CN102733615A - 非对称整体提升施工方法 - Google Patents
非对称整体提升施工方法 Download PDFInfo
- Publication number
- CN102733615A CN102733615A CN2012102452748A CN201210245274A CN102733615A CN 102733615 A CN102733615 A CN 102733615A CN 2012102452748 A CN2012102452748 A CN 2012102452748A CN 201210245274 A CN201210245274 A CN 201210245274A CN 102733615 A CN102733615 A CN 102733615A
- Authority
- CN
- China
- Prior art keywords
- construction method
- lifting
- asymmetric
- hoisted
- suspension centre
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 239000000725 suspension Substances 0.000 claims description 30
- 238000000034 method Methods 0.000 claims description 15
- 238000009434 installation Methods 0.000 claims description 10
- 238000012937 correction Methods 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- 239000010720 hydraulic oil Substances 0.000 claims description 4
- 230000003068 static effect Effects 0.000 claims description 2
- 230000005484 gravity Effects 0.000 abstract 2
- 238000005516 engineering process Methods 0.000 description 3
- 230000001737 promoting effect Effects 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 208000004350 Strabismus Diseases 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 230000001788 irregular Effects 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000013213 extrapolation Methods 0.000 description 1
- 238000012067 mathematical method Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/142—Means in or on the elements for connecting same to handling apparatus
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Engaging Elements For Cranes (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
Claims (9)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210245274.8A CN102733615B (zh) | 2012-07-12 | 2012-07-12 | 非对称整体提升施工方法 |
US13/939,749 US8745956B2 (en) | 2012-07-12 | 2013-07-11 | Asymmetric integral lifting construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210245274.8A CN102733615B (zh) | 2012-07-12 | 2012-07-12 | 非对称整体提升施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102733615A true CN102733615A (zh) | 2012-10-17 |
CN102733615B CN102733615B (zh) | 2014-10-15 |
Family
ID=46989860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210245274.8A Active CN102733615B (zh) | 2012-07-12 | 2012-07-12 | 非对称整体提升施工方法 |
Country Status (2)
Country | Link |
---|---|
US (1) | US8745956B2 (zh) |
CN (1) | CN102733615B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108894579A (zh) * | 2018-07-05 | 2018-11-27 | 中国二十冶集团有限公司 | 双塔连体钢结构的提升施工方法 |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101538897B (zh) * | 2009-04-10 | 2011-03-30 | 袁斌 | 钢筋混凝土建筑物的主体工程施工方法 |
WO2013188935A1 (en) * | 2012-06-18 | 2013-12-27 | Dentscare Ltda | Bendable prosthetic abutment applied to osseointegrated dental implants |
US10241499B1 (en) * | 2015-02-11 | 2019-03-26 | Lightforce Orthodontics, Inc. | Ceramic processing for the direct manufacture of customized labial and lingual orthodontic brackets |
WO2017038181A1 (ja) * | 2015-09-04 | 2017-03-09 | 株式会社ジーシー | 硬化性パテ及びその製造方法 |
US10829928B2 (en) * | 2019-03-29 | 2020-11-10 | Big Time Investment, Llc | Floor plate assembly system and method of constructing a building therewith |
US12018499B2 (en) * | 2020-03-05 | 2024-06-25 | Guangzhou Construction Engineering Co., Ltd. | Segmental track-changing and accumulative sliding construction method for unequal-span structure |
CN114622729B (zh) * | 2022-04-01 | 2024-03-12 | 中国化学工程重型机械化有限公司 | 一种异形钢结构的提升方法 |
CN114876215B (zh) * | 2022-06-16 | 2023-09-26 | 中铁建工集团有限公司 | 连体结构整体提升工艺 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06173458A (ja) * | 1992-12-08 | 1994-06-21 | Hazama Gumi Ltd | 建築物の構築工法および揚重装置 |
JPH07173943A (ja) * | 1993-12-20 | 1995-07-11 | Taisei Corp | 揚重物の吊り上げ方法 |
CN1609363A (zh) * | 2004-08-11 | 2005-04-27 | 中国机械工业建设总公司 | 建筑物桁架整体提升方法及其设备 |
CN102108786A (zh) * | 2010-12-09 | 2011-06-29 | 浙江省天和建材集团有限公司 | 超大型建筑构件整体提升施工方法及其装置 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030079436A1 (en) * | 2001-10-30 | 2003-05-01 | Manfre Mark Thomas | Lifting frame |
WO2005100707A1 (en) * | 2003-03-30 | 2005-10-27 | Moshe Keilaf | A method of constructing multi-storey building balconies |
US7421770B1 (en) * | 2006-04-25 | 2008-09-09 | Enloe Aluminum, Inc. | Method of replacing canopy support columns |
US8926227B2 (en) | 2007-12-31 | 2015-01-06 | SO.L.E.S.—Societa' Lavori Edili E Serbatoi S.p.A. | Method and system for raising a building structure |
CN101852019B (zh) | 2010-06-11 | 2011-10-05 | 北京市机械施工有限公司 | 一种倾斜钢屋盖的提升安装方法 |
US8875471B2 (en) * | 2012-08-24 | 2014-11-04 | Baltazar Siqueiros | Method and apparatus for lifting and leveling a concrete panel |
-
2012
- 2012-07-12 CN CN201210245274.8A patent/CN102733615B/zh active Active
-
2013
- 2013-07-11 US US13/939,749 patent/US8745956B2/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06173458A (ja) * | 1992-12-08 | 1994-06-21 | Hazama Gumi Ltd | 建築物の構築工法および揚重装置 |
JPH07173943A (ja) * | 1993-12-20 | 1995-07-11 | Taisei Corp | 揚重物の吊り上げ方法 |
CN1609363A (zh) * | 2004-08-11 | 2005-04-27 | 中国机械工业建设总公司 | 建筑物桁架整体提升方法及其设备 |
CN102108786A (zh) * | 2010-12-09 | 2011-06-29 | 浙江省天和建材集团有限公司 | 超大型建筑构件整体提升施工方法及其装置 |
Non-Patent Citations (2)
Title |
---|
张艳明: "烟台火车站异型悬挑网架安装方案选择及关键技术", 《建筑技术》, vol. 40, no. 10, 15 October 2009 (2009-10-15) * |
鲍广鑑等: "大面积钢屋盖多吊点非对称整体提升技术", 《施工技术》, vol. 33, no. 5, 30 May 2004 (2004-05-30) * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108894579A (zh) * | 2018-07-05 | 2018-11-27 | 中国二十冶集团有限公司 | 双塔连体钢结构的提升施工方法 |
Also Published As
Publication number | Publication date |
---|---|
US8745956B2 (en) | 2014-06-10 |
CN102733615B (zh) | 2014-10-15 |
US20140017059A1 (en) | 2014-01-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102733615B (zh) | 非对称整体提升施工方法 | |
CN202299464U (zh) | 钢柱快速吊装就位校正装置 | |
CN102900021B (zh) | 一种拼装式桥梁湿接缝施工方法 | |
CN105604334A (zh) | 一种用于大跨度钢桁架整体安装的快速施工方法 | |
CN203296361U (zh) | 大跨度钢结构跨外组对吊装平台 | |
CN103306205A (zh) | 一种预制t梁或箱梁纵向湿接缝模板施工方法 | |
CN102251483A (zh) | 自提升附着式吊机吊装钢管混凝土格构桥墩的施工方法 | |
CN102691269A (zh) | 主拱外包混凝土移动挂篮 | |
CN105040591A (zh) | 一种波形钢腹板的定位装置及其定位方法 | |
CN202626841U (zh) | 吊挂法外包主拱混凝土装置 | |
CN201176365Y (zh) | 轻型可调式吊架 | |
CN211312514U (zh) | 钢结构冷却塔锥段安装用移动式地锚装置 | |
CN105016220A (zh) | 一种抱杆加节装置 | |
CN202482772U (zh) | 铁路桥梁防落梁挡块安装系统 | |
CN203959697U (zh) | 吊装平台桁架的平衡梁 | |
CN204126297U (zh) | 一种钢桁架屋顶的临时支撑架 | |
CN203096620U (zh) | 钢管拱肋作业平台 | |
CN202988556U (zh) | 角钢型架体专用吊具 | |
CN214087316U (zh) | 一种用于混凝土箱梁拆除节段吊装装置 | |
CN206625251U (zh) | 可周转式凌空施工升降机基础 | |
CN102733612B (zh) | 电动葫芦轨道安装方法 | |
CN204780611U (zh) | 一种波形钢腹板的定位装置 | |
CN104120889B (zh) | 管桁架结构整体提升装置 | |
CN202369932U (zh) | 一种桥梁遮板安装车 | |
CN203333224U (zh) | 一种钢结构梁上吊具 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
ASS | Succession or assignment of patent right |
Owner name: SHANGHAI YESHENG Effective date: 20130121 |
|
C41 | Transfer of patent application or patent right or utility model | ||
C53 | Correction of patent of invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Wang Long Inventor after: Gao Junyue Inventor after: Chen Zhenying Inventor after: Wei Wai Inventor before: Wang Long Inventor before: Gao Junyue Inventor before: Chen Zhenying |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: WANG LONG GAO JUNYUE CHEN ZHENYING TO: WANG LONG GAO JUNYUE CHEN ZHENYING WEI WAI |
|
TA01 | Transfer of patent application right |
Effective date of registration: 20130121 Address after: 510030 Yuexiu District, Guangdong Province, Guang Wei Road, No. 4, No. Applicant after: Guangzhou Construction Co., Ltd. Applicant after: Shanghai Yesheng Electromechanical Control Technology Co., Ltd. Address before: 510030 Yuexiu District, Guangdong Province, Guang Wei Road, No. 4, No. Applicant before: Guangzhou Construction Co., Ltd. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Free format text: FORMER OWNER: SHANGHAI YESHENG Effective date: 20150217 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20150217 Address after: 510030 Yuexiu District, Guangdong Province, Guang Wei Road, No. 4, No. Patentee after: Guangzhou Construction Co., Ltd. Address before: 510030 Yuexiu District, Guangdong Province, Guang Wei Road, No. 4, No. Patentee before: Guangzhou Construction Co., Ltd. Patentee before: Shanghai Yesheng Electromechanical Control Technology Co., Ltd. |
|
CB03 | Change of inventor or designer information |
Inventor after: Wang Long Inventor after: Gao Junyue Inventor after: Liang Huqing Inventor after: Chen Zhenying Inventor after: Wei Wai Inventor after: Lou Feng Inventor after: Lu Dehui Inventor before: Wang Long Inventor before: Gao Junyue Inventor before: Chen Zhenying Inventor before: Wei Wai |
|
COR | Change of bibliographic data | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20121017 Assignee: GUANGZHOU FOURTH CONSTRUCTION CO., LTD. Assignor: Guangzhou Construction Co., Ltd. Contract record no.: 2016440000248 Denomination of invention: Asymmetric and integrated lifting construction method for large scale grid structure Granted publication date: 20141015 License type: Common License Record date: 20161202 Application publication date: 20121017 Assignee: ZHEJIANG JINGGONG STEEL STRUCTURE GROUP CO., LTD. Assignor: Guangzhou Construction Co., Ltd. Contract record no.: 2016440000246 Denomination of invention: Asymmetric and integrated lifting construction method for large scale grid structure Granted publication date: 20141015 License type: Common License Record date: 20161202 Application publication date: 20121017 Assignee: Shanghai Yesheng Electromechanical Control Technology Co., Ltd. Assignor: Guangzhou Construction Co., Ltd. Contract record no.: 2016440000247 Denomination of invention: Asymmetric and integrated lifting construction method for large scale grid structure Granted publication date: 20141015 License type: Common License Record date: 20161202 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20121017 Assignee: Guangdong Hangxiao Steel Structure Co., Ltd. Assignor: Guangzhou Construction Co., Ltd. Contract record no.: 2017440000077 Denomination of invention: Asymmetric and integrated lifting construction method for large scale grid structure Granted publication date: 20141015 License type: Common License Record date: 20170317 |
|
EE01 | Entry into force of recordation of patent licensing contract | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201216 Address after: 510030 Sixth Floor, 4 Guangwei Road, Yuexiu District, Guangzhou City, Guangdong Province Patentee after: Guangzhou Construction Engineering Co.,Ltd. Patentee after: GUANGZHOU INSTITUTE OF BUILDING SCIENCE Co.,Ltd. Address before: 510030 No. 4, Guang Wei Road, Guangzhou, Guangdong, Yuexiu District Patentee before: Guangzhou Construction Engineering Co.,Ltd. |
|
TR01 | Transfer of patent right |