CN103422447A - 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构 - Google Patents

用波形钢腹板分担荷载的悬臂施工轻型挂篮结构 Download PDF

Info

Publication number
CN103422447A
CN103422447A CN2013103060245A CN201310306024A CN103422447A CN 103422447 A CN103422447 A CN 103422447A CN 2013103060245 A CN2013103060245 A CN 2013103060245A CN 201310306024 A CN201310306024 A CN 201310306024A CN 103422447 A CN103422447 A CN 103422447A
Authority
CN
China
Prior art keywords
wavelike steel
steel webplate
hanging basket
load
basket structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103060245A
Other languages
English (en)
Other versions
CN103422447B (zh
Inventor
孙天明
陈小勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang CTB Corrugated Steel Web Co., Ltd.
Original Assignee
HANGZHOU BOSHU CIVIL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANGZHOU BOSHU CIVIL ENGINEERING TECHNOLOGY Co Ltd filed Critical HANGZHOU BOSHU CIVIL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201310306024.5A priority Critical patent/CN103422447B/zh
Publication of CN103422447A publication Critical patent/CN103422447A/zh
Application granted granted Critical
Publication of CN103422447B publication Critical patent/CN103422447B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,包括挂篮和波形钢腹板,挂篮包括顶板模、底板模、连接杆或连接带、托架,顶板模和波形钢腹板之间设有托架,底板模和波形钢腹板之间设有连接杆或连接带,波形钢腹板的数量为两排以上。用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,利用波形钢腹板自身的刚度承担底板模荷载,减少了挂篮的实际荷载,并使施工过程中的荷载得到了合理的分布,使挂篮更加轻盈,提高了整个挂篮结构的实用性,降低了施工成本。

