CN101126317A - 一种地下隧道施工中的地下围护结构 - Google Patents

一种地下隧道施工中的地下围护结构 Download PDF

Info

Publication number
CN101126317A
CN101126317A CNA2006101217783A CN200610121778A CN101126317A CN 101126317 A CN101126317 A CN 101126317A CN A2006101217783 A CNA2006101217783 A CN A2006101217783A CN 200610121778 A CN200610121778 A CN 200610121778A CN 101126317 A CN101126317 A CN 101126317A
Authority
CN
China
Prior art keywords
underground
frp
reinforcing cage
tunnel
exterior
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2006101217783A
Other languages
English (en)
Inventor
陈卫龙
何唯平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Oceanpower Industrial Co Ltd
Ocean Power Corp
Original Assignee
Shenzhen Oceanpower Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Oceanpower Industrial Co Ltd filed Critical Shenzhen Oceanpower Industrial Co Ltd
Priority to CNA2006101217783A priority Critical patent/CN101126317A/zh
Publication of CN101126317A publication Critical patent/CN101126317A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明提供一种地下隧道施工中的地下围护结构,包括筋笼和混凝土,其中筋笼采用FRP筋。采用本发明所述的地下围护结构,可以免除人工切割钢筋的工序,使得盾构可以直接开始掘进,掘进过程的最初时刻盾构就将FRP筋笼切割开,紧接着掘进隧道,节省工期。同时由于FRP筋是绝缘材料,可以很好地防止电磁干扰,不影响地铁内的无线通讯信号的效果。另外该FRP筋具有良好的抗腐蚀性。

Description

一种地下隧道施工中的地下围护结构
技术领域
本发明涉及一种隧道施工结构,尤其是一种围护结构。
背景技术
在我国目前的地铁等地下隧道施工中,地下围护结构通常采用钢筋混凝土结构。这样一来,在盾构刀盘开始掘进之前还需要在盾构刀盘的入口位置将上述钢筋混凝土结构切割部分,以便于盾构刀盘可以顺利开始掘进。由于切割这部分钢筋是人工操作,因此延误了工程工期、增强了工人劳动强度、降低了经济效益。
发明内容
本发明要解决的技术问题在于克服传统的地下隧道施工领域中在盾构掘进前需要人工切割地下围护结构中的钢筋的弊端。
为此本发明提供一种地下隧道施工中的地下围护结构,包括筋笼和混凝土,其特征在于:筋笼采用FRP(纤维增强聚合物)筋。
采用本发明所述的地下围护结构,可以免除人工切割钢筋的工序,使得盾构可以直接开始掘进,掘进过程的最初时刻盾构就将FRP筋笼切割开,紧接着掘进隧道,节省工期。同时由于FRP筋是绝缘材料,可以很好地防止电磁干扰,不影响地铁内的无线通讯信号的效果。另外该FRP筋具有良好的抗腐蚀性。
具体实施方式
本发明具体实施简单可行,没有特殊的施工工序,在设计地下围护结构之初,根据设计高程计算出盾构切割范围,并在此范围内用FRP筋材替代普通钢筋,FRP筋材规格型号需要经过计算确定。
在施工中需注意以下事项:
1、在盾构切割范围即FRP筋材布置范围内确保不出现除细扎丝以外的任何金属铁器;
2、FRP钢筋型号和规格与相邻普通钢筋一致,相邻FRP筋材与普通钢筋用细扎丝捆绑;
3、FRP筋的地下连续墙钢筋笼起吊工作采用“多点起吊法”。
4、在FRP筋材范围进行必要的加固处理,确保钢筋笼整体稳固牢靠。在此可采用φ48脚手架钢管纵横向加固,随后在下放笼体过程中边下放边拆除脚手架;
5、确保FRP筋材的布置范围准确无误,为防止在施工过程中笼体下落和上升产生的非人为误差,在具体施工中FRP筋材下料长度须比设计长度两端各长出2m;
6、在超出刀盘切割范围的FRP筋材与普通钢筋的连接,根据不同规格型号可用钢丝绳卡子连接并拧紧,不得出现松动和滑落;
7、FRP筋钢筋笼的制作应更加精心、严谨操作,每绑扎一根FRP筋都要与相连接的普通钢筋仔细对照,不仅要确保钢筋笼的水平,做到不漏筋、不错位,还要保证FRP筋区域不得有任何钢筋侵入。
8、在搬运、切割、帮扎FRP筋材过程中须佩带防护手套,防止纤维刺入皮肤。

Claims (1)

1.一种地下隧道施工中的地下围护结构,包括筋笼和混凝土,其特征在于:筋笼采用FRP筋。
CNA2006101217783A 2006-08-18 2006-08-18 一种地下隧道施工中的地下围护结构 Pending CN101126317A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2006101217783A CN101126317A (zh) 2006-08-18 2006-08-18 一种地下隧道施工中的地下围护结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2006101217783A CN101126317A (zh) 2006-08-18 2006-08-18 一种地下隧道施工中的地下围护结构

Publications (1)

Publication Number Publication Date
CN101126317A true CN101126317A (zh) 2008-02-20

Family

ID=39094433

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2006101217783A Pending CN101126317A (zh) 2006-08-18 2006-08-18 一种地下隧道施工中的地下围护结构

Country Status (1)

Country Link
CN (1) CN101126317A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892844A (zh) * 2009-05-20 2010-11-24 深圳市海川实业股份有限公司 一种超前锚杆支护的隧道crd开挖方法
CN103605169A (zh) * 2013-11-29 2014-02-26 河南理工大学 一种小型自重框式配载三维物理模拟实验方法
CN105143603A (zh) * 2013-02-28 2015-12-09 伊莱斯杰特尼卡公司 用于地下钢筋混凝土构造的增强件、结构和方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892844A (zh) * 2009-05-20 2010-11-24 深圳市海川实业股份有限公司 一种超前锚杆支护的隧道crd开挖方法
CN105143603A (zh) * 2013-02-28 2015-12-09 伊莱斯杰特尼卡公司 用于地下钢筋混凝土构造的增强件、结构和方法
CN103605169A (zh) * 2013-11-29 2014-02-26 河南理工大学 一种小型自重框式配载三维物理模拟实验方法

Similar Documents

Publication Publication Date Title
CN103775092B (zh) 隧道浅埋暗挖预留核心土改良crd施工工法
CN101539021B (zh) 公路隧道开挖方法
CN104314585A (zh) 隧道全断面预加固方法及结构
CN109404012A (zh) Ⅳ~ⅵ级围岩超挖隧道初期支护方法
CN102400694A (zh) 盾构隧道与矿山法隧道结合部的加固方法
CN105114098A (zh) 引水隧洞不良地质洞段处理方法及大直径引水隧洞结构
CN108150187A (zh) 一种巨型松散岩堆护拱进洞的方法
CN209444334U (zh) 一种用于盾构机刀盘正面检修清理的玻璃纤维筋中孔桩
CN101126317A (zh) 一种地下隧道施工中的地下围护结构
CN108203984A (zh) 一种危岩体锚网支护方法
CN107035383A (zh) 特大断面黄土隧道的支护结构及其开挖方法
CN109826657A (zh) 一种用于软岩隧道掌子面加固装置及其施工方法
CN110080296A (zh) 一种用于盾构洞门地连墙的单侧玻璃筋-钢筋笼结构
CN104141500A (zh) 一种板结砂砾石地层洞室施工方法
CN203835404U (zh) 一种既有隧道拱部衬砌严重开裂无净空加固体系
CN206204963U (zh) 一种危岩体防护治理结构
CN111577311A (zh) 一种软岩隧洞中悬臂式掘进机施工工艺
CN204716253U (zh) 圆形大直径引水隧洞结构
CN204436407U (zh) 一种大断面软弱围岩隧道双层初期支护预防地质灾害发生的结构
CN209873818U (zh) 一种崩坡积体边坡支护体系
CN109184753A (zh) 用于隧道初期支护后变形侵限的处理方法
CN207583398U (zh) 一种软弱围岩组合支护装置
CN108086306A (zh) 一种桩头混凝土施工及凿除方法
CN101725356A (zh) 地下建筑竖井围护结构及其盾构机切削施工方法
CN103470275A (zh) 一种大跨度地下洞室平交三岔口开挖支护方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080220