CN103015318A - 一种内套式斜拉索主塔索导管及其施工方法 - Google Patents

一种内套式斜拉索主塔索导管及其施工方法 Download PDF

Info

Publication number
CN103015318A
CN103015318A CN2012104686393A CN201210468639A CN103015318A CN 103015318 A CN103015318 A CN 103015318A CN 2012104686393 A CN2012104686393 A CN 2012104686393A CN 201210468639 A CN201210468639 A CN 201210468639A CN 103015318 A CN103015318 A CN 103015318A
Authority
CN
China
Prior art keywords
pipe
cable guide
guide pipe
built
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104686393A
Other languages
English (en)
Other versions
CN103015318B (zh
Inventor
刘汉顺
张强
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Original Assignee
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Reconnaissance and Design Institute Co Ltd filed Critical China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority to CN201210468639.3A priority Critical patent/CN103015318B/zh
Publication of CN103015318A publication Critical patent/CN103015318A/zh
Application granted granted Critical
Publication of CN103015318B publication Critical patent/CN103015318B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种内套式拉索主塔索导管及其施工方法。主塔内预埋的预埋管的安装角度与索导管相同,预埋管与主塔外侧平齐,预埋管内端头的预埋板与斜拉索锚块混凝土面齐平,索导管外端露出主塔外侧,内端头接锚垫板,锚垫板和预埋板焊接,索导管和预埋管之间留有空隙。施工方法是,在需要浇筑混凝土的主塔节段内预埋预埋管,完成混凝土浇筑后,顶升主塔模板,在预埋管内安装索导管, 两管间留有空隙,在预埋管外端头和索导管之间安装环状封堵,从压浆口压浆,即完成内套索导管的安装。本发明不在主塔模板上开索导管的孔洞,可延长模板的使用周期,节省下模板开孔放样时间;没有外露索导管的阻碍,施工进度快,工作效率高。本发明适用于混凝土主塔,斜拉索导管外露出主塔壁的情况。

Description

一种内套式斜拉索主塔索导管及其施工方法
技术领域
本发明涉及一种新型的内套式拉索主塔索导管及其施工方法。可用于公路和铁路的斜拉桥。设计适用范围为:钢绞线斜拉索和平行钢丝斜拉索。
背景技术
近几十年来,随着我国社会经济的高速发展,修建了大量的公路和铁路斜拉桥。这些斜拉桥中主塔基本都采用混凝土结构。为了斜拉索的安装和锚固,需要在主塔塔壁内预埋索导管。如果索导管长度较长,伸出了塔壁外侧,则需要在主塔模板上开孔,使索导管能够外露。因索导管的角度、位置等各不相同,因此模板开孔大小位置也不同。反复开孔必然减短了模板使用寿命。同时因为索导管外露,也对模板顶升形成阻碍。
发明内容
本发明目的是针对上述现状,旨在提供一种不需要在主塔上开孔,模板提升时无阻碍,施工进度快,工作效率高的内套式拉索主塔索导管及其施工方法。
本发明目的的实现方式为:一种内套式拉索主塔索导管,主塔内预埋的预埋管的安装角度与索导管相同,预埋管与主塔外侧平齐,预埋管内端头的预埋板与斜拉索锚块混凝土面齐平,索导管外端露出主塔外侧,内端头接锚垫板,锚垫板和预埋板焊接,索导管和预埋管之间留有空隙。
内套式拉索主塔索导管的施工方法,具体步骤如下:
1)在需要浇筑混凝土的主塔节段内预埋预埋管,预埋管的安装角度与索导管相同,预埋管与主塔外侧平齐,预埋管内端头的预埋板与斜拉索锚块混凝土面齐平;
2)完成节段混凝土浇筑后,顶升主塔模板,主塔模板顶升后,在预埋管内安装索导管, 索导管和预埋管之间留有空隙, 3)索导管外端露出主塔外侧,内端头接锚垫板,将锚垫板与预埋管内端头的预埋板焊接在一起,
4)在预埋管外端头和索导管之间安装环状封堵,环状封堵内、外分别与索导管、预埋管焊接,
5)在主塔内,下方开与索导管和预埋管之间空隙相通的压浆口,下方开与索导管和预埋管之间空隙相通的出浆口。
6)从压浆口压浆,即完成内套索导管的安装。
本发明将索导管设计为内套式结构,索导管套在预埋管内。主塔施工时先安装预埋管,因预埋管不外露,因此不需要在模板上开孔,也不会对模板顶升形成阻碍;模板顶升后,在已完成的节段,安装索导管,虽然索导管伸出塔壁外侧,但不会影响施工;预埋管端部和内套管之间设置封堵环,在压浆时可避免水泥浆外溢。
本发明不在主塔模板上开索导管的孔洞,可延长模板的使用周期,节省下模板开孔放样时间;没有外露索导管的阻碍,大大减小模板顶升难度,可加快现场的施工进度。本发明适用于混凝土主塔,斜拉索导管外露出主塔壁的情况。
附图说明
图1为预埋管埋设状态图,
图2为内套管结构示意图,
图3为内套管与预埋管组装图,
图4为图3的 1—1向视图,
图5为图3的2—2向视图,
图6为图3 A部分放大图。
具体实施方式
本发明是一种内套式拉索主塔索导管,主塔内预埋的预埋管的安装角度与索导管相同,预埋管1与主塔外侧平齐,预埋管内端头的预埋板2与斜拉索锚块3混凝土面齐平,索导管4外端露出主塔外侧,内端头接锚垫板5,锚垫板和预埋板2焊接,索导管4和预埋管1之间留有空隙。
索导管和预埋管之间留有空隙上方接出浆口7,下方接压浆口6,以保证压浆密实。预埋管1外端头和索导管4之间应有环状封堵8,避免压浆时浆体外流。
本发明是一种内套式拉索主塔索导管的施工方法,具体步骤如下:
1)在需要浇筑混凝土的主塔节段内预埋预埋管1,预埋管的安装角度与索导管相同,预埋管1与主塔外侧平齐,预埋管内端头的预埋板2与斜拉索锚块3混凝土面齐平(见图1);
2)完成节段混凝土浇筑后,顶升主塔模板,主塔模板顶升后,在预埋管1内安装索导管4, 索导管4和预埋管1之间留有空隙,
3)索导管4外端露出主塔外侧,内端头接锚垫板5,将锚垫板与预埋管内端头的预埋板2焊接在一起(见图1、2、3),
4)在预埋管1外端头和索导管4之间安装环状封堵8,环状封堵8内、外分别与索导管4、预埋管1焊接(见图6),
5)在主塔模板内上、下方开与索导管和预埋管之间空隙上方相通的出浆口7,上方相通的压浆口6(见图3、4、5),
6)从压浆口6压浆,在索导管和预埋管之间充满水泥浆9,多余的水泥浆从出浆口7流出,即完成内套索导管的安装。

Claims (4)

1.一种内套式拉索主塔索导管,其特征在于主塔内预埋的预埋管的安装角度与索导管相同,预埋管与主塔外侧平齐,预埋管内端头的预埋板与斜拉索锚块混凝土面齐平,索导管外端露出主塔外侧,内端头接锚垫板,锚垫板和预埋板焊接,索导管和预埋管之间留有空隙。
2.根据专利要求1所述的一种内套式拉索主塔索导管,其特征在于索导管和预埋管之间留有空隙上方接出浆口(7),下方接压浆口(6)。
3.根据专利要求1所述的一种内套式拉索主塔索导管,其特征在于预埋管(1)外端头和索导管(4)之间应有环状封堵(8)。
4.一种权利要求1所述的内套式拉索主塔索导管的施工方法,其特征在于具体步骤如下:
1)在需要浇筑混凝土的主塔节段内预埋预埋管,预埋管的安装角度与索导管相同,预埋管与主塔外侧平齐,预埋管内端头的预埋板与斜拉索锚块混凝土面齐平;
2)完成节段混凝土浇筑后,顶升主塔模板,主塔模板顶升后,在预埋管内安装索导管, 索导管和预埋管之间留有空隙,
3)索导管外端露出主塔外侧,内端头接锚垫板,将锚垫板与预埋管内端头的预埋板焊接在一起,
4)在预埋管外端头和索导管之间安装环状封堵,环状封堵内、外分别与索导管、预埋管焊接,
5)在主塔内,下方开与索导管和预埋管之间空隙相通的压浆口,下方开与索导管和预埋管之间空隙相通的出浆口,
6)从压浆口压浆,即完成内套索导管的安装。
CN201210468639.3A 2012-11-19 2012-11-19 一种内套式斜拉索主塔索导管及其施工方法 Active CN103015318B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210468639.3A CN103015318B (zh) 2012-11-19 2012-11-19 一种内套式斜拉索主塔索导管及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210468639.3A CN103015318B (zh) 2012-11-19 2012-11-19 一种内套式斜拉索主塔索导管及其施工方法

