EP3406802A1 - Offshore rock-drilling redriving-type large-diameter pile structure and construction method - Google Patents
Offshore rock-drilling redriving-type large-diameter pile structure and construction method Download PDFInfo
- Publication number
- EP3406802A1 EP3406802A1 EP18168006.7A EP18168006A EP3406802A1 EP 3406802 A1 EP3406802 A1 EP 3406802A1 EP 18168006 A EP18168006 A EP 18168006A EP 3406802 A1 EP3406802 A1 EP 3406802A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- pile
- steel pipe
- soil layer
- rock
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/50—Piles comprising both precast concrete portions and concrete portions cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
- E02D27/425—Foundations for poles, masts or chimneys specially adapted for wind motors masts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
- E02D27/525—Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/28—Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
Definitions
- the present invention relates to an offshore rock-drilling redriving-type large-diameter pile structure and construction method. It is suitable for the technical fields of offshore wind power and other ocean engineering.
- the monopile foundation is a structural form most widely applied in the field of offshore wind power, and it has such advantages as simple structure, convenient construction and high construction efficiency.
- the large-scale construction of offshore wind power industry as engineering sea areas like those in Fujian province and Guangdong province in China are featured by complex geologic conditions, the depths of sand deposits in some submarine formations are limited, and weathered rock formations are found in lower portions, so that it is relatively more difficult for a pile foundation to be driven to the designed depth once for all, and the traditional method in which pile driving is conducted merely by means of hammering limits the application of monopile foundations in these engineering sea areas.
- the technical problem to be solved by the present invention is to provide an offshore rock-drilling redriving-type large-diameter pile structure featured by simple structure and convenient construction, and construction method, so as to improve construction efficiency and reduce construction costs.
- an offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the rock layer, and a steel pipe pile is driven into the pile hole; the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer, a compact soil layer section corresponding to the compact soil layer and a rock layer section corresponding to the rock layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section and the rock layer section are formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer and the rock layer for a construction channel.
- the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile, and the rock layer section of the pile hole has a hole diameter slightly larger than the pile diameter of the steel pipe pile.
- the rock layer section of the pile hole is filled with underwater concrete, and the steel pipe pile is integrated with the rock layer section of the pile hole by means of the underwater concrete.
- a construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
- An offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the compact soil layer, and a steel pipe pile is driven into the pile hole; the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer and a compact soil layer section corresponding to the compact soil layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section is formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer for a construction channel.
- the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.
- a construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
- the present invention has the following beneficial effects: in the present invention, the driller apparatus is directly set up at the top of the steel pipe pile, thus making the steel pipe pile both a driller supporting mechanism and a drilled hole protection structure; in this manner, the construction procedure of setting up a rock-socketed platform is omitted, thus shortening the construction period and reducing the costs of rock-socketed construction.
- the steel pipe pile is subjected to pile driving and made to pass through the loose cover soil layer to be supported on the compact soil layer.
- the steel pipe pile itself can stand stably, which meet the requirements for setting up a driller apparatus.
- the present invention is featured by simple structure form and less drilling workload, which effectively shortens the construction period, thus greatly reducing the engineering investments.
- Embodiment 1 As shown in Fig. 1 , the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure.
- This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and a rock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all.
- the foundation is provided with a pile hole 3, and the designed bottom elevation of this pile hole is located within the rock layer 11.
- the bottom portion of the pile hole 3 is filled with underwater concrete 6, a steel pipe pile 1 is driven into the pile hole 3 by means of a pile driving hammer 4, and a lower end of the steel pipe pile 1 is integrated with the rock layer 11 by means of the underwater concrete 6.
- the pile hole 3 is sequentially divided into a loose soil layer section 31 located within the loose cover soil layer 9, a compact soil layer section 32 located within the compact soil layer 10 and a rock layer section 33 located within the rock layer 11 from top to bottom, wherein the loose soil layer section 31 is formed within the loose cover soil layer 9 after the steel pipe pile 1 is driven by the pile driving hammer 4 to be supported on the compact soil layer 10, and the compact soil layer section 32 and the rock layer section 33 are formed after the steel pipe pile 1, whose lower end is supported on the compact soil layer 10 after pile driving, conducts drilling on the compact soil layer 10 and the rock layer 11 under the bottom portion of the steel pipe pile 1 for the construction channel.
- the compact soil layer section 32 of the pile hole 3 has a hole diameter smaller than the pile diameter of the steel pipe pile 1
- the rock layer section 33 of the pile hole 3 has a hole diameter slightly larger than the pile diameter of the steel pipe pile 1.
- Embodiment 2 As shown in Fig. 5 , the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure.
- This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and a rock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all.
- the foundation is provided with a pile hole 3, the designed bottom elevation of this pile hole is located within the compact soil layer 10, and a steel pipe pile 1 is driven into the pile hole 3 by means of a pile driving hammer 4.
- the pile hole 3 is sequentially divided into a loose soil layer section 31 located within the loose cover soil layer, a compact soil layer section 32 located within the compact soil layer and a rock layer section 33 corresponding to the rock layer from top to bottom, wherein the loose soil layer section 31 is formed within the loose cover soil layer after the steel pipe pile is driven by the pile driving hammer to be supported on the compact soil layer, and the compact soil layer section 32 is formed after the steel pipe pile, whose lower end is supported on the compact soil layer upon pile driving, conducts drilling on the compact soil layer and the rock layer under the bottom portion of the steel pipe pile for the construction channel.
- the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Piles And Underground Anchors (AREA)
- Earth Drilling (AREA)
Abstract
Description
- The present invention relates to an offshore rock-drilling redriving-type large-diameter pile structure and construction method. It is suitable for the technical fields of offshore wind power and other ocean engineering.
- The monopile foundation is a structural form most widely applied in the field of offshore wind power, and it has such advantages as simple structure, convenient construction and high construction efficiency. With the large-scale construction of offshore wind power industry, as engineering sea areas like those in Fujian province and Guangdong province in China are featured by complex geologic conditions, the depths of sand deposits in some submarine formations are limited, and weathered rock formations are found in lower portions, so that it is relatively more difficult for a pile foundation to be driven to the designed depth once for all, and the traditional method in which pile driving is conducted merely by means of hammering limits the application of monopile foundations in these engineering sea areas.
- In view of the above geologic conditions, some engineering employs traditional high-piled cap rock-socketed pile foundations or jacket rock-socketed foundations. But the high-piled cap rock-socketed foundations are featured by complex construction processes, numerous procedures, low efficiency and high overall construction costs of foundation; for the jacket foundation structures, as pile tops are below the water surface, boring construction is rendered inconvenient.
- In view of the existing problems mentioned above, the technical problem to be solved by the present invention is to provide an offshore rock-drilling redriving-type large-diameter pile structure featured by simple structure and convenient construction, and construction method, so as to improve construction efficiency and reduce construction costs.
- The technical solution adopted by the present invention is as follows: an offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the rock layer, and a steel pipe pile is driven into the pile hole;
the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer, a compact soil layer section corresponding to the compact soil layer and a rock layer section corresponding to the rock layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section and the rock layer section are formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer and the rock layer for a construction channel. - The compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile, and the rock layer section of the pile hole has a hole diameter slightly larger than the pile diameter of the steel pipe pile.
- The rock layer section of the pile hole is filled with underwater concrete, and the steel pipe pile is integrated with the rock layer section of the pile hole by means of the underwater concrete.
- A construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
- S1 of conducting pile driving at the top of a steel pipe pile by means of the pile driving hammer until a lower end of the steel pipe pile is supported on the surface of the compact soil layer;
- S2 of setting up a driller apparatus at the top of the steel pipe pile, wherein a rock-socketed driller bit of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation in the rock layer, wherein the drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile; and of conducting hole broadening for the drilled hole within the rock layer until its hole diameter is slightly larger than the pile diameter of the steel pipe pile;
- S3 of removing the driller apparatus and cleaning the drilled hole;
- S4 of filling the drilled hole in the rock layer with underwater concrete;
- S5 of conducting pile driving at the top of the steel pipe pile by means of the pile driving hammer until the lower end of the steel pipe pile reaches the designed bottom elevation in the rock layer.
- An offshore rock-drilling redriving-type large-diameter pile structure is provided, which is suitable for a foundation including a loose cover soil layer, a compact soil layer and a rock layer from top to bottom, and it is characterized in that the foundation is provided with a pile hole extending into the compact soil layer, and a steel pipe pile is driven into the pile hole;
the pile hole is sequentially divided into a loose soil layer section corresponding to the loose cover soil layer and a compact soil layer section corresponding to the compact soil layer from top to bottom, wherein the loose soil layer section is formed after the steel pipe pile is subjected to pile driving, and the compact soil layer section is formed after the steel pipe pile driven in the loose cover soil layer conducts drilling on the compact soil layer for a construction channel. - The compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile.
- A construction method for offshore rock-drilling redriving-type large-diameter pile structure is provided, which is characterized in that the construction method comprises the steps of:
- S1 of conducting pile driving at the top of a steel pipe pile by means of a pile driving hammer until a lower end of the steel pipe pile is supported on the surface of a compact soil layer;
- S2 of setting up a driller apparatus at the top of the steel pipe pile, wherein a rock-socketed driller bit of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation in the compact soil layer, wherein the drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile;
- S3 of removing the driller apparatus and cleaning the drilled hole;
- S4 of conducting pile driving at the top of the steel pipe pile by means of the pile driving hammer until the lower end of the steel pipe pile reaches the designed bottom elevation in the compact soil layer.
- The present invention has the following beneficial effects: in the present invention, the driller apparatus is directly set up at the top of the steel pipe pile, thus making the steel pipe pile both a driller supporting mechanism and a drilled hole protection structure; in this manner, the construction procedure of setting up a rock-socketed platform is omitted, thus shortening the construction period and reducing the costs of rock-socketed construction. In the present invention, the steel pipe pile is subjected to pile driving and made to pass through the loose cover soil layer to be supported on the compact soil layer. Here, the steel pipe pile itself can stand stably, which meet the requirements for setting up a driller apparatus. The present invention is featured by simple structure form and less drilling workload, which effectively shortens the construction period, thus greatly reducing the engineering investments.
-
-
Fig. 1 is a schematic diagram illustrating the structure ofEmbodiment 1. -
Figs. 2-4 are schematic diagrams illustrating the construction process ofEmbodiment 1. -
Fig. 5 is a schematic diagram illustrating the structure of Embodiment 2. - Embodiment 1: As shown in
Fig. 1 , the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure. This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and arock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all. In the present embodiment, the foundation is provided with apile hole 3, and the designed bottom elevation of this pile hole is located within therock layer 11. The bottom portion of thepile hole 3 is filled withunderwater concrete 6, asteel pipe pile 1 is driven into thepile hole 3 by means of apile driving hammer 4, and a lower end of thesteel pipe pile 1 is integrated with therock layer 11 by means of theunderwater concrete 6. - In the present embodiment, the
pile hole 3 is sequentially divided into a loosesoil layer section 31 located within the loosecover soil layer 9, a compactsoil layer section 32 located within thecompact soil layer 10 and arock layer section 33 located within therock layer 11 from top to bottom, wherein the loosesoil layer section 31 is formed within the loosecover soil layer 9 after thesteel pipe pile 1 is driven by thepile driving hammer 4 to be supported on thecompact soil layer 10, and the compactsoil layer section 32 and therock layer section 33 are formed after thesteel pipe pile 1, whose lower end is supported on thecompact soil layer 10 after pile driving, conducts drilling on thecompact soil layer 10 and therock layer 11 under the bottom portion of thesteel pipe pile 1 for the construction channel. In the present embodiment, the compactsoil layer section 32 of thepile hole 3 has a hole diameter smaller than the pile diameter of thesteel pipe pile 1, and therock layer section 33 of thepile hole 3 has a hole diameter slightly larger than the pile diameter of thesteel pipe pile 1. - The construction method of the present embodiment is as follows:
- 1. Similar to a normal foundation pile, pile driving is conducted at the top of the
steel pipe pile 1 by means of thepile driving hammer 4. This requires no additional auxiliary apparatuses or measures, but pile driving must be controlled in strict accordance with the hammer-stopping standard so as to prevent the pile body from being damaged as a result of forcible pile driving. The pile driving may be continued until the lower end of thesteel pipe pile 1 is supported on the surface of the compact soil layer 10 (seeFig. 2 ), and the initially driven depth for the pile foundation of thesteel pipe pile 1 can meet the stability requirement of the driller during its construction process; - 2. The
steel pipe pile 1 itself is taken as both a driller supporting structure and a drilled hole protection structure. The driller apparatus 5 is set up at the top of thesteel pipe pile 1, wherein a rock-socketed driller bit 5-1 of the driller apparatus conducts drilling on thecompact soil layer 10 and therock layer 11 within and under thesteel pipe pile 1 through the channel within thesteel pipe pile 1 until it reaches the designed bottom elevation within therock layer 11, wherein the drilled hole has a hole diameter smaller than the pile diameter of thesteel pipe pile 1, and specific sizes may be properly adjusted according to on-site drilling conditions; hole broadening is conducted for the drilled hole within the rock layer 11 (the rock layer section of the pile hole) until its hole diameter is slightly larger than the pile diameter of the steel pipe pile (seeFig. 3 ); - 3. Rmoving the driller apparatus 5 , cleaning the drilled hole;
- 4. The
underwater concrete 6 is filled in the drilled hole of therock layer 11, and its filling height is slightly above the top surface of therock layer section 33; - 5. Pile driving is conducted at the top of the
steel pipe pile 1 by means of thepile driving hammer 4 until the lower end of thesteel pipe pile 1 sinks down to the designed bottom elevation within the rock layer 11 (seeFig. 4 ). - Embodiment 2: As shown in
Fig. 5 , the present embodiment is an offshore rock-drilling redriving-type large-diameter pile structure. This structure is suitable for a foundation including a loose cover soil layer 9 (into which a pile can be driven), a compact soil layer 10 (difficult for a pile to be driven) and arock layer 11 from top to bottom, and the geologic condition of the foundation is that the depth of sand deposits is limited. Therefore, a pile foundation may be driven to a certain depth, but can't be sunk down to the designed bottom elevation once for all. In the present embodiment, the foundation is provided with apile hole 3, the designed bottom elevation of this pile hole is located within thecompact soil layer 10, and asteel pipe pile 1 is driven into thepile hole 3 by means of apile driving hammer 4. - In the present embodiment, the
pile hole 3 is sequentially divided into a loosesoil layer section 31 located within the loose cover soil layer, a compactsoil layer section 32 located within the compact soil layer and arock layer section 33 corresponding to the rock layer from top to bottom, wherein the loosesoil layer section 31 is formed within the loose cover soil layer after the steel pipe pile is driven by the pile driving hammer to be supported on the compact soil layer, and the compactsoil layer section 32 is formed after the steel pipe pile, whose lower end is supported on the compact soil layer upon pile driving, conducts drilling on the compact soil layer and the rock layer under the bottom portion of the steel pipe pile for the construction channel. In the present embodiment, the compact soil layer section of the pile hole has a hole diameter smaller than the pile diameter of the steel pipe pile. - The construction method of the present embodiment is as follows:
- 1. Similar to a normal foundation pile, pile driving is conducted at the top of the
steel pipe pile 1 by means of thepile driving hammer 4. This requires no additional auxiliary apparatuses or measures, but pile driving must be controlled in strict accordance with the hammer-stopping standard so as to prevent the pile body from being damaged as a result of forcible pile driving. The pile driving may be continued until the lower end of the steel pipe pile is supported on the surface of the compact soil layer, and the initially driven depth for the pile foundation of the steel pipe pile can meet the stability requirement of the driller during its construction process; - 2. The
steel pipe pile 1 itself is taken as both a driller supporting structure and a drilled hole protection structure. The driller apparatus 5 is set up at the top of thesteel pipe pile 1, wherein a rock-socketed driller bit 5-1 of the driller apparatus conducts drilling on thecompact soil layer 10 within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation within the compact soil layer, wherein the drilled hole has a hole diameter smaller than the pile diameter of thesteel pipe pile 1, and specific sizes may be properly adjusted according to on-site drilling conditions; - 3. Removing the driller apparatus 5, and cleaning the drilled hole;
- 4. Pile driving is conducted at the top of the
steel pipe pile 1 by means of thepile driving hammer 4 until the lower end of thesteel pipe pile 1 sinks down to the designed bottom elevation within thecompact soil layer 10. - In the implementation process of the present invention, parameters of geological exploration are required to be analyzed, and related software is employed to analyze the initially driven depth of the foundation and the feasibility of the manner in which pile driving is conducted upon hole cleaning. Then, numerical simulations or other manners are employed to analyze the overall stability of foundation + driller during drilling and under the action of wave and current loads as well as vibration loads of the driller, and the vertical bearing capacity of the foundation after the drilled hole is cleaned. For geologic conditions under which piles can be successfully redriven after holes are drilled, the construction process of Embodiment 2 is employed; for those situations in which hard rock layers are required to be broken and redriving is still faced with difficulties even after holes are drilled, the construction process of
Embodiment 1 may be employed. - The above embodiments and construction processes are mainly applied to monopile foundations for offshore wind power, but they are not limited thereto. For other foundation structures to which oceaneering structures pertain, they can also be designed and constructed through the technical solution of the present invention.
Claims (7)
- An offshore rock-drilling redriving-type large-diameter pile structure suitable for a foundation including a loose cover soil layer (9), a compact soil layer (10) and a rock layer (11) from top to bottom, characterized in that the foundation is provided with a pile hole extending into the rock layer (11), and a steel pipe pile (1) is driven into the pile hole;
the pile hole (3) is sequentially divided into a loose soil layer section (31) corresponding to the loose cover soil layer (9), a compact soil layer section (32) corresponding to the compact soil layer (10) and a rock layer section (33) corresponding to the rock layer (11) from top to bottom, wherein the loose soil layer section (31) is formed after the steel pipe pile (1) is subjected to pile driving, and the compact soil layer section (32) and the rock layer section (33) are formed after the steel pipe pile (1) driven in the loose cover soil layer (9) conducts drilling on the compact soil layer (10) and the rock layer (11) for a construction channel. - The offshore rock-drilling redriving-type large-diameter pile structure according to claim 1, characterized in that the compact soil layer section (32) of the pile hole (3) has a hole diameter smaller than the pile diameter of the steel pipe pile (1), and the rock layer section (33) of the pile hole has a hole diameter slightly larger than the pile diameter of the steel pipe pile (1).
- The offshore rock-drilling redriving-type large-diameter pile structure according to claim 1 or 2, characterized in that the rock layer section (33) of the pile hole (3) is filled with underwater concrete (6), and the steel pipe pile (1) is integrated with the rock layer section of the pile hole by means of the underwater concrete.
- A construction method for the offshore rock-drilling redriving-type large-diameter pile structure according to any one of claims 1-3, characterized in that the construction method comprises the steps of:S4.1 of conducting pile driving at the top of a steel pipe pile (1) by means of a pile driving hammer (4) until a lower end of the steel pipe pile is supported on the surface of the compact soil layer (10);S4.2 of setting up a driller apparatus (5) at the top of the steel pipe pile (1), wherein a rock-socketed driller bit (5-1) of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile until it reaches the designed bottom elevation in the rock layer (11), wherein a drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile; and of conducting hole broadening for the drilled hole within the rock layer until its hole diameter is slightly larger than the pile diameter of the steel pipe pile;S4.3 of removing the driller apparatus (5) and cleaning the drilled hole;S4.4 of filling the drilled hole of the rock layer (11) with underwater concrete (6);S4.5 of conducting pile driving at the top of the steel pipe pile (1) by means of the pile driving hammer until the lower end of the steel pipe pile reaches the designed bottom elevation in the rock layer (11).
- An offshore rock-drilling redriving-type large-diameter pile structure suitable for a foundation including a loose cover soil layer (9), a compact soil layer (10) and a rock layer (11) from top to bottom, characterized in that the foundation is provided with a pile hole (3) extending into the compact soil layer (10), and a steel pipe pile (1) is driven into the pile hole;
the pile hole (3) is sequentially divided into a loose soil layer section (31) corresponding to the loose cover soil layer (9) and a compact soil layer section (32) corresponding to the compact soil layer (10) from top to bottom, wherein the loose soil layer section (31) is formed after the steel pipe pile (1) is subjected to pile driving, and the compact soil layer section (32) is formed after the steel pipe pile (1) driven in the loose cover soil layer (9) conducts drilling on the compact soil layer for a construction channel. - The offshore rock-drilling redriving-type large-diameter pile structure according to claim 5, characterized in that the compact soil layer section of the pile hole (3) has a hole diameter smaller than the pile diameter of the steel pipe pile (1).
- A construction method for the offshore rock-drilling redriving-type large-diameter pile structure according to claim 5 or 6, characterized in that the construction method comprises the steps of:S7.1 of conducting pile driving at the top of a steel pipe pile (1) by means of the pile driving hammer (4) until a lower end of the steel pipe pile is supported on the surface of the compact soil layer (10);S7.2 of setting up a driller apparatus (5) at the top of the steel pipe pile (1), wherein a rock-socketed driller bit (5-1) of the driller apparatus conducts drilling within and under the steel pipe pile through a channel within the steel pipe pile (1) until it reaches the designed bottom elevation in the compact soil layer (10), wherein a drilled hole has a hole diameter smaller than the pile diameter of the steel pipe pile;S7.3 of removing the driller apparatus (5) and cleaning the drilled hole;S7.4 of conducting pile driving at the top of the steel pipe pile (1) by means of the pile driving hammer (4) until the lower end of the steel pipe pile reaches the designed bottom elevation in the compact soil layer (10).
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710379587.5A CN107299632A (en) | 2017-05-25 | 2017-05-25 | Marine rock drilling strike-on type large diameter pile structure and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
EP3406802A1 true EP3406802A1 (en) | 2018-11-28 |
Family
ID=60137361
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP18168006.7A Withdrawn EP3406802A1 (en) | 2017-05-25 | 2018-04-18 | Offshore rock-drilling redriving-type large-diameter pile structure and construction method |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP3406802A1 (en) |
CN (1) | CN107299632A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109469080A (en) * | 2018-12-11 | 2019-03-15 | 中铁五局集团贵州工程有限公司 | A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water |
CN109811786A (en) * | 2019-03-26 | 2019-05-28 | 福建永福电力设计股份有限公司 | A kind of offshore wind farm composite base structure of outer and inner tube stake combination |
CN110258613A (en) * | 2019-07-02 | 2019-09-20 | 山东科技大学 | A kind of land single pile is inverted double barrels type wind power foundation and its application method |
CN113174990A (en) * | 2021-04-29 | 2021-07-27 | 福建永强岩土股份有限公司 | Rotary spraying reinforcement method for foundation around subsidence of ocean deep water inclined pile |
CN113174992A (en) * | 2021-04-29 | 2021-07-27 | 福建永强岩土股份有限公司 | Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile |
CN113981961A (en) * | 2021-10-08 | 2022-01-28 | 中交路桥华南工程有限公司 | Barge type pile planting method for deep water bare rock |
CN114438998A (en) * | 2022-02-14 | 2022-05-06 | 中交第三航务工程局有限公司 | Steel pipe pile rock-socketed construction process under complex geological conditions |
CN114673144A (en) * | 2022-04-28 | 2022-06-28 | 中铁十五局集团有限公司 | Rapid pile planting construction method for trestle steel pipe pile on bare rock of inclined base surface |
CN114960623A (en) * | 2022-06-29 | 2022-08-30 | 湖北道泽勘测设计院有限公司 | Basic structure and construction method of PSLC construction method pile |
CN115012405A (en) * | 2022-07-20 | 2022-09-06 | 中建八局第二建设有限公司 | Foundation pit supporting method for grouting of perforated pipe pile in stone-nitre area |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110080272A (en) * | 2019-04-25 | 2019-08-02 | 上海交通大学 | Offshore wind farm single-pile foundation and offshore wind farm device suitable for greater coasting area |
CN114319319A (en) * | 2021-12-03 | 2022-04-12 | 上海建工集团股份有限公司 | High-bearing core-filling steel pipe pile and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2418301A1 (en) | 1978-02-27 | 1979-09-21 | Cegeo Cie Etu Geotechniques | Mounting movable tools on tubes partic. in offshore petroleum mining - incorporates means of adjusting working position along tube and fixing it where required |
DE102009023466A1 (en) | 2009-06-02 | 2011-01-05 | Herrenknecht Ag | Method and device for creating an underwater foundation of a building |
EP2930275A1 (en) * | 2014-04-08 | 2015-10-14 | Herrenknecht AG | System and method for producing a foundation for a building in water |
KR20160017644A (en) | 2015-09-30 | 2016-02-16 | (주)삼일이엔씨 | Driven concrete pile with open lower part and construction method thereof |
EP3034702A1 (en) * | 2014-12-17 | 2016-06-22 | Bauer Spezialtiefbau GmbH | Method and device for erecting a foundation and foundation |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101135160A (en) * | 2007-09-29 | 2008-03-05 | 陈宁华 | Mixed pile forming method for high-bearing one-stage club-footed pile |
KR100964796B1 (en) * | 2010-02-26 | 2010-06-21 | 송기용 | Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction |
CN102286971A (en) * | 2011-07-15 | 2011-12-21 | 中交水运规划设计院有限公司 | Concrete-filled steel tube core column socketed pile |
CN205713982U (en) * | 2016-04-25 | 2016-11-23 | 辽宁有色基础工程公司 | A kind of pile foundation construction drilling equipment being applicable to karst area |
CN205917724U (en) * | 2016-06-28 | 2017-02-01 | 江苏海上龙源风力发电有限公司 | Do not have marine fan of grout and inlay rock single pile basis |
CN106088140A (en) * | 2016-06-28 | 2016-11-09 | 江苏海上龙源风力发电有限公司 | A kind of batholith sea bed offshore wind turbine embedding rock single-pile foundation construction technique |
CN206956717U (en) * | 2017-05-25 | 2018-02-02 | 中国电建集团华东勘测设计研究院有限公司 | Marine rock drilling strike-on type large diameter pile structure |
-
2017
- 2017-05-25 CN CN201710379587.5A patent/CN107299632A/en active Pending
-
2018
- 2018-04-18 EP EP18168006.7A patent/EP3406802A1/en not_active Withdrawn
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2418301A1 (en) | 1978-02-27 | 1979-09-21 | Cegeo Cie Etu Geotechniques | Mounting movable tools on tubes partic. in offshore petroleum mining - incorporates means of adjusting working position along tube and fixing it where required |
DE102009023466A1 (en) | 2009-06-02 | 2011-01-05 | Herrenknecht Ag | Method and device for creating an underwater foundation of a building |
EP2930275A1 (en) * | 2014-04-08 | 2015-10-14 | Herrenknecht AG | System and method for producing a foundation for a building in water |
EP3034702A1 (en) * | 2014-12-17 | 2016-06-22 | Bauer Spezialtiefbau GmbH | Method and device for erecting a foundation and foundation |
KR20160017644A (en) | 2015-09-30 | 2016-02-16 | (주)삼일이엔씨 | Driven concrete pile with open lower part and construction method thereof |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109469080A (en) * | 2018-12-11 | 2019-03-15 | 中铁五局集团贵州工程有限公司 | A kind of embedding rock steel sheet pile cofferdam structure and its construction method under water |
CN109469080B (en) * | 2018-12-11 | 2023-12-19 | 中铁五局集团贵州工程有限公司 | Underwater rock-socketed steel sheet pile cofferdam structure and construction method thereof |
CN109811786A (en) * | 2019-03-26 | 2019-05-28 | 福建永福电力设计股份有限公司 | A kind of offshore wind farm composite base structure of outer and inner tube stake combination |
CN109811786B (en) * | 2019-03-26 | 2024-03-26 | 福建永福电力设计股份有限公司 | Offshore wind power composite foundation structure with inner steel pipe pile and outer steel pipe pile combined |
CN110258613A (en) * | 2019-07-02 | 2019-09-20 | 山东科技大学 | A kind of land single pile is inverted double barrels type wind power foundation and its application method |
CN113174990B (en) * | 2021-04-29 | 2023-05-23 | 福建永强岩土股份有限公司 | Rotary spraying reinforcement method for pile periphery collapse foundation of ocean deep water inclined pile |
CN113174990A (en) * | 2021-04-29 | 2021-07-27 | 福建永强岩土股份有限公司 | Rotary spraying reinforcement method for foundation around subsidence of ocean deep water inclined pile |
CN113174992A (en) * | 2021-04-29 | 2021-07-27 | 福建永强岩土股份有限公司 | Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile |
CN113981961A (en) * | 2021-10-08 | 2022-01-28 | 中交路桥华南工程有限公司 | Barge type pile planting method for deep water bare rock |
CN113981961B (en) * | 2021-10-08 | 2023-06-23 | 中交路桥华南工程有限公司 | Ship-type pile planting method for deepwater bare rock |
CN114438998A (en) * | 2022-02-14 | 2022-05-06 | 中交第三航务工程局有限公司 | Steel pipe pile rock-socketed construction process under complex geological conditions |
CN114673144A (en) * | 2022-04-28 | 2022-06-28 | 中铁十五局集团有限公司 | Rapid pile planting construction method for trestle steel pipe pile on bare rock of inclined base surface |
CN114960623A (en) * | 2022-06-29 | 2022-08-30 | 湖北道泽勘测设计院有限公司 | Basic structure and construction method of PSLC construction method pile |
CN115012405A (en) * | 2022-07-20 | 2022-09-06 | 中建八局第二建设有限公司 | Foundation pit supporting method for grouting of perforated pipe pile in stone-nitre area |
Also Published As
Publication number | Publication date |
---|---|
CN107299632A (en) | 2017-10-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3406802A1 (en) | Offshore rock-drilling redriving-type large-diameter pile structure and construction method | |
US10267008B2 (en) | Offshore non-driven-in large-diameter monopile foundation structure and construction method | |
CN106759449B (en) | Rock-based seabed offshore wind turbine rock-socketed single-pile foundation and construction method thereof | |
CN103603342B (en) | Major diameter assembled casing super-long filling pile construction method | |
CN110409461A (en) | A kind of base pit stand construction based on assembled large-diameter tubular pile | |
CN101586340A (en) | Preconditioning process of continuous wall for weak weathering terrane grooving construction | |
CN204370469U (en) | A kind of drilled pile long leg jacket offshore wind turbine foundation | |
CN102776884B (en) | In stir and rotate prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof | |
CN102535440A (en) | Method of using all-casing drilling rig with rotary drilling rig to construct rock-socketed secant pile wall | |
CN112761076A (en) | Lock catch steel pipe pile cofferdam applied to water level change condition and construction method | |
CN107558488A (en) | A kind of embedding rock single pile of offshore wind farm and its construction system and construction method | |
CN114215049A (en) | Construction method for main steel casing of bored pile under deep water foundation and bare rock environment | |
CN107700479A (en) | A kind of construction method of large diameter drill hole pile | |
CN103015408A (en) | Cast-in-place pile synchronous casing hole-forming constructing method | |
CN206956717U (en) | Marine rock drilling strike-on type large diameter pile structure | |
CN102383428B (en) | Middle pick reverse drawing method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof | |
Wu et al. | Development of a novel self-entry exploitation device for marine natural gas hydrate and the feasibility studies | |
CN212716407U (en) | Karst area pile foundation drilling equipment | |
CN112901074A (en) | Rock-socketed drilling pore-forming process of marine large-diameter inclined pile rotary excavator | |
CN112281880A (en) | Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam | |
CN104264679A (en) | Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles | |
CN105804079A (en) | Tool and method for smashing hard rock in large-diameter pile hole | |
CN214997452U (en) | Large-scale long auger drilling that shakes | |
CN108411928A (en) | One kind passing through multilayer karst cave ultra-deep and large diameter pile foundation boring method | |
CN205100226U (en) | Underground continuous wall goes into rock grooving construction equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20180424 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
TPAC | Observations filed by third parties |
Free format text: ORIGINAL CODE: EPIDOSNTIPA |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20201015 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION HAS BEEN WITHDRAWN |
|
18W | Application withdrawn |
Effective date: 20210204 |