CN101892844A - 一种超前锚杆支护的隧道crd开挖方法 - Google Patents

一种超前锚杆支护的隧道crd开挖方法 Download PDF

Info

Publication number
CN101892844A
CN101892844A CN2009101074571A CN200910107457A CN101892844A CN 101892844 A CN101892844 A CN 101892844A CN 2009101074571 A CN2009101074571 A CN 2009101074571A CN 200910107457 A CN200910107457 A CN 200910107457A CN 101892844 A CN101892844 A CN 101892844A
Authority
CN
China
Prior art keywords
crd
tunnel
anchor bolt
bolt supporting
gfrp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2009101074571A
Other languages
English (en)
Other versions
CN101892844B (zh
Inventor
李明
何唯平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Oceanpower New Material Technology Co ltd
Original Assignee
Heyuan Ocean Power Technology Co Ltd
Shenzhen Oceanpower Industrial Co Ltd
Shanghai Qipeng Chemical Co Ltd
Shenzhen Oceanpower Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heyuan Ocean Power Technology Co Ltd, Shenzhen Oceanpower Industrial Co Ltd, Shanghai Qipeng Chemical Co Ltd, Shenzhen Oceanpower Engineering Technology Co Ltd filed Critical Heyuan Ocean Power Technology Co Ltd
Priority to CN200910107457.1A priority Critical patent/CN101892844B/zh
Publication of CN101892844A publication Critical patent/CN101892844A/zh
Application granted granted Critical
Publication of CN101892844B publication Critical patent/CN101892844B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种超前锚杆支护的隧道CRD开挖方法,包括以下步骤,隧道开挖前先进行超前锚杆支护,然后采用隧道CRD方法进行挖掘,所述超前锚杆支护采用的锚杆为GFRP锚杆。本发明代表了新的技术发展趋势,采用本发明的方法,施工强度低,效率高,施工而成的锚固抗腐蚀性强,耐久性强。

Description

一种超前锚杆支护的隧道CRD开挖方法
【技术领域】
本发明涉及隧道开挖方法,尤其涉及超前锚杆支护的隧道CRD开挖方法。
【背景技术】
我国幅员辽阔,地形复杂多变,山岭众多,造成了交通的不便。随时国民经济的迅速发展,对交通的安全、快捷、舒适性要求越来越高,传统的盘山修路已经无法满足现在的要求。进入21世纪,国家大力发展隧道技术,力求缩短两地之间的公路里程,提高效率。而由于我国气候和地质情况复杂,围岩条件也千差万别,很多山体由于风化,水的侵袭,多年沉积作用,导致或岩石分层或岩质松散,为隧道的施工留下了很多的安全隐患。
在隧道施工时,通常采用超前锚杆支护的CRD开挖方法进行施工。传统的超前锚杆支护方法采用的锚杆通常为钢筋制成,其施工强度大,效率低。锚固将作为永久支护的一部分还要承受长期荷载,要求具有较强的耐久性,特别是抗腐蚀性要强。
【发明内容】
本发明所要解决的技术问题是,提供一种超前锚杆支护的隧道CRD开挖方法,该方法施工强度低,效率高,以该方法施工而成的锚固抗腐蚀性强,耐久性强。
为实现上述目的,本发明采用如下技术方案:
一种超前锚杆支护的隧道CRD开挖方法,包括以下步骤,隧道开挖前先进行超前锚杆支护,然后采用隧道CRD方法进行挖掘,所述超前锚杆支护采用的锚杆为GFRP锚杆。所述隧道CRD方法是一种分层开挖方法,所述GFRP是玻璃纤维增强聚合物。
所述GFRP锚杆与隧道工作面的垂直方向成10~15度倾角,所述GFRP锚杆的横向及纵向间距为0.2~0.6米。
采用所述CRD方法进行挖掘时,将隧道工作面分为上中下三层,采取自下而上的方式挖掘。
采用本发明的超前锚杆支护的隧道CRD开挖方法,施工强度低,速度快,效率高,可以全手工操作,节省费用。采用本发明施工而成的超前锚杆支护结构,围岩安全性及稳定性高,耐腐蚀性强,耐久性强,并且开挖容易。本发明代表了新的技术发展趋势,推动了超前支护技术的发展。
【附图说明】
下面结合附图和实施例对本发明进行进一步详细的描述。
图1为本发明超前锚杆支护的隧道CRD开挖方法施工时的隧道工作面示意图。
图中各组件的附图标记说明如下:
GFRP锚杆1,隧道工作面2,左下面21,右下面22,左中面23,右中面24,左上面25,右上面26。
【具体实施方式】
如图1所示,本发明的超前锚杆支护的隧道CRD开挖方法是,在隧道施工开挖前,先在隧道工作面2上对其前方稳定岩层进行钻孔,随后将GFRP材料制成的GFRP锚杆1打入所钻孔内,该GFRP锚杆1与开挖方向即隧道工作面2的垂直方向成10~15度倾角,该GFRP锚杆1的横向及纵向间距依围岩等级而定为0.2~0.6米,然后向GFRP锚杆1内注浆并锚固,用以固定锚杆周围的围岩,有效地约束围岩在开挖时不发生松弛坍塌,然后采用CRD分层开挖方法进行隧道掘进,掘进时将隧道工作面2分为若干个工作区域,即左下面21,右下面22,左中面23,右中面24,左上面25,右上面26,采用自下而上对称顺序,先对下面的两个面进行掘进,然后对中间的两个面进行掘进,最后对上面的两个面进行掘进。
本发明的超前锚杆支护的隧道CRD开挖方法以GFRP锚杆代替钢筋锚杆作为增强结构进行施工。与钢筋相比,GFRP具有抗拉强度高、防腐蚀性好、质量轻、可切割等优点。采用本发明的超前锚杆支护的隧道CRD开挖方法,施工强度低,速度快,效率高,可以全手工操作,节省费用。采用本发明施工而成的超前锚杆支护结构,围岩安全性及稳定性高,耐腐蚀性强,耐久性强,开挖容易,不仅可用于软岩隧道侧壁加固,也可用于掌子面加固,对稳定掌子面和实现大断面开挖、加快施工进度具有非常好的经济效益。本发明代表了新的技术发展趋势,推动了超前支护技术的发展。
以上所述只是本发明的较佳实施例,并不用于限制本发明,凡在本发明精神内所作的修改、等同替换或者改进等,均应包含在本发明所保护的范围内。

Claims (3)

1.一种超前锚杆支护的隧道CRD开挖方法,包括以下步骤:隧道开挖前先进行超前锚杆支护,然后采用CRD方法进行挖掘,所述超前锚杆支护采用的锚杆为GFRP锚杆。
2.根据权利要求1所述的超前锚杆支护的隧道CRD开挖方法,其特征在于:所述GFRP锚杆与隧道工作面的垂直方向成10~15度倾角,所述GFRP锚杆的横向及纵向间距为0.2~0.6米。
3.根据权利要求1或2所述的超前锚杆支护的隧道CRD开挖方法,其特征在于:采用所述隧道CRD方法进行挖掘时,将隧道工作面分为上中下三层,采取自下而上的方式挖掘。
CN200910107457.1A 2009-05-20 2009-05-20 一种超前锚杆支护的隧道crd开挖方法 Active CN101892844B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910107457.1A CN101892844B (zh) 2009-05-20 2009-05-20 一种超前锚杆支护的隧道crd开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910107457.1A CN101892844B (zh) 2009-05-20 2009-05-20 一种超前锚杆支护的隧道crd开挖方法

Publications (2)

Publication Number Publication Date
CN101892844A true CN101892844A (zh) 2010-11-24
CN101892844B CN101892844B (zh) 2014-06-04

Family

ID=43102174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910107457.1A Active CN101892844B (zh) 2009-05-20 2009-05-20 一种超前锚杆支护的隧道crd开挖方法

Country Status (1)

Country Link
CN (1) CN101892844B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102226406A (zh) * 2011-05-10 2011-10-26 中铁十二局集团第一工程有限公司 超长超前锚杆施工方法
RU2723422C1 (ru) * 2019-07-19 2020-06-11 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Способ крепления лба забоя тоннеля
RU2743161C1 (ru) * 2020-04-20 2021-02-15 федеральное государственное бюджетное образовательное учреждение высшего образования "Санкт-Петербургский горный университет" Способ крепления горных выработок анкерами с армированными поясами

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11324596A (ja) * 1998-05-15 1999-11-26 Kfc Ltd Frp製ロックボルト
JP2002266583A (ja) * 2001-03-09 2002-09-18 Ohbayashi Corp 2重管構造のボーリングロッド
JP2003336479A (ja) * 2002-05-23 2003-11-28 St Engineering Kk 自穿孔ボルトとfrpボルトを使った先行地山固結工法
CN1873187A (zh) * 2006-06-23 2006-12-06 董淑练 隧道施工的开挖方法
CN101126317A (zh) * 2006-08-18 2008-02-20 深圳市海川实业股份有限公司 一种地下隧道施工中的地下围护结构
CN101144384A (zh) * 2007-11-01 2008-03-19 中铁二局股份有限公司 隧道工程非爆破弱扰动开挖施工方法
CN101196118A (zh) * 2008-01-07 2008-06-11 北京市政建设集团有限责任公司 超前双排注浆小导管施工工艺
CN101387202A (zh) * 2008-10-29 2009-03-18 中铁四局集团有限公司 隧道内已成初支软弱围岩地段扩挖管棚工作室的方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11324596A (ja) * 1998-05-15 1999-11-26 Kfc Ltd Frp製ロックボルト
JP2002266583A (ja) * 2001-03-09 2002-09-18 Ohbayashi Corp 2重管構造のボーリングロッド
JP2003336479A (ja) * 2002-05-23 2003-11-28 St Engineering Kk 自穿孔ボルトとfrpボルトを使った先行地山固結工法
CN1873187A (zh) * 2006-06-23 2006-12-06 董淑练 隧道施工的开挖方法
CN101126317A (zh) * 2006-08-18 2008-02-20 深圳市海川实业股份有限公司 一种地下隧道施工中的地下围护结构
CN101144384A (zh) * 2007-11-01 2008-03-19 中铁二局股份有限公司 隧道工程非爆破弱扰动开挖施工方法
CN101196118A (zh) * 2008-01-07 2008-06-11 北京市政建设集团有限责任公司 超前双排注浆小导管施工工艺
CN101387202A (zh) * 2008-10-29 2009-03-18 中铁四局集团有限公司 隧道内已成初支软弱围岩地段扩挖管棚工作室的方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
张建斌: "大断面浅埋暗挖隧道CRD法施工安全性分析", 《铁道建筑》 *
张建斌等: "厦门翔安海底隧道CRD法中各施工部对拱顶下沉的影响分析", 《现代隧道技术》 *
李金梗: "大跨度海底隧道CRD法施工位移控制基准研究", 《隧道建设》 *
毛红梅: "状元峰隧道大断面快速工法", 《山西建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102226406A (zh) * 2011-05-10 2011-10-26 中铁十二局集团第一工程有限公司 超长超前锚杆施工方法
CN102226406B (zh) * 2011-05-10 2013-09-18 中铁十二局集团第一工程有限公司 超长超前锚杆施工方法
RU2723422C1 (ru) * 2019-07-19 2020-06-11 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Способ крепления лба забоя тоннеля
RU2743161C1 (ru) * 2020-04-20 2021-02-15 федеральное государственное бюджетное образовательное учреждение высшего образования "Санкт-Петербургский горный университет" Способ крепления горных выработок анкерами с армированными поясами

Also Published As

Publication number Publication date
CN101892844B (zh) 2014-06-04

Similar Documents

Publication Publication Date Title
CN103277106B (zh) 公路隧道三台阶五步开挖施工方法
CN102587922B (zh) 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法
CN101338678B (zh) 一次扣拱暗挖逆作施工方法
CN102562074A (zh) 大断面隧道上硬下软复合地层的施工方法
CN206942764U (zh) 一种洞内组装和拆卸盾构机或tbm掘进机的辅助结构
CN104074524B (zh) 一种浅埋下穿高速公路大断面隧道的施工方法
CN105064397A (zh) 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法
CN204729099U (zh) 岩质地层暗挖三层地铁车站伞盖结构
CN105003272A (zh) 一种在地铁区间盾构隧道基础上扩挖车站的逆作施工方法
CN208502796U (zh) 隧道拱墙初期支护侵限换拱施工用门架式支撑结构
CN103953366B (zh) 单洞隧道改为连拱时中隔墙顶部原衬砌空腔回填施工方法
CN102865084B (zh) 从双线隧道断面到三线隧道超大断面的地下隧道扩挖方法
CN109707399A (zh) 隧道出洞支护构造及其施工方法
CN105089670A (zh) 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法
CN103850708A (zh) 一种采用混凝土充填体的沿空留巷方法
CN103233753A (zh) 用于浅埋大型地下结构建造的全断面开挖的管幕棚架法
CN202148907U (zh) 四线大跨隧道不等参初期支护构造
CN101892844B (zh) 一种超前锚杆支护的隧道crd开挖方法
CN103334778A (zh) 台阶临时支撑加部分双侧壁的施工工艺
CN204716248U (zh) 隧道横洞进主洞挑顶结构
CN212801573U (zh) 一种隧道洞口边仰坡预加固钢管桩
CN110118085A (zh) 一种大采深大采高复合顶工作面两巷超前二次成巷方法
CN211342952U (zh) 一种层状软岩隧道非对称支护结构
CN105178355B (zh) 地下空间施工的地层预加固处理方法
CN206646392U (zh) 一种组合式桥梁结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Free format text: FORMER OWNER: OCEANPOWER CORP. SHANGHAI KNP CHEMICAL CO., LTD. GUANGZHOU HAICHUAN TECHNOLOGY CO., LTD.

Effective date: 20140504

Owner name: SHENZHEN OCEANPOWER NEW MATERIALS TECHNOLOGY CO.,

Free format text: FORMER OWNER: HAICHUAN INDUSTRY CO., LTD., SHENZHEN

Effective date: 20140504

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Applicant after: SHENZHEN OCEANPOWER INDUSTRY Co.,Ltd.

Applicant after: SHENZHEN OCEAN POWER ENGINEERING TECHNOLOGY Co.,Ltd.

Applicant after: Shanghai Qipeng Chemical Co.,Ltd.

Applicant after: GUANGDONG OCEANPOWER TECHNOLOGY Co.,Ltd.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Applicant before: SHENZHEN OCEANPOWER INDUSTRY Co.,Ltd.

Applicant before: SHENZHEN OCEAN POWER ENGINEERING TECHNOLOGY Co.,Ltd.

Applicant before: Shanghai Qipeng Chemical Co.,Ltd.

Applicant before: HEYUAN OCEAN POWER TECHNOLOGY Co.,Ltd.

TA01 Transfer of patent application right

Effective date of registration: 20140504

Address after: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Applicant after: SHENZHEN OCEAN POWER MATERIAL TECHNOLOGY Co.,Ltd.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Applicant before: SHENZHEN OCEANPOWER INDUSTRY Co.,Ltd.

Applicant before: SHENZHEN OCEAN POWER ENGINEERING TECHNOLOGY Co.,Ltd.

Applicant before: Shanghai Qipeng Chemical Co.,Ltd.

Applicant before: GUANGDONG OCEANPOWER TECHNOLOGY Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Patentee after: SHENZHEN OCEANPOWER NEW MATERIAL TECHNOLOGY CO.,LTD.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Patentee before: SHENZHEN OCEAN POWER MATERIAL TECHNOLOGY Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220304

Address after: 212405 No. 6, Guangming science and Technology Innovation Park, Biancheng Town, Jurong City, Jiangsu Province

Patentee after: JIANGSU OCEANPOWER NEW MATERIAL TECHNOLOGY CO.,LTD.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Cheonan digital city building F3.8, block D, floor seven C

Patentee before: SHENZHEN OCEANPOWER NEW MATERIAL TECHNOLOGY CO.,LTD.