CN105781559A - 陡坡斜井风道进主洞挑顶施工方法 - Google Patents

陡坡斜井风道进主洞挑顶施工方法 Download PDF

Info

Publication number
CN105781559A
CN105781559A CN201610219790.1A CN201610219790A CN105781559A CN 105781559 A CN105781559 A CN 105781559A CN 201610219790 A CN201610219790 A CN 201610219790A CN 105781559 A CN105781559 A CN 105781559A
Authority
CN
China
Prior art keywords
main tunnel
supporting
steelframe
excavation
air channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610219790.1A
Other languages
English (en)
Inventor
王玉伟
王全亮
雒文军
宋建忠
赵骏
罗强
高烁亮
孙士亮
姚文娟
丁澍
侯斌
董录彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
China Railway Sixth Group Co Ltd
Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP, China Railway Sixth Group Co Ltd filed Critical TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
Priority to CN201610219790.1A priority Critical patent/CN105781559A/zh
Publication of CN105781559A publication Critical patent/CN105781559A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/36Linings or supports specially shaped for tunnels or galleries of irregular cross-section
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D19/00Provisional protective covers for working space
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Abstract

本发明具体为一种陡坡斜井风道进主洞挑顶施工方法,解决了现有斜井风道进主洞挑顶作业存在工作效率低、安全性能差的问题。a、在风道左右两侧均架立竖钢架,竖钢架顶端之间设置有钢横梁,钢横梁上方设置锚杆和锁脚锚杆;b、风道施工至正洞段后,斜向上进行掘进;c、对正洞中线左侧上台阶开挖完成后初喷混凝土,并进行临时支撑;d、对正洞中线右侧上台阶水平开挖完成后进行支护,通过锁脚锚杆固定拱部钢拱架,并进行临时支撑;e、沿正洞向前循环开挖支护,重复c、d步骤;f、拆除临时支护体系,正洞上导坑开始向其前后两侧双向掘进,待单侧掘进长度大于10m后,开始下导坑的开挖支护工作。本发明提高了施工效率,杜绝了安全隐患的发生。

Description

陡坡斜井风道进主洞挑顶施工方法
技术领域
本发明涉及隧道掘进施工方法,具体为一种陡坡斜井风道进主洞挑顶施工方法。
背景技术
隧道施工期间,斜井风道进入主洞时,由于开挖断面大,围岩较差,传统的挑顶方式无法保证安全及工期。
发明内容
本发明为了解决现有斜井风道进主洞挑顶作业存在工作效率低、安全性能差的问题,提供了一种陡坡斜井风道进主洞挑顶施工方法。
本发明是采用如下技术方案实现的:陡坡斜井风道进主洞挑顶施工方法,采用如下步骤:a、在风道与正洞交叉口段的风道左右两侧均架立有竖钢架,两竖钢架顶端之间设置有与两者连接的钢横梁,钢横梁上方设置锚杆和锁脚锚杆,为正洞钢架提供落脚平台;b、风道施工至正洞段后,斜向上进行掘进;c、对正洞中线左侧上台阶开挖完成后及时初喷混凝土,并根据围岩情况及测量结果采用短钢架进行临时支撑,通过钢筋焊接形成临时支护体系;d、对正洞中线右侧上台阶水平开挖完成后进行支护,通过锁脚锚杆固定拱部钢拱架,并采用短钢架进行临时支撑后,通过钢筋焊接形成临时支护体系;e、沿正洞向前循环开挖支护,重复c、d步骤,每循环进尺1-1.5m;f、待风道段的正洞上导坑开挖支护全部完成后,拆除临时支护体系,正洞上导坑开始向其前后两侧双向掘进,待单侧掘进长度大于10m后,开始下导坑的开挖支护工作。
采用该施工方法克服了现有斜井风道进主洞挑顶作业存在工作效率低、安全性能差的问题。
本发明所述的施工方法合理可靠,而且工序进行极大的简化,操作方便快捷,提高了施工效率,同时杜绝了安全隐患的发生,施工成本较低。
具体实施方式
陡坡斜井风道进主洞挑顶施工方法,采用如下步骤:a、在风道与正洞交叉口段的风道左右两侧均架立有竖钢架,两竖钢架顶端之间设置有与两者连接的钢横梁,钢横梁上方设置锚杆和锁脚锚杆,为正洞钢架提供落脚平台;b、风道施工至正洞段后,斜向上进行掘进;c、对正洞中线左侧上台阶开挖完成后及时初喷混凝土,并根据围岩情况及测量结果采用短钢架进行临时支撑,通过钢筋焊接形成临时支护体系;d、对正洞中线右侧上台阶水平开挖完成后进行支护,通过锁脚锚杆固定拱部钢拱架,并采用短钢架进行临时支撑后,通过钢筋焊接形成临时支护体系;e、沿正洞向前循环开挖支护,重复c、d步骤,每循环进尺1-1.5m;f、待风道段的正洞上导坑开挖支护全部完成后,拆除临时支护体系,正洞上导坑开始向其前后两侧双向掘进,待单侧掘进长度大于10m后,开始下导坑的开挖支护工作。
具体实施过程中,竖钢架采用2榀I18型钢钢架,斜向上掘进的角度为25%的坡率。

Claims (1)

1.一种陡坡斜井风道进主洞挑顶施工方法,其特征在于:采用如下步骤:a、在风道与正洞交叉口段的风道左右两侧均架立有竖钢架,两竖钢架顶端之间设置有与两者连接的钢横梁,钢横梁上方设置锚杆和锁脚锚杆,为正洞钢架提供落脚平台;b、风道施工至正洞段后,斜向上进行掘进;c、对正洞中线左侧上台阶开挖完成后及时初喷混凝土,并根据围岩情况及测量结果采用短钢架进行临时支撑,通过钢筋焊接形成临时支护体系;d、对正洞中线右侧上台阶水平开挖完成后进行支护,通过锁脚锚杆固定拱部钢拱架,并采用短钢架进行临时支撑后,通过钢筋焊接形成临时支护体系;e、沿正洞向前循环开挖支护,重复c、d步骤,每循环进尺1-1.5m;f、待风道段的正洞上导坑开挖支护全部完成后,拆除临时支护体系,正洞上导坑开始向其前后两侧双向掘进,待单侧掘进长度大于10m后,开始下导坑的开挖支护工作。
CN201610219790.1A 2016-04-11 2016-04-11 陡坡斜井风道进主洞挑顶施工方法 Pending CN105781559A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610219790.1A CN105781559A (zh) 2016-04-11 2016-04-11 陡坡斜井风道进主洞挑顶施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610219790.1A CN105781559A (zh) 2016-04-11 2016-04-11 陡坡斜井风道进主洞挑顶施工方法

Publications (1)

Publication Number Publication Date
CN105781559A true CN105781559A (zh) 2016-07-20

Family

ID=56396233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610219790.1A Pending CN105781559A (zh) 2016-04-11 2016-04-11 陡坡斜井风道进主洞挑顶施工方法

Country Status (1)

Country Link
CN (1) CN105781559A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437749A (zh) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 一种隧道双支洞挑顶施工方法
CN109681213A (zh) * 2019-01-09 2019-04-26 济南城建集团有限公司 一种在斜井端头增加竖井转正洞加速城市地下道路施工方法
CN113236296A (zh) * 2021-04-25 2021-08-10 中铁二局第二工程有限公司 一种地铁车站拱盖法施工的拱脚岩体保存方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0978980A (ja) * 1995-09-11 1997-03-25 Shimizu Corp 急勾配トンネルの施工方法および装置
CN102587922A (zh) * 2012-02-24 2012-07-18 中铁十二局集团第二工程有限公司 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法
CN103195432A (zh) * 2013-03-08 2013-07-10 中铁二十二局集团第一工程有限公司 一种软弱围岩隧道交叉口弧形导坑施工方法
CN104929649A (zh) * 2015-06-17 2015-09-23 大连市市政设计研究院有限责任公司 隧道横洞进主洞挑顶工法及挑顶结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0978980A (ja) * 1995-09-11 1997-03-25 Shimizu Corp 急勾配トンネルの施工方法および装置
CN102587922A (zh) * 2012-02-24 2012-07-18 中铁十二局集团第二工程有限公司 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法
CN103195432A (zh) * 2013-03-08 2013-07-10 中铁二十二局集团第一工程有限公司 一种软弱围岩隧道交叉口弧形导坑施工方法
CN104929649A (zh) * 2015-06-17 2015-09-23 大连市市政设计研究院有限责任公司 隧道横洞进主洞挑顶工法及挑顶结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙波: "张庄隧道斜井进正洞交叉口施工方法-斜井挑梁施工", 《现代隧道技术(增刊)》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437749A (zh) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 一种隧道双支洞挑顶施工方法
CN106437749B (zh) * 2016-08-26 2018-08-03 中铁十一局集团第四工程有限公司 一种隧道双支洞挑顶施工方法
CN109681213A (zh) * 2019-01-09 2019-04-26 济南城建集团有限公司 一种在斜井端头增加竖井转正洞加速城市地下道路施工方法
CN109681213B (zh) * 2019-01-09 2024-03-08 济南城建集团有限公司 一种在斜井端头增加竖井转正洞加速城市地下道路施工方法
CN113236296A (zh) * 2021-04-25 2021-08-10 中铁二局第二工程有限公司 一种地铁车站拱盖法施工的拱脚岩体保存方法
CN113236296B (zh) * 2021-04-25 2023-08-18 中铁二局第二工程有限公司 一种地铁车站拱盖法施工的拱脚岩体保存方法

Similar Documents

Publication Publication Date Title
CN101864963B (zh) 一种大断面黄土隧道施工方法
CN105370287B (zh) 大型地下停车场机械暗挖施工方法
CN202690082U (zh) 一种预防隧道变形沉降的组合钢架结构
CN103032073B (zh) 一种城市地铁泥岩地层联络通道与盾构掘进平行施工方法
CN104481546B (zh) 一种软岩隧道斜井进入正洞的双曲拱的施工方法
CN105041357B (zh) 单轨吊运尾变首式超前支护系统
CN104500075A (zh) 绳锯机切割地下障碍物的施工方法
CN101545376A (zh) 小断面隧道横向进入超大断面隧道的施工方法
CN102400689B (zh) 特大断面暗挖隧道回旋开挖法
CN105781559A (zh) 陡坡斜井风道进主洞挑顶施工方法
US20200095747A1 (en) Foundation Construction Device and Its Construction Method
CN203684234U (zh) 轨排施工吊装预留井支护结构
JP6681148B2 (ja) 橋梁構築方法、橋梁構築方法で用いる柱体及びガイド手段
AU2021105800A4 (en) Treatment method for side roof collapse of water-bearing broken soft rock tunnel
CN105781590A (zh) Tbm用接收洞负环拆除工艺
CN104790997A (zh) 一种用于综掘的自移动超前临时支护液压支架
CN204959762U (zh) 挡墙式龙门吊轨道梁结构
CN202945798U (zh) 一种悬挑式脚手架角部装置
CN110805305A (zh) 一种高层建筑物爬坡移位方法
CN110206571B (zh) 一种用于隧道锚杆支护施工的锚杆台车及其操作工法
CN106761873A (zh) 一种用于金属地下矿山巷道冒落区及破碎带的支护方法
CN102493819A (zh) 一种控制煤层巷道围岩稳定性的方法
CN113123800B (zh) 大直径盾构隧道钢结构始发基座施工方法
CN206439053U (zh) 隧洞仰拱衬砌悬模台车
CN1026605C (zh) 用于回收工作面支架及设备的巷道支护方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160720

RJ01 Rejection of invention patent application after publication