CN105545315A - 盾构法隧道施工中加固开挖面土层的常压换刀方法 - Google Patents

盾构法隧道施工中加固开挖面土层的常压换刀方法 Download PDF

Info

Publication number
CN105545315A
CN105545315A CN201511003910.6A CN201511003910A CN105545315A CN 105545315 A CN105545315 A CN 105545315A CN 201511003910 A CN201511003910 A CN 201511003910A CN 105545315 A CN105545315 A CN 105545315A
Authority
CN
China
Prior art keywords
construction
shield
reinforcing
normal pressure
excavation face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201511003910.6A
Other languages
English (en)
Inventor
郑世兴
张怡潾
易宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Foundation Engineering Group Co Ltd
Priority to CN201511003910.6A priority Critical patent/CN105545315A/zh
Publication of CN105545315A publication Critical patent/CN105545315A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种盾构法隧道施工中加固开挖面土体的常压换刀施工方法,通过对盾构前方土体进行置换加固,达到开挖面自稳的能力,其具体步骤是:(1)制定盾构机换刀加固体所需的大小及范围;(2)采用全回旋套管钻机对加固区土体进行加固;(3)盾构掘进至加固体内进行换刀施工。本发明采用简单易行的施工方法,解决了施工中不良地质中换刀施工的问题,达到安全、快速换刀的目的,大大缩减了施工周期。

Description

盾构法隧道施工中加固开挖面土层的常压换刀方法
技术领域
本发明涉及一种盾构在复杂地质条件下的施工方法,尤其是一种地铁盾构法隧道施工中利用全回旋钻机进行开挖面土体加固的常压换刀施工方法。
背景技术
随着城市地铁建设的发展,在硬土地区进行盾构施工情况越来越多,由于硬土地区主要以残疾土层为主,盾构机在此类土层中掘进易产生泥饼或磨损刀具。因此,研究分析出一套通俗有效的常压换刀方法,成为一个亟待解决的难题。
针对盾构机在残积土等硬土地层中掘进的施工特点,对盾构机常压换刀技术进行研究,发展出一套盾构机利用在全回旋钻机加固的地层中进行常压换刀施工技术,加强了盾构机在常压换刀施工条件下安全性,增加了人员出仓的次数,提高了盾构机换刀的效能,从而缩减了盾构施工工期。通过一整套施工控制技术的推广与运用,可为全社会节约资源,提高经济效率。
发明内容
本发明是要提供一种地铁盾构法隧道施工中加固开挖面土体的常压换刀施工方法,来达到完善的盾构常压换刀的目的。
为实现上述目的,本发明的技术方案是:一种地铁盾构法隧道施工中加固开挖面土体的常压换刀施工方法,具体步骤为:
(1)制定盾构机换刀加固体所需的大小及范围;
(2)采用全回旋套管钻机对加固区土体进行加固;
(3)盾构掘进至加固体内进行换刀施工。
所述采用全回旋套管钻机加固土体的具体方法:采用全回转钻机成孔在盾构机刀盘前方施工一道水泥砂浆咬合桩墙施工,每根桩成孔后使用M10商品水泥砂浆对钻孔进行灌注,地面至加固体上方的土体应均匀拌合20%水泥后回填;全回转施工时垂直度应控制在1/100。
本发明的有益效果是:
本发明能够实现地铁盾构法隧道施工中利用全回旋钻机进行开挖面土体加固的常压换刀施工,应用在全回旋钻机加固的地层中进行常压换刀施工技术,加强了盾构机在常压换刀施工条件下安全性,增加了人员出仓的次数,提高了盾构机换刀的效能,从而缩减了盾构施工工期。通过一整套施工控制技术的推广与运用,可为全社会节约资源,提高经济效率。
附图说明
图1为全回旋套管钻机示意图;
图2为咬合桩施工顺序示意图。
具体实施方式
一种地铁盾构法隧道施工中利用全回旋钻机进行开挖面土体加固的常压换刀施工方法,其具体施工步骤如下:
(1)制定盾构机换刀加固体所需的大小及范围;
(2)采用全回旋套管钻机对加固区土体进行加固;
(3)盾构掘进至加固体内进行换刀施工。
其中:采用全回旋套管钻机(图1)成孔并在盾构机前方施工一道水泥砂浆咬合桩墙施工,每根桩成孔后使用M10商品水泥砂浆对钻孔进行灌注,灌注范围为隧道顶部上方4m,隧道底部以下1.3m(加固范围可根据现场实际施工环境进行调整),地面至隧道上方4m的土体应均匀拌合20%水泥后回填。全回转施工时垂直度应控制在1/100,咬合桩桩径1.5m,此时桩间咬合弦长为1200mm。
如图2所示,根据咬合桩编号,其施工顺序为跳打:如1#、3#、2#。
施工注意要点:
(1)咬合桩成孔后需对孔深进行测量;
全回转成孔后,在灌注M10水泥砂浆前2h,应对地下水位进行量测,结果显示无较大水位变化再灌入水泥砂浆。如有较大变化,应使用水泵抽干后再灌入施工;
(2)水泥砂浆范围上的土方回填时间应控制在水泥砂浆的初凝(3h)之后。

Claims (2)

1.一种盾构法隧道施工中加固开挖面土体的常压换刀施工方法,通过对盾构前方土体进行置换加固,达到开挖面自稳的能力,其特征在于,具体步骤为:
(1)制定盾构机换刀加固体所需的大小及范围;
(2)采用全回旋套管钻机对加固区土体进行加固;
(3)盾构掘进至加固体内进行换刀施工。
2.根据权利要求1所述的盾构法隧道施工中加固开挖面土体的常压换刀施工方法,其特征在于:所述采用全回旋套管钻机加固土体的具体方法:采用全回转钻机成孔在盾构机刀盘前方施工一道水泥砂浆咬合桩墙施工,每根桩成孔后使用M10商品水泥砂浆对钻孔进行灌注,地面至加固体上方的土体应均匀拌合20%水泥后回填;全回转施工时垂直度控制在1/100。
CN201511003910.6A 2015-12-29 2015-12-29 盾构法隧道施工中加固开挖面土层的常压换刀方法 Pending CN105545315A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511003910.6A CN105545315A (zh) 2015-12-29 2015-12-29 盾构法隧道施工中加固开挖面土层的常压换刀方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511003910.6A CN105545315A (zh) 2015-12-29 2015-12-29 盾构法隧道施工中加固开挖面土层的常压换刀方法

Publications (1)

Publication Number Publication Date
CN105545315A true CN105545315A (zh) 2016-05-04

Family

ID=55824820

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511003910.6A Pending CN105545315A (zh) 2015-12-29 2015-12-29 盾构法隧道施工中加固开挖面土层的常压换刀方法

Country Status (1)

Country Link
CN (1) CN105545315A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761792A (zh) * 2017-01-20 2017-05-31 武汉市市政建设集团有限公司 一种全套管全回转钻机套筒及盾构刀盘前方障碍物清除方法
CN108086987A (zh) * 2018-01-11 2018-05-29 河海大学 上软下硬地层中土压盾构掘进保持开挖面稳定的控制方法
CN112576267A (zh) * 2021-02-22 2021-03-30 中铁九局集团第四工程有限公司 富水砂卵石地层高效常压换刀施工方法
CN112943269A (zh) * 2021-03-10 2021-06-11 中交隧道工程局有限公司 一种过井不开挖常压换刀作业方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2891431B2 (ja) * 1990-09-07 1999-05-17 株式会社鴻池組 地下鉄筋コンクリート連続壁工法
CN102168565A (zh) * 2011-03-21 2011-08-31 广东水电二局股份有限公司 一种实现盾构机常压开舱的土体加固方法
EP2201217B1 (de) * 2006-01-26 2011-10-19 Florianer Bahn Forschungs- und Errichtungsgesellschaft mbH Verfahren und vorrichtung zur lagestabilisierung von tunnelausbauelementen
CN104005769A (zh) * 2014-03-25 2014-08-27 中铁十六局集团地铁工程有限公司 一种无水砂卵石地层盾构开舱换刀的方法
CN105019913A (zh) * 2015-08-03 2015-11-04 中铁六局集团有限公司 基岩隆起区盾构换刀原位加固方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2891431B2 (ja) * 1990-09-07 1999-05-17 株式会社鴻池組 地下鉄筋コンクリート連続壁工法
EP2201217B1 (de) * 2006-01-26 2011-10-19 Florianer Bahn Forschungs- und Errichtungsgesellschaft mbH Verfahren und vorrichtung zur lagestabilisierung von tunnelausbauelementen
CN102168565A (zh) * 2011-03-21 2011-08-31 广东水电二局股份有限公司 一种实现盾构机常压开舱的土体加固方法
CN104005769A (zh) * 2014-03-25 2014-08-27 中铁十六局集团地铁工程有限公司 一种无水砂卵石地层盾构开舱换刀的方法
CN105019913A (zh) * 2015-08-03 2015-11-04 中铁六局集团有限公司 基岩隆起区盾构换刀原位加固方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘远书: "SMW工法在南水北调中线穿黄工程盾构机常压换刀时地基加固中的应用", 《水利水电技术》 *
周阳宗等: "复合地层下盾构换刀技术研究", 《施工技术》 *
陈建军: "超深搅拌桩在盾构常压换刀中的应用", 《城市道桥与防洪》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761792A (zh) * 2017-01-20 2017-05-31 武汉市市政建设集团有限公司 一种全套管全回转钻机套筒及盾构刀盘前方障碍物清除方法
CN108086987A (zh) * 2018-01-11 2018-05-29 河海大学 上软下硬地层中土压盾构掘进保持开挖面稳定的控制方法
CN112576267A (zh) * 2021-02-22 2021-03-30 中铁九局集团第四工程有限公司 富水砂卵石地层高效常压换刀施工方法
WO2021213098A1 (zh) * 2021-02-22 2021-10-28 中铁九局集团有限公司 富水砂卵石地层高效常压换刀施工方法
CN112576267B (zh) * 2021-02-22 2021-12-21 中铁九局集团第四工程有限公司 富水砂卵石地层高效常压换刀施工方法
CN112943269A (zh) * 2021-03-10 2021-06-11 中交隧道工程局有限公司 一种过井不开挖常压换刀作业方法

Similar Documents

Publication Publication Date Title
CN103089275B (zh) 富水极破碎围岩隧道塌方段围岩控制方法
CN102493822B (zh) 一种通过富水断层影响带的隧道的帷幕注浆施工方法
CN104790978B (zh) 小净距立体交叉隧道环形导坑施工方法
CN103835648B (zh) 一种通过地面注浆改善岩层性能反井钻井工艺
CN204312099U (zh) 基于环境保护的隧道涌水防治系统
CN103046931B (zh) 一种竖井/导井冲击式钻机冲击成孔施工方法
CN104963346A (zh) 复杂地质的深基坑围护施工方法
CN103758123A (zh) 人工挖孔灌注桩护壁衬的施工方法
CN102535440A (zh) 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法
CN103835723A (zh) 井筒穿越采空区地层的综合预治理方法
CN105545315A (zh) 盾构法隧道施工中加固开挖面土层的常压换刀方法
CN104033160A (zh) 一种适用于软土地层的浅埋暗挖隧道新型支护方法
CN105525619A (zh) 一种富水地层暗挖隧道咬合管幕及其施工方法
CN102777185A (zh) 一种斜井井筒施工工艺
CN103016027A (zh) 一种软弱、破碎复杂地质条件下隧道或巷道掘进方法
CN105909265B (zh) 穿越既有盾构隧道防隆起后退式深孔注浆系统及方法
CN103485347A (zh) 一种建筑基坑支护用斜桩及其施工方法
CN105909262B (zh) 一种暗挖隧道掘进方法
CN102635359A (zh) 隧道通风竖井节能快速施工方法
CN104074184B (zh) 一种桩底后注浆扩底灌注桩
CN101481913A (zh) 嵌岩地下连续墙冲孔槽段施工方法
CN103775102A (zh) 潜孔钻跟管成孔回填砼稳定临空面处理塌方施工方法
CN104452776B (zh) 遭遇孤石时地下连续墙的一种施工处治方法
CN105862725A (zh) 地下工程预注浆防水防渗支护技术
CN205296194U (zh) 一种富水地层暗挖隧道咬合管幕

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160504