CN101818479B - 移动模架空中退行解体拆除施工工艺 - Google Patents

移动模架空中退行解体拆除施工工艺 Download PDF

Info

Publication number
CN101818479B
CN101818479B CN200910024212A CN200910024212A CN101818479B CN 101818479 B CN101818479 B CN 101818479B CN 200910024212 A CN200910024212 A CN 200910024212A CN 200910024212 A CN200910024212 A CN 200910024212A CN 101818479 B CN101818479 B CN 101818479B
Authority
CN
China
Prior art keywords
girder
launching nose
remove
hoist engine
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910024212A
Other languages
English (en)
Other versions
CN101818479A (zh
Inventor
孙艳明
胡君琪
揣国新
林帆
施津安
蒲中花
高辉
齐鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Second Engineering Co Ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN200910024212A priority Critical patent/CN101818479B/zh
Publication of CN101818479A publication Critical patent/CN101818479A/zh
Application granted granted Critical
Publication of CN101818479B publication Critical patent/CN101818479B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明属于桥梁施工工艺领域,应用于现浇箱梁移动模架施工作业中,具体来讲是在现浇箱梁采用移动模架施工完后,移动模架空中退行解体拆除施工工艺,其特征是:包括桥梁两侧需要拆除的后导梁、主梁、前导梁、牛腿、小车、外模板、模板横梁、中横梁、牛腿对拉精扎螺纹钢;利用小车从牛腿上横移打开移动模架,在混凝土箱梁上安装卷扬机,利用卷扬机和汽车吊牵引吊牵拆除外模板,依次从上到下拆除模板横梁和中横梁,只留后导梁、主梁和前导梁,然后拆除移动模架主梁,最后拆除最后一节主梁和前导梁。此工艺加快施工进度、减少施工设备、保证施工安全和降低施工成本。

Description

移动模架空中退行解体拆除施工工艺
技术领域
本发明属于桥梁施工工艺领域,应用于现浇箱梁移动模架施工作业中,具体来讲是在现浇箱梁采用移动模架施工完后,移动模架空中退行解体拆除施工工艺。
背景技术
随着经济的发展,跨江、跨河、跨海大桥不断增多,移动模架以其独特的优势在工程中被广泛应用,施工工艺比较成熟,但移动模架拆除一直没有好的经验可以借鉴。传统的移动模架拆除方法是先平整场地或者搭设施工平台,然后将移动模架下放,在陆地或者平台上用吊机解体拆除,这种方法适用于低墩。当墩身较高时,也有将移动模架全主梁高空锁定拆除,但锚固和下放主梁、前后导梁需要在混凝土箱梁上预留很多预留孔,对混凝土箱梁破坏较大,同时多次转移拆除设备,浪费时间。
发明内容
本发明的目的是提供一种新型的移动模架空中退行解体拆除施工工艺,以便加快施工进度、减少施工设备、保证施工安全和降低施工成本。
本发明的技术方案是:设计一种移动模架空中退行解体拆除施工工艺,其特征是:包括桥梁两侧需要拆除的后导梁、主梁、前导梁、牛腿、小车、外模板、模板横梁、中横梁、牛腿对拉精扎螺纹钢;利用小车从牛腿上横移打开移动模架,在混凝土箱梁上安装卷扬机,利用卷扬机和汽车吊牵引吊牵拆除外模板,依次从上到下拆除模板横梁和中横梁,只留后导梁、主梁和前导梁,然后拆除移动模架主梁,最后拆除最后一节主梁和前导梁。
所述的移动模架主梁拆除方法是:在后导梁位置固定好卷扬机,利用滑轮组和卷扬机的箱梁预留孔拆除后导梁,保持卷扬机和滑轮组不动,开动小车上的纵移油缸,将移动模架主梁退行,当第一节主梁退行到滑轮组箱梁预留孔的吊点位置,挂好滑轮组,启动卷扬机,将滑轮组钢绳绷紧,之后拆除主梁之间的连接螺栓或插销,卷扬机缓慢下放,将主梁下放运走;之后采用相同的方法拆除后面各节段主梁。
所述的最后一节主梁和前导梁拆除方法是:利用八组扁担梁和吊杆将两侧的主梁和前导梁分别锚固在混凝土箱梁上,每侧锚固四个锚点,在主梁与墩身之间以及前导梁与墩身之间各设两道撑杆,在两侧的梁体之间设置四道拉杆;将剩余一节主梁和前导梁锚固好后,拆除牛腿和小车;转移卷扬机,从前端向后依次拆除各节前导梁,最后拆除剩余的一节主梁。
本发明的技术特点是:由于移动模架拆除顺序为:准备工作→拆除模板、后导梁、中横梁→移动模架退行,依次拆除各节段主梁→锚固最后一节主梁、前导梁→拆除牛腿、小车→依次从前向后拆除前导梁→拆除最后一节主梁。移动模架主梁在退行拆除过程中,移动模架的重心始终在两个墩之间,移动模架不会出现纵向失稳,小车上的行走轮对主梁有锁定作用,避免移动模架在打开状态下出现侧向失稳。移动模架在牛腿上横移打开,先将模板、模板支撑以及部分中横梁在混凝土箱梁上用吊机拆除,只留前后导梁和主梁,移动模架主梁拆除采用了退行技术,多节主梁在同一个位置拆除,减少了锚固点和下放预留孔,避免多次转移拆除设备,节约了拆除时间。
附图说明
下面结合附图和实施例对本发明做进一步说明。
图1是本发明实施例总体布置示意图;
图2是图1中在拆除模板、模板支撑以及部分中横梁示意图;
图3是图1中在拆除移动模架主梁示意图;
图4是图3的剖面图;
图5是图1中在拆除最后一节主梁和前导梁示意图;
图6是图5的剖面图。
图中:1、后导梁;2、主梁;3、前导梁;4、牛腿;5、小车;6、墩身;7、外模板;8、模板横梁;9、中横梁;10、汽车吊牵引;11、卷扬机;12、滑轮组;13、牛腿对拉精轧螺纹钢;14、箱梁预留孔;15、锚点;16、撑杆;17、拉杆;18、吊杆;19、扁担梁。
具体实施例
如图1、图2所示,移动模架空中退行解体拆除施工工艺,包括桥梁两侧需要拆除的后导梁1、主梁2、前导梁3、牛腿4、小车5、外模板7、模板横梁8、中横梁9、牛腿对拉精扎螺纹钢13;利用小车5从牛腿4上横移打开移动模架,在混凝土箱梁上安装卷扬机11,利用卷扬机11和汽车吊牵引10吊牵拆除外模板7,依次从上到下拆除模板横梁8和中横梁9,只留后导梁1、主梁2和前导梁3,然后拆除移动模架主梁2,最后拆除最后一节主梁2和前导梁3。
移动模架主梁2拆除(不含最后一节主梁2)如图3、图4所示。在最后拆除的一节后导梁1位置固定好卷扬机11,利用滑轮组12和卷扬机11拆除最后一节后导梁1,这节后导梁1拆除后卷扬机11和滑轮组12不移动,此时开动小车5上的纵移油缸,将移动模架主梁2退行,当第一节主梁2吊点位置退行到滑轮组12位置,挂好滑轮组12,启动卷扬机11,将滑轮组12钢绳绷紧,之后拆除主梁2之间的连接螺栓或插销,卷扬机11缓慢下放,将主梁2下放到船上或者挂车上运走。之后后面的各节段主梁2拆除方法与第一节主梁2拆除方法相同,最后留一节主梁2和前导梁3。
移动模架最后一节主梁2和前导梁3拆除如图5、图6所示。利用八组扁担梁19和吊杆18将两侧的主梁2和前导梁3分别锚固在混凝土箱梁上,每侧锚固四个锚点15,为了保证两侧梁体的稳定性,在主梁2与墩身6之间以及前导梁3与墩身6之间各设两道撑杆16,在两侧的梁体之间设置四道拉杆17。剩余一节主梁2和前导梁3锚固好后,拆除牛腿4和小车5。转移卷扬机11,从前端向后依次拆除各节前导梁3,最后拆除剩余的一节主梁2。

Claims (2)

1.移动模架空中退行解体拆除施工工艺,其特征是:包括桥梁两侧需要拆除的后导梁(1)、主梁(2)、前导梁(3)、牛腿(4)、小车(5)、外模板(7)、模板横梁(8)、中横梁(9)、牛腿对拉精扎螺纹钢(13);利用小车(5)从牛腿(4)上横移打开移动模架,在混凝土箱梁上安装卷扬机(11),利用卷扬机(11)和汽车吊牵引(10)吊牵拆除外模板(7),依次从上到下拆除模板横梁(8)和中横梁(9),只留后导梁(1)、主梁(2)和前导梁(3),然后拆除移动模架主梁(2),最后拆除最后一节主梁(2)和前导梁(3);所述的移动模架主梁(2)拆除方法是:在后导梁(1)位置固定好卷扬机(11),利用滑轮组(12)和卷扬机(11)的箱梁预留孔(14)拆除后导梁(1),保持卷扬机(11)和滑轮组(12)不动,开动小车(5)上的纵移油缸,将移动模架主梁(2)退行,当第一节主梁(2)退行到滑轮组(12)箱梁预留孔(14)的吊点位置,挂好滑轮组(12),启动卷扬机(11),将滑轮组(12)钢绳绷紧,之后拆除主梁(2)之间的连接螺栓或插销,卷扬机(11)缓慢下放,将主梁(2)下放运走;之后采用相同的方法拆除后面各节段主梁(2)。
2.根据权利要求1所述的移动模架空中退行解体拆除施工工艺,其特征是:所述的最后一节主梁(2)和前导梁(3)拆除方法是:利用八组扁担梁(19)和吊杆(18)将两侧的主梁(2)和前导梁(3)分别锚固在混凝土箱梁上,每侧锚固四个锚点(15),在主梁(2)与墩身(6)之间以及前导梁(3)与墩身(6)之间各设两道撑杆(16),在两侧的梁体之间设置四道拉杆(17);将剩余一节主梁(2)和前导梁(3)锚固好后,拆除牛腿(4)和小车(5),转移卷扬机(11),从前端向后依次拆除各节前导梁(3),最后拆除剩余的一节主梁(2)。
CN200910024212A 2009-10-10 2009-10-10 移动模架空中退行解体拆除施工工艺 Expired - Fee Related CN101818479B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910024212A CN101818479B (zh) 2009-10-10 2009-10-10 移动模架空中退行解体拆除施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910024212A CN101818479B (zh) 2009-10-10 2009-10-10 移动模架空中退行解体拆除施工工艺

Publications (2)

Publication Number Publication Date
CN101818479A CN101818479A (zh) 2010-09-01
CN101818479B true CN101818479B (zh) 2012-08-29

Family

ID=42653736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910024212A Expired - Fee Related CN101818479B (zh) 2009-10-10 2009-10-10 移动模架空中退行解体拆除施工工艺

Country Status (1)

Country Link
CN (1) CN101818479B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040991B (zh) * 2015-07-03 2017-03-29 中国建筑第八工程局有限公司 大跨度钢结构分段吊装的支撑结构及支撑方法
CN105648912B (zh) * 2015-12-11 2017-04-19 中铁大桥局集团第二工程有限公司 一种整体转运、拼装移动模架的施工方法
CN105887694A (zh) * 2016-05-20 2016-08-24 中交第航务工程局有限公司 桥梁盖梁底模拆除装置
CN106192761B (zh) * 2016-08-12 2017-09-12 中铁二十五局集团第三工程有限公司 一种在桥隧狭短过渡段拆解移动模架的方法
CN106436581A (zh) * 2016-10-10 2017-02-22 山东省路桥集团有限公司 上行式移动模架原位模块化快速拆卸施工方法
CN108611981B (zh) * 2018-05-22 2020-04-24 江苏省交通工程集团有限公司 一种简单拆除的门洞支架及其拆除方法
CN113152287B (zh) * 2021-03-19 2022-12-27 中铁大桥局集团第一工程有限公司 一种下行式移动模架拆除方法及装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040009781A (ko) * 2002-07-25 2004-01-31 김남식 교량용 상부받침 지지장치
CN101122116A (zh) * 2007-09-15 2008-02-13 中铁三局集团有限公司 过隧道箱梁翼缘板补浇筑方法及其专用模架装置
CN101158146A (zh) * 2007-11-20 2008-04-09 中铁大桥局集团第二工程有限公司 斜拉桥主梁滑动模架系统及施工方法
KR20090015624A (ko) * 2007-08-09 2009-02-12 주식회사 동아기술공사 I형 콘크리트 빔의 하부플랜지에 조립식으로 설치된무지보거푸집 및 이를 이용한 교량상부슬래브 시공과무지보거푸집해체방법

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040009781A (ko) * 2002-07-25 2004-01-31 김남식 교량용 상부받침 지지장치
KR20090015624A (ko) * 2007-08-09 2009-02-12 주식회사 동아기술공사 I형 콘크리트 빔의 하부플랜지에 조립식으로 설치된무지보거푸집 및 이를 이용한 교량상부슬래브 시공과무지보거푸집해체방법
CN101122116A (zh) * 2007-09-15 2008-02-13 中铁三局集团有限公司 过隧道箱梁翼缘板补浇筑方法及其专用模架装置
CN101158146A (zh) * 2007-11-20 2008-04-09 中铁大桥局集团第二工程有限公司 斜拉桥主梁滑动模架系统及施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林世发、周文.武汉天兴洲公铁两用长江大桥移动模架拆除施工技术.《桥梁建设》.2008,(第2期),5-8页. *

Also Published As

Publication number Publication date
CN101818479A (zh) 2010-09-01

Similar Documents

Publication Publication Date Title
CN101818479B (zh) 移动模架空中退行解体拆除施工工艺
CN100543235C (zh) 斜拉索辅助全悬臂架设钢桁梁的方法及系统
CN108532465B (zh) 一种下承式钢箱拱桥的主桥的施工方法
CN102182147B (zh) 一种钢箱梁架设方法
CN101260650B (zh) 50m/1430t双幅整体箱梁架设工艺
CN104195952A (zh) 应用于钢混混合梁斜拉桥钢箱梁架设方法
CN102094392B (zh) 桥梁施工中的下承式挂篮及其应用
CN105421249A (zh) 一种拖吊结合式新型挂篮结构及施工方法
CN101586330A (zh) 预应力砼连续梁桥挂篮后退施工方法
CN102286935A (zh) 一种混合式结合梁斜拉桥全新施工方法
CN101446074B (zh) 钢桁梁桥顶面钢柔性拱的安装及合龙施工方法
CN201106155Y (zh) 斜拉索辅助全悬臂架设钢桁梁装置
CN101210419A (zh) 小半径曲线混凝土箱梁施工用内外梁系统造桥机及其施工方法
CN205223872U (zh) 一种拖吊结合式新型挂篮结构
CN203049470U (zh) 一种挂篮行走系统
CN109653105A (zh) 箱梁桥悬臂施工挂篮主桁系统及其使用方法
CN101831876B (zh) 移动造桥机及其架桥方法
CN102154988A (zh) 大跨度钢箱叠拱桥先梁后拱的施工方法
CN101481903B (zh) 跨缆吊机倒退拼装架设山区悬索桥主桁方法
CN102134832A (zh) 活动支架辅助不变幅架梁吊机架设钢箱梁方法及活动支架
CN109680614B (zh) 装配式钢混组合桥梁超大型架桥机快速转移方法及设备
CN105088970A (zh) 一种波形钢腹板pc箱梁斜拉桥的施工方法
CN105019357B (zh) 一种拱桥敞口格构式钢梁上异形预制桥面板的安装方法
CN104120659A (zh) 下行式挂篮
CN203716044U (zh) 一种下承或中承式索拱组合结构桥

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120829

Termination date: 20211010

CF01 Termination of patent right due to non-payment of annual fee