Description

用波形钢腹板分担荷载的悬臂施工轻型挂篮结构
技术领域
本发明涉及桥梁施工中使用的挂篮结构,尤其是波形钢腹板分担荷载的悬臂施工轻型挂篮结构。
背景技术
随着我国桥梁结构的不断发展,新的桥梁结构形式不断涌现,波形钢腹板桥梁被逐渐应用。波形钢腹板桥梁悬臂施工时,需要用到挂篮结构。但是现有挂篮的荷载受力结构决定了其重量较重,生产成本较高,所以增加了整个施工作业的整体成本。
发明内容
本发明是为解决现有挂篮结构所具有的成本高等不足而提出的,旨在提供具有成本低,利用波形钢腹板分担荷载的悬臂施工轻型挂篮结构。
为了解决上述技术问题,本发明通过下述技术方案得以解决:
用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,包括挂篮和波形钢腹板,挂篮包括顶板模、底板模、连接杆或连接带、托架,顶板模和波形钢腹板之间设有托架,底板模和波形钢腹板之间设有连接杆或连接带,波形钢腹板的数量为两排以上。将顶板模和底板模直接与波形钢腹板连接,利用波形钢腹板自身的刚度来承担顶板模和底板模的荷载,减少了挂篮自身的荷载。
作为优选,波形钢腹板各节段相互连接。波形钢腹板相互之间纵向连接形成一排波形钢腹板,并且桥梁上有至少两排波形钢腹板。
作为优选,各排波形钢腹板之间设有水平支撑装置或倾斜支撑装置。水平支撑装置或倾斜支撑装置使排与排之间的波形钢腹板连接更加牢固。
作为优选,底板模荷载由波形钢腹板承担,顶板模荷载由挂篮承担。顶板模还可以通过连接杆或连接带与挂篮连接。
作为优选,施工荷载由挂篮及波形钢腹板共同承担,施工节段的波形钢腹板下部承担压应力,施工节段的波形钢腹板上部承担拉应力。施工荷载得到合理的分布,降低了施工的难度。
作为优选,波形钢腹板各节段之间的上部为销轴或电焊或螺栓连接,波形钢腹板各节段之间的下部为销轴或电焊或螺栓连接。波形钢腹板相互之间连接牢固,使整体结构足以承担顶板模和底板模的荷载。
作为优选,波形钢腹板上下部各节段之间设有临时连接件。临时连接件临时性的提高了波形钢腹板相互之间的连接强度,使施工更加安全。
作为优选,临时连接件位于波形钢腹板上部或/和下部,临时连接件为临时钢梁,临时钢梁和波形钢腹板上部或下部采用电焊或螺栓连接。根据实际情况的需要选择临时钢梁的位置和固定方式,使施工过程更加灵活、方便。
作为优选,临时钢梁沿桥梁纵向设置且位于波形钢腹板的内侧或外侧。根据实际情况的需要选择临时钢梁固定于波形钢腹板的内侧或外侧。
作为优选,临时钢梁为分段连接方式,各连接口均一致。节约了临时钢梁的用量,降低了施工成本,以及方便了临时钢梁的统一化生产、制作。
按照本发明的技术方案,用波形钢腹板分担荷载的悬臂施工轻型挂篮结构利用波形钢腹板自身的刚度和结构来承担顶板模和底板模的荷载,分担了挂篮的荷载,减低了挂篮的荷载,使施工过程中的荷载得到了合理的分布,施工更加简单、方便,以及安全。提高了整个结构的使用性,同时也为整个施工降低了成本。
附图说明
图1为本发明用波形钢腹板分担荷载的悬臂施工轻型挂篮结构的示意图。
具体实施方式
下面结合附图与具体实施方式对本发明作进一步详细描述:
实施例1
用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,包括挂篮8、挂篮前吊带7、波形钢腹板3,挂篮包括顶板模1、底板模5、连接杆或连接带4、托架2,顶板模1和波形钢腹板3之间设有托架2,底板模5和波形钢腹板3之间设有连接杆或连接带4,波形钢腹板3的数量为两排以上。
波形钢腹板3各节段相互连接。
各排波形钢腹板3之间设有水平支撑装置或倾斜支撑装置。
底板模5荷载由波形钢腹板3承担,顶板模1荷载由挂篮承担。
施工荷载由挂篮及波形钢腹板3共同承担,施工节段的波形钢腹板3下部承担压应力,施工节段的波形钢腹板3上部承担拉应力。
波形钢腹板3各节段之间的上部为销轴或电焊或螺栓连接,波形钢腹板3各节段之间的下部为销轴或电焊或螺栓连接。
波形钢腹板3上下部各节段之间设有临时连接件6。
临时连接件6位于波形钢腹板3上部或/和下部,临时连接件6为临时钢梁,临时钢梁和波形钢腹板3上部或下部采用电焊或螺栓连接。
临时钢梁沿桥梁纵向设置且位于波形钢腹板3的内侧或外侧。
临时钢梁为分段连接方式,各连接口均一致。
总之,以上所述仅为本发明的较佳实施例,凡依本发明申请专利范围所作的均等变化与修饰,皆应属本发明专利的涵盖范围。

Claims (10)

1.用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,包括挂篮和波形钢腹板(3),挂篮包括顶板模(1)、底板模(5)、连接杆或连接带(4)、托架(2),其特征在于:顶板模(1)和波形钢腹板(3)之间设有托架(2),底板模(5)和波形钢腹板(3)之间设有连接杆或连接带(4),波形钢腹板(3)的数量为两排以上。
2.根据权利要求1所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:波形钢腹板(3)各节段相互连接。
3.根据权利要求2所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:各排波形钢腹板(3)之间设有水平支撑装置或倾斜支撑装置。
4.根据权利要求1所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:底板模(5)荷载由波形钢腹板(3)承担,顶板模(1)荷载由挂篮承担。
5.根据权利要求1所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:施工荷载由挂篮及波形钢腹板(3)共同承担,施工节段的波形钢腹板(3)下部承担压应力,施工节段的波形钢腹板(3)上部承担拉应力。
6.根据权利要求1所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:波形钢腹板(3)各节段之间的上部为销轴或电焊或螺栓连接,波形钢腹板(3)各节段之间的下部为销轴或电焊或螺栓连接。
7.根据权利要求1所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:波形钢腹板(3)上下部各节段之间设有临时连接件(6)。
8.根据权利要求7所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:临时连接件(6)位于波形钢腹板(3)上部或/和下部,临时连接件(6)为临时钢梁,临时钢梁和波形钢腹板(3)上部或下部采用电焊或螺栓连接。
9.根据权利要求7所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:临时钢梁沿桥梁纵向设置且位于波形钢腹板(3)的内侧或外侧。
10.根据权利要求7所述的用波形钢腹板分担荷载的悬臂施工轻型挂篮结构,其特征在于:临时钢梁为分段连接方式,各连接口均一致。
CN201310306024.5A 2013-07-18 2013-07-18 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构 Active CN103422447B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310306024.5A CN103422447B (zh) 2013-07-18 2013-07-18 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310306024.5A CN103422447B (zh) 2013-07-18 2013-07-18 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构

Publications (2)

Publication Number Publication Date
CN103422447A true CN103422447A (zh) 2013-12-04
CN103422447B CN103422447B (zh) 2015-10-14

Family

ID=49647799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310306024.5A Active CN103422447B (zh) 2013-07-18 2013-07-18 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构

Country Status (1)

Country Link
CN (1) CN103422447B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047234A (zh) * 2014-04-02 2014-09-17 中铁二院工程集团有限责任公司 波形钢腹板连续刚构桥自承重边跨合龙施工方法
CN105088970A (zh) * 2015-09-09 2015-11-25 上海城建市政工程(集团)有限公司 一种波形钢腹板pc箱梁斜拉桥的施工方法
CN110820565A (zh) * 2019-10-16 2020-02-21 广西翔路建设有限责任公司 波形钢腹板挂篮悬浇方法
CN111535205A (zh) * 2020-05-07 2020-08-14 浙江省交通运输科学研究院 一种利用波形钢腹板承担部分底板重量的悬臂施工工法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000110114A (ja) * 1998-10-02 2000-04-18 Ps Corp 波形鋼板ウエブを用いた張出架設桁橋の施工方法及び張出架設作業装置
JP2001020226A (ja) * 1999-07-09 2001-01-23 Mitsui Miike Mach Co Ltd 橋梁施工における波形鋼板ウェブ部材の搬送方法
JP2006118314A (ja) * 2004-10-25 2006-05-11 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブ橋の架設方法
JP2006316506A (ja) * 2005-05-12 2006-11-24 Sumitomo Mitsui Construction Co Ltd 橋桁の構築方法
CN201619964U (zh) * 2010-01-07 2010-11-03 中交第二公路工程局有限公司 悬臂施工桁车后端吊装波形钢腹板装置
CN201695319U (zh) * 2010-01-07 2011-01-05 中交第二公路工程局有限公司 波形钢腹板箱梁桥面混凝土浇筑波形组合钢模板
CN102154992A (zh) * 2011-04-28 2011-08-17 中交第二公路工程局有限公司 波形钢腹板错位安装方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000110114A (ja) * 1998-10-02 2000-04-18 Ps Corp 波形鋼板ウエブを用いた張出架設桁橋の施工方法及び張出架設作業装置
JP2001020226A (ja) * 1999-07-09 2001-01-23 Mitsui Miike Mach Co Ltd 橋梁施工における波形鋼板ウェブ部材の搬送方法
JP2006118314A (ja) * 2004-10-25 2006-05-11 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブ橋の架設方法
JP2006316506A (ja) * 2005-05-12 2006-11-24 Sumitomo Mitsui Construction Co Ltd 橋桁の構築方法
CN201619964U (zh) * 2010-01-07 2010-11-03 中交第二公路工程局有限公司 悬臂施工桁车后端吊装波形钢腹板装置
CN201695319U (zh) * 2010-01-07 2011-01-05 中交第二公路工程局有限公司 波形钢腹板箱梁桥面混凝土浇筑波形组合钢模板
CN102154992A (zh) * 2011-04-28 2011-08-17 中交第二公路工程局有限公司 波形钢腹板错位安装方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
梁朝晖: ""鄄城黄河公路特大桥波形钢腹板PC结合梁施工技术"", 《桥梁建设》 *
王侃: ""波形钢腹板PC 箱梁桥的施工技术与效益分析"", 《施工技术》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047234A (zh) * 2014-04-02 2014-09-17 中铁二院工程集团有限责任公司 波形钢腹板连续刚构桥自承重边跨合龙施工方法
CN104047234B (zh) * 2014-04-02 2016-05-11 中铁二院工程集团有限责任公司 波形钢腹板连续刚构桥自承重边跨合龙施工方法
CN105088970A (zh) * 2015-09-09 2015-11-25 上海城建市政工程(集团)有限公司 一种波形钢腹板pc箱梁斜拉桥的施工方法
CN110820565A (zh) * 2019-10-16 2020-02-21 广西翔路建设有限责任公司 波形钢腹板挂篮悬浇方法
CN111535205A (zh) * 2020-05-07 2020-08-14 浙江省交通运输科学研究院 一种利用波形钢腹板承担部分底板重量的悬臂施工工法

Also Published As

Publication number Publication date
CN103422447B (zh) 2015-10-14

Similar Documents

Publication Publication Date Title
CN103422447A (zh) 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构
CN202688888U (zh) 上承式倒挂模板吊架
CN201848849U (zh) 冷轧轧辊摆放双层辊架
CN203411917U (zh) 基于桥梁同步顶升和整体置换技术的快速降梁机构
CN101633483B (zh) 一种钢结构网架整体提升装置
CN203903754U (zh) 一种新型扶梯桁架
CN105369745A (zh) 一种桥梁支座更换顶升反力架
CN202924576U (zh) 共箱封闭母线导体用吊具
CN203583376U (zh) 用波形钢腹板分担荷载的悬臂施工轻型挂篮结构
CN201810003U (zh) 一种变电站500kV构架
CN204001189U (zh) 一种不承受竖向荷载的钢框架支撑结构体系
CN202788873U (zh) 一种组合式门架隧道衬砌台车
CN203049956U (zh) 一种折叠舞台梯
CN202744957U (zh) 三角托架
CN203257123U (zh) 便于折叠的建筑支撑架
CN202249004U (zh) 改进型钢结构厂房结构
CN203529707U (zh) 双板孔式工字钢有弯矩平衡梁
CN201952103U (zh) 一种钢筋吊架
CN201865328U (zh) 整体脚手架的竖向承重主框架
CN206375570U (zh) 起重机及其支腿结构
CN207390920U (zh) 一种汽车托架
CN205223842U (zh) 斜拉桥结构体系防止主梁出现负反力构造
CN201679271U (zh) 电力三角塔
CN201695400U (zh) 联动支撑结构
CN202804054U (zh) 基于对c型板安装时提供支撑的内置桁架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: ZHEJIANG CTB CORRUGATED STEEL WEB CO., LTD.

Free format text: FORMER OWNER: HANGZHOU BOSHU CIVIL ENGINEERING TECHNOLOGY CO., LTD.

Effective date: 20141124

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 311215 HANGZHOU, ZHEJIANG PROVINCE TO: 314422 HANGZHOU, ZHEJIANG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20141124

Address after: 314422, No. 168-2, village, town, Hangzhou, Xiaoshan District, Zhejiang

Applicant after: Zhejiang CTB Corrugated Steel Web Co., Ltd.

Address before: Hangzhou City, Zhejiang province 311215 Xiaoshan economic and Technological Development Zone, North Building 2 room 1711 Ning'an

Applicant before: Hangzhou Boshu Civil Engineering Technology Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant