CN106315426A - Block form tower crane mounting and jacking method for assembled building - Google Patents

Block form tower crane mounting and jacking method for assembled building Download PDF

Info

Publication number
CN106315426A
CN106315426A CN201610795175.5A CN201610795175A CN106315426A CN 106315426 A CN106315426 A CN 106315426A CN 201610795175 A CN201610795175 A CN 201610795175A CN 106315426 A CN106315426 A CN 106315426A
Authority
CN
China
Prior art keywords
tower crane
crane
tower
assembly
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610795175.5A
Other languages
Chinese (zh)
Other versions
CN106315426B (en
Inventor
吴晓东
赵业荣
冯海荣
曹生财
魏乾
马成
张华翠
花程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI TONGJI CONSTRUCTION GROUP Co Ltd
Original Assignee
ANHUI TONGJI CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI TONGJI CONSTRUCTION GROUP Co Ltd filed Critical ANHUI TONGJI CONSTRUCTION GROUP Co Ltd
Priority to CN201610795175.5A priority Critical patent/CN106315426B/en
Publication of CN106315426A publication Critical patent/CN106315426A/en
Application granted granted Critical
Publication of CN106315426B publication Critical patent/CN106315426B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/28Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
    • B66C23/283Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels with frameworks composed of assembled elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Transportation (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a block form tower crane mounting and jacking method for an assembled building. The method comprises the following steps: S1, foundation design and construction; S2, tower crane member assembly; S3, tower crane main body mounting; S4, jacking and knot adding; and S5, debugging and inspection. In the step S3 of a tower crane main body mounting process and the step S4 of a jacking and knot adding process, the deviation of perpendicularity of the tower crane main body is controlled to be smaller than or equal to 2/1000. The invention provides a mounting and using method of a large block form tower crane. The method has superhigh safety, and the system is stable to work, reliable and long in service life. The method is convenient and safe to operate, and the construction quality can be effectively guaranteed and the construction period is shortened.

Description

A kind of assembling flat-top tower crane for building is installed, jacking method
Technical field
The present invention relates to a kind of assembling flat-top tower crane for building installation, jacking method, belong to the realm of building construction.
Background technology
In building industrialization, monomer members is more and more heavier, and construction technology becomes increasingly complex, and the construction period is more and more tighter. In order to ensure construction safety and quality, shortening construction period, improve construction production efficiency, select advanced in performance, elevating capacity is big Lifting vertical transport equipment, it has also become large-scale assembled architecture construction in first-selection.And traditional tower crane wherein load is little, arm Long shorter, efficiency of construction is low, security performance and poor stability, is difficult to meet the construction requirement of assembled architecture.Therefore, in assembling In formula building, it is necessary to use the large-scale flat-top tower crane that a kind of architectural industrialization is special, its installing/dismounting and jack-up construction side Method and traditional tower crane construction method have bigger difference.
Summary of the invention
The present invention proposes a kind of assembling flat-top tower crane for building installation, jacking method, solves large-scale flat-top tower crane Installation question.
The technical scheme is that and be achieved in that: a kind of assemble flat-top tower crane for building install, jacking method, bag Include following steps:
S1, basic engineering and construction
First determine that foundation for tower crane position, the ground of foundation for tower crane position need to be arranged on silty strata, at ground reinforcing bar bag After bundle completes, casting concrete pre-buried supporting leg, remove the foreign material around foundation for tower crane, and alert by being set as around foundation for tower crane Guard against region, hang caution notice, send special messenger's supervision and management;
S2, tower crane component assembly
First tower crane component is marched into the arena, and to join according to list of delivery order and receipt during marching into the arena, and utilizes truck crane by tower crane structure Part is unloaded and is positioned over region set in advance, reexamines the number of components and quality, finally utilizes truck crane to complete tower crane component Assembly, makes tower crane component in the range of truck crane lifts, it is to avoid on-the-spot Secondary Transport during assembly as far as possible;
S3, tower crane main body is installed
First base section is lifted on pre-buried supporting leg, utilizes bolt to connect base section and supporting leg, then install one successively Joint strengthens joint, jacking stock assembly, rotating assembly, first segment counter-jib assembly, first segment crane arm assembly, second section crane arm Assembly, Section of three crane arm assembly, first piece of balance weight, remaining crane arm assembly is installed, exists with haulage cable the most again After passing around on luffing assembly pulley, it is connected with variable-amplitude steel wire rope, utilizes master winch and the effective of luffing elevator to coordinate luffing Passing around of steel wire rope, the fag end of hoist rope is sling, and is slowly drawn from reel, led by hoist rope from crane arm It is put into ground again in guiding to the pulley of arm end, puts on suspension hook, remaining balance weight is finally installed;
S4, lifting guide support adding
First inspection hydraulic system and the safety of attached wall part, the putting position of check criteria joint, total according to the object treating lifting Weight, lifts by crane the counterweight of corresponding weight, then removes bearing pin, installs standard knot, determines jacking according to the height of required jacking Tower body joint number amount, is subsequently mounted first segment tower body joint, then removes bearing pin, install standard knot, installs second section tower body joint, repeat on State installation first segment tower body joint and save process to installing second section tower body, until tower body joint is all installed, then start the process of debugging, After having debugged, carry out examination and hang, finally by tower crane by multiple band steel ground connection, adjust each spacing, fastening bolt, complete jacking and add Joint process;
S5, debugs and checks
First debug spacing, then check comprehensively and carry out load test, last inspection declaration, i.e. install after inspection declaration and terminate.
Preferably, truck crane payload ratings described in step S2 is not less than 50t.
Preferably, in step S3 tower crane main body installation process and during step S4 lifting guide support adding, control tower owner The perpendicularity deviation of body is less than or equal to 2/1000.
Preferably, in step S3 tower crane main body installation process, installing after first piece of balance weight, installation remaining The total length of crane arm assembly is not less than 55m.
Preferably, in step S1 basic engineering and work progress, the bearing capacity of ground is more than or equal to 0.2MP.
The invention has the beneficial effects as follows: the present invention proposes the installation and application of a kind of large-scale flat-top tower crane, the party Method has the safety of superelevation;System working stability, reliable, the life-span is long;Easy and safe to operate, can be effectively ensured construction quality, Shorten the construction period.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to Other accompanying drawing is obtained according to these accompanying drawings.
Fig. 1 be the present invention propose assemble flat-top tower crane for building install, the schematic flow sheet of jacking method.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise Embodiment, broadly falls into the scope of protection of the invention.
With reference to Fig. 1, a kind of assembling flat-top tower crane for building is installed, jacking method, comprises the following steps:
S1, basic engineering and construction
First determine that foundation for tower crane position, the ground of foundation for tower crane position need to be arranged on silty strata, the bearing capacity of ground More than or equal to 0.2MP, after ground reinforcing bar has been wrapped up, casting concrete pre-buried supporting leg, that removes around foundation for tower crane is miscellaneous Thing, and warning region around foundation for tower crane, will be set as, hang caution notice, send special messenger's supervision and management.
S2, tower crane component assembly
First tower crane component is marched into the arena, and to join according to list of delivery order and receipt during marching into the arena, and utilizes payload ratings to be not less than Tower crane component is unloaded and is positioned over region set in advance by the truck crane of 50t, reexamines the number of components and quality, finally utilizes vapour Car has hung the assembly of tower crane component, makes tower crane component in the range of truck crane lifts, it is to avoid on-the-spot during assembly as far as possible Secondary Transport.
S3, tower crane main body is installed
First base section is lifted on pre-buried supporting leg, utilizes bolt to connect base section and supporting leg, then install one successively Joint strengthens joint, jacking stock assembly, rotating assembly, first segment counter-jib assembly, first segment crane arm assembly, second section crane arm Assembly, Section of three crane arm assembly, first piece of balance weight, remaining total length is installed it is not less than the crane arm assembly of 55m, then After passing around on luffing assembly pulley with haulage cable, being connected with variable-amplitude steel wire rope, utilize master winch and luffing elevator has again Effect has coordinated passing around of variable-amplitude steel wire rope, and the fag end of hoist rope is sling, and slowly draws from reel, by lifting steel Cord is put into ground in being drawn to the pulley of arm end from crane arm again, puts on suspension hook, finally installs remaining balance weight, at this In tower crane main body installation process, the perpendicularity deviation of control tower owner's body is less than or equal to 2/1000.
S4, lifting guide support adding
First inspection hydraulic system and the safety of attached wall part, the putting position of check criteria joint, total according to the object treating lifting Weight, lifts by crane the counterweight of corresponding weight, then removes bearing pin, installs standard knot, determines jacking according to the height of required jacking Tower body joint number amount, is subsequently mounted first segment tower body joint, then removes bearing pin, install standard knot, installs second section tower body joint, repeat on State installation first segment tower body joint and save process to installing second section tower body, until tower body joint is all installed, then start the process of debugging, After having debugged, carry out examination and hang, finally by tower crane by multiple band steel ground connection, adjust each spacing, fastening bolt, complete jacking and add Joint process, during this lifting guide support adding, the perpendicularity deviation of control tower owner's body is less than or equal to 2/1000.
S5, debugs and checks
First debug spacing, then check comprehensively and carry out load test, last inspection declaration, i.e. install after inspection declaration and terminate.
During the method enforcement that the present invention proposes, first it is basic engineering and construction, the side proposed because of the present invention The large-scale flat-top tower crane special to liking architectural industrialization that method is implemented, needs to take into account the operating radius of tower crane, and place is also Need to carry out cure process, followed by tower crane component assembly, need the auxiliary of truck crane in this process, then be tower crane main body peace Dress, followed by lifting guide support adding process, concrete include jacking preparation, tower crane load-carrying trim, lifting guide support adding, debug and try Hang, jacking terminates, and finally debugs and checks, comprehensively inspection, load test, inspection declaration, i.e. installs and terminate after inspection declaration.The method has The safety of superelevation;System working stability, reliable, the life-span is long;Easy and safe to operate, construction quality can be effectively ensured, shorten and execute The work duration.
It addition, the installation method that this assembled architecture flat-top tower crane unloading process is the present invention to be proposed is reverse reverse Process, seldom repeats at this.
These are only presently preferred embodiments of the present invention, not in order to limit the present invention, all spirit in the present invention and Within principle, any modification, equivalent substitution and improvement etc. made, should be included within the scope of the present invention.

Claims (5)

1. one kind is assembled flat-top tower crane for building installation, jacking method, it is characterised in that comprise the following steps:
S1, basic engineering and construction
First determine that foundation for tower crane position, the ground of foundation for tower crane position need to be arranged on silty strata, wrapped up at ground reinforcing bar Cheng Hou, casting concrete pre-buried supporting leg, remove the foreign material around foundation for tower crane, and be set as security area by around foundation for tower crane Territory, hangs caution notice, sends special messenger's supervision and management;
S2, tower crane component assembly
First tower crane component is marched into the arena, and to join according to list of delivery order and receipt during marching into the arena, and utilizes truck crane to be unloaded by tower crane component Car is positioned over region set in advance, reexamines the number of components and quality, finally utilizes truck crane to complete the assembly of tower crane component, Make tower crane component during assembly in the range of truck crane lifts, it is to avoid on-the-spot Secondary Transport as far as possible;
S3, tower crane main body is installed
First base section is lifted on pre-buried supporting leg, utilizes bolt to connect base section and supporting leg, then installation one joint adds successively Qiang Jie, jacking stock assembly, rotating assembly, first segment counter-jib assembly, first segment crane arm assembly, second section crane arm are total Become, Section three crane arm assembly, first piece of balance weight, remaining crane arm assembly be installed, the most again with haulage cable in change After passing around on width assembly pulley, it is connected with variable-amplitude steel wire rope, utilizes master winch and the effective of luffing elevator to coordinate luffing steel Passing around of cord, the fag end of hoist rope is sling, and is slowly drawn from reel, is drawn by hoist rope from crane arm In the pulley of arm end, it is put into ground again, puts on suspension hook, remaining balance weight is finally installed;
S4, lifting guide support adding
First check hydraulic system and the safety of attached wall part, the putting position of check criteria joint, according to treating the object gross weight of lifting, Lift by crane the counterweight of corresponding weight, then remove bearing pin, standard knot is installed, determines that jacking tower body saves according to the height of required jacking Quantity, is subsequently mounted first segment tower body joint, then removes bearing pin, install standard knot, installs second section tower body joint, repeats above-mentioned installation First segment tower body joint, to installing second section tower body joint process, until tower body joint is all installed, then starts the process of debugging, has debugged Cheng Hou, carries out examination and hangs, and finally by tower crane by multiple band steel ground connection, adjusts each spacing, and fastening bolt completes lifting guide support adding mistake Journey;
S5, debugs and checks
First debug spacing, then check comprehensively and carry out load test, last inspection declaration, i.e. install after inspection declaration and terminate.
2. the installation of assembling as claimed in claim 1 flat-top tower crane for building, jacking method, it is characterised in that in step S2 Described truck crane payload ratings is not less than 50t.
3. the installation of assembling as claimed in claim 1 flat-top tower crane for building, jacking method, it is characterised in that in step S3 In tower crane main body installation process and during step S4 lifting guide support adding, the perpendicularity deviation of control tower owner's body is less than or equal to 2/ 1000。
4. the installation of assembling as claimed in claim 1 flat-top tower crane for building, jacking method, it is characterised in that in step S3 In tower crane main body installation process, after installing first piece of balance weight, the total length of the remaining crane arm assembly of installation is the lowest In 55m.
5. the installation of assembling as claimed in claim 1 flat-top tower crane for building, jacking method, it is characterised in that in step S1 In basic engineering and work progress, the bearing capacity of ground is more than or equal to 0.2MP.
CN201610795175.5A 2016-08-31 2016-08-31 A kind of assembling flat-top tower crane for building is installed, jacking method Active CN106315426B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610795175.5A CN106315426B (en) 2016-08-31 2016-08-31 A kind of assembling flat-top tower crane for building is installed, jacking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610795175.5A CN106315426B (en) 2016-08-31 2016-08-31 A kind of assembling flat-top tower crane for building is installed, jacking method

Publications (2)

Publication Number Publication Date
CN106315426A true CN106315426A (en) 2017-01-11
CN106315426B CN106315426B (en) 2018-06-19

Family

ID=57786283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610795175.5A Active CN106315426B (en) 2016-08-31 2016-08-31 A kind of assembling flat-top tower crane for building is installed, jacking method

Country Status (1)

Country Link
CN (1) CN106315426B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165421A (en) * 2017-06-12 2017-09-15 江苏建科建设监理有限公司 A kind of construction method of concrete assembled building
CN107697818A (en) * 2017-10-17 2018-02-16 郑州科润机电工程有限公司 A kind of prestressed concrete wind-power tower wall construction method and special construction apparatus
CN110745718A (en) * 2019-09-19 2020-02-04 珠海鉴安检测技术有限公司 Deviation rectifying method for tower crane
CN111039197A (en) * 2019-12-30 2020-04-21 广州市第三建筑工程有限公司 Construction method for reverse-order joint addition of jacking of internal-climbing tower crane

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201240787Y (en) * 2008-06-20 2009-05-20 重庆建工升立建设机械有限责任公司 Flat-top tower crane
CN101434369A (en) * 2008-09-19 2009-05-20 沈阳建筑大学 Flat top tower crane with tetragon cross section boom support
CN201495051U (en) * 2009-08-24 2010-06-02 中昇建机(南京)重工有限公司 Crane jib for flat-top tower crane
CN104692261A (en) * 2015-03-24 2015-06-10 启东建筑集团有限公司 Symmetrical dismounting construction method for attachment device of tower crane
CN105271009A (en) * 2015-10-09 2016-01-27 徐州建机工程机械有限公司 Double-horizontal-boom crane

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201240787Y (en) * 2008-06-20 2009-05-20 重庆建工升立建设机械有限责任公司 Flat-top tower crane
CN101434369A (en) * 2008-09-19 2009-05-20 沈阳建筑大学 Flat top tower crane with tetragon cross section boom support
CN201495051U (en) * 2009-08-24 2010-06-02 中昇建机(南京)重工有限公司 Crane jib for flat-top tower crane
CN104692261A (en) * 2015-03-24 2015-06-10 启东建筑集团有限公司 Symmetrical dismounting construction method for attachment device of tower crane
CN105271009A (en) * 2015-10-09 2016-01-27 徐州建机工程机械有限公司 Double-horizontal-boom crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吕强: "固定自升式塔式起重机安装、拆除工艺要点", 《建筑安全》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165421A (en) * 2017-06-12 2017-09-15 江苏建科建设监理有限公司 A kind of construction method of concrete assembled building
CN107697818A (en) * 2017-10-17 2018-02-16 郑州科润机电工程有限公司 A kind of prestressed concrete wind-power tower wall construction method and special construction apparatus
CN107697818B (en) * 2017-10-17 2023-10-17 郑州科润机电工程有限公司 Construction method and special construction equipment for wall of prestressed concrete wind power tower
CN110745718A (en) * 2019-09-19 2020-02-04 珠海鉴安检测技术有限公司 Deviation rectifying method for tower crane
CN110745718B (en) * 2019-09-19 2020-09-18 珠海鉴安检测技术有限公司 Deviation rectifying method for tower crane
CN111039197A (en) * 2019-12-30 2020-04-21 广州市第三建筑工程有限公司 Construction method for reverse-order joint addition of jacking of internal-climbing tower crane
CN111039197B (en) * 2019-12-30 2021-04-23 广州市第三建筑工程有限公司 Construction method for reverse-order joint addition of jacking of internal-climbing tower crane

Also Published As

Publication number Publication date
CN106315426B (en) 2018-06-19

Similar Documents

Publication Publication Date Title
CN105858435A (en) Technology for hoisting strip-shaped inclined steel structures in place through single crane
CN104652807B (en) Self-circulation construction system and method for internal climbing tower supporting steel beam in hydraulic climbing formwork system
CN205387439U (en) Mast hoisting accessory
CN106315426A (en) Block form tower crane mounting and jacking method for assembled building
CN205348733U (en) Furred ceiling operation platform
CN104477736A (en) Shaft elevator installation method
CN111021749A (en) Simple hoisting mechanism for bare concrete exterior wall cladding and construction method thereof
CN103420281B (en) The attaching/detaching apparatus of hoisting crane and accessory structure thereof, method for dismounting and installation method
CN208292530U (en) A kind of twin beams Grab Bucket Type Crane
KR101068229B1 (en) Dismantled tower crane cargo handling system and cargo handling method using thereof
CN104234636B (en) Jack-up unit derrick installation method
CN212270712U (en) Construction device for mounting and dismounting steel box girder by suspension of bridge girder erection machine
CN104695425A (en) Hoisting construction technology of steel bar cage
CN113023590A (en) Railway box wagon
CN111483924A (en) Bridge crane
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN203794505U (en) Internal climbing steel beam conveying device of internal climbing movable arm tower crane
CN204001751U (en) Super high steel structure construction overhanging unloading platform
CN110409803A (en) Dismantle the hanging method of hydraulic mould lifting device center drum circle
CN109378767A (en) A kind of lifting engineering method of hoist engine to skyscraper electricity well inner cable
CN205662256U (en) High rises pergola side and hangs a semi -portal bridge crane
CN202729645U (en) Tower crane with elevator
CN106012854B (en) The transporting equipment of prefabricated assembled overpass bridge plate
CN211691536U (en) Simple lifting mechanism for bare concrete exterior wall cladding
CN108059088B (en) Method and device for deflection turning and transposition of carrying pole Liang Kongzhong of slot erecting machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant