CN203255914U - Unit-typed curtain wall lifting device - Google Patents

Unit-typed curtain wall lifting device Download PDF

Info

Publication number
CN203255914U
CN203255914U CN2013202566819U CN201320256681U CN203255914U CN 203255914 U CN203255914 U CN 203255914U CN 2013202566819 U CN2013202566819 U CN 2013202566819U CN 201320256681 U CN201320256681 U CN 201320256681U CN 203255914 U CN203255914 U CN 203255914U
Authority
CN
China
Prior art keywords
fixed
curtain wall
hoisting
hoist
mast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2013202566819U
Other languages
Chinese (zh)
Inventor
刘亚松
全有维
李书信
李文明
夏峰海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN2013202566819U priority Critical patent/CN203255914U/en
Application granted granted Critical
Publication of CN203255914U publication Critical patent/CN203255914U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

本实用新型公开一种单元式幕墙吊装设备,包括机座、卷扬机系统和吊装架,所述机座上沿其长度方向依次固定有卷扬机系统和吊装架;所述卷扬机系统包括配重块、卷扬机滚筒和卷扬机,所述卷扬机滚筒上缠绕有钢丝绳,所述吊装架悬挑连接于机座上,所述吊装架的顶端固定有滑轮,所述钢丝绳一端固定于卷扬机滚筒上,另一端绕过吊装架顶端的滑轮且端部固定有挂钩;本实用新型结构简单,设计合理,设备轻便、占地少,移动、拆装方便且能重复使用,既能大大的提高安装效率,快速有序的完成幕墙单元的吊装,又节省了大量的劳动力,降低了施工成本和事故发生率,可应用于各种建筑物幕墙单元的安装工程中。

The utility model discloses a unit type curtain wall hoisting device, which comprises a machine base, a winch system and a hoisting frame. The hoist system and the hoisting frame are sequentially fixed on the machine base along its length direction; Drum and hoist, the hoist drum is wound with a steel wire rope, the hoisting frame is suspended and connected to the base, the top of the hoisting frame is fixed with a pulley, one end of the wire rope is fixed on the hoist drum, and the other end is bypassed for hoisting The pulley at the top of the frame and the end is fixed with a hook; the utility model has simple structure, reasonable design, light equipment, less land occupation, convenient movement, disassembly and assembly, and can be reused, which can greatly improve the installation efficiency and complete quickly and orderly The hoisting of the curtain wall unit saves a lot of labor, reduces the construction cost and the accident rate, and can be applied to the installation project of various building curtain wall units.

Description

一种单元式幕墙吊装设备A unitized curtain wall hoisting device

技术领域 technical field

本实用新型涉及一种幕墙安装设备,具体涉及一种单元式幕墙吊装设备,属于建筑安装技术领域。 The utility model relates to a curtain wall installation device, in particular to a unit type curtain wall hoisting device, which belongs to the technical field of building installation.

背景技术 Background technique

单元式幕墙是指由各种墙面与支承框架在工厂制成完整的幕墙结构的基本单位,其直接安装在建筑物主体结构上。单元式幕墙的单元件高度为楼层高度,传力简捷,可直接挂在楼层预埋件上,安装方便。单元件在工厂内加工制作,可以把玻璃、铝板或其它材料在加工厂内组装在一个单元件上,促进了建筑工业化程度。同时,因为单元件在加工厂内整件组装,易于在工厂内进行检查,有利于保证多元化整体质量,保证了幕墙的工程质量。单元式幕墙从楼层下方向上方安装能够和土建配合同步施工,大大缩短了工程周期。单元式幕墙所有工程均可在楼层内完成,在安装期间可以省出高大的脚手架和吊船。另外,单元式幕墙框件接缝紧密排成直行,容易构成一个优良的外墙形象。单元式幕墙是在工厂加工制作和现场安装,需要吊装设备吊运至楼层内,但目前市场上没有成品的吊装设备,往往采用类似于塔吊的装置,移动及操作性较差,安装效率较低。 Unitized curtain wall refers to the basic unit of a complete curtain wall structure made of various walls and supporting frames in the factory, which is directly installed on the main structure of the building. The height of the unit elements of the unitized curtain wall is the height of the floor, and the force transmission is simple and convenient. It can be directly hung on the embedded parts of the floor, and the installation is convenient. The unit unit is processed and manufactured in the factory, and glass, aluminum plates or other materials can be assembled on a unit unit in the processing plant, which promotes the industrialization of the building. At the same time, because the unit parts are assembled in the processing plant as a whole, it is easy to inspect in the factory, which is conducive to ensuring the overall quality of diversification and the engineering quality of the curtain wall. The unitized curtain wall can be installed from the bottom of the floor to the top and can be constructed simultaneously with the civil engineering, which greatly shortens the project cycle. All the works of the unitized curtain wall can be completed within the floor, and tall scaffolding and gondolas can be saved during installation. In addition, the joints of the unitized curtain wall frame parts are closely arranged in a straight line, which is easy to form an excellent external wall image. The unitized curtain wall is manufactured in the factory and installed on site. It needs hoisting equipment to lift it into the floor. However, there is no hoisting equipment for finished products on the market at present, and a device similar to a tower crane is often used. The movement and operability are poor, and the installation efficiency is low. .

实用新型内容 Utility model content

实用新型目的:本实用新型的目的在于针对现有技术的不足,提供一种单元式幕墙吊装设备,其结构简单,设计合理,拆装方便且能重复使用,既能大大的提高安装效率,快速有序的完成幕墙单元的吊装,又节省了大量的劳动力,降低了施工成本和事故发生率。 Purpose of the utility model: The purpose of this utility model is to provide a unitized curtain wall hoisting device for the deficiencies of the prior art, which has a simple structure, reasonable design, convenient disassembly and assembly, and can be reused. The orderly completion of the hoisting of the curtain wall units saves a lot of labor and reduces the construction cost and accident rate.

技术方案:本实用新型所述的一种单元式幕墙吊装设备,包括机座、卷扬机系统和吊装架,所述机座上沿其长度方向依次固定有卷扬机系统和吊装架; Technical solution: A unitized curtain wall hoisting device described in the utility model includes a machine base, a hoist system and a hoisting frame, and the hoist system and the hoisting frame are sequentially fixed on the machine base along its length direction;

所述卷扬机系统包括配重块、卷扬机滚筒和卷扬机,所述卷扬机滚筒上缠绕有钢丝绳,所述吊装架悬挑连接于机座上,所述吊装架的顶端固定有滑轮,所述钢丝绳一端固定于卷扬机滚筒上,另一端绕过吊装架顶端的滑轮且端部固定有挂钩。 The hoist system includes a counterweight, a hoist drum and a hoist, a steel wire rope is wound on the hoist drum, the hoisting frame is suspended and connected to the machine base, a pulley is fixed on the top of the hoisting frame, and one end of the wire rope is fixed On the hoist drum, the other end goes around the pulley at the top of the hoisting frame and the end is fixed with a hook.

其中,配重块的重量根据设备的起重重量及放置位置确定。 Wherein, the weight of the counterweight is determined according to the lifting weight and placement position of the equipment.

进一步完善上述技术方案,所述吊装架包括两根斜拉杆和两根支撑杆,所述两根斜拉杆的底端分别对称固定于机座的两侧靠近卷扬机滚筒位置处,所述两根斜拉杆顶端固定连接,所述两根支撑杆的底端分别对称固定于机座的两侧远离卷扬机滚筒位置处,所述两根支撑杆的顶端固定连接,所述两根斜拉杆和两根支撑杆的顶端连接点相互重合。 To further improve the above technical solution, the hoisting frame includes two diagonal stay rods and two support rods, the bottom ends of the two diagonal stay rods are symmetrically fixed on both sides of the machine base near the position of the hoist drum, and the two diagonal stay rods The top ends of the pull rods are fixedly connected, and the bottom ends of the two support rods are symmetrically fixed on both sides of the machine base away from the position of the hoist drum. The top ends of the two support rods are fixedly connected, and the two diagonal stay rods and the two The top connection points of the rods coincide with each other.

