CN102587922B - 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法 - Google Patents
一种软弱破碎岩层斜交斜井上弧导挑顶施工方法 Download PDFInfo
- Publication number
- CN102587922B CN102587922B CN201210043696.7A CN201210043696A CN102587922B CN 102587922 B CN102587922 B CN 102587922B CN 201210043696 A CN201210043696 A CN 201210043696A CN 102587922 B CN102587922 B CN 102587922B
- Authority
- CN
- China
- Prior art keywords
- inclined shaft
- arc guide
- upper arc
- positive hole
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明涉及斜井挑顶领域,具体为一种软弱破碎岩层斜交斜井上弧导挑顶施工方法,解决现有现有斜井挑顶施工,采用小导洞挑顶存在诸多问题,在斜井与正洞交叉口设曲线过渡,使斜井口与正洞正交;交叉口设门型钢架支撑,正洞钢拱架与门型钢架连接牢固;紧邻正洞斜井段落设套拱支护,底板增设工字钢横撑;正洞范围内利用上弧导挑顶,上弧导最后一榀拱架与线路方向垂直,拱顶与正洞拱顶平齐;按正洞断面扩挖,施作正洞上导初期支护;反向逐榀拆除上弧导钢拱架临时支撑,施作另一侧正洞上导初期支护;正洞范围正常施工,挑顶完成。提高了工效、加快了施工进展、降低了安全风险,安全、快速、优质、高效地完成了斜井挑顶施工,取得了良好的效果。
Description
技术领域
本发明涉及斜井挑顶施工领域,具体为一种软弱破碎岩层斜交斜井上弧导挑顶施工方法。
背景技术
斜井挑顶施工,通常采用小导洞挑顶方法:设钢拱架棚洞临时支护,上导范围内小导洞开挖及临时支护完成后,安装钢拱架,之后拆除钢拱架棚洞临时支护,向两侧扩挖,施工正洞上导初期支护。对于软弱破碎岩层斜交式斜井,以上方法具有一定的局限性,主要表现在:小导洞设钢拱架棚洞临时支护,棚洞断面为梯形,若遇软弱破碎岩层极易坍塌,不利安全;因小导洞断面较小,一般采用人工开挖方法,工效极低;小导洞通视条件差,测量放样复杂,施工精度不易控制;斜井与正洞斜交,交叉口位置跨度过长,不利受力,安全风险大。
发明内容
本发明为了解决现有对于软弱破碎岩层斜交式斜井挑顶施工,通常采用小导洞挑顶方法存在诸多问题,提供一种软弱破碎岩层斜交斜井上弧导挑顶施工方法。
本发明是采用如下技术方案实现的:一种软弱破碎岩层斜交斜井上弧导挑顶施工方法,包括以下步骤:(1)斜井开挖及支护;(2)在距正洞与斜井交叉口位置10~20m开始,设曲线过渡,使斜井口与正洞正交;(3)交叉口段加强支护:在斜井与正洞交叉口处架立至少3榀并排设置的门型钢架,外侧设型钢钢架支撑柱及落脚横梁,正洞钢拱架与门型钢架横梁之间焊接牢固,在与正洞交叉口相接9~11m范围设套拱加固,底板混凝土增设工字钢横撑,与已施工完的初期支护形成整体受力;(4)上弧导挑顶支护:正洞范围内采用上弧导挑顶,上弧导最后一榀拱架与线路方向垂直,拱顶与正洞拱顶平齐,挑顶段上弧导临时支护采用钢拱架,开挖断面同斜井上导,开挖每循环进尺1.0~1.5m,施作超前小导管;(5)正洞扩挖支护:上弧导挑顶到位后,继续向前开挖,开挖断面同正洞尺寸,在上弧导临时支撑的基础上进行扩挖,扩挖第一榀间距不超过60cm,扩挖到位后及时喷射混凝土封闭,快速安装钢拱架;(6) 正洞上导挑顶段初期支护:在正洞上导扩挖长度达到3~6m后,反向施作另一侧正洞上导初期支护,每拆除一榀上弧导临时支撑,及时安装上导钢拱架,钢拱架间距不超过0.6m;(7)斜井挑顶段上导施工完成后,继续进行正洞上导开挖及支护,及时施作仰拱及二衬,正洞范围开始正常施工,挑顶完成。
与现有技术相比,本发明具有以下优点:
1、通过在交叉口附近设曲线过渡,使斜井口与正洞正交,不仅优化了受力结构,同时缩短了斜井长度,节约了投资,此外斜井口与正洞正交,为上弧导挑顶施工提供了作业条件,方便施工;
2、 与正洞交叉口相邻段斜井采用套拱加固,相对于二衬混凝土加固等工艺而言,简化了施工工艺,缩短了加固周期,加快了施工进展,同时节约了费用;
3、采用上弧导挑顶,为大型机械设备提供了作业空间、提高了工效,缩短了挑顶施工时间,减少施工成本,经济效益显著;
4、上弧导挑顶,开挖断面为拱形,充分利用围岩的自稳能力,有效避免拱部掉块、坍塌;上弧导挑顶至正洞位置后,在上弧导的保护下,进行正洞扩挖,保证了施工安全;
5、上弧导临时支护体系,相对于小导洞挑顶棚洞支护体系而言,空间相对较大,降低了粉尘污染及噪音污染,作业环境得到改善;
总之,对于软弱破碎岩层斜交斜井挑顶施工,提高了工效、加快了施工进展、降低了安全风险,安全、快速、优质、高效地完成了斜井挑顶施工,取得了良好的效果,为软弱破碎岩层挑顶施工积累了宝贵的经验。
附图说明
图1为本发明斜井挑顶段平面示意图;
图2为本发明斜井挑顶纵断面示意图;
图3为本发明所述门型钢架结构示意图;
图4为本发明所述套拱断面结构示意图;
图中:1-斜井;2-正洞;3-门型钢架;4-套拱;5-隧道左中线;6-隧洞右中线;7-隧道中线;8-平坡段;9-斜井底板;10-正洞混凝土底板;11-纵坡段。
具体实施方式
一种软弱破碎岩层斜交斜井上弧导挑顶施工方法,其特征是包括以下步骤:
1)斜井1开挖及支护:斜井断面小,一般采用上下台阶法施工,台阶长度控制在3~5m,有利于施工设备作业,加快施工进展,施工中,遵循“弱爆破、短进尺”原则,以挖机辅以人工开挖为主。按照设计参数施作,超前小导管、锁脚锚管等施作到位,若遇围岩较差时,加密超前小导管及缩脚锚管数量。底板混凝土紧跟,底板混凝土距掌子面距离不超过35m。底板两侧设排水沟,以避免拱脚位置积水。
2)在距正洞2与斜井交叉口位置10~20m开始,设曲线过渡,使斜井口与正洞正交,具体根据斜井斜交角度及断面尺寸确定,以方便施工车辆行驶并满足测量通视为原则。曲线半径R=100~150m,曲线地段斜井断面相应加大,与正常断面间顺接过渡,曲线内侧与斜井一边平齐,曲线外侧钢架呈扇形支护,过渡段支护相应加强,采用I20以上工字钢支护。正洞与斜井交叉口向斜井方向不小于10m长度范围设为平坡段8,斜井底板9标高与正洞混凝土底板10相同,并与斜井范围底板混凝土面顺接。斜井挑顶段平面图如图1,斜井挑顶纵断面图如图2。
3)交叉口段加强支护
在斜井与正洞交叉口处架立至少3榀并排设置的门型钢架3,外侧设型钢钢架支撑柱及落脚横梁,门型钢架采用工字钢不小于Ⅰ20,采用φ22钢筋纵向连接、焊接牢固,喷射混凝土封闭。喷射混凝土前,门型钢架顶梁位置用彩条布或其他材料包裹,在安装挑顶段正洞钢拱架时扯掉彩条布即可,正洞钢拱架与门型钢架横梁之间焊接牢固。在与正洞交叉口相接9~11m范围设套拱加固,套拱钢拱架工字钢不小于Ⅰ16,底板混凝土增设工字钢横撑,与已施工完的初期支护形成整体受力,确保安全。门型钢架如图3,套拱断面如图4。
4)上弧导挑顶支护
正洞范围内采用上弧导挑顶,平面位置及标高逐渐过渡,上弧导最后一榀拱架与线路方向垂直,拱顶与正洞拱顶平齐,可提前设曲线进行理论计算或通过CAD模拟画图,根据理论数据进行现场放样。挑顶段上弧导临时支护采用钢拱架,开挖断面同斜井上导,开挖每循环进尺1.0~1.5m,施作超前小导管,小导管间距控制在30cm左右,拱脚部位设3.5m长φ42锁脚锚管,钢架与锁脚锚管之间通过“L”型或“U”型钢筋焊接牢固,喷C25混凝土封闭。
5)正洞扩挖支护
上弧导挑顶到位后,继续向前开挖,开挖断面同正洞尺寸,在上弧导临时支撑的基础上进行扩挖,扩挖第一榀间距不超过60cm,扩挖到位后及时喷射混凝土封闭,快速安装钢拱架,钢拱架规格同设计,拱脚部位设φ42锁脚锚管,锁脚锚管可根据围岩情况适当加强,钢架与锁脚锚管之间通过“L”型或“U”型钢筋焊接牢固,喷C25混凝土封闭。
6) 正洞上导挑顶段初期支护
在正洞上导扩挖长度达到3~6m后,反向施作另一侧正洞上导初期支护,每拆除一榀上弧导临时支撑,及时安装上导钢拱架,钢拱架间距不超过0.6m,钢拱架一侧位于上台阶拱脚处,采用28槽钢支垫,拱脚部位设φ42锁脚锚管,锁脚锚管可根据围岩情况适当加强,钢架与锁脚锚管之间通过“L”型或“U”型钢筋焊接牢固;另一侧与门型钢架横梁连接牢固,并周边焊接加强,喷射混凝土封闭。挑顶段预留沉落量按不小于30cm设置。
7)斜井挑顶段上导施工完成后,继续进行正洞上导开挖及支护,当掌子面围岩松散、自稳能力差时,采用弱爆破方式,上导预留核心土开挖;当施工空间具备中、下导施工条件时,及时接中、下导施工,按照三台阶七步开挖法施工。挑顶段每侧10m范围支护参数比设计适当加强,钢拱架规格不小于Ⅰ20,钢架间距不大于0.6m,上、中、下导位置施作φ42锁脚锚管,锁脚锚管加倍设置,钢拱架与锁脚锚管之间通过“L”型或“U”型钢筋焊接牢固。锁脚锚管下倾30~45°;钢架应架设在坚实的基岩面上,当岩层软弱时,应在拱脚处加垫槽钢或木板;台阶长度为3~5m,左右相错开挖,相错量为2榀以上拱架间距。
及时施作正洞仰拱、二衬混凝土,保证结构安全,正洞段开始正常施工,挑顶结束。
工程实例:
山西中南部铁路通道武家岭隧道全隧以砂岩、泥质砂岩、泥岩为主,强风化~弱风化,节理裂隙发育,岩体破碎、结构松散,1号斜井与正洞相交处富含水,拱顶易掉块、坍塌,属软弱破碎岩层,斜井与正洞斜交。设计为小导洞挑顶方案,设棚洞临时支护。
经分析:挑顶段围岩结构复杂、岩体破碎、富含水,安全风险极高。若采用设计挑顶方案,存在的主要问题为:小导洞钢拱架棚洞临时支护断面为梯形,在软弱破碎岩层地段极易坍塌,不利安全;小导洞断面较小,一般采用人工开挖方法,工效极低;斜井与正洞斜交,交叉口位置跨度过长,不利受力,安全风险大。为有效解决以上问题,经过反复论证必选后,优化了设计方案,施工中采用了本发明所述的上弧导挑顶施工,提高了工效、加快了施工进展、降低了安全风险,取得了良好的效果。斜井缩短32m,节约投资50万元;与正洞交叉口相邻段斜井采用套拱加固,相对于二衬混凝土加固等工艺而言,节约了施工成本,加固段按共30m考虑,每米节约投资1.5万元,合计节约45万元;采用本发明所述方法,施工效率高,施工进展大大加快,提前10天左右完成挑顶施工,节约成本20万元,合计节约费用115万元,经济效益显著。
进一步推广该方法,在武家岭隧道2号斜井挑顶施工中再次得到成功应用,安全、快速、优质、高效地完成了斜井挑顶施工,取得了良好的效果,得到了各方的较高评价,取得了良好的社会效益。
Claims (1)
1.一种软弱破碎岩层斜交斜井上弧导挑顶施工方法,其特征是包括以下步骤:
1)斜井(1)开挖及支护;
2)在距正洞(2)与斜井交叉口位置10~20m开始,设曲线过渡,使斜井口与正洞正交;
3)交叉口段加强支护
在斜井与正洞交叉口处架立至少3榀并排设置的门型钢架(3),外侧设型钢钢架支撑柱及落脚横梁,正洞钢拱架与门型钢架横梁之间焊接牢固,在与正洞交叉口相接9~11m范围设套拱(4)加固,底板混凝土增设工字钢横撑,与已施工完的初期支护形成整体受力;
4)上弧导挑顶支护
正洞范围内采用上弧导挑顶,上弧导最后一榀拱架与线路方向垂直,拱顶与正洞拱顶平齐,挑顶段上弧导临时支护采用钢拱架,开挖断面同斜井上导,开挖每循环进尺1.0~1.5m,施作超前小导管;
5)正洞扩挖支护
上弧导挑顶到位后,继续向前开挖,开挖断面同正洞尺寸,在上弧导临时支撑的基础上进行扩挖,扩挖第一榀间距不超过60cm,扩挖到位后及时喷射混凝土封闭,快速安装钢拱架;
6) 正洞上导挑顶段初期支护
在正洞上导扩挖长度达到3~6m后,反向施作另一侧正洞上导初期支护,每拆除一榀上弧导临时支撑,及时安装上导钢拱架,钢拱架间距不超过0.6m;
7)斜井挑顶段上导施工完成后,继续进行正洞上导开挖及支护,及时施作仰拱及二衬,正洞范围开始正常施工,挑顶完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210043696.7A CN102587922B (zh) | 2012-02-24 | 2012-02-24 | 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210043696.7A CN102587922B (zh) | 2012-02-24 | 2012-02-24 | 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102587922A CN102587922A (zh) | 2012-07-18 |
CN102587922B true CN102587922B (zh) | 2014-04-23 |
Family
ID=46477089
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210043696.7A Active CN102587922B (zh) | 2012-02-24 | 2012-02-24 | 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102587922B (zh) |
Families Citing this family (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102913249B (zh) * | 2012-10-30 | 2014-08-27 | 中铁十九局集团有限公司 | 斜井横向贯通正洞单喇叭挑高施工方法 |
CN103939107B (zh) * | 2014-04-28 | 2015-12-09 | 山东黄金矿业(玲珑)有限公司 | 一种冒落松散岩体中的成巷方法 |
CN104329098A (zh) * | 2014-08-29 | 2015-02-04 | 中铁十六局集团有限公司 | 一种软弱围岩辅助坑道小导洞横穿正洞挑顶施工方法 |
CN104481546B (zh) * | 2014-11-25 | 2016-09-28 | 中铁十二局集团有限公司 | 一种软岩隧道斜井进入正洞的双曲拱的施工方法 |
CN104675407B (zh) * | 2015-01-14 | 2017-04-26 | 中铁第四勘察设计院集团有限公司 | 一种单线矿山法地铁隧道斜井进正洞的处理方法 |
CN105781559A (zh) * | 2016-04-11 | 2016-07-20 | 中铁六局集团有限公司 | 陡坡斜井风道进主洞挑顶施工方法 |
CN106907161B (zh) * | 2017-04-28 | 2019-02-12 | 中铁二十二局集团第五工程有限公司 | 一种隧道斜井挑顶专项施工方法 |
CN107605489B (zh) * | 2017-08-28 | 2018-12-21 | 深圳市市政设计研究院有限公司 | 三线大跨隧道斜井进正洞施工方法 |
CN108301845B (zh) * | 2018-02-11 | 2023-08-29 | 中铁第一勘察设计院集团有限公司 | 附属隧洞开主体隧洞的接口钢架支撑体系及其施工方法 |
CN109057807A (zh) * | 2018-09-28 | 2018-12-21 | 北京市市政三建设工程有限责任公司 | 一种渐变大跨隧道反向扩挖方法 |
CN109403985A (zh) * | 2018-10-18 | 2019-03-01 | 中铁十二局集团有限公司 | 极软弱破碎围岩层的门式挑顶工法 |
CN110242305B (zh) * | 2019-06-25 | 2020-09-01 | 北京市市政工程设计研究总院有限公司 | 一种斜井进单侧壁导坑法施作主洞的施工工艺方法 |
CN110318763A (zh) * | 2019-07-11 | 2019-10-11 | 中国水利水电建设工程咨询北京有限公司 | 多平台台车式斜井扩挖方法 |
CN110307013A (zh) * | 2019-08-09 | 2019-10-08 | 长沙理工大学 | 一种偏压隧道拱架和偏压隧道拱架挑顶结构 |
CN110685698B (zh) * | 2019-10-29 | 2021-04-27 | 中铁(贵州)市政工程有限公司 | 既有洞室侧向新建为大断面隧道的爬升反向施工法 |
CN110984995A (zh) * | 2019-12-18 | 2020-04-10 | 中国水利水电第五工程局有限公司 | 一种竖井弯段开挖体型控制方法 |
CN111894599B (zh) * | 2020-06-09 | 2022-02-15 | 甘肃路桥建设集团有限公司 | 一种斜交偏压隧道正进的施工方法 |
CN111677517B (zh) * | 2020-07-03 | 2022-06-24 | 中铁十八局集团有限公司 | 一种隧道辅助导坑进入正洞方法 |
CN113338951B (zh) * | 2021-06-30 | 2023-11-03 | 中交路桥建设有限公司 | 快速隧道交叉口三台阶挑顶施工方法 |
CN114320378B (zh) * | 2021-12-16 | 2024-06-18 | 中铁十局集团第三建设有限公司 | 破碎带支洞挑顶快速施工装置及方法 |
CN117967323B (zh) * | 2024-03-21 | 2024-06-14 | 中铁四局集团有限公司 | 水工隧洞岔洞转支洞接口处加强环结构及挑顶施工方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101775988A (zh) * | 2010-02-09 | 2010-07-14 | 中铁四局集团有限公司 | 软弱围岩斜井转正洞的施工方法 |
-
2012
- 2012-02-24 CN CN201210043696.7A patent/CN102587922B/zh active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101775988A (zh) * | 2010-02-09 | 2010-07-14 | 中铁四局集团有限公司 | 软弱围岩斜井转正洞的施工方法 |
Non-Patent Citations (4)
Title |
---|
付国宏.7号斜井进正洞挑顶施工技术.《铁道标准设计》.2005, * |
付艳丽.隧道斜井进正洞挑顶施工技术.《铁道建筑》.2011, * |
初厚永.大断面黄土隧道斜井进入正洞挑顶施工技术.《铁道建筑技术》.2010,46页右栏第2段. * |
郭新兵.黄土隧道斜井交叉口挑顶施工方法.《山西建筑》.2010, * |
Also Published As
Publication number | Publication date |
---|---|
CN102587922A (zh) | 2012-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102587922B (zh) | 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法 | |
CN102226403B (zh) | 地铁大跨度车站主体拱盖法施工方法及车站主体结构 | |
CN202707075U (zh) | 基于柱拱法施工成型的地铁大跨度车站主体结构 | |
CN101737061B (zh) | 既有单洞隧道改扩建为连拱隧道的施工方法 | |
CN102733827B (zh) | 隧道换拱施工方法及用于隧道换拱施工中的施工结构 | |
CN103775092B (zh) | 隧道浅埋暗挖预留核心土改良crd施工工法 | |
CN101864963B (zh) | 一种大断面黄土隧道施工方法 | |
CN102748040B (zh) | 地铁大跨度车站主体结构及其柱拱法施工方法 | |
CN104612698A (zh) | 一种浅埋暗挖隧道上台阶中隔壁施工方法 | |
CN103174434B (zh) | 一种不对称双联拱隧道结构的施工方法 | |
CN105041349A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的暗挖施工方法 | |
CN104074524B (zh) | 一种浅埋下穿高速公路大断面隧道的施工方法 | |
CN103375170A (zh) | 三孔小净距隧洞下穿铁路干线的暗挖施工变形控制方法 | |
CN105443132A (zh) | 浅埋暗挖十字横撑隧道施工方法 | |
CN102562074A (zh) | 大断面隧道上硬下软复合地层的施工方法 | |
CN110130927A (zh) | 一种炭质板岩隧道大变形控制施工方法 | |
CN110700841B (zh) | 用于隧道开挖的双侧壁导坑式开挖方法 | |
CN104165056A (zh) | 一种富水浅埋暗挖隧道的开挖施工方法 | |
CN204729099U (zh) | 岩质地层暗挖三层地铁车站伞盖结构 | |
CN105064397A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法 | |
CN105003272A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的逆作施工方法 | |
CN102305091B (zh) | 一种硬岩大断面隧道施工的支撑结构及其施工方法 | |
CN105201516A (zh) | 一种地铁车站主体结构及其四联拱pba暗挖施工方法 | |
CN104295301B (zh) | 一种浅埋暗挖碎裂岩体地铁隧道交叉点的施工方法 | |
CN107130983A (zh) | 一种大断面隧道掘进施工格栅拱架加强支护方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |