CN102774740B - Arc balancing beam - Google Patents

Arc balancing beam Download PDF

Info

Publication number
CN102774740B
CN102774740B CN201210291870.XA CN201210291870A CN102774740B CN 102774740 B CN102774740 B CN 102774740B CN 201210291870 A CN201210291870 A CN 201210291870A CN 102774740 B CN102774740 B CN 102774740B
Authority
CN
China
Prior art keywords
arc
equalizing bar
pulley
hoist
hoist cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210291870.XA
Other languages
Chinese (zh)
Other versions
CN102774740A (en
Inventor
王海波
徐明贤
屈振江
张金钟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Merchants Heavy Industry Shenzhen Co Ltd
Original Assignee
China Merchants Heavy Industry Shenzhen Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Merchants Heavy Industry Shenzhen Co Ltd filed Critical China Merchants Heavy Industry Shenzhen Co Ltd
Priority to CN201210291870.XA priority Critical patent/CN102774740B/en
Publication of CN102774740A publication Critical patent/CN102774740A/en
Application granted granted Critical
Publication of CN102774740B publication Critical patent/CN102774740B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an arc balancing beam, which is characterized in that a beam body of the arc balancing beam is arc-shaped along the horizontal direction, a plurality of lifting points of the arc balancing beam are distributed into an arc shape consistent with the shape of a lifted arc barrel consisting of a plurality of devices, the number of the lifting points can be the same as that of the devices, and the positions of the lifting points are consistent with those of the devices. The balancing beam disclosed by the invention can conveniently lift an arc barrel consisting of a plurality of plate-type assembling structures which are distributed in an arc shape, and the lifting operation is high in efficiency, and is safe and reliable.

Description

A kind of arc equalizing bar
Technical field
The present invention relates to lifting construction equipment, particularly relate to a kind of arc equalizing bar.
Background technology
Equalizing bar is the important component part of hoisting machine tool, in lifting engineering, is widely used.Equalizing bar claims again fringed iris herb, can be used for the balance that equipment is hung in maintenance, avoids hoist cable damage equipment; Shorten the height of hoist cable, reduce the sling height of movable pulley; The horizontal pressure bearing when the lifting of minimizing equipment, avoids damage equipment.But general equalizing bar cannot efficiently and safely and reliably solve the lifting problem of the arc cylindrical shell part of large-scale arc plate type assembled.
In addition, general equalizing bar upper end is connected with loop wheel machine pulley by suspension hook, steel rope, shackle, from suspension hook to equalizing bar, need take larger working space, and, in equalizing bar lower end, be to hang over by shackle with steel rope on the otic placode of equalizing bar bottom to realize lifting, connect distance longer.This causes existing equalizing bar cannot meet the lifting operation that preparation of construction is had to the specific workyard that operation height restriction requires (as near Active workings airport etc.).
Summary of the invention
Main purpose of the present invention is exactly for the deficiencies in the prior art, and a kind of arc equalizing bar is provided, and can lift easily the arc cylindrical shell of many plate type assembled structures compositions of arc distribution, and efficiency is high, safe and reliable.
For achieving the above object, the present invention is by the following technical solutions:
A kind of arc equalizing bar, the beam body along continuous straight runs of described arc equalizing bar is curved, and what multiple suspension centres of described arc equalizing bar were arranged to form with many members is hung the consistent arc of arc cylindrical shell.
Preferably, to have the quantity identical with member position corresponding consistent with each member for the suspension centre of described arc equalizing bar.But in the situation that meeting safety, several members of not getting rid of linking together adopt a suspension centre.
Preferably, the beam body of described arc equalizing bar comprises the box-like body and a series of horizontal inner side gussets that are connected two arcuate flanks with two arcuate flanks.Thus, can conveniently increase or reduce suspension centre for actual needs.
Preferably, the top level of described arc equalizing bar is provided with the main otic placode of two subtend upper process symmetrically, plate body is vertical with the beam body of described arc equalizing bar, on described main otic placode, offer the hole for hoist for lifting main shaft is installed, hole for hoist on every pair of main otic placode and execute hole for hoist on the corresponding loop wheel machine pulley of loop wheel machine all by a lifting main shaft, for two pairs of main otic placodes and two loop wheel machine pulleys are connected and fixed separately.
Preferably, described arc equalizing bar is provided with the pulley pallet for location, leading sheave.
Preferably, described pulley pallet comprises perpendicular to the horizontal component of beam body and upwards extends to form the part of groove from horizontal component both sides, described loop wheel machine pulley bottom is provided with pulley base, hole for hoist on described loop wheel machine pulley is opened on described pulley base, the described pulley base of described groove for locating, leading and be placed therein, bottom and the both sides of described groove and described pulley base are the arc cooperatively interacting on cross-sectional plane.
Preferably, each suspension centre comprises the some paired small ear plate that is positioned at described arc equalizing bar top, described arc equalizing bar is provided with the hoist cable passage that runs through up and down beam body, described some paired small ear plates are arranged on the hoist cable channel exit both sides at arc equalizing bar top in opposite directions, on described small ear plate, offer little axle mounting hole, on the little axle mounting hole of every pair of small ear plate, the little axle across described hoist cable channel outlet is installed, hoist cable is fixed on described little axle and extends to the below of described arc equalizing bar through described hoist cable passage, the lower end of hoist cable is hung member by shackle with quilt and is connected.
Preferably, described hoist cable passage is vertically offered along described arc equalizing bar horizontal surface midway location.
The technique effect that the present invention is useful is:
The present invention is directed to the large-scale arc Barrel hoisting demand assembled by the lath of some quantity, the curved arc equalizing bar of beam body along continuous straight runs has been proposed, its suspension centre is arranged to and is hung the consistent arc of arc cylindrical shell, thereby can lift easily the arc cylindrical shell including many plate type assembled structures, efficiency is high, safe and reliable.The present invention is specially adapted to the lifting construction of the large-scale workpieces such as the thin-walled arc body that strip type framing member is assembled into.
Brief description of the drawings
Fig. 1 is the arc equalizing bar birds-eye view of one embodiment of the invention; .
Fig. 2 is the lifting schematic diagram of one embodiment of the invention;
Fig. 3 is the stage casing enlarged diagram of the arc equalizing bar shown in Fig. 1;
Fig. 4 is the left-half enlarged diagram of the arc equalizing bar shown in Fig. 1;
Fig. 5 is the connection diagram (H-H cross section) of suspension centre and the pulley of an embodiment;
Fig. 6 is the main otic placode structural representation (C-C cross section) of an embodiment;
Fig. 7 is the beam body schematic cross-section (Q-Q cross section) of an embodiment;
Fig. 8 is the structural representation of the hoist cable passage of an embodiment;
Fig. 9 is the small ear plate structural representation of an embodiment.
Detailed description of the invention
By reference to the accompanying drawings the present invention is described in further detail by the following examples.
Refer to Fig. 1 and Fig. 2, in some embodiments, the beam body along continuous straight runs of arc equalizing bar is curved, and the suspension centre of described arc equalizing bar is arranged the arc that is hung arc cylindrical shell consistent (arc herein all refers to non-full circle) with many member compositions.
In an embodiment, the suspension centre of described arc equalizing bar is consistent with the member that is hung arc cylindrical shell with on installation site in quantity.,, in this embodiment, hung each member of arc cylindrical shell to there being a suspension centre, and mutual alignment relation is one to one.
But, in the situation that meeting safety, do not get rid of arc equalizing bar the multiple members that link together are executed and hung with a suspension centre.
As shown in Figure 1, Figure 3 and Figure 4, in preferred embodiment, the beam body of described arc equalizing bar is joined and forms successively by a series of box-like body and inner side gussets with arcuate flanks.A benefit of this design is conveniently for actual needs change beam body size, to comprise and to increase or reduce suspension centre.
As shown in Fig. 2, Fig. 4-Fig. 6, at two places separated by a distance, arc equalizing bar top, every place is provided with a pair of main otic placode 6 to upper process, lifting main shaft 1 is through the hole for hoist of main otic placode 6 and the hole for hoist of loop wheel machine pulley 3, directly main otic placode 6 is connected with loop wheel machine pulley 3, thereby loop wheel machine pulley 3 is connected with arc equalizing bar 5, and by the nut fixation on it.As shown in Figure 5, preferably, arc equalizing bar upper end is provided with pulley pallet 2, location, guiding while lifting for pulley.Loop wheel machine pulley 3 matches with loop wheel machine steel rope 4.
Equalizing bar in the past all passes through suspension hook, steel rope, shackle and is connected with loop wheel machine pulley (general pulley is made as one with suspension hook), the present embodiment has been cancelled suspension hook and the shackle on equalizing bar top, pulley is directly connected with the main otic placode of equalizing bar by lifting main shaft, reduce top and connected distance, can save like this suspension hook, steel rope, shackle and be connected needed space with equalizing bar.
In an embodiment, as the hanger that hangs below hoist cable, arc equalizing bar top is distributed with and the paired small ear plate 12 of member equivalent amount by arc, and makes the layout of small ear plate consistent with the radian that arc barrel components 11 distributes.
As shown in Figure 5-Figure 8, this arc equalizing bar inside is provided with the wire rope sling passage 8 that runs through up and down equalizing bar, respectively there is a small ear plate 12 hoist cable channel exit both sides in the upper plane of arc equalizing bar, as the hanger of the wire rope sling 9 of suspension element, little axle 7 cross-ties are arranged in the little axle mounting hole of every a pair of small ear plate 12.Lifting wire rope sling 9 passes by hoist cable passage, is fixed on little axle 7.Under equalizing bar, can hoist cable be hung to member 11 with quilt by shackle 10 is connected.Shackle can be general lockset.This design, lifting wire rope sling 9 passes by the hoist cable passage 8 of equalizing bar inside, the length of hoist cable 9 is hidden in the middle of arc equalizing bar to greatest extent, for lifting space has been saved in the lifting of member 11, shorten hoisting height, therefore can reduce the operating altitude of loop wheel machine.Suspension centre is located to equalizing bar top, is also convenient to unload steel rope.
As shown in Figure 1, Figure 3 and Figure 4, wire rope sling passage is preferably arranged on the line of centers of equalizing bar longitudinal (being horizontal direction).
In preferred embodiment, adopt aforementioned arrangements that the upper and lower lifting of equalizing bar is reduced the distance simultaneously, can more effectively solve and hang high limited problem, also solve the problem that facilitates rope unloading simultaneously.
In a practical application example, loop wheel machine, arc equalizing bar and to be hung the concrete installation process of arc cylindrical shell as follows:
(1) member of the arc cylindrical shell assembled some laths being formed (arc cylindrical shell conventionally by lath splicing in specific frock in advance that for example approximately many single-pieces of 20 ~ 30m are very long, close up form) be connected with cable wire end 9 accordingly by shackle 10 one by one, as treating hanging piece 11;
(2) arc equalizing bar 5 is placed in above the frock of assembled arc cylindrical shell;
(3) each cable wire end 9 is connected with the little axle 7 being arranged on small ear plate 12 through hoist cable passage 8 in the middle of corresponding arc equalizing bar;
(4) loop wheel machine pulley 3 is placed on arc equalizing bar 5 by pulley pallet 2 guiding;
(5) lifting main shaft 1, successively through the hole for hoist of the main otic placode 6 of arc equalizing bar and the hole for hoist of pulley 3, is connected loop wheel machine pulley 3 with arc equalizing bar 5, and the nut screwing clamping on it is firm to install.
After above-mentioned steps completes, check and just can implement lifting after errorless.
Above content is in conjunction with concrete preferred implementation further description made for the present invention, can not assert that specific embodiment of the invention is confined to these explanations.For general technical staff of the technical field of the invention, without departing from the inventive concept of the premise, can also make some simple deduction or replace, all should be considered as belonging to protection scope of the present invention.

Claims (7)

1. an arc equalizing bar, it is characterized in that, the beam body along continuous straight runs of described arc equalizing bar is curved, what multiple suspension centres of described arc equalizing bar were arranged to form with many members is hung the consistent arc of arc cylindrical shell, each suspension centre comprises the some paired small ear plate that is positioned at described arc equalizing bar top, described arc equalizing bar is provided with the some hoist cable passages that run through up and down beam body, described some paired small ear plates are arranged on the hoist cable channel exit both sides at arc equalizing bar top in opposite directions, on described small ear plate, offer little axle mounting hole, on the little axle mounting hole of every pair of small ear plate, the little axle across described hoist cable channel outlet is installed, hoist cable is fixed on described little axle and extends to the below of described arc equalizing bar through described hoist cable passage, the lower end of hoist cable is hung member by shackle with quilt and is connected.
2. arc equalizing bar as claimed in claim 1, is characterized in that, the suspension centre of described arc equalizing bar has the quantity identical with member and position is corresponding consistent with each member.
3. arc equalizing bar as claimed in claim 1, is characterized in that, the beam body of described arc equalizing bar comprises the box-like body and a series of horizontal inner side gussets that are connected two arcuate flanks with two arcuate flanks.
4. arc equalizing bar as claimed in claim 1, it is characterized in that, the top level of described arc equalizing bar is provided with the main otic placode of two subtend upper process symmetrically, plate body is vertical with the beam body of described arc equalizing bar, on described main otic placode, offer the hole for hoist for lifting main shaft is installed, hole for hoist on every pair of main otic placode and execute hole for hoist on the corresponding loop wheel machine pulley of loop wheel machine all by a lifting main shaft, for two pairs of main otic placodes and two loop wheel machine pulleys are connected and fixed separately.
5. arc equalizing bar as claimed in claim 3, is characterized in that, described arc equalizing bar is provided with the pulley pallet for location, guiding loop wheel machine pulley.
6. arc equalizing bar as claimed in claim 5, it is characterized in that, described pulley pallet comprises perpendicular to the horizontal component of beam body and upwards extends to form the part of groove from horizontal component both sides, described loop wheel machine pulley bottom is provided with pulley base, hole for hoist on described loop wheel machine pulley is opened on described pulley base, the described pulley base of described groove for locating, leading and be placed therein, bottom and the both sides of described groove and described pulley base are the arc cooperatively interacting on cross-sectional plane.
7. arc equalizing bar as claimed in claim 1, is characterized in that, described hoist cable passage is vertically offered along described arc equalizing bar horizontal surface midway location.
CN201210291870.XA 2012-08-16 2012-08-16 Arc balancing beam Expired - Fee Related CN102774740B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210291870.XA CN102774740B (en) 2012-08-16 2012-08-16 Arc balancing beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210291870.XA CN102774740B (en) 2012-08-16 2012-08-16 Arc balancing beam

Publications (2)

Publication Number Publication Date
CN102774740A CN102774740A (en) 2012-11-14
CN102774740B true CN102774740B (en) 2014-10-29

Family

ID=47119885

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210291870.XA Expired - Fee Related CN102774740B (en) 2012-08-16 2012-08-16 Arc balancing beam

Country Status (1)

Country Link
CN (1) CN102774740B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107601257A (en) * 2017-10-26 2018-01-19 上海市安装工程集团有限公司 Large scale arc special hoisting bar and its application method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200951923Y (en) * 2006-09-19 2007-09-26 张宏生 Transverse hanging bean for railway hoister
CN201330136Y (en) * 2009-01-12 2009-10-21 陈炯 Arc crane boom
CN201362570Y (en) * 2008-12-26 2009-12-16 佑图物理应用科技发展(武汉)有限公司 Rotary moving pulley for stage crane
CN201439475U (en) * 2009-08-11 2010-04-21 渤海船舶重工有限责任公司 Multifunctional balance hanging beam
CN201923769U (en) * 2011-02-22 2011-08-10 抚顺隆基电磁科技有限公司 Bridge type hanging beam for permanent magnet jack
CN201980837U (en) * 2010-12-24 2011-09-21 本钢板材股份有限公司 Lifting appliance for replacing furnace top roller of annealing furnace

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU1785987C (en) * 1990-11-22 1993-01-07 Черноморское Отделение Морских Берегозащитных Сооружений Им.А.М.Жданова Всесоюзного Научно-Исследовательского Института Транспортного Строительства Load gripper
CN201268549Y (en) * 2008-06-06 2009-07-08 中国海洋石油总公司 Hoisting appliance for offshore wind power generation tower frame

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200951923Y (en) * 2006-09-19 2007-09-26 张宏生 Transverse hanging bean for railway hoister
CN201362570Y (en) * 2008-12-26 2009-12-16 佑图物理应用科技发展(武汉)有限公司 Rotary moving pulley for stage crane
CN201330136Y (en) * 2009-01-12 2009-10-21 陈炯 Arc crane boom
CN201439475U (en) * 2009-08-11 2010-04-21 渤海船舶重工有限责任公司 Multifunctional balance hanging beam
CN201980837U (en) * 2010-12-24 2011-09-21 本钢板材股份有限公司 Lifting appliance for replacing furnace top roller of annealing furnace
CN201923769U (en) * 2011-02-22 2011-08-10 抚顺隆基电磁科技有限公司 Bridge type hanging beam for permanent magnet jack

Also Published As

Publication number Publication date
CN102774740A (en) 2012-11-14

Similar Documents

Publication Publication Date Title
CN201864516U (en) Lifting appliance special for overhauling isolating switch
CN203372984U (en) Beam body pulley turnover device
CN109095343A (en) Assembled hanger
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN203255914U (en) Unit-typed curtain wall lifting device
CN102774740B (en) Arc balancing beam
CN207346996U (en) A kind of Bridge Erector
CN106315426A (en) Block form tower crane mounting and jacking method for assembled building
CN108675170A (en) Roofing monorail crane and its construction method
CN205603125U (en) Special hoist device that horizontal water tube cooler heat exchange tube was changed
CN204371545U (en) A kind of power station impeller apparatus for examination and repair
CN206521755U (en) A kind of dismounting device of building foundation pit prestressing force shaped steel combination inner bracing member
CN205662256U (en) High rises pergola side and hangs a semi -portal bridge crane
CN105329766A (en) Automatic balance type lifting beam
CN208948679U (en) Assembled hanger
CN203715136U (en) Tool for hoisting lifting hole cover plate in nuclear power plant
CN209567730U (en) A kind of small-sized lattice dead man steel construction
CN206872220U (en) Elevator counterweight
CN207511712U (en) A kind of confined space Portable portal frame device
CN202181161U (en) Suspension beam device for crane
CN108928729B (en) Lifting appliance and lifting device using same
CN205114815U (en) Parallel hoist of diesel engine
CN105060124A (en) Intra-frame portal crane system and hoisting use method thereof
CN206969990U (en) The special auxiliary hoisting device of steel grating structure workshop construction
CN205034948U (en) Rack formula hanging beam device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141029

Termination date: 20200816