Publications (2)

Publication Number Publication Date
CN103015318A true CN103015318A (zh) 2013-04-03
CN103015318B CN103015318B (zh) 2015-03-18

Family

ID=47964382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210468639.3A Active CN103015318B (zh) 2012-11-19 2012-11-19 一种内套式斜拉索主塔索导管及其施工方法

Country Status (1)

Country Link
CN (1) CN103015318B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590333A (zh) * 2013-11-26 2014-02-19 中铁大桥勘测设计院集团有限公司 分段后装式斜拉索主塔索导管结构
CN104088228A (zh) * 2014-07-24 2014-10-08 中建三局集团有限公司 无牛腿钢锚梁电加热施加预应力的方法
CN106436576A (zh) * 2016-08-24 2017-02-22 广西长长路桥建设有限公司 一种斜拉桥主塔环向预应力施工工法
CN109024295A (zh) * 2018-08-22 2018-12-18 中铁九局集团第二工程有限公司 基于测量机器人测量定位斜拉桥梁端索导管的施工方法
CN114016405A (zh) * 2021-11-26 2022-02-08 中铁二局集团有限公司 一种斜拉桥塔柱索导管的安装方法
CN114134814A (zh) * 2021-11-16 2022-03-04 中铁广州工程局集团有限公司 一种锚垫板与预埋钢管精确定位施工方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003055911A (ja) * 2001-08-13 2003-02-26 Sumitomo Electric Ind Ltd 斜材ケーブルのサドル出口部における構造
CN1936188A (zh) * 2006-10-16 2007-03-28 江阴法尔胜住电新材料有限公司 斜拉索纠偏装置
CN200955122Y (zh) * 2006-10-16 2007-10-03 江阴法尔胜住电新材料有限公司 带楔块的双重管式索鞍
JP2008169675A (ja) * 2007-01-15 2008-07-24 Sumitomo Mitsui Construction Co Ltd サドル構造体
KR20100043165A (ko) * 2010-02-04 2010-04-28 스미토모 덴코 스틸 와이어 가부시키가이샤 새들 구조체와 긴장용 케이블
CN201553986U (zh) * 2009-12-10 2010-08-18 中国水电顾问集团华东勘测设计研究院 斜拉索钢锚固梁结构
CN202989776U (zh) * 2012-11-19 2013-06-12 中铁大桥勘测设计院集团有限公司 一种内套式斜拉索主塔索导管

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003055911A (ja) * 2001-08-13 2003-02-26 Sumitomo Electric Ind Ltd 斜材ケーブルのサドル出口部における構造
CN1936188A (zh) * 2006-10-16 2007-03-28 江阴法尔胜住电新材料有限公司 斜拉索纠偏装置
CN200955122Y (zh) * 2006-10-16 2007-10-03 江阴法尔胜住电新材料有限公司 带楔块的双重管式索鞍
JP2008169675A (ja) * 2007-01-15 2008-07-24 Sumitomo Mitsui Construction Co Ltd サドル構造体
CN201553986U (zh) * 2009-12-10 2010-08-18 中国水电顾问集团华东勘测设计研究院 斜拉索钢锚固梁结构
KR20100043165A (ko) * 2010-02-04 2010-04-28 스미토모 덴코 스틸 와이어 가부시키가이샤 새들 구조체와 긴장용 케이블
CN202989776U (zh) * 2012-11-19 2013-06-12 中铁大桥勘测设计院集团有限公司 一种内套式斜拉索主塔索导管

