CN101818570B - 高层建筑梁式结构转换层的施工方法 - Google Patents
高层建筑梁式结构转换层的施工方法 Download PDFInfo
- Publication number
- CN101818570B CN101818570B CN2010101358561A CN201010135856A CN101818570B CN 101818570 B CN101818570 B CN 101818570B CN 2010101358561 A CN2010101358561 A CN 2010101358561A CN 201010135856 A CN201010135856 A CN 201010135856A CN 101818570 B CN101818570 B CN 101818570B
- Authority
- CN
- China
- Prior art keywords
- muscle
- concrete
- concreting
- shelf
- row
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明公开了一种高层建筑梁式结构转换层的施工方法,包括模板支撑体系的设计与布置、钢筋工程、混凝土工程。本发明施工效率高、质量容易控制,造价低,施工方便。
Description
技术领域:
本发明涉及一种高层建筑梁式结构转换层的施工方法。
背景技术:
由于转换层具有传力直接、受力明确、造价较节省的优点,在实际中得到了较广泛的推广应用,是目前高层建筑中实现垂直转换最常用的结构形式。因此如何采取合理的施工方法,保证施工质量达到设计要求,是关系到建筑物整体结构质量的重大问题。
发明内容:
本发明的目的在于提供一种施工效率高、质量容易控制的高层建筑梁式结构转换层的施工方法。
本发明的技术解决方案是:
一种高层建筑梁式结构转换层的施工方法,包括模板支撑体系的设计与布置、钢筋工程、混凝土工程,其特征是:
(1)模板支撑体系的设计与布置:混凝土浇筑前,应检查支撑的牢固性,并严格按照施工方案要求搭设,支撑楼板的木龙骨采用80mm×80mm松杂木枋,间距450mm,面铺18mm厚胶合板,所有板缝用胶带纸封闭,支撑系统采用门式脚手架加可调底座和顶托,门架间距900~950mm,中间用交叉支撑连接,在两层门架竖向连接处加水平连接杆一道,材料用φ48mm钢管和扣件;转换大梁的木龙骨采用80×100mm松杂木枋,间距400mm;支撑系统搭设φ48mm满堂钢管脚手架,立杆沿梁方向间距500mm;转换梁的侧模,则沿梁高每隔450mm设水平加固钢管一道,配合对拉螺栓使用;跨度大于4m的梁应起拱3L%;结构转换层位于第二层,为了确保支撑牢固,在筏板基础以上从负二层至负一层设独立支撑,间距500mm,范围同转换层满堂红支撑,首层梁板支撑在转换层顶梁板施工完毕后7d内不拆除;
混凝土浇筑过程中,应派专人负责看护支撑跑位、支撑挠度、侧模跑位及挠度,随时采取处理措施;
(2)钢筋工程:
钢筋翻样与下料:
大梁的最上一排面筋向下弯并锚至底筋以上;底筋的最下一排主筋靠柱边上弯25d,其余主筋均不弯起,负筋亦不弯起;大梁主筋接头全部采用闪光对焊;梁上部的主筋接头设置在跨中1/3跨长内,下部主筋接头设在靠近支座1/3跨长内;
钢筋的安装与就位:
大梁钢筋的安放在梁底板铺设结束后进行;先在梁底上方搭设临时钢管搁架,搁架立杆支撑在梁两侧的楼板模板上,搁架下横杆高出梁底30~35cm,上横杆比梁面高10~15cm。在搁架下横杆上铺设梁的最下一排纵筋,之后,按放一排横杆铺设一排纵筋的原则铺设完梁下部的全部主筋,横杆与搁架立杆扣接并贴紧下层纵筋;在搁架的上横杆上铺设梁最上一排面筋,用φ6钢筋制成的“S”钩在上排面筋上挂起上部第二排纵筋,同样用“S”钩在第二排纵筋上挂起第三排纵筋,直至梁上部纵筋全部逐层挂起;主筋铺设完后,套箍筋、放吊筋:由下而上逐根拆除搁架下横杆,同时将下部纵筋与箍筋绑扎固定:同样由下而上把上部挂起的纵筋与箍筋绑扎固定:放置梁底保护层垫块;松动扣件,放下搁架的上横杆使骨架就位;最后,穿负筋、腰筋、接筋,绑扎新生柱插筋及洞口加固筋;
(3)混凝土工程:
混凝土的泵送与浇筑:
本转换层梁板采用商品混凝土泵送运输浇筑,混凝土坍落度控制在15~16cm;混凝土的浇筑宜采用从中部开始、逐渐向两边扩展的方式进行浇筑;混凝土浇筑前,应清理干净模板内的杂物,并洒水湿润;转换层混凝土浇筑根据设计要求一次浇筑完毕,不留施工缝;混凝土浇筑时分层进行浇筑,每层浇筑厚度控制在500mm左右,每层间隔时间1.5~2h,第一次浇筑混凝土时,只浇筑无转换大梁部分剪力墙,浇筑至梁底10cm位置,有转换大梁部分不浇筑;第二次浇筑混凝土时,有转换大梁部分剪力墙、柱及梁板混凝土一次浇筑完毕,按振动棒的有效范围500mm来控制振捣质量,振动棒插点为梅花状,棒距控制在500mm;
混凝土的裂缝控制:
控制混凝土坍落度,混凝土坍落度不大于160mm;在梁柱相交的核心区混凝土浇筑完毕1~1.5h后并在初凝前,用直径为35mm的振动棒二次振捣,加强混凝土密实度,提高其抗裂性;对楼板混凝土表面抹光压实;加强养护措施。砼浇筑完毕后,在楼面密铺麻袋,保持湿润。大梁砼浇筑完毕后3d后拆除侧模,混凝土表面保持湿润,使混凝土处于潮湿状态养护14d。
本发明施工效率高、质量容易控制,造价低,施工方便。
下面结合实施例对本发明作进一步说明。
具体实施方式:
一种高层建筑梁式结构转换层的施工方法,包括模板支撑体系的设计与布置、钢筋工程、混凝土工程;
(1)模板支撑体系的设计与布置:混凝土浇筑前,应检查支撑的牢固性,并严格按照施工方案要求搭设,支撑楼板的木龙骨采用80mm×80mm松杂木枋,间距450mm,面铺18mm厚胶合板,所有板缝用胶带纸封闭,支撑系统采用门式脚手架加可调底座和顶托,门架间距900~950mm,中间用交叉支撑连接,在两层门架竖向连接处加水平连接杆一道,材料用φ48mm钢管和扣件;转换大梁的木龙骨采用80×100mm松杂木枋,间距400mm;支撑系统搭设φ48mm满堂钢管脚手架,立杆沿梁方向间距500mm;转换梁的侧模,则沿梁高每隔450mm设水平加固钢管一道,配合对拉螺栓使用;跨度大于4m的梁应起拱3L%;结构转换层位于第二层,为了确保支撑牢固,在筏板基础以上从负二层至负一层设独立支撑,间距500mm,范围同转换层满堂红支撑,首层梁板支撑在转换层顶梁板施工完毕后7d内不拆除;
混凝土浇筑过程中,应派专人负责看护支撑跑位、支撑挠度、侧模跑位及挠度,随时采取处理措施;
(2)钢筋工程:
钢筋翻样与下料:
大梁的最上一排面筋向下弯并锚至底筋以上;底筋的最下一排主筋靠柱边上弯25d,其余主筋均不弯起,负筋亦不弯起;大梁主筋接头全部采用闪光对焊;梁上部的主筋接头设置在跨中1/3跨长内,下部主筋接头设在靠近支座1/3跨长内;
钢筋的安装与就位:
大梁钢筋的安放在梁底板铺设结束后进行;先在梁底上方搭设临时钢管搁架,搁架立杆支撑在梁两侧的楼板模板上,搁架下横杆高出梁底30~35cm,上横杆比梁面高10~15cm。在搁架下横杆上铺设梁的最下一排纵筋,之后,按放一排横杆铺设一排纵筋的原则铺设完梁下部的全部主筋,横杆与搁架立杆扣接并贴紧下层纵筋;在搁架的上横杆上铺设梁最上一排面筋,用φ6钢筋制成的“S”钩在上排面筋上挂起上部第二排纵筋,同样用“S”钩在第二排纵筋上挂起第三排纵筋,直至梁上部纵筋全部逐层挂起;主筋铺设完后,套箍筋、放吊筋:由下而上逐根拆除搁架下横杆,同时将下部纵筋与箍筋绑扎固定:同样由下而上把上部挂起的纵筋与箍筋绑扎固定:放置梁底保护层垫块;松动扣件,放下搁架的上横杆使骨架就位;最后,穿负筋、腰筋、接筋,绑扎新生柱插筋及洞口加固筋;
(3)混凝土工程:
混凝土的泵送与浇筑:
本转换层梁板采用商品混凝土泵送运输浇筑,混凝土坍落度控制在15~16cm;混凝土的浇筑宜采用从中部开始、逐渐向两边扩展的方式进行浇筑;混凝土浇筑前,应清理干净模板内的杂物,并洒水湿润;转换层混凝土浇筑根据设计要求一次浇筑完毕,不留施工缝;混凝土浇筑时分层进行浇筑,每层浇筑厚度控制在500mm左右,每层间隔时间1.5~2h,第一次浇筑混凝土时,只浇筑无转换大梁部分剪力墙,浇筑至梁底10cm位置,有转换大梁部分不浇筑;第二次浇筑混凝土时,有转换大梁部分剪力墙、柱及梁板混凝土一次浇筑完毕,按振动棒的有效范围500mm来控制振捣质量,振动棒插点为梅花状,棒距控制在500mm;
混凝土的裂缝控制:
控制混凝土坍落度,混凝土坍落度不大于160mm;在梁柱相交的核心区混凝土浇筑完毕1~1.5h后并在初凝前,用直径为35mm的振动棒二次振捣,加强混凝土密实度,提高其抗裂性;对楼板混凝土表面抹光压实;加强养护措施。砼浇筑完毕后,在楼面密铺麻袋,保持湿润。大梁砼浇筑完毕后3d后拆除侧模,混凝土表面保持湿润,使混凝土处于潮湿状态养护14d。
Claims (1)
1.一种高层建筑梁式结构转换层的施工方法,包括模板支撑体系的设计与布置、钢筋工程、混凝土工程,其特征是:
(1)模板支撑体系的设计与布置:混凝土浇筑前,应检查支撑的牢固性,并严格按照施工方案要求搭设,支撑楼板的木龙骨采用80mm×80mm松杂木枋,间距450mm,面铺18mm厚胶合板,所有板缝用胶带纸封闭,支撑系统采用门式脚手架加可调底座和顶托,门架间距900~950mm,中间用交叉支撑连接,在两层门架竖向连接处加水平连接杆一道,材料用φ48mm钢管和扣件;转换大梁的木龙骨采用80×100mm松杂木枋,间距400mm;支撑系统搭设φ48mm满堂钢管脚手架,立杆沿梁方向间距500mm;转换梁的侧模,则沿梁高每隔450mm设水平加固钢管一道,配合对拉螺栓使用;跨度大于4m的梁应起拱3L%;结构转换层位于第二层,为了确保支撑牢固,在筏板基础以上从负二层至负一层设独立支撑,间距500mm,范围同转换层满堂红支撑,首层梁板支撑在转换层顶梁板施工完毕后7d内不拆除;
混凝土浇筑过程中,应派专人负责看护支撑跑位、支撑挠度、侧模跑位及挠度,随时采取处理措施;
(2)钢筋工程:
钢筋翻样与下料:
大梁的最上一排面筋向下弯并锚至底筋以上;底筋的最下一排主筋靠柱边上弯25D,其余主筋均不弯起,负筋亦不弯起;大梁主筋接头全部采用闪光对焊;梁上部的主筋接头设置在跨中1/3跨长内,下部主筋接头设在靠近支座1/3跨长内;
钢筋的安装与就位:
大梁钢筋的安放在梁底板铺设结束后进行;先在梁底上方搭设临时钢管搁架,搁架立杆支撑在梁两侧的楼板模板上,搁架下横杆高出梁底30~35cm,上横杆比梁面高10~15cm。在搁架下横杆上铺设梁的最下一排纵筋,之后,按放一排横杆铺设一排纵筋的原则铺设完梁下部的全部主筋,横杆与搁架立杆扣接并贴紧下层纵筋;在搁架的上横杆上铺设梁最上一排面筋,用φ6钢筋制成的“S”钩在上排面筋上挂起上部第二排纵筋,同样用“S”钩在第二排纵筋上挂起第三排纵筋,直至梁上部纵筋全部逐层挂起;主筋铺设完后,套箍筋、放吊筋:由下而上逐根拆除搁架下横杆,同时将下部纵筋与箍筋绑扎固定:同样由下而上把上部挂起的纵筋与箍筋绑扎固定:放置梁底保护层垫块;松动扣件,放下搁架的上横杆使骨架就位;最后,穿负筋、腰筋、接筋,绑扎新生柱插筋及洞口加固筋;
(3)混凝土工程:
混凝土的泵送与浇筑:
本转换层梁板采用商品混凝土泵送运输浇筑,混凝土坍落度控制在15~16cm;混凝土的浇筑宜采用从中部开始、逐渐向两边扩展的方式进行浇筑;混凝土浇筑前,应清理干净模板内的杂物,并洒水湿润;转换层混凝土浇筑根据设计要求一次浇筑完毕,不留施工缝;混凝土浇筑时分层进行浇筑,每层浇筑厚度控制在500mm左右,每层间隔时间1.5~2h,第一次浇筑混凝土时,只浇筑无转换大梁部分剪力墙,浇筑至梁底10cm位置,有转换大梁部分不浇筑;第二次浇筑混凝土时,有转换大梁部分剪力墙、柱及梁板混凝土一次浇筑完毕,按振动棒的有效范围500mm来控制振捣质量,振动棒插点为梅花状,棒距控制在500mm;
混凝土的裂缝控制:
控制混凝土坍落度,混凝土坍落度不大于160mm;在梁柱相交的核心区混凝土浇筑完毕1~1.5h后并在初凝前,用直径为35mm的振动棒二次振捣,加强混凝土密实度,提高其抗裂性;对楼板混凝土表面抹光压实;加强养护措施;砼浇筑完毕后,在楼面密铺麻袋,保持湿润;大梁砼浇筑完毕后3d后拆除侧模,混凝土表面保持湿润,使混凝土处于潮湿状态养护14d。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101358561A CN101818570B (zh) | 2010-03-23 | 2010-03-23 | 高层建筑梁式结构转换层的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101358561A CN101818570B (zh) | 2010-03-23 | 2010-03-23 | 高层建筑梁式结构转换层的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101818570A CN101818570A (zh) | 2010-09-01 |
CN101818570B true CN101818570B (zh) | 2011-06-15 |
Family
ID=42653824
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101358561A Expired - Fee Related CN101818570B (zh) | 2010-03-23 | 2010-03-23 | 高层建筑梁式结构转换层的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101818570B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836602A (zh) * | 2017-01-19 | 2017-06-13 | 杭州江润科技有限公司 | 大跨度钢筋混凝土无柱式悬挂楼板的施工方法 |
CN106906897A (zh) * | 2017-03-31 | 2017-06-30 | 安徽金鹏建设集团股份有限公司 | 一种高层建筑梁氏结构转换层的施工方法 |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102619331B (zh) * | 2011-03-08 | 2014-07-16 | 青光绪 | 高层建筑梁式转换层钢管支撑叠合浇筑一次成型施工方法 |
CN102758524A (zh) * | 2011-04-27 | 2012-10-31 | 五冶集团上海有限公司 | 苯加氢工程钢筋制作及安装方法 |
CN102587688B (zh) * | 2012-03-20 | 2014-05-14 | 中建三局第二建设工程有限责任公司 | 下部原有结构加固与上部新加建结构同时施工的方法 |
CN103015716A (zh) * | 2012-11-28 | 2013-04-03 | 泰兴市第一建筑安装工程有限公司 | 一种超宽截面转换梁钢筋工程施工方法 |
CN104110136A (zh) * | 2013-04-18 | 2014-10-22 | 中冶天工上海十三冶建设有限公司 | 结构转换层内含h型钢大梁的混凝土浇筑模板搭设方法 |
CN103526928B (zh) * | 2013-09-22 | 2017-02-22 | 中国建筑第八工程局有限公司 | 高层悬挑转换空间框架结构施工方法 |
CN103821359A (zh) * | 2014-02-28 | 2014-05-28 | 中天建设集团有限公司 | 大截面混凝土梁分层浇筑施工工法 |
CN104831932B (zh) * | 2015-05-27 | 2018-06-15 | 浙江宏超建设集团有限公司 | 一种高标号混凝土柱脚的施工工艺 |
CN105672568B (zh) * | 2016-03-29 | 2018-01-16 | 济南长兴建设集团有限公司 | 超大截面劲性混凝土转换梁分层浇筑施工方法 |
CN108019040B (zh) * | 2017-05-10 | 2019-08-02 | 江苏省华建建设股份有限公司 | 一种高层建筑转换层贝雷架平台施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101041974A (zh) * | 2007-04-19 | 2007-09-26 | 浙江省建工集团有限责任公司 | 结构转换层型钢砼大梁挂模施工方法 |
CN101333825A (zh) * | 2008-08-06 | 2008-12-31 | 北京首钢建设集团有限公司 | 高层建筑框支型钢砼梁式结构转换层施工方法 |
CN101353912A (zh) * | 2008-08-28 | 2009-01-28 | 温州建设集团公司 | 结构转换层混凝土大梁钢托架模板支撑施工方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001227094A (ja) * | 2000-02-21 | 2001-08-24 | Ki Kyo | 鉄骨ビルの階床構造 |
-
2010
- 2010-03-23 CN CN2010101358561A patent/CN101818570B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101041974A (zh) * | 2007-04-19 | 2007-09-26 | 浙江省建工集团有限责任公司 | 结构转换层型钢砼大梁挂模施工方法 |
CN101333825A (zh) * | 2008-08-06 | 2008-12-31 | 北京首钢建设集团有限公司 | 高层建筑框支型钢砼梁式结构转换层施工方法 |
CN101353912A (zh) * | 2008-08-28 | 2009-01-28 | 温州建设集团公司 | 结构转换层混凝土大梁钢托架模板支撑施工方法 |
Non-Patent Citations (1)
Title |
---|
JP特开2001-227094A 2001.08.24 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836602A (zh) * | 2017-01-19 | 2017-06-13 | 杭州江润科技有限公司 | 大跨度钢筋混凝土无柱式悬挂楼板的施工方法 |
CN106836602B (zh) * | 2017-01-19 | 2018-04-27 | 杭州江润科技有限公司 | 大跨度钢筋混凝土无柱式悬挂楼板的施工方法 |
CN106906897A (zh) * | 2017-03-31 | 2017-06-30 | 安徽金鹏建设集团股份有限公司 | 一种高层建筑梁氏结构转换层的施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN101818570A (zh) | 2010-09-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101818570B (zh) | 高层建筑梁式结构转换层的施工方法 | |
CN103015565B (zh) | 预制装配整体式钢筋混凝土承重墙及建筑施工方法 | |
CN103046746B (zh) | 高层建筑结构转换梁钢筋施工方法 | |
CN102493341A (zh) | 铁路空心薄壁高墩无支架翻模的施工方法 | |
CN105863253B (zh) | 整体支模异步浇筑楼梯间墙柱支模体系及施工方法 | |
CN105178603A (zh) | 一种eps聚苯免拆模板混凝土楼盖板施工工艺方法 | |
CN105133755B (zh) | 一种钢筋焊接网架复合剪力墙的施工方法及剪力墙结构 | |
CN104480922B (zh) | 空间桁架支模系统及其施工方法 | |
CN102619331B (zh) | 高层建筑梁式转换层钢管支撑叠合浇筑一次成型施工方法 | |
CN108005387A (zh) | 一种装配式墙板与短肢剪力墙现浇主体同步施工方法 | |
CN100460613C (zh) | 悬浮架施工方法 | |
CN206428968U (zh) | 一种钢筋桁架式无支撑模板体系 | |
CN106703407A (zh) | 悬挑梁板双层型钢支撑架施工方法 | |
CN103806659B (zh) | 超厚预应力转换板单层综合支撑与控裂控温施工工艺 | |
CN206438529U (zh) | 梁板式筏型基础模板支撑结构 | |
CN107401279A (zh) | 一次性整体浇筑楼梯间墙梯组合钢模板安装施工方法 | |
CN101614039B (zh) | 现浇剪力墙结构体系模板工程逆序施工方法 | |
CN103122691A (zh) | 塔吊标准节支承高空支模钢平台结构及施工方法 | |
CN110219422A (zh) | 抗震混凝土楼梯设计方法 | |
CN2816164Y (zh) | 现浇钢筋砼空中连廊 | |
CN203034799U (zh) | 塔吊标准节支承高空支模钢平台结构 | |
CN103397778A (zh) | 高层商住楼结构转换层施工方法 | |
CN103147573A (zh) | 游泳馆顶梁板高支模施工方法 | |
CN106907022B (zh) | 一种高空斜拉式型钢操作平台模板支撑体系施工工艺 | |
CN109853928A (zh) | 搭设电梯井剪力墙浇筑模板的内架式工作台及其架设方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110615 Termination date: 20150323 |
|
EXPY | Termination of patent right or utility model |