CN105088970A - 一种波形钢腹板pc箱梁斜拉桥的施工方法 - Google Patents

一种波形钢腹板pc箱梁斜拉桥的施工方法 Download PDF

Info

Publication number
CN105088970A
CN105088970A CN201510568872.2A CN201510568872A CN105088970A CN 105088970 A CN105088970 A CN 105088970A CN 201510568872 A CN201510568872 A CN 201510568872A CN 105088970 A CN105088970 A CN 105088970A
Authority
CN
China
Prior art keywords
wavelike steel
steel webplate
concrete
sections
hanging basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510568872.2A
Other languages
English (en)
Other versions
CN105088970B (zh
Inventor
黄永春
陈立生
赵国强
万义辉
刘中杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Original Assignee
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Municipal Engineering Group Co Ltd filed Critical Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority to CN201510568872.2A priority Critical patent/CN105088970B/zh
Publication of CN105088970A publication Critical patent/CN105088970A/zh
Application granted granted Critical
Publication of CN105088970B publication Critical patent/CN105088970B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种波形钢腹板PC箱梁斜拉桥的施工方法,包括如下步骤:起吊N号波形钢腹板节段并同N-1号波形钢腹板节段纵向连接就位;将挂篮前移,并通过斜拉索张拉N-1号波形钢腹板节段;在N号波形钢腹板节段下方搭设底模,并在底模上浇筑N号波形钢腹板节段的混凝土底板;待混凝土底板养护达到预定强度后,在混凝土底板上自下而上依次架设钢管支架和顶模,并在顶模上浇筑混凝土顶板;待混凝土顶板养护达到预定强度后,张拉混凝土底板和混凝土顶板中的纵横向预应力筋,完成一个节段的施工。本发明的优点是,分阶段浇筑波形钢腹板PC箱梁顶底板混凝土,充分利用节段既有结构的承载能力承担自重与后续结构的重量从而减轻了挂篮的施工荷载。

Description

一种波形钢腹板PC箱梁斜拉桥的施工方法
技术领域
本发明属于桥梁工程技术领域,具体涉及一种波形钢腹板PC箱梁斜拉桥的施工方法。
背景技术
我国对波形钢腹板PC箱梁桥的研究开始于20世纪90年代中期,现已建成波形钢腹板PC箱梁桥三十余座,以简支梁桥和连续梁桥居多,对波形钢腹板PC箱梁的认识日趋成熟,而对于波形钢腹板PC箱梁斜拉桥的施工方法,理论研究和实践经验尚且不足。传统的后支点挂篮悬臂施工工艺采取顶底板混凝土同时浇筑并由挂篮承担几乎全部节段重量,增加了挂篮重量和造价,而挂篮重量增加对悬臂施工的桥梁结构受力也极为不利。前支点挂篮悬臂施工工艺虽然可以减轻挂篮重量,但浇筑一个节段需要分阶段调索并且必须设置转动锚座,工艺复杂。
发明内容
本发明的目的是根据上述现有技术的不足之处,提供一种波形钢腹板PC箱梁斜拉桥的施工方法,该施工方法通过改进传统的后支点挂篮悬臂施工工艺,分阶段浇筑波形钢腹板节段的底板和顶板,充分利用波形钢腹板节段既有结构的承载能力承担自重与后续结构的重量,从而减轻挂篮的施工荷载。
本发明目的实现由以下技术方案完成:
一种波形钢腹板PC箱梁斜拉桥的施工方法,其特征在于所述施工方法包括如下步骤:起吊N号波形钢腹板节段并同N-1号波形钢腹板节段纵向连接就位;将挂篮前移至所述N-1号波形钢腹板节段的前端部,之后通过所述斜拉桥塔柱上的斜拉索张拉所述N-1号波形钢腹板节段;在所述N号波形钢腹板节段下方搭设底模,并在所述底模上浇筑所述N号波形钢腹板节段的混凝土底板;待所述N号波形钢腹板节段的混凝土底板养护达到预定强度后,在所述混凝土底板上自下而上依次架设钢管支架和顶模,并在所述顶模上浇筑混凝土顶板;待所述N号波形钢腹板节段的混凝土顶板养护达到预定强度后,张拉所述混凝土底板和所述混凝土顶板中的纵横向预应力筋,完成一个节段的施工。
所述底模由其下方的底篮支撑,所述底篮的前端横梁经吊杆吊挂于所述挂篮的前上横梁上,所述底篮的后端横梁经吊杆吊挂于所述N-1号波形钢腹板节段的混凝土底板上。
所述挂篮为后支点挂篮。
在浇筑所述混凝土顶板前,将所述挂篮前端的吊杆进行预张拉抬高后锁定。
本发明的优点是,(1)相比传统的后支点挂篮悬臂施工工艺,挂篮自重可大大减轻;相比前支点挂篮悬臂施工工艺,又可省去一个节段分阶段调索以及设置转动锚座等复杂工艺;(2)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可使钢管支架支承于底板之上,避免直接支承于底模上与底板钢筋和预应力管道产生冲突并于底板上预留很多孔道,保证了底板混凝土浇筑质量;(3)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可避免于顶板上开天窗并且波形钢腹板下翼缘与底板间的混凝土必须靠人工铲入,保证了波形钢腹板下翼缘与底板结合处的混凝土浇筑质量;(4)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可避免立模或浇筑顶板混凝土过程中波形钢腹板产生侧向位移或失稳,波形钢腹板的临时支撑无需加强;(5)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可降低施工难度和工作量,提高了施工质量,具备极佳的经济性。
附图说明
图1为本发明中波形钢腹板PC箱梁斜拉桥的施工示意图;
图2为本发明中波形钢腹板PC箱梁斜拉桥的施工正面视图。
具体实施方式
以下结合附图通过实施例对本发明的特征及其它相关特征作进一步详细说明,以便于同行业技术人员的理解:
如图1-2,图中标记1-13分别为:波形钢腹板1、挂篮2、底篮3、斜拉索4、混凝土底板5、钢管支架6、混凝土顶板7、前端横梁8、后端横梁9、前上横梁10、吊杆11、顶模12、底模13。
实施例:本实施例具体涉及一种适用于单箱多室、多箱多室的波形钢腹板PC箱梁斜拉桥的施工方法,该施工方法的主要思路为,在挂篮悬臂施工过程中先吊装波形钢腹板,通过焊缝及高强螺栓与已浇注PC箱梁连接让挂篮和波形钢腹板共同承担当前节段底板混凝土部分重量;待底板混凝土达到一定强度后浇筑顶板混凝土,利用底板、波形钢腹板和挂篮共同担顶板混凝土重量;一个节段循环,挂篮承受的施工荷载仅为挂篮自重与部分顶底板重量,挂篮可设计得更为轻巧。
如图1、2所示,本实施例中波形钢腹板PC箱梁斜拉桥的施工方法具体包括如下步骤:
(1)在完成N-2号、N-1号波形钢腹板节段的施工后,通过挂篮2起吊N号波形钢腹板节段并同N-1号波形钢腹板节段进行纵向连接就位,即将N号波形钢腹板节段中的各波形钢腹板1同N-1号波形钢腹板节段端面采用贴角焊以及高强螺栓实现纵向连接就位;
(2)挂篮2为后支点挂篮,呈倾斜的平行四边形状,将其底部前移至N-1号波形钢腹板节段的前端部并固定,此时其桁架上的前上横梁10突出于N号波形钢腹板节段的前端部;待挂篮2前移就位后,通过斜拉桥塔柱上的斜拉索4张拉N-1号波形钢腹板节段固定,提高其承载力;
(3)在N号波形钢腹板节段的下方设置底篮3,底篮3的前端横梁8经吊杆11吊挂于挂篮2的前上横梁10上,底篮3的后端横梁9经吊杆吊挂于N-1号波形钢腹板的混凝土底板5上,以使挂篮2与N-1号波形钢腹板共同承载受力;
在底篮3的支承下,搭设N号波形钢腹板节段的底模13,并在底模13上安装底板普通钢筋以及纵横向预应力筋;
(4)在底模13上浇筑N号波形钢腹板节段的混凝土底板5,并使混凝土底板5与波形钢腹板1之间通过连接件连成一个整体;
(5)待N号波形钢腹板节段的混凝土底板5养护达到预定强度后,在混凝土底板5上自下而上依次架设钢管支架6和顶模12,顶模12通过波形钢腹板1以及钢管支架6支承于混凝土底板5上,之后在顶模12上安装顶板普通钢筋以及纵横向预应力筋;
(6)将挂篮2前上横梁10下方的吊杆11进行预张拉抬高,之后锁定吊杆;在顶模12上浇筑N号波形钢腹板节段的混凝土顶板7;
(7)待N号波形钢腹板节段的混凝土顶板7和混凝土底板5均养护达到预定强度后,分别张拉混凝土顶板7和混凝土底板5内的纵横向预应力筋,以完成该节段的施工;
(8)拆除N号波形钢腹板节段上的底篮3、底模13、钢管支架6以及顶模12,开始下一波形钢腹板节段的施工,如此循环,直至完成全桥施工。
将本实施例中的施工方法应用于主桥通航孔(79+5×150+79)为波形钢腹板PC箱梁六塔单索面斜拉桥上,与传统的挂篮悬臂施工法相比,单个挂篮仅主桁架就可降低自重40%,节省钢材46.8t,全桥共节省钢材561.6t。
本实施的有益效果在于:
(1)相比传统的后支点挂篮悬臂施工工艺,挂篮自重可大大减轻;相比前支点挂篮悬臂施工工艺,又可省去一个节段分阶段调索以及设置转动锚座等复杂工艺;
(2)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可使钢管支架支承于底板之上,避免直接支承于底模上与底板钢筋和预应力管道产生冲突并于底板上预留很多孔道,保证了底板混凝土浇筑质量;
(3)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可避免于顶板上开天窗并且波形钢腹板下翼缘与底板间的混凝土必须靠人工铲入,保证了波形钢腹板下翼缘与底板结合处的混凝土浇筑质量;
(4)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可避免立模或浇筑顶板混凝土过程中波形钢腹板产生侧向位移或失稳,波形钢腹板的临时支撑无需加强;
(5)相比一次性整体浇筑,分阶段浇筑顶底板混凝土可降低施工难度和工作量,提高了施工质量,具备极佳的经济性。

Claims (4)

1.一种波形钢腹板PC箱梁斜拉桥的施工方法,其特征在于所述施工方法包括如下步骤:起吊N号波形钢腹板节段并同N-1号波形钢腹板节段纵向连接就位;将挂篮前移至所述N-1号波形钢腹板节段的前端部,之后通过所述斜拉桥塔柱上的斜拉索张拉所述N-1号波形钢腹板节段;在所述N号波形钢腹板节段下方搭设底模,并在所述底模上浇筑所述N号波形钢腹板节段的混凝土底板;待所述N号波形钢腹板节段的混凝土底板养护达到预定强度后,在所述混凝土底板上自下而上依次架设钢管支架和顶模,并在所述顶模上浇筑混凝土顶板;待所述N号波形钢腹板节段的混凝土顶板养护达到预定强度后,张拉所述混凝土底板和所述混凝土顶板中的纵横向预应力筋,完成一个节段的施工。
2.根据权利要求1所述的一种波形钢腹板PC箱梁斜拉桥的施工方法,其特征在于所述底模由其下方的底篮支撑,所述底篮的前端横梁经吊杆吊挂于所述挂篮的前上横梁上,所述底篮的后端横梁经吊杆吊挂于所述N-1号波形钢腹板节段的混凝土底板上。
3.根据权利要求1或2所述的一种波形钢腹板PC箱梁斜拉桥的施工方法,其特征在于所述挂篮为后支点挂篮。
4.根据权利要求2所述的一种波形钢腹板PC箱梁斜拉桥的施工方法,其特征在于在浇筑所述混凝土顶板前,将所述挂篮前端的吊杆进行预张拉抬高后锁定。
CN201510568872.2A 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥的施工方法 Active CN105088970B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510568872.2A CN105088970B (zh) 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510568872.2A CN105088970B (zh) 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥的施工方法

Publications (2)

Publication Number Publication Date
CN105088970A true CN105088970A (zh) 2015-11-25
CN105088970B CN105088970B (zh) 2017-03-22

Family

ID=54570230

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510568872.2A Active CN105088970B (zh) 2015-09-09 2015-09-09 一种波形钢腹板pc箱梁斜拉桥的施工方法

Country Status (1)

Country Link
CN (1) CN105088970B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625195A (zh) * 2016-03-16 2016-06-01 河南大建桥梁钢构股份有限公司 新型波形钢腹板scc工法移动挂篮及其施工方法
CN108425324A (zh) * 2018-03-12 2018-08-21 湖州市交通工程建设集团有限公司 一种桥梁模板结构以及移动搭接模板施工方法
CN111877169A (zh) * 2020-07-23 2020-11-03 中铁大桥局集团第五工程有限公司 一种无支架无大型吊机架设陆地重型端横梁的施工方法
CN112323640A (zh) * 2020-11-10 2021-02-05 中交二公局第三工程有限公司 一种临时斜拉波形钢腹板桥梁先行合龙腹板施工方法
CN114438868A (zh) * 2022-01-06 2022-05-06 广东省冶金建筑设计研究院有限公司 一种波形钢腹板组合箱梁及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020226A (ja) * 1999-07-09 2001-01-23 Mitsui Miike Mach Co Ltd 橋梁施工における波形鋼板ウェブ部材の搬送方法
JP2008088782A (ja) * 2006-10-05 2008-04-17 Zenitaka Corp 波形鋼板ウェブ橋の片持ち張り出し架設工法
CN201280693Y (zh) * 2008-10-22 2009-07-29 中铁大桥局集团第一工程有限公司 全封闭式挂篮
CN102154992A (zh) * 2011-04-28 2011-08-17 中交第二公路工程局有限公司 波形钢腹板错位安装方法
CN203270465U (zh) * 2013-05-31 2013-11-06 黑龙江省龙建路桥第六工程有限公司 悬浇挂篮液压预压施工装置
CN103422447A (zh) * 2013-07-18 2013-12-04 杭州博数土木工程技术有限公司 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020226A (ja) * 1999-07-09 2001-01-23 Mitsui Miike Mach Co Ltd 橋梁施工における波形鋼板ウェブ部材の搬送方法
JP2008088782A (ja) * 2006-10-05 2008-04-17 Zenitaka Corp 波形鋼板ウェブ橋の片持ち張り出し架設工法
CN201280693Y (zh) * 2008-10-22 2009-07-29 中铁大桥局集团第一工程有限公司 全封闭式挂篮
CN102154992A (zh) * 2011-04-28 2011-08-17 中交第二公路工程局有限公司 波形钢腹板错位安装方法
CN203270465U (zh) * 2013-05-31 2013-11-06 黑龙江省龙建路桥第六工程有限公司 悬浇挂篮液压预压施工装置
CN103422447A (zh) * 2013-07-18 2013-12-04 杭州博数土木工程技术有限公司 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张秋祥: "黄河大桥大跨波形钢腹板PC连续梁桥合拢施工技术", 《铁道建筑技术》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625195A (zh) * 2016-03-16 2016-06-01 河南大建桥梁钢构股份有限公司 新型波形钢腹板scc工法移动挂篮及其施工方法
CN105625195B (zh) * 2016-03-16 2017-10-20 河南大建桥梁钢构股份有限公司 新型波形钢腹板scc工法移动挂篮及其施工方法
CN108425324A (zh) * 2018-03-12 2018-08-21 湖州市交通工程建设集团有限公司 一种桥梁模板结构以及移动搭接模板施工方法
CN108425324B (zh) * 2018-03-12 2020-06-16 湖州市交通工程建设集团有限公司 一种桥梁模板结构以及移动搭接模板施工方法
CN111877169A (zh) * 2020-07-23 2020-11-03 中铁大桥局集团第五工程有限公司 一种无支架无大型吊机架设陆地重型端横梁的施工方法
CN112323640A (zh) * 2020-11-10 2021-02-05 中交二公局第三工程有限公司 一种临时斜拉波形钢腹板桥梁先行合龙腹板施工方法
CN112323640B (zh) * 2020-11-10 2023-11-07 中交二公局第三工程有限公司 一种临时斜拉波形钢腹板桥梁先行合龙腹板施工方法
CN114438868A (zh) * 2022-01-06 2022-05-06 广东省冶金建筑设计研究院有限公司 一种波形钢腹板组合箱梁及其施工方法

Also Published As

Publication number Publication date
CN105088970B (zh) 2017-03-22

Similar Documents

Publication Publication Date Title
CN105088970A (zh) 一种波形钢腹板pc箱梁斜拉桥的施工方法
CN102587286A (zh) 桥梁上部结构简支变连续施工方法
CN101787678B (zh) 大跨度节段拼装造桥机及其拼装施工工艺
CN108033367B (zh) 一种钢柱筒架交替支撑式钢平台与塔吊同步提升装置及其提升方法
CN109914244B (zh) 一种适用于高塔钢混结合横梁钢结构安装及底、顶板混凝土浇筑的弱支架系统及其操作方法
CN208087078U (zh) 一种大跨度钢混组合梁架桥机的起吊装置
CN110258352A (zh) 两跨连做的钢混组合桥梁施工方法
CN102587282B (zh) 大风及高空条件下大截面简支箱梁预制及拼装工艺
CN102704406A (zh) 基于组合槽型梁的道床板无拉应力施工方法
CN102134833B (zh) 贝雷架吊装拆除的施工方法
CN211498526U (zh) 自提式波形钢腹板现浇箱梁挂篮
CN103510469A (zh) 一种制造薄壁空心墩的施工方法
CN106758872A (zh) 波形钢腹板scc工法随车回旋吊移动挂篮及利用其施工的方法
CN215252400U (zh) 一种波形钢腹板施工自承式同步吊架系统
CN111483925B (zh) 一种波形钢腹板桥梁异步挂篮
CN203034799U (zh) 塔吊标准节支承高空支模钢平台结构
CN110409318B (zh) 一种大跨度简支钢混结合梁拼装架设方法
CN110344334B (zh) 采用背索式架桥机的两跨连做钢混组合桥梁施工方法
CN108086168A (zh) 骑索式桥面吊机
CN219218724U (zh) 一种用于组合梁斜拉桥的主梁吊铺一体机
CN201511439U (zh) 箱梁钢筋骨架整体绑扎、整体吊装系统
CN201605110U (zh) 悬臂施工桁车前端吊装波形钢腹板装置
CN207987749U (zh) 骑索式桥面吊机
CN213358342U (zh) 一种波形钢腹板承重同步施工挂篮系统
CN105220609B (zh) 组合梁自锚式悬索桥及其施工工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant