CN102535440A - 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法 - Google Patents

全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法 Download PDF

Info

Publication number
CN102535440A
CN102535440A CN201210007192XA CN201210007192A CN102535440A CN 102535440 A CN102535440 A CN 102535440A CN 201210007192X A CN201210007192X A CN 201210007192XA CN 201210007192 A CN201210007192 A CN 201210007192A CN 102535440 A CN102535440 A CN 102535440A
Authority
CN
China
Prior art keywords
pile
hole
casing
stake
drilling rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210007192XA
Other languages
English (en)
Inventor
刘富华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Original Assignee
Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Jiecheng Foundation Engineering & Machine Co Ltd filed Critical Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Priority to CN201210007192XA priority Critical patent/CN102535440A/zh
Publication of CN102535440A publication Critical patent/CN102535440A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明涉及一种在岩石层采用全套管钻机与旋挖钻机组合进行嵌岩咬合桩墙的施工方法。本发明工艺为①平整场地,在桩顶位置制作砼或钢筋砼导墙;②全套管钻机就位,其抱管器中心对应定位于导墙定位孔中心,套管、取土、成孔至岩面,移到下一工位;③素桩孔中灌注超缓凝砼,拔出套管,成桩;④旋挖凿岩机在钢筋砼桩孔就位,凿岩装置装入套管内,以小于10转/分的转速启动,钻压1~35T,钻进,排碴,直至设计深度,移开旋挖凿岩机;⑤压入套管,使钢筋砼桩孔与相邻素桩相切割;⑥孔内安装钢筋笼,灌注砼,拔出套管,形成咬合桩墙。本发明操作简单易行,对地面破损小,凿岩量较少,可缩短施工工期,工程造价低。

Description

全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法
技术领域
本发明涉及一种建筑施工方法,特别是一种专门在岩石层进行嵌岩咬合灌注桩施工的方法。
背景技术
地下连续墙有刚度大,整体性好,变形相对小,能较好的抗渗止水等优点,但造价较高,在岩层中成槽,采用现有常规的地下连续墙普通工艺成槽困难,效率较低,如选用铣槽机工艺时,则能满足其在岩石中成槽工效,但造价高。
全套管钻孔咬合桩墙是近年来应用发展较快的围护形式,具有刚度大,变形小,造价较地下连续墙低,施工方便,环境污染小,在施工过程中对周边建筑物及管线影响最小等优点,但由于城市二次建设的建筑物高度更高且深层地下存在残留桩,因此在进行长尺寸咬合桩施工时必然会遇到坚硬岩层或残留桩。全套管钻机的工法很适用于土层或软岩层,而入硬岩则较困难,遇大于桩径一半的孤石处理难度大,在实际操作中虽然可采用辅助设施凿除硬岩,但是施工效率会因此大大降低,操作也较为复杂。
旋挖钻机具有装机功率大、输出扭矩大、轴向压力大、机动灵活,适用性强,自动化程度高,劳动强度低,钻进效率高,施工效率高及多功能特点,可配合不同钻具,进行不同地质条件的钻孔及施工。但是对于松散易坍塌地层,或有地下水分布,孔壁不稳定,必须采用静态泥浆护壁钻进工艺,向孔内投入护壁泥浆或稳定液进行护壁,这会增加施工成本,污染环境;当地质太硬会引起钻锥跳动及偏斜、加大钻杆摆动,难以保证成孔(桩)质量。
本申请人曾在中国专利文献中提出了全套管钻机配合潜孔锤凿岩钻机进行嵌岩咬合灌注桩的施工方法,其操作简单易行,对地面破损小,可凿除较大尺寸的硬岩,凿岩量比地下连续墙凿岩量大大降低,从而可达到提高工效、缩短施工工期,又相应的降低工程造价的目的。但是施工中遇到岩层深度大于30米时,潜孔锤凿岩钻机的凿岩能力仍有限,因此施工效率还不够理想。
发明内容
本发明所要解决的技术问题是提供一种全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法,其操作简单易行,对地面破损小,设计桩长时更加灵活,采用荤素桩长短结合,凿除较大尺寸的硬岩效率高,从而可达到提高工效、缩短施工工期,又相应的降低工程造价的目的。
实现本发明目的所采用的技术方案步骤如下:①平整场地,在桩顶位置制作砼或钢筋砼导墙;②全套管钻机就位,其抱管器中心对应定位于导墙定位孔中心,套管、取土、成孔至岩面,移到下一工位;③素桩孔中灌注超缓凝砼,拔出套管,成桩;④旋挖凿岩机在钢筋砼桩孔就位,凿岩装置装入套管,以小于10转/分的转速启动,钻压1~35T钻进,且转速和钻压值从小到大,排碴,直至设计深度,移开旋挖凿岩机;⑤压入套管,使钢筋砼桩孔与相邻素桩相切割;⑥孔内安装钢筋笼,灌注砼,拔出套管,形成咬合桩墙。
本发明的技术方案还包括:
①所述导墙的定位孔直径应比桩径大20mm;②桩的咬合厚度按公式d-2(kL+q)控制,其中,L为桩长,k为桩垂直度,q为孔口定位误差容许值,d为桩的设计咬合厚度;③桩的垂直度应小于5‰,全部套管相连的顺直度偏差控制在1~2‰。
①素桩的超缓凝砼初凝时间≥60小时,3天的强度≤3MPa;②在钢筋砼桩孔成孔操作中,采取套管底口始终位于套管内取土面之下2.5m以上,控制相邻素桩孔中超缓凝砼坍落度小于180mm。
本发明的有益效果是:简单易行,对地面破损小,设计桩长时更加灵活,采用荤素桩长短结合,凿岩量比地下连续墙凿岩量大大降低,合理地控制旋挖钻机在套管中的操作参数,充分地利用了其较强的凿岩能力,有保证了良好的施工质量,可达到提高工效、缩短施工工期,又相应的降低工程造价的目的。
具体实施方式
实施例:本发明的工艺步骤如下。
①平整场地,在桩顶位置制作砼或钢筋砼导墙,导墙的定位孔直径应比桩径大20mm,并且校直套管,使全部套管相连的顺直度偏差控制在1~2‰;②全套管钻机就位,其抱管器中心对应定位于导墙定位孔中心,取土成孔至岩面,移到下一工位;③素桩孔中灌注超缓凝砼,拔出套管,连续成桩,素桩的超缓凝砼初凝时间≥60小时,3天的强度≤3MPa;④旋挖凿岩机在钢筋砼桩孔就位,为了防止管涌,在钻孔取土过程中采取套管底口始终位于套管内取土面之下2.5m以上,控制相邻素桩孔中超缓凝砼坍落度小于180mm,然后凿岩装置装入套管,以小于10转/分的转速启动,钻压1~35T钻进,且转速和钻压值都是从小逐渐增加到大,排碴,直至设计深度,移开旋挖凿岩机;⑤压入套管,使钢筋砼桩孔与相邻素桩相切割,桩的咬合厚度按前述的公式严格控制,素桩和钢筋砼桩的垂直度都控制在小于5‰;⑥在钢筋砼桩孔内安装带配重的钢筋笼(即在笼底固定钢板或水泥块),灌注砼,拔出套管,形成咬合桩墙。

Claims (3)

