EP3406802A1 - Offshore rock-drilling redriving-type large-diameter pile structure and construction method - Google Patents

Offshore rock-drilling redriving-type large-diameter pile structure and construction method Download PDF

Info

Publication number
EP3406802A1
EP3406802A1 EP18168006.7A EP18168006A EP3406802A1 EP 3406802 A1 EP3406802 A1 EP 3406802A1 EP 18168006 A EP18168006 A EP 18168006A EP 3406802 A1 EP3406802 A1 EP 3406802A1
Authority
EP
European Patent Office
Prior art keywords
pile
steel pipe
soil layer
rock
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP18168006.7A
Other languages
German (de)
French (fr)
Inventor
Na LV
Hu ZHOU
Haifeng Qi
Jinping LUO
Danshan WANG
Hongbao RONG
Ning LIANG
Yu Li
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Publication of EP3406802A1 publication Critical patent/EP3406802A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes

Definitions

  • the present invention relates to an offshore rock-drilling redriving-type large-diameter pile structure and construction method. It is suitable for the technical fields of offshore wind power and other ocean engineering.
  • the monopile foundation is a structural form most widely applied in the field of offshore wind power, and it has such advantages as simple structure, convenient construction and high construction efficiency.
  • the large-scale construction of offshore wind power industry as engineering sea areas like those in Fujian province and Guangdong province in China are featured by complex geologic conditions, the depths of sand deposits in some submarine formations are limited, and weathered rock formations are found in lower portions, so that it is relatively more difficult for a pile foundation to be driven to the designed depth once for all, and the traditional method in which pile driving is conducted merely by means of hammering limits the application of monopile foundations in these engineering sea areas.
  • the technical problem to be solved by the present invention is to provide an offshore rock-drilling redriving-type large-diameter pile structure featured by simple structure and convenient construction, and construction method, so as to improve construction efficiency and reduce construction costs.
  • an offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the rock layer, and a steel pipe pile is driven into the pile hole; the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer, a compact soil layer section corresponding to the compact soil layer and a rock layer section corresponding to the rock layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section and the rock layer section are formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer and the rock layer for a construction channel.
  • the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile, and the rock layer section of the pile hole has a hole diameter slightly larger than the pile diameter of the steel pipe pile.
  • the rock layer section of the pile hole is filled with underwater concrete, and the steel pipe pile is integrated with the rock layer section of the pile hole by means of the underwater concrete.
  • a construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
  • An offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the compact soil layer, and a steel pipe pile is driven into the pile hole; the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer and a compact soil layer section corresponding to the compact soil layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section is formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer for a construction channel.
  • the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.
  • a construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
  • the present invention has the following beneficial effects: in the present invention, the driller apparatus is directly set up at the top of the steel pipe pile, thus making the steel pipe pile both a driller supporting mechanism and a drilled hole protection structure; in this manner, the construction procedure of setting up a rock-socketed platform is omitted, thus shortening the construction period and reducing the costs of rock-socketed construction.
  • the steel pipe pile is subjected to pile driving and made to pass through the loose cover soil layer to be supported on the compact soil layer.
  • the steel pipe pile itself can stand stably, which meet the requirements for setting up a driller apparatus.
  • the present invention is featured by simple structure form and less drilling workload, which effectively shortens the construction period, thus greatly reducing the engineering investments.
  • Embodiment 1 As shown in Fig. 1 , the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure.
  • This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and a rock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all.
  • the foundation is provided with a pile hole 3, and the designed bottom elevation of this pile hole is located within the rock layer 11.
  • the bottom portion of the pile hole 3 is filled with underwater concrete 6, a steel pipe pile 1 is driven into the pile hole 3 by means of a pile driving hammer 4, and a lower end of the steel pipe pile 1 is integrated with the rock layer 11 by means of the underwater concrete 6.
  • the pile hole 3 is sequentially divided into a loose soil layer section 31 located within the loose cover soil layer 9, a compact soil layer section 32 located within the compact soil layer 10 and a rock layer section 33 located within the rock layer 11 from top to bottom, wherein the loose soil layer section 31 is formed within the loose cover soil layer 9 after the steel pipe pile 1 is driven by the pile driving hammer 4 to be supported on the compact soil layer 10, and the compact soil layer section 32 and the rock layer section 33 are formed after the steel pipe pile 1, whose lower end is supported on the compact soil layer 10 after pile driving, conducts drilling on the compact soil layer 10 and the rock layer 11 under the bottom portion of the steel pipe pile 1 for the construction channel.
  • the compact soil layer section 32 of the pile hole 3 has a hole diameter smaller than the pile diameter of the steel pipe pile 1
  • the rock layer section 33 of the pile hole 3 has a hole diameter slightly larger than the pile diameter of the steel pipe pile 1.
  • Embodiment 2 As shown in Fig. 5 , the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure.
  • This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and a rock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all.
  • the foundation is provided with a pile hole 3, the designed bottom elevation of this pile hole is located within the compact soil layer 10, and a steel pipe pile 1 is driven into the pile hole 3 by means of a pile driving hammer 4.
  • the pile hole 3 is sequentially divided into a loose soil layer section 31 located within the loose cover soil layer, a compact soil layer section 32 located within the compact soil layer and a rock layer section 33 corresponding to the rock layer from top to bottom, wherein the loose soil layer section 31 is formed within the loose cover soil layer after the steel pipe pile is driven by the pile driving hammer to be supported on the compact soil layer, and the compact soil layer section 32 is formed after the steel pipe pile, whose lower end is supported on the compact soil layer upon pile driving, conducts drilling on the compact soil layer and the rock layer under the bottom portion of the steel pipe pile for the construction channel.
  • the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)
  • Earth Drilling (AREA)

Abstract

An offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, wherein a pile hole (3) is drilled into the rock layer, and a steel pipe pile (1) is driven into the pile hole (3); the pile hole (3) being sequentially divided into a loose soil layer section corresponding to the loose cover soil layer, a compact soil layer section corresponding to the compact soil layer and a rock layer section corresponding to the rock layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section and the rock layer section are formed after the steel pipe pile driven in the loose cover soil layer and drilling is performed on the compact soil layer and the rock layer for a construction channel.

Description

    TECHNICAL FIELD
  • The present invention relates to an offshore rock-drilling redriving-type large-diameter pile structure and construction method. It is suitable for the technical fields of offshore wind power and other ocean engineering.
  • BACKGROUND ART
  • The monopile foundation is a structural form most widely applied in the field of offshore wind power, and it has such advantages as simple structure, convenient construction and high construction efficiency. With the large-scale construction of offshore wind power industry, as engineering sea areas like those in Fujian province and Guangdong province in China are featured by complex geologic conditions, the depths of sand deposits in some submarine formations are limited, and weathered rock formations are found in lower portions, so that it is relatively more difficult for a pile foundation to be driven to the designed depth once for all, and the traditional method in which pile driving is conducted merely by means of hammering limits the application of monopile foundations in these engineering sea areas.
  • In view of the above geologic conditions, some engineering employs traditional high-piled cap rock-socketed pile foundations or jacket rock-socketed foundations. But the high-piled cap rock-socketed foundations are featured by complex construction processes, numerous procedures, low efficiency and high overall construction costs of foundation; for the jacket foundation structures, as pile tops are below the water surface, boring construction is rendered inconvenient.
  • SUMMARY OF THE INVENTION
  • In view of the existing problems mentioned above, the technical problem to be solved by the present invention is to provide an offshore rock-drilling redriving-type large-diameter pile structure featured by simple structure and convenient construction, and construction method, so as to improve construction efficiency and reduce construction costs.
  • The technical solution adopted by the present invention is as follows: an offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the rock layer, and a steel pipe pile is driven into the pile hole;
    the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer, a compact soil layer section corresponding to the compact soil layer and a rock layer section corresponding to the rock layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section and the rock layer section are formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer and the rock layer for a construction channel.
  • The compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile, and the rock layer section of the pile hole has a hole diameter slightly larger than the pile diameter of the steel pipe pile.
  • The rock layer section of the pile hole is filled with underwater concrete, and the steel pipe pile is integrated with the rock layer section of the pile hole by means of the underwater concrete.
  • A construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
    • S1 of conducting pile driving at the top of a steel pipe pile by means of the pile driving hammer until a lower end of the steel pipe pile is supported on the surface of the compact soil layer;
    • S2 of setting up a driller apparatus at the top of the steel pipe pile, wherein a rock-socketed driller bit of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation in the rock layer, wherein the drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile; and of conducting hole broadening for the drilled hole within the rock layer until its hole diameter is slightly larger than the pile diameter of the steel pipe pile;
    • S3 of removing the driller apparatus and cleaning the drilled hole;
    • S4 of filling the drilled hole in the rock layer with underwater concrete;
    • S5 of conducting pile driving at the top of the steel pipe pile by means of the pile driving hammer until the lower end of the steel pipe pile reaches the designed bottom elevation in the rock layer.
  • An offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the compact soil layer, and a steel pipe pile is driven into the pile hole;
    the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer and a compact soil layer section corresponding to the compact soil layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section is formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer for a construction channel.
  • The compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.
  • A construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
    • S1 of conducting pile driving at the top of a steel pipe pile by means of a pile driving hammer until a lower end of the steel pipe pile is supported on the surface of a compact soil layer;
    • S2 of setting up a driller apparatus at the top of the steel pipe pile, wherein a rock-socketed driller bit of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation in the compact soil layer, wherein the drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile;
    • S3 of removing the driller apparatus and cleaning the drilled hole;
    • S4 of conducting pile driving at the top of the steel pipe pile by means of the pile driving hammer until the lower end of the steel pipe pile reaches the designed bottom elevation in the compact soil layer.
  • The present invention has the following beneficial effects: in the present invention, the driller apparatus is directly set up at the top of the steel pipe pile, thus making the steel pipe pile both a driller supporting mechanism and a drilled hole protection structure; in this manner, the construction procedure of setting up a rock-socketed platform is omitted, thus shortening the construction period and reducing the costs of rock-socketed construction. In the present invention, the steel pipe pile is subjected to pile driving and made to pass through the loose cover soil layer to be supported on the compact soil layer. Here, the steel pipe pile itself can stand stably, which meet the requirements for setting up a driller apparatus. The present invention is featured by simple structure form and less drilling workload, which effectively shortens the construction period, thus greatly reducing the engineering investments.
  • BRIEF DESCRIPTION OF THE DRAWINGS
    • Fig. 1 is a schematic diagram illustrating the structure of Embodiment 1.
    • Figs. 2-4 are schematic diagrams illustrating the construction process of Embodiment 1.
    • Fig. 5 is a schematic diagram illustrating the structure of Embodiment 2.
    DETAILED DESCRIPTION OF THE INVENTION
  • Embodiment 1: As shown in Fig. 1, the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure. This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and a rock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all. In the present embodiment, the foundation is provided with a pile hole 3, and the designed bottom elevation of this pile hole is located within the rock layer 11. The bottom portion of the pile hole 3 is filled with underwater concrete 6, a steel pipe pile 1 is driven into the pile hole 3 by means of a pile driving hammer 4, and a lower end of the steel pipe pile 1 is integrated with the rock layer 11 by means of the underwater concrete 6.
  • In the present embodiment, the pile hole 3 is sequentially divided into a loose soil layer section 31 located within the loose cover soil layer 9, a compact soil layer section 32 located within the compact soil layer 10 and a rock layer section 33 located within the rock layer 11 from top to bottom, wherein the loose soil layer section 31 is formed within the loose cover soil layer 9 after the steel pipe pile 1 is driven by the pile driving hammer 4 to be supported on the compact soil layer 10, and the compact soil layer section 32 and the rock layer section 33 are formed after the steel pipe pile 1, whose lower end is supported on the compact soil layer 10 after pile driving, conducts drilling on the compact soil layer 10 and the rock layer 11 under the bottom portion of the steel pipe pile 1 for the construction channel. In the present embodiment, the compact soil layer section 32 of the pile hole 3 has a hole diameter smaller than the pile diameter of the steel pipe pile 1, and the rock layer section 33 of the pile hole 3 has a hole diameter slightly larger than the pile diameter of the steel pipe pile 1.
  • The construction method of the present embodiment is as follows:
    1. 1. Similar to a normal foundation pile, pile driving is conducted at the top of the steel pipe pile 1 by means of the pile driving hammer 4. This requires no additional auxiliary apparatuses or measures, but pile driving must be controlled in strict accordance with the hammer-stopping standard so as to prevent the pile body from being damaged as a result of forcible pile driving. The pile driving may be continued until the lower end of the steel pipe pile 1 is supported on the surface of the compact soil layer 10 (see Fig. 2), and the initially driven depth for the pile foundation of the steel pipe pile 1 can meet the stability requirement of the driller during its construction process;
    2. 2. The steel pipe pile 1 itself is taken as both a driller supporting structure and a drilled hole protection structure. The driller apparatus 5 is set up at the top of the steel pipe pile 1, wherein a rock-socketed driller bit 5-1 of the driller apparatus conducts drilling on the compact soil layer 10 and the rock layer 11 within and under the steel pipe pile 1 through the channel within the steel pipe pile 1 until it reaches the designed bottom elevation within the rock layer 11, wherein the drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile 1, and specific sizes may be properly adjusted according to on-site drilling conditions; hole broadening is conducted for the drilled hole within the rock layer 11 (the rock layer section of the pile hole) until its hole diameter is slightly larger than the pile diameter of the steel pipe pile (see Fig. 3);
    3. 3. Rmoving the driller apparatus 5 , cleaning the drilled hole;
    4. 4. The underwater concrete 6 is filled in the drilled hole of the rock layer 11, and its filling height is slightly above the top surface of the rock layer section 33;
    5. 5. Pile driving is conducted at the top of the steel pipe pile 1 by means of the pile driving hammer 4 until the lower end of the steel pipe pile 1 sinks down to the designed bottom elevation within the rock layer 11 (see Fig. 4).
  • Embodiment 2: As shown in Fig. 5, the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure. This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and a rock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all. In the present embodiment, the foundation is provided with a pile hole 3, the designed bottom elevation of this pile hole is located within the compact soil layer 10, and a steel pipe pile 1 is driven into the pile hole 3 by means of a pile driving hammer 4.
  • In the present embodiment, the pile hole 3 is sequentially divided into a loose soil layer section 31 located within the loose cover soil layer, a compact soil layer section 32 located within the compact soil layer and a rock layer section 33 corresponding to the rock layer from top to bottom, wherein the loose soil layer section 31 is formed within the loose cover soil layer after the steel pipe pile is driven by the pile driving hammer to be supported on the compact soil layer, and the compact soil layer section 32 is formed after the steel pipe pile, whose lower end is supported on the compact soil layer upon pile driving, conducts drilling on the compact soil layer and the rock layer under the bottom portion of the steel pipe pile for the construction channel. In the present embodiment, the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.
  • The construction method of the present embodiment is as follows:
    1. 1. Similar to a normal foundation pile, pile driving is conducted at the top of the steel pipe pile 1 by means of the pile driving hammer 4. This requires no additional auxiliary apparatuses or measures, but pile driving must be controlled in strict accordance with the hammer-stopping standard so as to prevent the pile body from being damaged as a result of forcible pile driving. The pile driving may be continued until the lower end of the steel pipe pile is supported on the surface of the compact soil layer, and the initially driven depth for the pile foundation of the steel pipe pile can meet the stability requirement of the driller during its construction process;
    2. 2. The steel pipe pile 1 itself is taken as both a driller supporting structure and a drilled hole protection structure. The driller apparatus 5 is set up at the top of the steel pipe pile 1, wherein a rock-socketed driller bit 5-1 of the driller apparatus conducts drilling on the compact soil layer 10 within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation within the compact soil layer, wherein the drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile 1, and specific sizes may be properly adjusted according to on-site drilling conditions;
    3. 3. Removing the driller apparatus 5, and cleaning the drilled hole;
    4. 4. Pile driving is conducted at the top of the steel pipe pile 1 by means of the pile driving hammer 4 until the lower end of the steel pipe pile 1 sinks down to the designed bottom elevation within the compact soil layer 10.
  • In the implementation process of the present invention, parameters of geological exploration are required to be analyzed, and related software is employed to analyze the initially driven depth of the foundation and the feasibility of the manner in which pile driving is conducted upon hole cleaning. Then, numerical simulations or other manners are employed to analyze the overall stability of foundation + driller during drilling and under the action of wave and current loads as well as vibration loads of the driller, and the vertical bearing capacity of the foundation after the drilled hole is cleaned. For geologic conditions under which piles can be successfully redriven after holes are drilled, the construction process of Embodiment 2 is employed; for those situations in which hard rock layers are required to be broken and redriving is still faced with difficulties even after holes are drilled, the construction process of Embodiment 1 may be employed.
  • The above embodiments and construction processes are mainly applied to monopile foundations for offshore wind power, but they are not limited thereto. For other foundation structures to which oceaneering structures pertain, they can also be designed and constructed through the technical solution of the present invention.

Claims (7)

  1. An offshore rock-drilling redriving-type large-diameter pile structure suitable for a foundation including a loose cover soil layer (9), a compact soil layer (10) and a rock layer (11) from top to bottom, characterized in that the foundation is provided with a pile hole extending into the rock layer (11), and a steel pipe pile (1) is driven into the pile hole;
    the pile hole (3) is sequentially divided into a loose soil layer section (31) corresponding to the loose cover soil layer (9), a compact soil layer section (32) corresponding to the compact soil layer (10) and a rock layer section (33) corresponding to the rock layer (11) from top to bottom, wherein the loose soil layer section (31) is formed after the steel pipe pile (1) is subjected to pile driving, and the compact soil layer section (32) and the rock layer section (33) are formed after the steel pipe pile (1) driven in the loose cover soil layer (9) conducts drilling on the compact soil layer (10) and the rock layer (11) for a construction channel.
  2. The offshore rock-drilling redriving-type large-diameter pile structure according to claim 1, characterized in that the compact soil layer section (32) of the pile hole (3) has a hole diameter smaller than the pile diameter of the steel pipe pile (1), and the rock layer section (33) of the pile hole has a hole diameter slightly larger than the pile diameter of the steel pipe pile (1).
  3. The offshore rock-drilling redriving-type large-diameter pile structure according to claim 1 or 2, characterized in that the rock layer section (33) of the pile hole (3) is filled with underwater concrete (6), and the steel pipe pile (1) is integrated with the rock layer section of the pile hole by means of the underwater concrete.
  4. A construction method for the offshore rock-drilling redriving-type large-diameter pile structure according to any one of claims 1-3, characterized in that the construction method comprises the steps of:
    S4.1 of conducting pile driving at the top of a steel pipe pile (1) by means of a pile driving hammer (4) until a lower end of the steel pipe pile is supported on the surface of the compact soil layer (10);
    S4.2 of setting up a driller apparatus (5) at the top of the steel pipe pile (1), wherein a rock-socketed driller bit (5-1) of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation in the rock layer (11), wherein a drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile; and of conducting hole broadening for the drilled hole within the rock layer until its hole diameter is slightly larger than the pile diameter of the steel pipe pile;
    S4.3 of removing the driller apparatus (5) and cleaning the drilled hole;
    S4.4 of filling the drilled hole of the rock layer (11) with underwater concrete (6);
    S4.5 of conducting pile driving at the top of the steel pipe pile (1) by means of the pile driving hammer until the lower end of the steel pipe pile reaches the designed bottom elevation in the rock layer (11).
  5. An offshore rock-drilling redriving-type large-diameter pile structure suitable for a foundation including a loose cover soil layer (9), a compact soil layer (10) and a rock layer (11) from top to bottom, characterized in that the foundation is provided with a pile hole (3) extending into the compact soil layer (10), and a steel pipe pile (1) is driven into the pile hole;
    the pile hole (3) is sequentially divided into a loose soil layer section (31) corresponding to the loose cover soil layer (9) and a compact soil layer section (32) corresponding to the compact soil layer (10) from top to bottom, wherein the loose soil layer section (31) is formed after the steel pipe pile (1) is subjected to pile driving, and the compact soil layer section (32) is formed after the steel pipe pile (1) driven in the loose cover soil layer (9) conducts drilling on the compact soil layer for a construction channel.
  6. The offshore rock-drilling redriving-type large-diameter pile structure according to claim 5, characterized in that the compact soil layer section of the pile hole (3) has a hole diameter smaller than the pile diameter of the steel pipe pile (1).
  7. A construction method for the offshore rock-drilling redriving-type large-diameter pile structure according to claim 5 or 6, characterized in that the construction method comprises the steps of:
    S7.1 of conducting pile driving at the top of a steel pipe pile (1) by means of the pile driving hammer (4) until a lower end of the steel pipe pile is supported on the surface of the compact soil layer (10);
    S7.2 of setting up a driller apparatus (5) at the top of the steel pipe pile (1), wherein a rock-socketed driller bit (5-1) of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile (1) until it reaches the designed bottom elevation in the compact soil layer (10), wherein a drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile;
    S7.3 of removing the driller apparatus (5) and cleaning the drilled hole;
    S7.4 of conducting pile driving at the top of the steel pipe pile (1) by means of the pile driving hammer (4) until the lower end of the steel pipe pile reaches the designed bottom elevation in the compact soil layer (10).
EP18168006.7A 2017-05-25 2018-04-18 Offshore rock-drilling redriving-type large-diameter pile structure and construction method Withdrawn EP3406802A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710379587.5A CN107299632A (en) 2017-05-25 2017-05-25 Marine rock drilling strike-on type large diameter pile structure and construction method

Publications (1)

Publication Number Publication Date
EP3406802A1 true EP3406802A1 (en) 2018-11-28

Family

ID=60137361

Family Applications (1)

Application Number Title Priority Date Filing Date
EP18168006.7A Withdrawn EP3406802A1 (en) 2017-05-25 2018-04-18 Offshore rock-drilling redriving-type large-diameter pile structure and construction method

Country Status (2)

Country Link
EP (1) EP3406802A1 (en)
CN (1) CN107299632A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469080A (en) * 2018-12-11 2019-03-15 中铁五局集团贵州工程有限公司 A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water
CN109811786A (en) * 2019-03-26 2019-05-28 福建永福电力设计股份有限公司 A kind of offshore wind farm composite base structure of outer and inner tube stake combination
CN110258613A (en) * 2019-07-02 2019-09-20 山东科技大学 A kind of land single pile is inverted double barrels type wind power foundation and its application method
CN113174990A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Rotary spraying reinforcement method for foundation around subsidence of ocean deep water inclined pile
CN113174992A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile
CN113981961A (en) * 2021-10-08 2022-01-28 中交路桥华南工程有限公司 Barge type pile planting method for deep water bare rock
CN114438998A (en) * 2022-02-14 2022-05-06 中交第三航务工程局有限公司 Steel pipe pile rock-socketed construction process under complex geological conditions
CN114673144A (en) * 2022-04-28 2022-06-28 中铁十五局集团有限公司 Rapid pile planting construction method for trestle steel pipe pile on bare rock of inclined base surface
CN114960623A (en) * 2022-06-29 2022-08-30 湖北道泽勘测设计院有限公司 Basic structure and construction method of PSLC construction method pile
CN115012405A (en) * 2022-07-20 2022-09-06 中建八局第二建设有限公司 Foundation pit supporting method for grouting of perforated pipe pile in stone-nitre area

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080272A (en) * 2019-04-25 2019-08-02 上海交通大学 Offshore wind farm single-pile foundation and offshore wind farm device suitable for greater coasting area
CN114319319A (en) * 2021-12-03 2022-04-12 上海建工集团股份有限公司 High-bearing core-filling steel pipe pile and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2418301A1 (en) 1978-02-27 1979-09-21 Cegeo Cie Etu Geotechniques Mounting movable tools on tubes partic. in offshore petroleum mining - incorporates means of adjusting working position along tube and fixing it where required
DE102009023466A1 (en) 2009-06-02 2011-01-05 Herrenknecht Ag Method and device for creating an underwater foundation of a building
EP2930275A1 (en) * 2014-04-08 2015-10-14 Herrenknecht AG System and method for producing a foundation for a building in water
KR20160017644A (en) 2015-09-30 2016-02-16 (주)삼일이엔씨 Driven concrete pile with open lower part and construction method thereof
EP3034702A1 (en) * 2014-12-17 2016-06-22 Bauer Spezialtiefbau GmbH Method and device for erecting a foundation and foundation

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101135160A (en) * 2007-09-29 2008-03-05 陈宁华 Mixed pile forming method for high-bearing one-stage club-footed pile
KR100964796B1 (en) * 2010-02-26 2010-06-21 송기용 Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction
CN102286971A (en) * 2011-07-15 2011-12-21 中交水运规划设计院有限公司 Concrete-filled steel tube core column socketed pile
CN205713982U (en) * 2016-04-25 2016-11-23 辽宁有色基础工程公司 A kind of pile foundation construction drilling equipment being applicable to karst area
CN205917724U (en) * 2016-06-28 2017-02-01 江苏海上龙源风力发电有限公司 Do not have marine fan of grout and inlay rock single pile basis
CN106088140A (en) * 2016-06-28 2016-11-09 江苏海上龙源风力发电有限公司 A kind of batholith sea bed offshore wind turbine embedding rock single-pile foundation construction technique
CN206956717U (en) * 2017-05-25 2018-02-02 中国电建集团华东勘测设计研究院有限公司 Marine rock drilling strike-on type large diameter pile structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2418301A1 (en) 1978-02-27 1979-09-21 Cegeo Cie Etu Geotechniques Mounting movable tools on tubes partic. in offshore petroleum mining - incorporates means of adjusting working position along tube and fixing it where required
DE102009023466A1 (en) 2009-06-02 2011-01-05 Herrenknecht Ag Method and device for creating an underwater foundation of a building
EP2930275A1 (en) * 2014-04-08 2015-10-14 Herrenknecht AG System and method for producing a foundation for a building in water
EP3034702A1 (en) * 2014-12-17 2016-06-22 Bauer Spezialtiefbau GmbH Method and device for erecting a foundation and foundation
KR20160017644A (en) 2015-09-30 2016-02-16 (주)삼일이엔씨 Driven concrete pile with open lower part and construction method thereof

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469080A (en) * 2018-12-11 2019-03-15 中铁五局集团贵州工程有限公司 A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water
CN109469080B (en) * 2018-12-11 2023-12-19 中铁五局集团贵州工程有限公司 Underwater rock-socketed steel sheet pile cofferdam structure and construction method thereof
CN109811786A (en) * 2019-03-26 2019-05-28 福建永福电力设计股份有限公司 A kind of offshore wind farm composite base structure of outer and inner tube stake combination
CN109811786B (en) * 2019-03-26 2024-03-26 福建永福电力设计股份有限公司 Offshore wind power composite foundation structure with inner steel pipe pile and outer steel pipe pile combined
CN110258613A (en) * 2019-07-02 2019-09-20 山东科技大学 A kind of land single pile is inverted double barrels type wind power foundation and its application method
CN113174990B (en) * 2021-04-29 2023-05-23 福建永强岩土股份有限公司 Rotary spraying reinforcement method for pile periphery collapse foundation of ocean deep water inclined pile
CN113174990A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Rotary spraying reinforcement method for foundation around subsidence of ocean deep water inclined pile
CN113174992A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile
CN113981961A (en) * 2021-10-08 2022-01-28 中交路桥华南工程有限公司 Barge type pile planting method for deep water bare rock
CN113981961B (en) * 2021-10-08 2023-06-23 中交路桥华南工程有限公司 Ship-type pile planting method for deepwater bare rock
CN114438998A (en) * 2022-02-14 2022-05-06 中交第三航务工程局有限公司 Steel pipe pile rock-socketed construction process under complex geological conditions
CN114673144A (en) * 2022-04-28 2022-06-28 中铁十五局集团有限公司 Rapid pile planting construction method for trestle steel pipe pile on bare rock of inclined base surface
CN114960623A (en) * 2022-06-29 2022-08-30 湖北道泽勘测设计院有限公司 Basic structure and construction method of PSLC construction method pile
CN115012405A (en) * 2022-07-20 2022-09-06 中建八局第二建设有限公司 Foundation pit supporting method for grouting of perforated pipe pile in stone-nitre area

Also Published As

Publication number Publication date
CN107299632A (en) 2017-10-27

Similar Documents

Publication Publication Date Title
EP3406802A1 (en) Offshore rock-drilling redriving-type large-diameter pile structure and construction method
US10267008B2 (en) Offshore non-driven-in large-diameter monopile foundation structure and construction method
CN106759449B (en) Rock-based seabed offshore wind turbine rock-socketed single-pile foundation and construction method thereof
CN103603342B (en) Major diameter assembled casing super-long filling pile construction method
CN110409461A (en) A kind of base pit stand construction based on assembled large-diameter tubular pile
CN101586340A (en) Preconditioning process of continuous wall for weak weathering terrane grooving construction
CN204370469U (en) A kind of drilled pile long leg jacket offshore wind turbine foundation
CN102776884B (en) In stir and rotate prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN102535440A (en) Method of using all-casing drilling rig with rotary drilling rig to construct rock-socketed secant pile wall
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN107558488A (en) A kind of embedding rock single pile of offshore wind farm and its construction system and construction method
CN114215049A (en) Construction method for main steel casing of bored pile under deep water foundation and bare rock environment
CN107700479A (en) A kind of construction method of large diameter drill hole pile
CN103015408A (en) Cast-in-place pile synchronous casing hole-forming constructing method
CN206956717U (en) Marine rock drilling strike-on type large diameter pile structure
CN102383428B (en) Middle pick reverse drawing method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
Wu et al. Development of a novel self-entry exploitation device for marine natural gas hydrate and the feasibility studies
CN212716407U (en) Karst area pile foundation drilling equipment
CN112901074A (en) Rock-socketed drilling pore-forming process of marine large-diameter inclined pile rotary excavator
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam
CN104264679A (en) Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles
CN105804079A (en) Tool and method for smashing hard rock in large-diameter pile hole
CN214997452U (en) Large-scale long auger drilling that shakes
CN108411928A (en) One kind passing through multilayer karst cave ultra-deep and large diameter pile foundation boring method
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20180424

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

TPAC Observations filed by third parties

Free format text: ORIGINAL CODE: EPIDOSNTIPA

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20201015

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN WITHDRAWN

18W Application withdrawn

Effective date: 20210204