CN102226406A - 超长超前锚杆施工方法 - Google Patents
超长超前锚杆施工方法 Download PDFInfo
- Publication number
- CN102226406A CN102226406A CN2011101197992A CN201110119799A CN102226406A CN 102226406 A CN102226406 A CN 102226406A CN 2011101197992 A CN2011101197992 A CN 2011101197992A CN 201110119799 A CN201110119799 A CN 201110119799A CN 102226406 A CN102226406 A CN 102226406A
- Authority
- CN
- China
- Prior art keywords
- drilling rod
- anchor bolt
- rig
- advance anchor
- advanced
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Earth Drilling (AREA)
Abstract
本发明公开了超长超前锚杆施工方法,涉及隧道施工中超前支护的方法,解决隧道超前支护中超前小导管长度过短而出现的支护效果不好,影响施工进度的问题。包括准备工作;起钻开孔;接钻杆继续钻进至设计深度;洗孔;退钻杆;插入超前锚杆:逐节安装超前锚杆,超前锚杆间采用连接套连接,使用管钳将锚杆与连接套拧紧;超前锚杆注浆。本发明为隧道超前支护施工提供了一种新的施工方法,操作流程简单,易于推广,极大的降低了在后续开挖中发生岩石滑落、塌方的概率,提高了施工的安全性。
Description
技术领域
本发明属于隧道施工技术领域,涉及隧道超前支护方法,具体涉及一种超长超前锚杆施工方法。
背景技术
软岩隧道中当围岩级别在Ⅴ级及Ⅴ级以上时,超前支护一般设计成单层小导管或双层小导管,每排小导管长度常为3~5m。然而在施工中常常由于超前小导管长度过短而失去超前支护的部分功能,效果不好,容易在后续开挖中发生岩石滑落,甚至发生塌方,而且超前小导管施作的频率也不高,增加工序循环时间,影响施工进度。
为了弥补在软弱围岩的超前支护施工中存在的这种安全缺陷,需要研究一种新的隧道超前支护方法。
发明内容
本发明的目的是为了解决隧道超前支护中超前小导管长度过短而出现的支护效果不好,影响施工进度等问题,而提供了一种超长超前锚杆施工方法。
本发明是通过以下技术方案实现的:
超长超前锚杆施工方法,包括以下步骤:
(1)准备工作:包括施作工作室、搭设施工平台、架立定位拱架、钻机就位,其中钻机就位时使钻杆能穿过定位拱架上预留孔,调整钻杆角度,然后将钻机位置固定;
(2)起钻开孔:开孔前根据钻杆角度调整钻机,安装好冲击器和钻头的钻杆穿过定位拱架预留孔后使钻头顶在需钻进的掌子面,用水平尺或连通管调平钻杆,然后将钻杆调为上倾2-3°的角度,固定钻机,然后开风钻进;
(3)接钻杆继续钻进:当钻杆钻进1-2m后,使用专用扳手将钻进围岩中的钻杆尾部固定,反转将外面的钻杆松下,钻机动力器退后1-2m,取新钻杆,两头分别接在已钻进围岩的钻杆尾部和钻机动力器动力头上,动力头正转使接上的钻杆拧紧后卸掉扳手,继续钻进,重复以上步骤直至钻进到设计深度;
(4)洗孔:用高压风从孔底向孔口清理钻渣,使得孔内无钻渣;
(5)退钻杆:当钻进至设计深度后,逐节退出钻杆;
(6)插入超前锚杆:逐节安装超前锚杆,超前锚杆间采用连接套连接,使用管钳将锚杆与连接套拧紧;
(7)超前锚杆注浆:按照现有方法注浆即可。
所述的超前锚杆的长度为1m或者和2m,壁厚为7mm,外径为51mm,内径为37mm。
超前锚杆在使用前打设注浆孔,浆液固结后形成承载能力很强的棚式超前支护,能够有效控制岩体下沉,保证下方掘进的顺利施工。
所述的连接套的长度为18cm,外径为65mm,内径为52mm,内面设内螺纹,螺纹以中间分界反向,螺纹与超前锚杆外螺纹配套。
本发明为隧道超前支护施工提供了一种新的施工方法,解决了普通超前小导管存在的长度过短而出现的支护效果不好,影响施工进度等问题,操作流程简单,易于推广,极大的降低了在后续开挖中发生岩石滑落、塌方的概率,提高了施工的安全性。
具体实施方式:
实施例1
超长超前锚杆施工方法,包括以下步骤:
(1)准备工作:包括施作工作室、搭设施工平台、架立定位拱架、钻机就位,其中钻机就位时使钻杆能穿过定位拱架上预留孔,调整钻杆角度,然后将钻机位置固定;
(2)起钻开孔:开孔前根据钻杆角度调整钻机,安装好冲击器和钻头的钻杆穿过定位拱架预留孔后使钻头顶在需钻进的掌子面,用水平尺或连通管调平钻杆,然后将钻杆调为上倾2°的角度,固定钻机,然后开风钻进;
(3)接钻杆继续钻进:当钻杆钻进1m后,使用专用扳手将钻进围岩中的钻杆尾部固定,反转将外面的钻杆松下,钻机动力器退后1m,取新钻杆,两头分别接在已钻进围岩的钻杆尾部和钻机动力器动力头上,动力头正转使接上的钻杆拧紧后卸掉扳手,继续钻进,重复以上步骤直至钻进到设计深度;
(4)洗孔:用高压风从孔底向孔口清理钻渣,使得孔内无钻渣;
(5)退钻杆:当钻进至设计深度后,逐节退出钻杆;
(6)插入超前锚杆:逐节安装超前锚杆,超前锚杆的长度为1m,壁厚为7mm,外径为51mm,内径为37mm,超前锚杆间采用连接套连接,连接套的长度为18cm,外径为65mm,内径为52mm,内面设内螺纹,螺纹以中间分界反向,螺纹与超前锚杆外螺纹配套,然后使用管钳将锚杆与连接套拧紧,施工时注意相邻两孔锚杆接头错开;
(7)超前锚杆注浆:按照现有方法注浆即可。
实施例2
超长超前锚杆施工方法,包括以下步骤:
(1)准备工作:包括施作工作室、搭设施工平台、架立定位拱架、钻机就位,其中钻机就位时使钻杆能穿过定位拱架上预留孔,调整钻杆角度,然后将钻机位置固定;
(2)起钻开孔:开孔前根据钻杆角度调整钻机,安装好冲击器和钻头的钻杆穿过定位拱架预留孔后使钻头顶在需钻进的掌子面,用水平尺或连通管调平钻杆,然后将钻杆调为上倾3°的角度,固定钻机,然后开风钻进;
(3)接钻杆继续钻进:当钻杆钻进1.5m后,使用专用扳手将钻进围岩中的钻杆尾部固定,反转将外面的钻杆松下,钻机动力器退后1.5m,取新钻杆,两头分别接在已钻进围岩的钻杆尾部和钻机动力器动力头上,动力头正转使接上的钻杆拧紧后卸掉扳手,继续钻进,重复以上步骤直至钻进到设计深度;
(4)洗孔:用高压风从孔底向孔口清理钻渣,使得孔内无钻渣;
(5)退钻杆:当钻进至设计深度后,逐节退出钻杆;
(6)插入超前锚杆:逐节安装超前锚杆,超前锚杆在使用前打设注浆孔,长度为2m,壁厚为7mm,外径为51mm,内径为37mm,超前锚杆间采用连接套连接,使用管钳将锚杆与连接套拧紧;
(7)超前锚杆注浆:按照现有方法注浆即可。
实施例3
超长超前锚杆施工方法,包括以下步骤:
(1)准备工作:包括施作工作室、搭设施工平台、架立定位拱架、钻机就位,其中钻机就位时使钻杆能穿过定位拱架上预留孔,调整钻杆角度,然后将钻机位置固定;
(2)起钻开孔:开孔前根据钻杆角度调整钻机,安装好冲击器和钻头的钻杆穿过定位拱架预留孔后使钻头顶在需钻进的掌子面,用水平尺或连通管调平钻杆,然后将钻杆调为上倾2°的角度,固定钻机,然后开风钻进;
(3)接钻杆继续钻进:当钻杆钻进2m后,使用专用扳手将钻进围岩中的钻杆尾部固定,反转将外面的钻杆松下,钻机动力器退后2m,取新钻杆,两头分别接在已钻进围岩的钻杆尾部和钻机动力器动力头上,动力头正转使接上的钻杆拧紧后卸掉扳手,继续钻进,重复以上步骤直至钻进到设计深度;
(4)洗孔:用高压风从孔底向孔口清理钻渣,使得孔内无钻渣;
(5)退钻杆:当钻进至设计深度后,逐节退出钻杆;
(6)插入超前锚杆:逐节安装超前锚杆,锚杆间采用连接套连接,使用管钳将锚杆与连接套拧紧,施工时注意相邻两孔锚杆接头错开;
(7)超前锚杆注浆:按照现有方法注浆即可。
Claims (4)
1.一种超长超前锚杆施工方法,其特征是包括以下步骤:
(1)准备工作:包括施作工作室、搭设施工平台、架立定位拱架、钻机就位,其中钻机就位时使钻杆能穿过定位拱架上预留孔,调整钻杆角度,然后将钻机位置固定;
(2)起钻开孔:开孔前根据钻杆角度调整钻机,安装好冲击器和钻头的钻杆穿过定位拱架预留孔后使钻头顶在需钻进的掌子面,用水平尺或连通管调平钻杆,然后将钻杆调为上倾2-3°的角度,固定钻机,然后开风钻进;
(3)接钻杆继续钻进:当钻杆钻进1-2m后,使用专用扳手将钻进围岩中的钻杆尾部固定,反转将外面的钻杆松下,钻机动力器退后1-2m,取新钻杆,两头分别接在已钻进围岩的钻杆尾部和钻机动力器动力头上,动力头正转使接上的钻杆拧紧后卸掉扳手,继续钻进,重复以上步骤直至钻进到设计深度;
(4)洗孔:用高压风从孔底向孔口清理钻渣,使得孔内无钻渣;
(5)退钻杆:当钻进至设计深度后,逐节退出钻杆;
(6)插入超前锚杆:逐节安装超前锚杆,超前锚杆间采用连接套连接,使用管钳将锚杆与连接套拧紧;
(7)超前锚杆注浆:按照现有方法注浆即可。
2.根据权利要求1所述的超长超前锚杆施工方法,其特征是所述的超前锚杆的长度为1m或者和2m,壁厚为7mm,外径为51mm,内径为37mm。
3.根据权利要求1或2所述的超长超前锚杆施工方法,其特征是所述的超前锚杆在使用前打设注浆孔。
4.根据权利要求1或2所述的超长超前锚杆施工方法,其特征是所述的连接套的长度为18cm,外径为65mm,内径为52mm,内面设内螺纹,螺纹以中间分界反向,螺纹与超前锚杆外螺纹配套。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101197992A CN102226406B (zh) | 2011-05-10 | 2011-05-10 | 超长超前锚杆施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101197992A CN102226406B (zh) | 2011-05-10 | 2011-05-10 | 超长超前锚杆施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102226406A true CN102226406A (zh) | 2011-10-26 |
CN102226406B CN102226406B (zh) | 2013-09-18 |
Family
ID=44807400
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011101197992A Active CN102226406B (zh) | 2011-05-10 | 2011-05-10 | 超长超前锚杆施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102226406B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102817626A (zh) * | 2012-05-07 | 2012-12-12 | 淮南矿业(集团)有限责任公司 | 液压支架拉运索具和拉运系统 |
CN106014187A (zh) * | 2016-05-23 | 2016-10-12 | 安庆市峰邦工业产品设计有限公司 | 一种管棚钻机反转提钻冲击调节装置 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0213900A (ja) * | 1988-04-26 | 1990-01-18 | Philips Gloeilampenfab:Nv | 密封高ビーム束中性子管 |
JPH0913900A (ja) * | 1995-06-29 | 1997-01-14 | K F C:Kk | ロックボルト打設施工方法 |
US20090191005A1 (en) * | 2008-01-28 | 2009-07-30 | Frank Schmidt | Ground anchor or rock anchor with an anchor tension member comprised of one or more individual elements with corrosion-protected anchor head design |
CN101892844A (zh) * | 2009-05-20 | 2010-11-24 | 深圳市海川实业股份有限公司 | 一种超前锚杆支护的隧道crd开挖方法 |
CN101929340A (zh) * | 2009-12-31 | 2010-12-29 | 平煤建工集团有限公司 | 煤矿井下平斜巷管棚预注浆超前支护施工工艺 |
-
2011
- 2011-05-10 CN CN2011101197992A patent/CN102226406B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0213900A (ja) * | 1988-04-26 | 1990-01-18 | Philips Gloeilampenfab:Nv | 密封高ビーム束中性子管 |
JPH0913900A (ja) * | 1995-06-29 | 1997-01-14 | K F C:Kk | ロックボルト打設施工方法 |
US20090191005A1 (en) * | 2008-01-28 | 2009-07-30 | Frank Schmidt | Ground anchor or rock anchor with an anchor tension member comprised of one or more individual elements with corrosion-protected anchor head design |
CN101892844A (zh) * | 2009-05-20 | 2010-11-24 | 深圳市海川实业股份有限公司 | 一种超前锚杆支护的隧道crd开挖方法 |
CN101929340A (zh) * | 2009-12-31 | 2010-12-29 | 平煤建工集团有限公司 | 煤矿井下平斜巷管棚预注浆超前支护施工工艺 |
Non-Patent Citations (5)
Title |
---|
何穗燕: "浅谈隧洞开挖超前加固技术", 《广东水利水电》 * |
吴大炜: "浅谈黄土浅埋段隧道的开挖及支护", 《科协论坛(下半月)》 * |
吴建东等: "浅析超前锚固施工", 《工程建设与设计》 * |
宋涛: "TBM不良地质地段施工技术", 《湖南水利水电》 * |
罗建兴: "自进式锚杆在隧洞塌方处理中的应用", 《甘肃水利水电技术》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102817626A (zh) * | 2012-05-07 | 2012-12-12 | 淮南矿业(集团)有限责任公司 | 液压支架拉运索具和拉运系统 |
CN102817626B (zh) * | 2012-05-07 | 2014-09-17 | 淮南矿业(集团)有限责任公司 | 液压支架拉运索具和拉运系统 |
CN106014187A (zh) * | 2016-05-23 | 2016-10-12 | 安庆市峰邦工业产品设计有限公司 | 一种管棚钻机反转提钻冲击调节装置 |
Also Published As
Publication number | Publication date |
---|---|
CN102226406B (zh) | 2013-09-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10794183B2 (en) | Self-drilling differential grouting combined bolt and anchoring method therefor | |
CN100567698C (zh) | 隧道超前支护风循环钻进施工方法及钻具 | |
CN102174894A (zh) | 跟进式管棚施工方法 | |
CN106592588A (zh) | 一种机械扩孔扩大头锚索施工方法 | |
CN110409461A (zh) | 一种基于装配式大直径管桩的基坑支护施工方法 | |
CN107288671A (zh) | 松软破碎煤岩体钻封注一体化可接长锚杆及其施工方法 | |
CN109183857B (zh) | 一种抗浮锚杆施工方法 | |
CN105672316A (zh) | 钢桩下沉减阻装置及施工方法 | |
CN102226406B (zh) | 超长超前锚杆施工方法 | |
CN206503562U (zh) | 一种冲击回转挤密钻头 | |
CN204572026U (zh) | 一种多功能锚杆装置 | |
CN207122284U (zh) | 扩地钻具 | |
CN103628814A (zh) | 一种两用式同心跟管钻具 | |
CN203129151U (zh) | 钻孔注浆同步的注浆头 | |
CN102425428A (zh) | 巷道迎头极破碎顶板控制方法 | |
CN102182469B (zh) | 一种大跨隧道中洞二次衬砌防开裂的施工方法 | |
CN102235151B (zh) | 砂卵石漂石层超前成孔方法 | |
CN109519184B (zh) | 一种超前钻孔控制盾构机姿态漂移的施工方法 | |
CN204551463U (zh) | 一种可旋转变向和回收的锚杆 | |
CN106761845A (zh) | 一种软岩大变形隧道钢架的锁脚工艺 | |
CN105821896A (zh) | 一种人工桩基施工成孔方法 | |
CN111005379A (zh) | 清除钢筋混凝土灌注桩桩体的施工方法 | |
CN202730756U (zh) | 一种用于钻孔灌注桩施工的套管接连装置 | |
CN212104063U (zh) | 灌浆式双锚头锚杆 | |
CN101270578A (zh) | 跟进式锚索二次注浆施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |