CN102409702A - 一种地下连续墙中埋式橡胶止水带接缝防水施工方法 - Google Patents
一种地下连续墙中埋式橡胶止水带接缝防水施工方法 Download PDFInfo
- Publication number
- CN102409702A CN102409702A CN2011102750935A CN201110275093A CN102409702A CN 102409702 A CN102409702 A CN 102409702A CN 2011102750935 A CN2011102750935 A CN 2011102750935A CN 201110275093 A CN201110275093 A CN 201110275093A CN 102409702 A CN102409702 A CN 102409702A
- Authority
- CN
- China
- Prior art keywords
- width
- diaphragm wall
- cloth diaphragm
- cloth
- reinforcing cage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明属于地下连续墙施工的技术领域,具体涉及一种地下连续墙中埋式橡胶止水带接缝防水施工方法,解决了现有地下连续墙施工中的接缝防水处理方式容易造成工程事故的问题。地下连续墙中埋式橡胶止水带接缝防水施工方法,第一幅钢筋笼两侧埋入橡胶止水带,橡胶止水带两侧下放双块式接头柱,后续钢筋笼,一侧埋入橡胶止水带,另一侧设置凹形角槽,凹形角槽对应前一付钢筋笼的橡胶止水带,最后一幅钢筋笼两侧为凹形角槽,实现一周地下连续墙合拢。本发明施工工艺简便,易操作,造价低廉,对于基坑透水事故频发的地区有极大的推广价值和经济效益。
Description
技术领域
本发明属于富水地层明挖基坑维护或地铁车站建设过程中地下连续墙施工的技术领域,具体涉及一种地下连续墙中埋式橡胶止水带接缝防水施工方法。
背景技术
现有的地下连续墙施工过程中接缝防水技术主要有:
①接头管方式的接缝防水技术。这是一种目前常用的地下连续墙接头防水处理方法,即,在地下连续墙成槽以后,混凝土浇筑以前,槽段两端放置接头管,在接头管中间下方钢筋笼,然后浇筑成地下连续墙,待地下连续墙混凝土达到初凝后,拔出接头管。这种接头处理方法工艺方法简单,接头为圆弧型有利于地下连续墙的整体性,对接缝防水有一定作用。但是这种方式的接头施工,很难掌握接头管的起把时机,起把过早,混凝土强度不够,产生拉裂裂缝,起把过晚混凝土强度太高,不但起把接头管困难,而且起把过程中很容易对成型墙体产生硬伤。所以接头管方法在后期基坑开挖过程中经常漏水冒砂造成工程事故。
②预制“工”字接头桩。这也是目前地下连续墙施工常用的接头处理方式之一,即成槽以后,在槽段两端(中间片只需放置一端即可) 把预先预制好的工字型预制桩插入至地下连续墙以下,并用木楔等固定,然后再在两工字型预制桩间槽段吊放钢筋笼,再浇注混凝土成墙,工字型预制桩不再起拔,其作为永久结构的一部分。此种方法虽然不用起拔接头桩,但是预制桩与现浇混凝土地下连续墙间始终存在施工缝,后期基坑开挖很容易从此施工缝处冒水冒砂,造成工程事故。
发明内容
本发明为了解决现有地下连续墙施工中的接缝防水处理方式容易造成工程事故的问题,提供了一种地下连续墙中埋式橡胶止水带接缝防水施工方法。
本发明采用如下的技术方案实现:
一种地下连续墙中埋式橡胶止水带接缝防水施工方法,步骤如下:
1)、绑扎第一幅地下连续墙钢筋笼,在其两侧的中部绑定埋入其内的橡胶止水带,开挖第一幅地下连续墙的基槽,基槽的长度大于等于第一幅地下连续墙钢筋笼的设计长度和两侧橡胶止水带的外露长度之和,下放第一幅地下连续墙钢筋笼,在第一幅地下连续墙钢筋笼两侧下放双块式接头柱,双块式接头柱将对应侧的橡胶止水带夹在中间,浇注第一幅地下连续墙;
2)、绑扎第二幅地下连续墙钢筋笼,在其一侧的中部绑定埋入其内的橡胶止水带,另一侧设置凹形角槽,开挖第二幅地下连续墙的基槽,基槽的长度大于等于第二幅地下连续墙钢筋笼的设计长度和一侧橡胶止水带外露长度之和;然后拔出第一幅地下连续墙开挖方向一侧的双块式接头柱;下放第二幅地下连续墙钢筋笼,并使第二幅地下连续墙钢筋笼上的凹形角槽内对应插入第一幅地下连续墙的橡胶止水带,第二幅地下连续墙钢的另一侧下放双块式接头柱,双块式接头柱将该侧的橡胶止水带夹在中间,浇注第二幅地下连续墙;
3)、第三、四副直至倒数第二幅的地下连续墙的施工过程同上述步骤2)第二幅地下连续墙的施工过程;
4)、绑扎最后一幅地下连续墙钢筋笼,其一侧设置与第一幅地下连续墙预埋的橡胶止水带外露部分对应的凹形角槽,另一侧设置与倒数第二幅地下连续墙预埋的橡胶止水带外露部分对应的凹形角槽,开挖最后一幅地下连续墙的基槽,基槽的长度大于等于最后一幅地下连续墙钢筋笼的设计长度;拔出倒数第二幅地下连续墙开挖方向和双块式接头柱和第一幅地下连续墙保留的双块式接头柱;下放最后一幅地下连续墙钢筋笼,并使最后一幅地下连续墙钢筋笼上两侧的凹形角槽内分别对应插入倒数第二幅地下连续墙和第一幅地下连续墙的橡胶止水带,浇注最后一幅地下连续墙。
上述步骤中,每幅地下连续墙钢筋笼上凹形角槽的深度与相邻的地下连续墙钢筋笼侧对应侧的橡胶止水带外露的长度相等。
本发明在前一幅地下连续墙浇筑前预埋橡胶止水带,在浇筑下一幅地下连续墙的过程中把预留的橡胶止水带浇筑进去,这样橡胶止水带处于两幅相邻地下连续墙之间,完全封闭了相邻两片地下连续墙的接缝,起到极为有效的防水作用,同时由于橡胶止水带易于弯曲折叠,所以本发明施工简便快捷经济。
本发明的有益效果:利用中埋式橡胶止水带,改变了传统的施工工艺,有效解决了富水地层地下连续墙间的接缝防水问题。避免不良地层中由于地下连续墙接缝漏水而造成的灾难性事故,尤其适用于东部沿海城市富水地层中明挖基坑或地铁车站建设过程中地下连续墙的施工。本发明施工工艺简便,易操作,造价低廉,对于基坑透水事故频发的地区有极大的推广价值和经济效益。
附图说明
图1为在第一幅钢筋笼上绑定橡胶止水带的示意图
图2为下放第一幅地下连续墙的钢筋笼并两端锁口示意图
图3为第二幅地下连续墙的钢筋笼、止水带及凹形角槽示意图
图4为开挖第二槽段并拔除第一幅地下连续墙开挖方向的接头柱示意图
图5为下放第二幅地下连续墙钢筋笼的示意图
图中:1-钢筋笼,2-预埋橡胶止水带,3-两侧导墙,4-双块式接头柱,5-未开挖的土体,6-凹形角槽,7-浇注完成的第一幅地下连续墙,8-开挖完成的第二槽段。
具体实施方式
地下连续墙中埋式橡胶止水带接缝防水施工方法,步骤如下:
(1)开挖第一幅地下连续墙的基槽,基槽的开挖长度不小于第一幅地下连续墙钢筋笼设计长度和两侧橡胶止水带的外露长度之和,第一幅地下连续墙钢筋笼绑扎完成后,在其两侧绑定埋入其内的橡胶止水带,如图1所示。下放第一幅钢筋笼,并在两侧下放双块式接头柱,并保证两侧的双块式接头柱把预埋的橡胶止水带夹在中间,如图2所示。然后浇筑完成第一幅地下连续墙的浇筑。
(2)开挖第二幅地下连续墙基槽,此段基槽的长度不小于第二幅地下连续墙钢筋笼设计长度与一侧橡胶止水带外漏长度之和,同时绑扎第二幅地下连续墙的钢筋笼,并在钢筋的一侧设计有对应第一幅地下连续墙预埋橡胶止水带的凹形角槽,另一侧绑定橡胶止水带如图3所示。然后拔出第一幅地下连续墙开挖方向一侧的双块式接头柱,如图4所示。下放第二幅地下连续墙的钢筋笼,并使凹槽一侧与第一幅连续墙预埋的橡胶止水带相对应,另一侧下放双块式接头柱并保证下放的双块式接头柱把预埋在本幅钢筋笼上的橡胶止水带夹在中间,如图5。然后浇筑完成第二幅地下连续墙的浇筑。
(3)开挖第三幅地下连续墙基槽,此段基槽的长度不小于第三幅地下连续墙钢筋笼设计长度与一侧橡胶止水带外漏长度之和,同时绑扎第三幅地下连续墙的钢筋笼,并在钢筋的一侧设计有对应第二幅地下连续墙预埋橡胶止水带的凹形角槽,另一侧绑定橡胶止水带。然后拔出第二幅地下连续墙开挖方向一侧的双块式接头柱,下放第三幅地下连续墙的钢筋笼,并使凹槽一侧与第二幅连续墙预埋的橡胶止水带相对应。另一侧下放双块式接头柱并保证下放的双块式接头柱把预埋在本幅钢筋笼上的橡胶止水带夹在中间。然后浇筑完成第三幅地下连续墙的浇筑。
(4)依次下去,完成第四、五、六……幅至倒数第二幅地下连续墙的浇筑。
(5)绑扎最后一幅地下连续墙钢筋笼,其一侧设置与第一幅地下连续墙预埋的橡胶止水带外露部分对应的凹形角槽,另一侧设置与倒数第二幅地下连续墙预埋的橡胶止水带外露部分对应的凹形角槽,开挖最后一幅地下连续墙的基槽,基槽的长度大于等于最后一幅地下连续墙钢筋笼的设计长度;拔出倒数第二幅地下连续墙开挖方向和双块式接头柱和第一幅地下连续墙保留的双块式接头柱;下放最后一幅地下连续墙钢筋笼,并使最后一幅地下连续墙钢筋笼上两侧的凹形角槽内分别对应插入倒数第二幅地下连续墙和第一幅地下连续墙的橡胶止水带,浇注最后幅地下连续墙。如此,一周地下连续墙合拢,即完成整个地下连续墙的浇筑施工。
Claims (1)
1.一种地下连续墙中埋式橡胶止水带接缝防水施工方法,其特征在于步骤如下:
1)、绑扎第一幅地下连续墙钢筋笼,在其两侧的中部绑定埋入其内的橡胶止水带,开挖第一幅地下连续墙的基槽,基槽的长度大于等于第一幅地下连续墙钢筋笼的设计长度和两侧橡胶止水带的外露长度之和,下放第一幅地下连续墙钢筋笼,在第一幅地下连续墙钢筋笼两侧下放双块式接头柱,双块式接头柱将对应侧的橡胶止水带夹在中间,浇注第一幅地下连续墙;
2)、绑扎第二幅地下连续墙钢筋笼,在其一侧的中部绑定埋入其内的橡胶止水带,另一侧设置凹形角槽,开挖第二幅地下连续墙的基槽,基槽的长度大于等于第二幅地下连续墙钢筋笼的设计长度和一侧橡胶止水带外露长度之和;然后拔出第一幅地下连续墙开挖方向一侧的双块式接头柱;下放第二幅地下连续墙钢筋笼,并使第二幅地下连续墙钢筋笼上的凹形角槽内对应插入第一幅地下连续墙的橡胶止水带,第二幅地下连续墙钢的另一侧下放双块式接头柱,双块式接头柱将该侧的橡胶止水带夹在中间,浇注第二幅地下连续墙;
3)、第三、四副直至倒数第二幅的地下连续墙的施工过程同上述步骤2)第二幅地下连续墙的施工过程;
4)、绑扎最后一幅地下连续墙钢筋笼,其一侧设置与第一幅地下连续墙预埋的橡胶止水带外露部分对应的凹形角槽,另一侧设置与倒数第二幅地下连续墙预埋的橡胶止水带外露部分对应的凹形角槽,开挖最后一幅地下连续墙的基槽,基槽的长度大于等于最后一幅地下连续墙钢筋笼的设计长度;拔出倒数第二幅地下连续墙开挖方向和双块式接头柱和第一幅地下连续墙保留的双块式接头柱;下放最后一幅地下连续墙钢筋笼,并使最后一幅地下连续墙钢筋笼上两侧的凹形角槽内分别对应插入倒数第二幅地下连续墙和第一幅地下连续墙的橡胶止水带,浇注最后一幅地下连续墙,
上述步骤中,每幅地下连续墙钢筋笼上凹形角槽的深度与相邻的地下连续墙钢筋笼侧对应侧的橡胶止水带外露的长度相等。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102750935A CN102409702A (zh) | 2011-09-16 | 2011-09-16 | 一种地下连续墙中埋式橡胶止水带接缝防水施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102750935A CN102409702A (zh) | 2011-09-16 | 2011-09-16 | 一种地下连续墙中埋式橡胶止水带接缝防水施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102409702A true CN102409702A (zh) | 2012-04-11 |
Family
ID=45912021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102750935A Pending CN102409702A (zh) | 2011-09-16 | 2011-09-16 | 一种地下连续墙中埋式橡胶止水带接缝防水施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102409702A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102864791A (zh) * | 2012-10-10 | 2013-01-09 | 中国建筑第八工程局有限公司 | 预溶模液体膨胀橡胶止水带的施工方法 |
CN106812132A (zh) * | 2017-03-09 | 2017-06-09 | 江苏建筑职业技术学院 | 用于地下连续墙中埋式防水钢板的接头管及其施工方法 |
CN109488344A (zh) * | 2018-10-29 | 2019-03-19 | 中铁十二局集团有限公司 | 地铁止水带防水施工方法 |
CN109944280A (zh) * | 2019-04-16 | 2019-06-28 | 上海长凯岩土工程有限公司 | 预先装配式地下连续墙接驳器止水结构 |
CN111424681A (zh) * | 2020-04-27 | 2020-07-17 | 中铁上海工程局集团华海工程有限公司 | 地下连续墙与灌注桩分段应用情况下的防水接头结构及其施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2239995Y (zh) * | 1995-04-14 | 1996-11-13 | 上海宝钢冶金建设公司第五工程公司 | 地下连续墙刚性接头装置 |
CN1193675A (zh) * | 1997-03-19 | 1998-09-23 | 沈海晏 | 人工挖孔桩地下连续墙及其施工方法 |
JP2002047670A (ja) * | 2000-08-03 | 2002-02-15 | Kajima Corp | 地下タンクの構築方法およびせん断伝達機構 |
CN2630317Y (zh) * | 2003-06-05 | 2004-08-04 | 上海市隧道工程轨道交通设计研究院 | 一种地下挡墙内部连接方式 |
CN101608447A (zh) * | 2009-07-10 | 2009-12-23 | 上海隧道工程股份有限公司 | 一种十字钢板止水接头地下连续墙及其接头施工方法 |
CN102155010A (zh) * | 2011-05-28 | 2011-08-17 | 上海远方基础工程有限公司 | 地下连续墙接缝方法 |
-
2011
- 2011-09-16 CN CN2011102750935A patent/CN102409702A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2239995Y (zh) * | 1995-04-14 | 1996-11-13 | 上海宝钢冶金建设公司第五工程公司 | 地下连续墙刚性接头装置 |
CN1193675A (zh) * | 1997-03-19 | 1998-09-23 | 沈海晏 | 人工挖孔桩地下连续墙及其施工方法 |
JP2002047670A (ja) * | 2000-08-03 | 2002-02-15 | Kajima Corp | 地下タンクの構築方法およびせん断伝達機構 |
CN2630317Y (zh) * | 2003-06-05 | 2004-08-04 | 上海市隧道工程轨道交通设计研究院 | 一种地下挡墙内部连接方式 |
CN101608447A (zh) * | 2009-07-10 | 2009-12-23 | 上海隧道工程股份有限公司 | 一种十字钢板止水接头地下连续墙及其接头施工方法 |
CN102155010A (zh) * | 2011-05-28 | 2011-08-17 | 上海远方基础工程有限公司 | 地下连续墙接缝方法 |
Non-Patent Citations (1)
Title |
---|
高国财: "北京北四环路路堑地下连续墙挡墙的施工", 《铁道建筑》, no. 12, 20 December 2006 (2006-12-20) * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102864791A (zh) * | 2012-10-10 | 2013-01-09 | 中国建筑第八工程局有限公司 | 预溶模液体膨胀橡胶止水带的施工方法 |
CN106812132A (zh) * | 2017-03-09 | 2017-06-09 | 江苏建筑职业技术学院 | 用于地下连续墙中埋式防水钢板的接头管及其施工方法 |
CN109488344A (zh) * | 2018-10-29 | 2019-03-19 | 中铁十二局集团有限公司 | 地铁止水带防水施工方法 |
CN109488344B (zh) * | 2018-10-29 | 2020-08-04 | 中铁十二局集团有限公司 | 地铁止水带防水施工方法 |
CN109944280A (zh) * | 2019-04-16 | 2019-06-28 | 上海长凯岩土工程有限公司 | 预先装配式地下连续墙接驳器止水结构 |
CN109944280B (zh) * | 2019-04-16 | 2024-04-09 | 上海长凯岩土工程有限公司 | 预先装配式地下连续墙接驳器止水结构 |
CN111424681A (zh) * | 2020-04-27 | 2020-07-17 | 中铁上海工程局集团华海工程有限公司 | 地下连续墙与灌注桩分段应用情况下的防水接头结构及其施工方法 |
CN111424681B (zh) * | 2020-04-27 | 2024-03-08 | 中铁上海工程局集团华海工程有限公司 | 地下连续墙与灌注桩分段应用情况下的防水接头结构及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103981898B (zh) | 一种整体明挖节点逆作的地下工程施工方法 | |
CN104404983B (zh) | 一种用于顶管施工的骑马井装置及其施工方法 | |
CN111456773A (zh) | 密贴式明暗挖结合地铁车站结构及其施工方法 | |
CN110004991B (zh) | 基于外凸式翼脚板的地下结构抗浮体系及构建方法 | |
CN111395391B (zh) | 一种多孔矩形顶管与明暗挖交接管廊接头施工方法 | |
CN108396780B (zh) | 一种既有检查井改建方法 | |
CN108035337B (zh) | 一种地下连续墙的施工方法和应用于该方法中的接头 | |
CN107747308A (zh) | 一种地下连续墙及施工方法 | |
CN102409702A (zh) | 一种地下连续墙中埋式橡胶止水带接缝防水施工方法 | |
CN108343059A (zh) | 地下综合管廊组合预制管筒的二墙合一半逆作建造方法 | |
CN109578014B (zh) | 一种抗突涌封底结构及施工方法 | |
CN201649068U (zh) | 一种u型混凝土板桩 | |
CN102691301A (zh) | 围护结构支撑腰梁与主体结构墙柱同步施工方法 | |
CN109881661A (zh) | 装配式地下连续墙横向连接结构 | |
CN207512777U (zh) | 装配式地下管廊 | |
CN103031849B (zh) | 基坑内布置降水井及降水井柔性封闭的施工方法 | |
CN107326932A (zh) | 一种地下车库的准半逆作施工方法 | |
CN112726667A (zh) | 一种半刚性装配式综合管廊及其施工方法 | |
CN110117959B (zh) | 一种临近江河基坑支护施工方法 | |
CN104314104B (zh) | 一种与地下箱涵斜交的变形缝设置方法 | |
CN110924438A (zh) | 一种装配式矩形检查井预制件 | |
CN106638670B (zh) | 半预制管廊及施工方法 | |
CN110056071A (zh) | 一种市政雨水管道组装模块及施工方法 | |
CN101603299B (zh) | 一种折线型坝接头结构及其施工方法 | |
CN212202085U (zh) | 密贴式明暗挖结合地铁车站结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120411 |