1.一种的施工方法,其特征是步骤如下:①平整场地,在桩顶位置制作砼或钢筋砼导墙;②全套管钻机就位,其抱管器中心对应定位于导墙定位孔中心,套管、取土、成孔至岩面,移到下一工位;③素桩孔中灌注超缓凝砼,拔出套管,成桩;④旋挖凿岩机在钢筋砼桩孔就位,凿岩装置装入套管,以以小于10转/分的转速启动,钻压1~35T钻进,且转速和钻压值从小到大,排碴,直至设计深度,移开旋挖凿岩机;⑤压入套管,使钢筋砼桩孔与相邻素桩相切割;⑥孔内安装钢筋笼,灌注砼,拔出套管,形成咬合桩墙。
2.按权利要求1所述的施工方法,其特征是:①所述导墙的定位孔直径应比桩径大20mm;②桩的咬合厚度按公式d-2(kL+q)控制,其中,L为桩长,k为桩垂直度,q为孔口定位误差容许值,d为桩的设计咬合厚度;③桩的垂直度应小于5‰,全部套管相连的顺直度偏差控制在1~2‰。
3.按权利要求2所述的施工方法,其特征是:①素桩的超缓凝砼初凝时间≥60小时,3天的强度≤3MPa;②在钢筋砼桩孔成孔操作中,采取套管底口始终位于套管内取土面之下2.5m以上,控制相邻素桩孔中超缓凝砼坍落度小于180mm。
CN201210007192XA 2012-01-11 2012-01-11 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法 Pending CN102535440A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210007192XA CN102535440A (zh) 2012-01-11 2012-01-11 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210007192XA CN102535440A (zh) 2012-01-11 2012-01-11 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法

Publications (1)

Publication Number Publication Date
CN102535440A true CN102535440A (zh) 2012-07-04

Family

ID=46343345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210007192XA Pending CN102535440A (zh) 2012-01-11 2012-01-11 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法

Country Status (1)

Country Link
CN (1) CN102535440A (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264662A (zh) * 2014-10-17 2015-01-07 中亿丰建设集团股份有限公司 富含水土层中深嵌硬质岩咬合桩施工方法
CN104929136A (zh) * 2015-07-14 2015-09-23 上海市水利工程集团有限公司 城区复杂地下障碍工况咬合桩围护施工方法
CN107938652A (zh) * 2018-01-03 2018-04-20 山东科技大学 一种嵌岩型钢水泥搅拌墙及其施工方法
CN108589707A (zh) * 2018-05-14 2018-09-28 上海腾尚基础工程有限公司 一种全套管长螺旋钻与旋挖钻组合式施工工法
CN109706919A (zh) * 2018-12-14 2019-05-03 中铁四局集团第二工程有限公司 一种入岩咬合桩施工方法
CN110306561A (zh) * 2019-07-05 2019-10-08 广州穗岩土木科技股份有限公司 一种基坑硬性咬合桩施工方法
CN110409476A (zh) * 2019-07-05 2019-11-05 中国建筑第八工程局有限公司 超深基坑围护结构侧壁漏水处理方法
CN110886577A (zh) * 2019-11-29 2020-03-17 深圳宏业基岩土科技股份有限公司 深厚填石区旋挖硬咬合桩垂直度控制的施工方法
CN111663522A (zh) * 2020-06-11 2020-09-15 深圳市工勘岩土集团有限公司 深厚填石层止水帷幕潜孔锤跟管咬合综合施工方法
CN113668551A (zh) * 2021-08-04 2021-11-19 深圳宏业基岩土科技股份有限公司 深厚填石淤泥地层旋挖硬切割咬合桩的成桩施工方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285777A (ja) * 2001-03-23 2002-10-03 Shuei Kogyo:Kk ロータリケーシングドリル

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285777A (ja) * 2001-03-23 2002-10-03 Shuei Kogyo:Kk ロータリケーシングドリル

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
沈保汉等: "捷程MZ系列全套管钻孔咬合桩", 《建筑技术》 *
沈保汉等: "第五讲捷程MZ系列全套管钻孔咬合桩施工工艺(2)", 《施工技术》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264662A (zh) * 2014-10-17 2015-01-07 中亿丰建设集团股份有限公司 富含水土层中深嵌硬质岩咬合桩施工方法
CN104929136A (zh) * 2015-07-14 2015-09-23 上海市水利工程集团有限公司 城区复杂地下障碍工况咬合桩围护施工方法
CN107938652A (zh) * 2018-01-03 2018-04-20 山东科技大学 一种嵌岩型钢水泥搅拌墙及其施工方法
CN107938652B (zh) * 2018-01-03 2023-08-22 山东科技大学 一种嵌岩型钢水泥搅拌墙及其施工方法
CN108589707A (zh) * 2018-05-14 2018-09-28 上海腾尚基础工程有限公司 一种全套管长螺旋钻与旋挖钻组合式施工工法
CN109706919A (zh) * 2018-12-14 2019-05-03 中铁四局集团第二工程有限公司 一种入岩咬合桩施工方法
CN110306561A (zh) * 2019-07-05 2019-10-08 广州穗岩土木科技股份有限公司 一种基坑硬性咬合桩施工方法
CN110409476A (zh) * 2019-07-05 2019-11-05 中国建筑第八工程局有限公司 超深基坑围护结构侧壁漏水处理方法
CN110886577A (zh) * 2019-11-29 2020-03-17 深圳宏业基岩土科技股份有限公司 深厚填石区旋挖硬咬合桩垂直度控制的施工方法
CN111663522A (zh) * 2020-06-11 2020-09-15 深圳市工勘岩土集团有限公司 深厚填石层止水帷幕潜孔锤跟管咬合综合施工方法
CN111663522B (zh) * 2020-06-11 2021-09-21 深圳市工勘岩土集团有限公司 深厚填石层止水帷幕潜孔锤跟管咬合综合施工方法
CN113668551A (zh) * 2021-08-04 2021-11-19 深圳宏业基岩土科技股份有限公司 深厚填石淤泥地层旋挖硬切割咬合桩的成桩施工方法

Similar Documents

Publication Publication Date Title
CN102535440A (zh) 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法
CN105649012B (zh) 上软下硬地层地铁车站围护结构钻孔桩施工方法
EP3406802A1 (en) Offshore rock-drilling redriving-type large-diameter pile structure and construction method
CN109371974A (zh) 一种适用于坚硬地质的phc管桩植入施工方法
CN104947690A (zh) 地下连续墙入岩成槽施工方法
CN105780763A (zh) 中孔振动套管护壁长螺旋钻孔压灌桩的施工方法
CN101586340A (zh) 连续墙在微风化岩层成槽施工中的预处理工艺
CN106939595A (zh) 一种旋挖扩底灌注桩施工工艺
CN102912791B (zh) 一种钻孔灌注桩的施工方法
CN102704480B (zh) 前端振动钢护筒处理桩基超厚流沙层施工方法
CN107060800A (zh) 一种盾构施工孤石处理施工方法
CN101982614A (zh) 全套管钻机凿取岩石成桩的方法
CN110656947A (zh) 海底基岩凸起段的掘进方法
CN103015408A (zh) 灌注桩同步跟管成孔施工方法
CN112942399A (zh) 一种穿岩层的沉井机械施工装置和方法
CN104314071A (zh) 一种通过旋挖机进行地下连续墙施工的方法
CN101985836B (zh) 一种桩、墙式深基坑支护结构遇大块孤石的处理方法
CN103174133A (zh) 一种钢管护壁超强嵌岩灌注桩的成桩装置与方法
CN105545315A (zh) 盾构法隧道施工中加固开挖面土层的常压换刀方法
CN102425388A (zh) 钻孔桩捞渣筒钻
CN108071110A (zh) 复杂地质条件下旋挖钻机嵌岩桩施工方法
CN102002943B (zh) 嵌岩咬合灌注桩的施工方法
JP2017025618A (ja) 先進ボーリング工法
CN206071589U (zh) 一种多功能数控竖井掘进装置
CN104452776A (zh) 遭遇孤石时地下连续墙的一种施工处治方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120704