CN104120889B - 管桁架结构整体提升装置 - Google Patents

管桁架结构整体提升装置 Download PDF

Info

Publication number
CN104120889B
CN104120889B CN201410341624.XA CN201410341624A CN104120889B CN 104120889 B CN104120889 B CN 104120889B CN 201410341624 A CN201410341624 A CN 201410341624A CN 104120889 B CN104120889 B CN 104120889B
Authority
CN
China
Prior art keywords
module
piece
card
steel strand
lower edge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410341624.XA
Other languages
English (en)
Other versions
CN104120889A (zh
Inventor
司坤
孙伟
韩向科
张侃
刘明路
王馥琴
贾文彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd, CMTCC Shanghai Shisanye Construction Co Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201410341624.XA priority Critical patent/CN104120889B/zh
Publication of CN104120889A publication Critical patent/CN104120889A/zh
Application granted granted Critical
Publication of CN104120889B publication Critical patent/CN104120889B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明具体为一种管桁架结构整体提升装置;其特征是:它包括设于管桁架整体结构顶部的上吊点提升模块,设于管桁架整体结构上弦处的固定钢绞线模块、与固定钢绞线模块连接的上弦卡紧模块,设于管桁架整体结构下弦处的下弦卡紧模块和用于连接上弦卡紧模块、下弦卡紧模块的连接杆件。本发明采用上述设计,其结构简单、制作安装方便;能够应用于大跨度、结构形势复杂的管桁架整体提升作业,从而有效缩短了复杂空间结构的安装施工工期并大量降低了施工成本。

Description

管桁架结构整体提升装置
技术领域
本发明涉及大跨度钢桁架整体提升领域,具体为一种管桁架结构整体提升装置。
背景技术
建筑钢结构由于具有大跨度、结构安全、造型复杂等特点,越来越受到人民的青睐。传统钢结构的安装多采用满堂脚手架高空施工工艺,使用的措施费用较大。近年来,对于一些复杂空间结构,为了缩短工期、节约工程成本,钢结构整体提升技术在钢结构安装中得到应用,但由于整体钢结构往往跨度长达几十米,采用传统的散装法或分块吊装法精度难以控制,且吊装过程中存在的安全隐患大。
发明内容
本发明的目的在于,提供一种用于及大跨度、结构形式复杂管桁架的整体提升装置,其具有结构简单、安装快,成本低的特点。
为了达到上述目的,本发明是这样实现的:
一种管桁架结构整体提升装置,它包括设于管桁架整体结构顶部的上吊点提升模块,设于管桁架整体结构上弦处的固定钢绞线模块、与固定钢绞线模块连接的上弦卡紧模块,设于管桁架整体结构下弦处的下弦卡紧模块和用于连接上弦卡紧模块、下弦卡紧模块的连接杆件;
上吊点提升模块包括支撑架和箱型梁,支撑架包括立杆、斜拉杆和斜撑,箱型梁为双腹板结构且两端部开有槽口以供钢绞线穿入,其通过支撑架而固定连接于管桁架整体结构的顶部;
固定钢绞线模块垂直布置并与管桁架整体结构上弦杆固定连接,其包括一对对称设置的侧板、固定于两块侧板之间的两块穿地锚板,穿地锚板中央开有通孔,以供钢绞线穿入及固定;
上弦卡紧模块包括两块分别固定于固定钢绞线模块两块侧板外侧的第一夹紧板和固定于两块第一夹紧板之间的两块第一插板,所述第一插板中央开有通孔以供管桁架结构上弦杆插入及固定;
下弦卡紧模块包括两块第二夹紧板和固定于两块第二夹紧板之间的两块第二插板,所述第二插板中央开有通孔以供管桁架结构下弦杆插入及固定;下弦卡紧模块的两块第二夹紧板与管桁架整体结构固定连接。
所述的管桁架结构整体提升装置,还包括第一加劲板,所述第一加劲板分别与固定钢绞线模块和管桁架整体结构的上弦杆固定连接。
所述的管桁架结构整体提升装置,还包括第二加劲板,所述第二加劲板分别与固定钢绞线模块的侧板和穿地锚板固定连接。
所述的管桁架结构整体提升装置,连接杆件与上弦卡紧模块的连接、与下弦卡紧模块的连接均为焊接,且焊接长度不小于300mm。
所述的管桁架结构整体提升装置,连接杆件为槽钢。
本发明采用上述设计,其结构简单、制作安装方便;能够应用于大跨度、结构形势复杂的管桁架整体提升作业,从而有效缩短了复杂空间结构的安装施工工期并大量降低了施工成本。
附图说明
图1为本发明的结构示意图。
图2为图1中A-A的局部向视图。
图3为图1中B-B的局部向视图。
图4为图1中D-D的局部向视图。
图5为图1中C-C的局部向视图。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1、图2所示,一种管桁架结构整体提升装置,它包括设于管桁架整体结构顶部的上吊点提升模块,设于管桁架整体结构上弦处的固定钢绞线模块、与固定钢绞线模块连接的上弦卡紧模块,设于管桁架整体结构下弦处的下弦卡紧模块和用于连接上弦卡紧模块、下弦卡紧模块的连接杆件7;
上吊点提升模块包括支撑架和箱型梁1,支撑架包括立杆3、斜拉杆2和斜撑4,箱型梁1为双腹板结构且两端部开有槽口101以供钢绞线9穿入,其通过支撑架而固定连接于管桁架整体结构的顶部;
如图3、图4所示固定钢绞线模块5垂直布置并与管桁架整体结构的上弦杆固定连接,其包括一对对称设置的侧板501、固定于两块侧板501之间的两块穿地锚板503、504,穿地锚板503、504中央开有通孔,以供钢绞线9穿入及固定;
如图4所示,上弦卡紧模块包括两块分别固定于固定钢绞线模块5两块侧板501外侧的第一夹紧板601和固定于两块第一夹紧板601之间的两块第一插板602,所述第一插板602中央开有通孔以供管桁架上弦杆插入及固定;
如图5所示下弦卡紧模块8包括两块第二夹紧板801和固定于两块第二夹紧板801之间的两块第二插板802,所述第二插板802中央开有通孔以供管桁架下弦杆插入及固定;下弦卡紧模块的两块第二夹紧板801与管桁架整体结构固定连接;
如图5所示,连接杆件7两端分别与上弦卡紧模块、下弦卡紧模块固定连接。
所述的管桁架结构整体提升装置,还包括第一加劲板10,所述第一加劲板10分别与固定钢绞线模块5和管桁架整体结构的上弦杆固定连接。
所述的管桁架结构整体提升装置,还包括第二加劲板505,所述第二加劲板505分别与固定钢绞线模块5的侧板501和穿地锚板503固定连接。
所述的管桁架结构整体提升装置,连接杆件7与上弦卡紧模块的连接、与下弦卡紧模块的连接均为焊接,且焊接长度不小于300mm。
所述的管桁架结构整体提升装置,连接杆件为槽钢。
本发明采用上述设计,其结构简单、制作安装方便;能够应用于大跨度、结构形势复杂的管桁架整体提升作业,从而有效缩短了复杂空间结构的安装施工工期并大量降低了施工成本。

Claims (5)

1.一种管桁架结构整体提升装置,其特征是:它包括设于管桁架整体结构顶部的上吊点提升模块,设于管桁架整体结构上弦处的固定钢绞线模块、与固定钢绞线模块连接的上弦卡紧模块,设于管桁架整体结构下弦处的下弦卡紧模块和用于连接上弦卡紧模块、下弦卡紧模块的连接杆件;
上吊点提升模块包括支撑架和箱型梁,支撑架包括立杆、斜拉杆和斜撑,箱型梁为双腹板结构且两端部开有槽口以供钢绞线穿入,其通过支撑架而固定连接于管桁架整体结构的顶部;
固定钢绞线模块垂直布置并与管桁架整体结构上弦杆固定连接,其包括一对对称设置的侧板、固定于两块侧板之间的两块穿地锚板,穿地锚板中央开有通孔,以供钢绞线穿入及固定;
上弦卡紧模块包括两块分别固定于固定钢绞线模块两块侧板外侧的第一夹紧板和固定于两块第一夹紧板之间的两块第一插板,所述第一插板中央开有通孔以供管桁架结构上弦杆插入及固定;
下弦卡紧模块包括两块第二夹紧板和固定于两块第二夹紧板之间的两块第二插板,所述第二插板中央开有通孔以供管桁架结构下弦杆插入及固定;下弦卡紧模块的两块第二夹紧板与管桁架整体结构固定连接。
2.根据权利要求1所述的管桁架结构整体提升装置,其特征是:还包括第一加劲板,所述第一加劲板分别与固定钢绞线模块和管桁架整体结构的上弦杆固定连接。
3.根据权利要求1所述的管桁架结构整体提升装置,其特征是:还包括第二加劲板,所述第二加劲板分别与固定钢绞线模块的侧板和穿地锚板固定连接。
4.根据权利要求1所述的管桁架结构整体提升装置,其特征是:连接杆件与上弦卡紧模块的连接、与下弦卡紧模块的连接均为焊接,且焊接长度不小于300mm。
5.根据权利要求1所述的管桁架结构整体提升装置,其特征是:连接杆件为角钢、双拼角钢或槽钢。
CN201410341624.XA 2014-07-18 2014-07-18 管桁架结构整体提升装置 Active CN104120889B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410341624.XA CN104120889B (zh) 2014-07-18 2014-07-18 管桁架结构整体提升装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410341624.XA CN104120889B (zh) 2014-07-18 2014-07-18 管桁架结构整体提升装置

Publications (2)

Publication Number Publication Date
CN104120889A CN104120889A (zh) 2014-10-29
CN104120889B true CN104120889B (zh) 2016-06-01

Family

ID=51766505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410341624.XA Active CN104120889B (zh) 2014-07-18 2014-07-18 管桁架结构整体提升装置

Country Status (1)

Country Link
CN (1) CN104120889B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114263276B (zh) * 2021-12-24 2024-07-16 中核华辰工程管理有限公司 一种大跨度建筑钢结构及其施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3896717A (en) * 1973-08-13 1975-07-29 Jack N Schmitt Roof truss machine
DE3742296A1 (de) * 1987-12-14 1989-06-29 Jun Ernst Hohrenk Hubvorrichtung fuer schwere lasten
CN102071814A (zh) * 2010-12-16 2011-05-25 中建二局第三建筑工程有限公司 高层大跨度门式桁架整体提升装置及其施工方法
CN102661054A (zh) * 2012-05-23 2012-09-12 中建二局第三建筑工程有限公司 平面钢桁架整体提升中的侧向加固结构及整体提升方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3896717A (en) * 1973-08-13 1975-07-29 Jack N Schmitt Roof truss machine
DE3742296A1 (de) * 1987-12-14 1989-06-29 Jun Ernst Hohrenk Hubvorrichtung fuer schwere lasten
CN102071814A (zh) * 2010-12-16 2011-05-25 中建二局第三建筑工程有限公司 高层大跨度门式桁架整体提升装置及其施工方法
CN102661054A (zh) * 2012-05-23 2012-09-12 中建二局第三建筑工程有限公司 平面钢桁架整体提升中的侧向加固结构及整体提升方法

Also Published As

Publication number Publication date
CN104120889A (zh) 2014-10-29

Similar Documents

Publication Publication Date Title
CN102733615B (zh) 非对称整体提升施工方法
CN202881856U (zh) 混凝土浇筑支架预压装置
CN105401714A (zh) 一种附着式升降脚手架及升降方法
CN107355037A (zh) 装配式钢结构建筑自承式钢桁架楼板支撑体系及施工方法
CN105275253A (zh) 等径杆立杆器及其使用方法
CN104532850B (zh) 基坑支撑系统
CN103288002B (zh) 简易组合门架高空重物吊装装置
CN105040591A (zh) 一种波形钢腹板的定位装置及其定位方法
CN205100531U (zh) 一种升降脚手架架体总成
CN204454235U (zh) 一种新型多吊点平衡梁装置
CN203284126U (zh) 简易组合门架高空重物吊装装置
CN104120889B (zh) 管桁架结构整体提升装置
CN208981167U (zh) 吊挂式系梁施工装置
CN204126297U (zh) 一种钢桁架屋顶的临时支撑架
CN204040437U (zh) 悬挑三角架及单排悬挑防护架体系
CN206014261U (zh) 一种钢吊车梁平整度调节设备
CN205397790U (zh) 一种用于施工电梯附墙拉杆超长的组件
CN205663282U (zh) 一种大容量轻型格构式钢柱
CN204079226U (zh) 一种能增加管桁架吊装时刚度的活动式张弦梁吊装装置
CN104963410B (zh) 钢结构梁柱滑动连接节点
CN203545501U (zh) 狭小空间内爬式塔机辅助提升装置
CN210947661U (zh) 一种承插式悬挑脚手架的安装装置
CN204038917U (zh) 可拆卸外挂式操作平台
CN203361596U (zh) 一种集成式升降操作平台辅助支架
CN203821812U (zh) 梁板架空结构悬挑架体

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee after: MCC TIANGONG GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee after: MCC TIANGONG GROUP Corp.,Ltd.

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20200514

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

TR01 Transfer of patent right