensive high-voltage live lines
CN203445520U (en) Live spanning device
CN204696565U (en) Line pulley is crossed in a kind of simple and easy scissors crossing
CN104393524B (en) Avoid setting up using aerial earth wire extension pulley group job and cross over frame construction method
CN102290738B (en) Construction method for replacing 35kV line tension pole cross arm
CN204230763U (en) A kind of 10kV overhead distribution electrical verification operation insulating bar
CN203445521U (en) Draw gear for live spanning rack

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130605