进一步地,所述两根支撑杆之间固定有加强杆。  Further, a reinforcing rod is fixed between the two supporting rods. the

进一步地,所述机座的底面固定有移动脚轮和支腿。 Further, the bottom surface of the base is fixed with movable casters and outriggers.

本实用新型与现有技术相比,其有益效果是:本实用新型结构简单,设计合理,设备轻便、占地少,移动、拆装方便且能重复使用,既能大大的提高安装效率,快速有序的完成幕墙单元的吊装,又节省了大量的劳动力,降低了施工成本和事故发生率,可应用于各种建筑物幕墙单元的安装工程中。 Compared with the prior art, the utility model has the beneficial effects as follows: the utility model has simple structure, reasonable design, light equipment, less land occupation, convenient movement, disassembly and assembly, and can be reused, which can greatly improve the installation efficiency and quickly The orderly completion of the hoisting of the curtain wall units saves a lot of labor, reduces the construction cost and the accident rate, and can be applied to the installation projects of various building curtain wall units.

附图说明 Description of drawings

图1为本实用新型的左视示意图。 Fig. 1 is a left view schematic diagram of the utility model.

图2为本实用新型的俯视示意图。 Fig. 2 is a schematic top view of the utility model.

具体实施方式 Detailed ways

下面对本实用新型技术方案进行详细说明,但是本实用新型的保护范围不局限于所述实施例。 The technical solutions of the utility model are described in detail below, but the protection scope of the utility model is not limited to the embodiments.

实施例1:如图1和2所示,一种单元式幕墙吊装设备,包括机座1、卷扬机系统和吊装架,所述机座1上沿其长度方向依次固定有卷扬机系统和吊装架。 Embodiment 1: As shown in Figures 1 and 2, a unitized curtain wall hoisting device includes a machine base 1, a hoist system and a hoisting frame, and the hoist system and the hoisting frame are sequentially fixed on the machine base 1 along its length direction.

所述机座1采用10#、8#槽钢制作、焊接而成,底面固定有移动脚轮2和支腿3,便于设备的移动和吊装时的固定,所述机座靠近卷扬机系统的一端连接有安全绳13,吊装时将安全绳13与楼层内的固定件连接,防止吊装设备滑出楼层。 The machine base 1 is made of 10# and 8# channel steel and welded, and the bottom surface is fixed with mobile casters 2 and outriggers 3, which are convenient for moving the equipment and fixing during hoisting. The machine base is connected to one end close to the winch system Safety rope 13 is arranged, and safety rope 13 is connected with the fixture in the floor during hoisting, prevents hoisting equipment from slipping out of floor.

所述卷扬机系统包括配重块4、卷扬机滚筒5和卷扬机6,所述卷扬机滚筒6上缠绕有钢丝绳7,所述吊装架悬挑连接于机座1上,所述吊装架的顶端固定有滑轮8,所述钢丝绳7一端固定于卷扬机滚筒5上,另一端绕过吊装架顶端的滑轮8且端部固定有挂钩9。 The hoist system includes a counterweight 4, a hoist drum 5 and a hoist 6, the hoist drum 6 is wound with a steel wire rope 7, the hoisting frame is suspended and connected to the machine base 1, and a pulley is fixed on the top of the hoisting frame 8. One end of the steel wire rope 7 is fixed on the drum 5 of the hoist, the other end goes around the pulley 8 at the top of the hoisting frame and a hook 9 is fixed at the end.

所述吊装架包括两根斜拉杆10和两根支撑杆11,所述斜拉杆10采用采用L63×5角钢焊接,所述两根斜拉杆10的底端分别对称焊接固定于机座1的两侧靠近卷扬机滚筒5位置处,所述两根斜拉杆10顶端焊接固定连接,所述支撑杆11采用8#槽钢焊接,所述两根支撑杆11的底端分别对称焊接固定于机座1的两侧远离卷扬机滚筒5位置处,所述两根支撑杆11的顶端焊接固定连接,所述两根斜拉杆10和两根支撑杆11的顶端连接点相互重合,所述两根支撑杆11之间固定有加强杆12。  The hoisting frame includes two diagonal stay rods 10 and two support rods 11. The diagonal stay rods 10 are welded with L63×5 angle steel. At the position close to the drum 5 of the hoist, the top ends of the two diagonal stay rods 10 are welded and fixedly connected, the support rods 11 are welded with 8# channel steel, and the bottom ends of the two support rods 11 are symmetrically welded and fixed to the base 1 respectively. The two sides of the two sides are far away from the position of the hoist drum 5, the top ends of the two support rods 11 are welded and fixedly connected, the top connection points of the two diagonal stay rods 10 and the two support rods 11 overlap each other, and the two support rods 11 Reinforcing rods 12 are fixed therebetween. the

安装玻璃幕墙单元板块时,钢丝绳沿吊装架顶端的滑轮伸出楼层结构处,设备后部设置相应的配重块,开启卷扬机起吊幕墙单元,起吊时地面施工人员用揽风绳挂住幕墙单元的下口,使幕墙单元保持平衡,直至将幕墙单元提升到指定安装位置附近;再由高空施工人员将幕墙单元与连于墙体的钢角码固定连接,将幕墙单元落入到指定安装位置。 When installing the glass curtain wall unit plate, the steel wire rope extends out of the floor structure along the pulley at the top of the hoisting frame. The corresponding counterweight is set at the rear of the equipment, and the hoist is turned on to lift the curtain wall unit. When lifting, the ground construction personnel use the wind rope to hang the curtain wall unit. The lower opening keeps the curtain wall unit in balance until the curtain wall unit is lifted to the vicinity of the designated installation position; then the high-altitude construction personnel will fix the curtain wall unit with the steel corner code connected to the wall, and drop the curtain wall unit to the designated installation position.

如上所述,尽管参照特定的优选实施例已经表示和表述了本实用新型,但其不得解释为对本实用新型自身的限制。在不脱离所附权利要求定义的本实用新型的精神和范围前提下,可对其在形式上和细节上作出各种变化。 As stated above, although the invention has been shown and described with reference to certain preferred embodiments, this should not be construed as limiting the invention itself. Various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (4)

1. a type unitized curtain wall hanging device is characterized in that, comprises support, hoist system and mast-up, is fixed with successively hoist system and mast-up along its length direction on the described support;
Described hoist system comprises clump weight, winch cylinder and winch, be wound with steel rope on the described winch cylinder, described mast-up is encorbelmented and is connected on the support, the top of described mast-up is fixed with pulley, described steel rope one end is fixed on the winch cylinder, and pulley and end that the other end is walked around the mast-up top are fixed with hook.
2. type unitized curtain wall hanging device according to claim 1, it is characterized in that, described mast-up comprises two digonal links and two strut bars, the bottom of described two digonal links is symmetrically fixed on respectively the both sides of support near winch cylinder position place, described two digonal link top captive joints, the bottom of described two strut bars is symmetrically fixed on respectively the both sides of support away from winch cylinder position place, the top captive joint of described two strut bars, the top point of connection of described two digonal links and two strut bars overlaps.
3. type unitized curtain wall hanging device according to claim 2 is characterized in that, is fixed with stirrup between described two strut bars.
4. type unitized curtain wall hanging device according to claim 1 is characterized in that, the bottom surface of described support is fixed with Moving caster and supporting leg.
CN2013202566819U 2013-05-13 2013-05-13 Unit-typed curtain wall lifting device Expired - Lifetime CN203255914U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013202566819U CN203255914U (en) 2013-05-13 2013-05-13 Unit-typed curtain wall lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013202566819U CN203255914U (en) 2013-05-13 2013-05-13 Unit-typed curtain wall lifting device

Publications (1)

Publication Number Publication Date
CN203255914U true CN203255914U (en) 2013-10-30

Family

ID=49468499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013202566819U Expired - Lifetime CN203255914U (en) 2013-05-13 2013-05-13 Unit-typed curtain wall lifting device

Country Status (1)

Country Link
CN (1) CN203255914U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104261296A (en) * 2014-09-18 2015-01-07 苏州金螳螂幕墙有限公司 Hoisting trolley for unitized curtain wall
CN105060155A (en) * 2015-07-31 2015-11-18 常州市金坛区直溪镇农业综合服务站 Movable hoisting device for pond floating catching fish box
CN105752872A (en) * 2016-04-29 2016-07-13 张哲瑜 Pole-mounted circuit breaker lifting device
CN106672873A (en) * 2017-03-27 2017-05-17 盐城市港城特种玻璃制品有限公司 Protective device for glass door and window installation
CN111824987A (en) * 2020-06-02 2020-10-27 上海建工二建集团有限公司 Hoisting device and application construction method thereof
CN114476977A (en) * 2022-02-15 2022-05-13 中国十七冶集团有限公司 Curtain wall unit element hoisting equipment and curtain wall unit element hoisting method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104261296A (en) * 2014-09-18 2015-01-07 苏州金螳螂幕墙有限公司 Hoisting trolley for unitized curtain wall
CN105060155A (en) * 2015-07-31 2015-11-18 常州市金坛区直溪镇农业综合服务站 Movable hoisting device for pond floating catching fish box
CN105060155B (en) * 2015-07-31 2017-07-28 常州市金坛区直溪镇农业综合服务站 A kind of portable pond, which is floated, fishes for fish box boom hoisting
CN105752872A (en) * 2016-04-29 2016-07-13 张哲瑜 Pole-mounted circuit breaker lifting device
CN105752872B (en) * 2016-04-29 2019-01-22 陈朱亨 A kind of pole-mounted circuit breaker boom hoisting
CN106672873A (en) * 2017-03-27 2017-05-17 盐城市港城特种玻璃制品有限公司 Protective device for glass door and window installation
CN111824987A (en) * 2020-06-02 2020-10-27 上海建工二建集团有限公司 Hoisting device and application construction method thereof
CN114476977A (en) * 2022-02-15 2022-05-13 中国十七冶集团有限公司 Curtain wall unit element hoisting equipment and curtain wall unit element hoisting method

Similar Documents

Publication Publication Date Title
CN203255914U (en) Unit-typed curtain wall lifting device
CN101177959A (en) Curtain wall unit hanging equipment and construction method thereof
CN105905781A (en) Hanger used for hoisting large-section steel truss girders and hoisting method
CN109440985A (en) Super high-rise building super large curtain wall unit hydraulic synchronizing lifting system and its construction method
CN207748760U (en) A kind of bridge crane of hoisting large-size drainpipe
CN206753012U (en) A kind of attachment type raise scaffold just hangs hanging apparatus
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN104291222B (en) The inner hard protection of a kind of high-rise building Core Walls Structure hangs integrated system with row
CN206720558U (en) A kind of adjustable steel-reinforcement cage hanger
CN203474231U (en) Steel bar tower safety hoisting device
CN211622534U (en) Movable cantilever operation platform
CN205419580U (en) A hoist and mount system for dismantling tower crane overlength pull rod
CN204999517U (en) Coal transporting trestle steel truss hoist device in power plant's chimney
CN203289011U (en) Tension cross arm hoisting device
CN202731270U (en) Movable platform for aerial installation operation of space steel structure
CN202729645U (en) Tower crane with elevator
CN103470057B (en) A kind of high-altitude component hoisting construction method
CN202865749U (en) Installation equipment of bridge guardrail framework
CN105152052A (en) Glass curtain wall component lifting device and glass curtain wall component installing method
CN102383613B (en) Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device
CN110697585A (en) A mechanism for self-detaching attachment device
CN203699783U (en) Hanging bracket fixed with wire pole
CN210944589U (en) Self-detaching attachment mechanism
CN201896016U (en) Lifting basket device for storage tank maintenance
CN209940330U (en) A tower crane plug-in detachable pedestrian safety passage

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20131030

CX01 Expiry of patent term