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590333A (zh) * 2013-11-26 2014-02-19 中铁大桥勘测设计院集团有限公司 分段后装式斜拉索主塔索导管结构
CN104088228A (zh) * 2014-07-24 2014-10-08 中建三局集团有限公司 无牛腿钢锚梁电加热施加预应力的方法
CN104088228B (zh) * 2014-07-24 2016-04-13 中建三局集团有限公司 无牛腿钢锚梁电加热施加预应力的方法
CN106436576A (zh) * 2016-08-24 2017-02-22 广西长长路桥建设有限公司 一种斜拉桥主塔环向预应力施工工法
CN109024295A (zh) * 2018-08-22 2018-12-18 中铁九局集团第二工程有限公司 基于测量机器人测量定位斜拉桥梁端索导管的施工方法
CN109024295B (zh) * 2018-08-22 2020-03-17 中铁九局集团第二工程有限公司 基于测量机器人测量定位斜拉桥梁端索导管的施工方法
CN114134814A (zh) * 2021-11-16 2022-03-04 中铁广州工程局集团有限公司 一种锚垫板与预埋钢管精确定位施工方法
CN114134814B (zh) * 2021-11-16 2023-12-22 中铁广州工程局集团有限公司 一种锚垫板与预埋钢管精确定位施工方法
CN114016405A (zh) * 2021-11-26 2022-02-08 中铁二局集团有限公司 一种斜拉桥塔柱索导管的安装方法

Also Published As

Publication number Publication date
CN103015318B (zh) 2015-03-18

Similar Documents

Publication Publication Date Title
CN103015318B (zh) 一种内套式斜拉索主塔索导管及其施工方法
CN102425310B (zh) 装配式住宅剪力墙结构墙体竖向连接施工方法
CN204753844U (zh) 圆钢管混凝土柱套筒连接节点
CN203022024U (zh) 一种管廊现浇施工整体移动式模架
CN102966121A (zh) 一种管廊现浇施工整体移动式模架
CN107386127B (zh) 一种桥墩拼装装置
CN106437767A (zh) 隧道预埋槽道安装结构以及隧道预埋槽道安装方法
CN205530344U (zh) 一种分体式无模浇筑地下综合管廊
CN109024870A (zh) 装配式地下结构竖向构件的连接结构及其施工方法
CN110273531A (zh) 一种地铁车站预制轨顶风道施工方法
CN105970803B (zh) 装配式桥墩的抗剪耗能装置及施工方法
CN108999281A (zh) 一种新型预制混凝土梁柱节点及其施工方法
CN205662838U (zh) 预制节段拼装桥墩的预应力连接构造
CN204112525U (zh) 高强度混凝土预制框架内嵌带竖缝预制剪力墙结构
CN203807931U (zh) 一种预制桥墩与基础的连接结构
CN205063056U (zh) 装配式建筑外墙干挂节点的防腐结构
CN113863166A (zh) 一种先转体后安装支座的逆序施工方法
CN211080782U (zh) 一种灌浆套筒
CN202989776U (zh) 一种内套式斜拉索主塔索导管
CN101545259A (zh) 钻孔桩非水下灌注混凝土的装置和方法
CN201511439U (zh) 箱梁钢筋骨架整体绑扎、整体吊装系统
CN207525779U (zh) 一种循环使用的组装式综合管廊基坑支护与结构外模组合结构
CN203668894U (zh) 可快速安装的混凝土预制模板结构
CN109914476A (zh) 一种现浇城市综合管廊的施工工艺
CN114197526B (zh) 一种逆作法竖向结构支模体系及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant