CN103015743B - 一种钢结构托梁拔柱施工方法 - Google Patents

一种钢结构托梁拔柱施工方法 Download PDF

Info

Publication number
CN103015743B
CN103015743B CN201210503558.2A CN201210503558A CN103015743B CN 103015743 B CN103015743 B CN 103015743B CN 201210503558 A CN201210503558 A CN 201210503558A CN 103015743 B CN103015743 B CN 103015743B
Authority
CN
China
Prior art keywords
steel
jack
steel column
jackscrew
cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210503558.2A
Other languages
English (en)
Other versions
CN103015743A (zh
Inventor
张中善
田鹏
张鹏
周申彬
邢亚飞
侯振国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201210503558.2A priority Critical patent/CN103015743B/zh
Publication of CN103015743A publication Critical patent/CN103015743A/zh
Application granted granted Critical
Publication of CN103015743B publication Critical patent/CN103015743B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种钢结构工程托梁拔柱施工方法,属建筑施工改造领域,其施工流程包含以下步骤:在拟拆除钢柱上焊接钢牛腿并进行焊缝检测,在钢牛腿上安放并旋紧千斤顶,切除钢牛腿以上部分钢柱,顶升千斤顶,焊接补强托梁,拆除千斤顶,最后切除下段钢柱。本发明充分利用待拆除钢柱,不需要搭设满堂支撑,施工方法工艺简洁,大大缩短工期,降低施工成本,具有广阔的应用前景。

Description

一种钢结构托梁拔柱施工方法
技术领域
  本发明专利涉及建筑施工改造的技术领域,具体地说是一种钢结构托梁拔柱施工方法。
技术背景
 托梁拔柱是在不拆上部结构的情况下实施拆除柱子的一门综合性技术,传统的托梁拔柱法采用采用搭设满堂支撑的方法支撑梁和楼盖,待拆除钢柱并焊接托梁加固后,再拆除满堂支撑,完成整个加固改造,施工投入大、工期长、成本高。
发明内容
本发明提供一种钢结构托梁拔柱施工方法,所要解决的问题是传统的托梁拔柱法需搭设满堂支撑,施工投入大、工期长、成本高的问题。
本发明的目的是这样实现的:
一种钢结构托梁拔柱施工方法,具体步骤为在拟拆除钢柱1上焊接钢牛腿2并进行焊缝检测、在钢牛腿2上安放并旋紧千斤顶3、用气割拆除钢牛腿3以上部分钢柱、在待加固钢梁4下焊接T型加固钢梁5、拆除千斤顶3、拆除下段钢柱,拆除过程中需进行变形监测;
千斤顶3为普通型螺旋千斤顶,千斤顶3的规格需要根据计算选择,在使用前使用荷重传感器进行检测,确保性能良好;
变形监测是指在待加固钢梁5上安放千分表,施工过程中检测千分表读数变化以掌握卸载过程的结构变形情况。
积极有益效果:在待拆除钢柱上焊接钢牛腿,利用放置在钢牛腿上的千斤顶支撑钢梁,拆除钢牛腿以上部分钢柱,使钢柱与梁脱离,再焊接T型托梁加固,落下千斤顶,拆除钢柱下部。采用本发明拆除钢柱,施工工艺简洁方便,大大缩短施工工期,有效降低施工成本。
附图说明
图1为本发明的施工工艺流程图。
图2为钢柱拆除前安放千斤顶示意图。
图3为焊接T型加固钢梁后示意图。
图中为:待拆除钢柱1、钢牛腿2、螺旋千斤顶3、待加固钢梁4、T型加固钢梁5。
具体实施方式
下面结合附图,对本发明作进一步的说明:
如图1、图2、图3所示,具体施工步骤及操作要点如下:
步骤1,焊接钢牛腿
在待拆除钢柱的适当位置上焊接钢牛腿,钢牛腿焊接位置根据千斤顶规格确定,钢牛腿的规格尺寸需根据受力进行验算,焊接完成后进行焊缝检测。
步骤2,安放螺旋千斤顶
千斤顶的规格需要根据计算选择,在使用前使用荷重传感器进行检测,确保性能良好。把两个螺旋千斤顶放置在钢牛腿上,螺旋千斤顶对称支撑在钢梁或钢柱环板的下翼缘。
步骤3,拆除上段钢柱
  旋紧螺旋千斤顶,用气割沿切割线切割拆除钢牛腿以上部分钢柱;在切割钢柱时,采用两人对称切割,边切割边观察切割缝隙的大小变化,如果切割缝隙变小,应停止切割,调节千斤顶,增加千斤顶向上的顶应力。
  步骤4,安装补强钢梁
对加工好的补强T型加固钢梁在地面的拼装。采用在原钢梁下设置吊装葫芦的方法对钢梁进行提升,提升到位临时固定且校正合格后进行补强钢梁的焊接,焊缝焊接完成后进行焊缝探伤验收以及T型加固钢梁施工质量验收。
步骤5,千斤顶卸载
卸载前必须确保T型加固钢梁焊缝探伤验收施工质量经验收,支撑螺旋千斤顶处于很好的受力状态。在待加固钢梁上安放千分表,施工过程中检测千分表读数变化以掌握卸载过程的结构变形情况。
卸载方案采用螺旋千斤顶的自锁功能,两侧的两个千斤顶同步卸载,先卸载5mm,让结构自身受力过度完成后,再卸载至千斤顶离开钢梁的底面,完成本次卸载工作,让结构受力达到设计状态。
 步骤6,拆除下段钢柱
最后拆除下段钢柱,对焊接点部位进行打磨及油漆涂装,对补强部位进行防火涂料涂装。
以上实施例仅用于说明本发明的优选实施方式,但本发明并不限于上述实施方式,在所述领域普通技术人员所具备的知识范围内,本发明的精神和原则之内所作的任何修改、等同替代和改进等,其均应涵盖在本发明请求保护的技术方案范围之内。

Claims (1)

1.一种钢结构托梁拔柱施工方法,其特征在于其施工方法:具体步骤为
步骤1,焊接钢牛腿
在待拆除钢柱的适当位置上焊接钢牛腿,钢牛腿焊接位置根据千斤顶规格确定,钢牛腿的规格尺寸需根据受力进行验算,焊接完成后进行焊缝检测;
步骤2,安放螺旋千斤顶
千斤顶的规格需要根据计算选择,在使用前使用荷重传感器进行检测,确保性能良好;把两个螺旋千斤顶放置在钢牛腿上,螺旋千斤顶对称支撑在钢梁或钢柱环板的下翼缘;
步骤3,拆除上段钢柱
  旋紧螺旋千斤顶,用气割沿切割线切割拆除钢牛腿以上部分钢柱;在切割钢柱时,采用两人对称切割,边切割边观察切割缝隙的大小变化,如果切割缝隙变小,应停止切割,调节千斤顶,增加千斤顶向上的顶应力;
步骤4,安装补强钢梁
对加工好的补强T型加固钢梁在地面的拼装,采用在原钢梁下设置吊装葫芦的方法对钢梁进行提升,提升到位临时固定且校正合格后进行补强钢梁的焊接,焊缝焊接完成后进行焊缝探伤验收以及T型加固钢梁施工质量验收;
步骤5,千斤顶卸载
卸载前必须确保T型加固钢梁焊缝探伤验收施工质量经验收,支撑螺旋千斤顶处于很好的受力状态;在待加固钢梁上安放千分表,施工过程中检测千分表读数变化以掌握卸载过程的结构变形情况;
卸载方案采用螺旋千斤顶的自锁功能,两侧的两个千斤顶同步卸载,先卸载5mm,让结构自身受力过度完成后,再卸载至千斤顶离开钢梁的底面,完成本次卸载工作,让结构受力达到设计状态;
步骤6,拆除下段钢柱
最后拆除下段钢柱,对焊接点部位进行打磨及油漆涂装,对补强部位进行防火涂料涂装。
CN201210503558.2A 2012-12-01 2012-12-01 一种钢结构托梁拔柱施工方法 Active CN103015743B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210503558.2A CN103015743B (zh) 2012-12-01 2012-12-01 一种钢结构托梁拔柱施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210503558.2A CN103015743B (zh) 2012-12-01 2012-12-01 一种钢结构托梁拔柱施工方法

Publications (2)

Publication Number Publication Date
CN103015743A CN103015743A (zh) 2013-04-03
CN103015743B true CN103015743B (zh) 2015-11-04

Family

ID=47964800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210503558.2A Active CN103015743B (zh) 2012-12-01 2012-12-01 一种钢结构托梁拔柱施工方法

Country Status (1)

Country Link
CN (1) CN103015743B (zh)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005569A (zh) * 2014-06-20 2014-08-27 方大特钢科技股份有限公司 一种托梁拔柱施工方法
CN105442866B (zh) * 2014-08-28 2017-12-19 上海宝冶集团有限公司 用于大型高耸钢结构的保护性拆除和安装方法
CN105064717B (zh) * 2015-07-24 2017-03-29 武大巨成结构股份有限公司 一种钢滑道顶升建筑物增层的施工方法
CN105002985A (zh) * 2015-07-31 2015-10-28 中铁城市规划设计研究院有限公司 门刚抽柱托梁结构
CN105328799B (zh) * 2015-11-05 2017-09-12 盐城亿之诺机械有限公司 一种假牛腿切除装置
CN105756368A (zh) * 2016-04-06 2016-07-13 上海十三冶建设有限公司 一种简便的重型工业厂房托梁拔柱施工方法
CN105781142B (zh) * 2016-04-26 2017-10-17 中南大学 用于建筑结构顶层抽柱的加固结构及加固方法
CN106836845B (zh) * 2017-04-12 2023-06-20 广州市胜特建筑科技开发有限公司 托梁拔柱后预留结构的变形控制方法及系统
CN108166770B (zh) * 2017-11-27 2020-12-01 广东精特建设工程有限公司 关于建筑结构柱切割免支撑的一种切除方法
CN111648618A (zh) * 2020-05-31 2020-09-11 杭州圣基建筑特种工程有限公司 大跨度托梁抽柱挠度控制方法
CN112502471B (zh) * 2020-12-30 2022-06-28 中国电建集团河南省电力勘测设计院有限公司 一种钢框架结构托梁拔柱改造加固方法及结构
CN114482592A (zh) * 2021-11-26 2022-05-13 北京建工四建工程建设有限公司 皮带廊托梁拔柱改造施工方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476397A (zh) * 2009-01-15 2009-07-08 二十三冶建设集团有限公司 钢屋架与砼柱铰接的厂房屋盖整体顶升方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5617130B2 (ja) * 2010-12-27 2014-11-05 戸田建設株式会社 建築物の解体工法と、解体装置

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476397A (zh) * 2009-01-15 2009-07-08 二十三冶建设集团有限公司 钢屋架与砼柱铰接的厂房屋盖整体顶升方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
混凝土结构加固技术的研究(九);万墨林,韩继云;《施工技术》;19941130(第11期) *

Also Published As

Publication number Publication date
CN103015743A (zh) 2013-04-03

Similar Documents

Publication Publication Date Title
CN103015743B (zh) 一种钢结构托梁拔柱施工方法
WO2022062294A1 (zh) 一种用于大跨度悬挑钢桁架悬挂连接节点及其施工方法
CN101886466B (zh) 捣固式焦炉煤塔模板支撑结构的施工方法
CN101603372B (zh) 高层建筑钢筋砼柱整体置换砼加固方法
CN103422674B (zh) 装配式混凝土结构现浇段混凝土施工方法
CN102587689B (zh) 一种既有钢筋混凝土梁柱节点的修复和加固方法
CN205000974U (zh) 一种用于隧道开挖施工的轮胎式自动升降组装台架
CN106836498A (zh) 一种超大跨度体育场看台屋盖钢桁架吊装施工工法
CN103981897B (zh) 一种地下室外墙劲性柱的防水施工方法
CN109488039B (zh) 一种内置螺旋调节千斤顶钢筋混凝土柱置换加固结构及其加固方法
CN207863507U (zh) 一种用于高层建筑楼层的竖向构件置换装置
CN203947771U (zh) 一种贝雷梁悬吊模板支撑体系
CN104141318A (zh) 一种大直径钢管柱柱脚安装施工方法
CN107060070A (zh) 荷载转移装置及用该装置吊装钢连廊的施工方法
CN204589822U (zh) 一种独柱双悬臂盖梁抱箍施工支撑系统
CN107939050A (zh) 一种基于拼装胎架的钢结构件拼装工艺
CN103216103A (zh) 环形屋盖的斜弧形组合钢结构柱安装预变形施工方法
CN204552141U (zh) 一种用于梁支柱置换施工的支撑结构
CN105756368A (zh) 一种简便的重型工业厂房托梁拔柱施工方法
CN108051161B (zh) 一种考虑约束效应的钢吊车梁结构完整性评估方法
CN102691267A (zh) 一种外置整体操作平台高墩施工方法
CN103046743B (zh) 一种超高层转换层型钢混凝土大梁吊挂式模板支撑体系及施工方法
CN205502623U (zh) 一种建筑结构加固用连接装置
CN106996083B (zh) 一种对架桥机进行加固的方法
CN207332305U (zh) 一种塔柱施工内爬架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant