CN101748662B - 路基双块式无砟轨道道床施工工艺 - Google Patents

路基双块式无砟轨道道床施工工艺 Download PDF

Info

Publication number
CN101748662B
CN101748662B CN200910312558A CN200910312558A CN101748662B CN 101748662 B CN101748662 B CN 101748662B CN 200910312558 A CN200910312558 A CN 200910312558A CN 200910312558 A CN200910312558 A CN 200910312558A CN 101748662 B CN101748662 B CN 101748662B
Authority
CN
China
Prior art keywords
rail
sleeper
track
laying
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200910312558A
Other languages
English (en)
Other versions
CN101748662A (zh
Inventor
赵�智
谢录杲
秦瑞谦
王智勇
白昆华
龚斯昆
赵代强
梅红
肖肃宇
万轶
宋德佩
杜建武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN200910312558A priority Critical patent/CN101748662B/zh
Publication of CN101748662A publication Critical patent/CN101748662A/zh
Priority to PCT/CN2010/079302 priority patent/WO2011079677A1/zh
Application granted granted Critical
Publication of CN101748662B publication Critical patent/CN101748662B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • E01B1/004Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明涉及高速铁路客运专线修建工艺领域,公开了一种桥上双块式无砟轨道道床施工工艺,其包括如下步骤:第一步,确保桥梁沉降满足施工要求;第二步,清理桥面;第三步,施工防撞墙、伸缩缝和防水层;第四步,铺设保护层和预埋抗剪凸台;第五步,铺设隔离层;第六步,组装轨排;第七步,铺设面层钢筋层;第八步,精调轨排;第九步,道床板混凝土浇筑。本发明的优点在于,通过施工支撑调整装置的应用和工艺操作控制,使双块式轨排系统的几何空间位置在整个施工过程中保持稳固、可无级调整;提高桥上双块式无砟轨道铺设精度,有效提高施工质量。

Description

路基双块式无砟轨道道床施工工艺
技术领域
本发明涉及高速铁路客运专线修建工艺领域,具体涉及一种双块式无砟轨道在路基地段的铺设施工工艺。
背景技术
在铁路上,“砟”的意思是小块的石头。传统的铁路都是在小块石头的基础上,再铺设枕木或水泥钢轨,钢轨固定放在枕木上,之下为小碎石铺成的路砟。路砟和枕木均起加大受力面、分散火车压力、帮助铁轨承重的作用,防止铁轨因压力太大而下陷到泥土里。这种传统有碴轨道具有铺设简便、综合造价低廉等特点,但是在高速列车长期荷载作用下已达到了承载能力的极限,轨道平顺度变差,维修作业量加大,可用的维修时间越来越少,严重阻碍了高速铁路的发展。无砟轨道的轨枕本身是混凝土浇灌而成,而路基也不用碎石,铁轨、轨枕直接铺在混凝土路上。因此,无砟轨道因其具有高平顺性、高稳定性、高耐久性等特点,在高速铁路客运专线建设领域得到广泛的应用。是当今世界先进的轨道技术,可以减少维护、降低粉尘、美化环境,而且列车时速可以达到200公里以上。
双块式无砟轨道是无砟轨道系统的一种,无砟轨道床混凝土主要采用支撑轨排后现浇法成型。即采用支撑词整装置支撑固定轨排,轨排精确调整到位后立模现场浇筑混凝土形成道床板。这种施工工艺是在长期的工程实践中完善的,全部采用机械化施工,特别是需控制轨道铺设精度的专用设备和装置,以及相关工艺控制措施。目前国内的技术研究处于起步阶段。
发明内容
本发明的目的是提供一种施工支撑调整装置和工艺控制措施相配套的路基双块式无砟轨道道床施工工艺,使路基双块式无砟轨道实现高精度铺设。
一种路基双块式无砟轨道道床施工工艺,它包括如下步骤:
第一步,确保路基沉降满足施工要求:
第二步,清理路基基础面:
清除路基基础面上的浮渣、灰尘及杂物;
第三步,采用滑膜摊铺机施工混凝土支承层:
a)支承层测量放线:
通过CPIII控制网测试支承层两侧引导线的位置,引导线位于摊铺机
两侧;引导线到线路中线的距离为2.9m,高度距设计路基面50cm;引导线拉杆纵向间距为10m,曲线地段为5m;
b)确定混合料的施工配合比:
原材料重量比为:水泥、矿物掺合料1%,粗、细骨料比例2%,拌合水比
例1%,其投料顺序力:细骨料一水泥一粉煤灰一搅拌均匀后加水一粗骨料;支承层混合料充分搅拌、使各种材料混合均匀、颜色一致后,将混合料运输到施工现场备用;
c)混合料摊铺:
首次摊铺前,采用钉桩或引导线法校准滑模摊铺机挤压底板4角点高程
和侧模前进方向,开动摊铺机进入设好的线位,然后在摊铺范围内均匀布料,布料与摊铺速度相协调,纵向布料长度超过5m后,启动摊铺机开始摊铺作业;
d)支承层切缝、养护:
支承层摊铺完成12小时内,按纵向5m间距切割出一道横向缝,缝深为
支承层混凝土厚度的1/3;切缝后,在支承层表面洒水并覆盖塑料薄膜养生5天;
第四步,支承层表面进行拉毛处理:
对支承层表面进行拉毛处理,确保与道床板的粘结牢固;
第五步,组装轨排:
a)铺设道床底层钢筋层;
b)铺设预制好的轨枕:
首先在铺设轨枕前用画线器将轨枕两端的位置直接画在混凝土支承层上,然后将轨枕从存放地抬到轨枕划线位置,在底层钢筋层上按照画好的轨枕两端的位置放置轨枕;
c)铺设钢轨:
铺设钢轨前,清除轨枕承轨台上的施工杂物,人工配合吊车将钢轨吊放到轨枕承轨槽垫板上,两段钢轨的端头通过鱼尾板进衍连接,钢轨接头缝隙根据轨温定。
d)调整轨枕间距:
将两股钢轨端头放正,并使其对正无砟轨道铺设起点位置处,根据设计图纸,在钢轨上画标识线标识出轨枕的中心位置,人工使用套橡胶的撬棍将或橡皮锤将轨枕中心调整到标识线位置处;
e)紧固扣件
扣件弹条朝钢轨的一侧完全扣在干净的钢轨轨底上,扣件弹条背向钢轨的一侧在角形支撑板上,先用扭距扳手紧固螺栓,再用螺拴紧松机拧紧扣件,钢轨两侧的扣件同时施加扭矩,并用塞尺检查扣件弹条与轨底之间的间隙,保证不大于0.5mm:
第六步,铺设面层钢筋层
用起道机粗调轨排标高和中线,到位后在钢轨上竖向设置支撑装置并牢固支撑
轨排,安装地锚式侧向调整装置,与双块式轨枕桁架钢筋连接,然后在道床上安装面层钢筋层;所有横向和纵向钢筋的节点之间加垫绝缘材料,内部的钢筋节点绝缘,道床板纵横向钢筋不形成回路,不产生电磁感应,从而道床板对钢轨信号传输距离不会由此产生影响;
第七步,精调轨排
采用轨道检测小车测量轨排几何形位与设计值进行比较,并通过地锚式侧向调整装置和竖向调整装置精调轨排标高和中线位置,到位后锁紧调整装置、可靠固定轨排;
第八步,道床板混凝土浇筑
满足设计要求后,灌注道床板混凝土固定轨排,当达到初凝后,松开钢轨扣件和竖向支撑装置;道床板混凝土浇筑完成12个小时后,用钢轨运输平车将钢轨运输到下一施工段继续使用。
由于采用了上述技术方案,本发明的优点是:
通过施工支撑调整装置的应用和工艺操作控制,使双块式轨排系统的几何空间位置在整个施工过程中保持稳固、可无级调整;提高路基双块式无砟轨道铺设精度,有效提高施工质量。
附图说明
图1是本发明结构示意图。
附图标记:1是混凝土支承层,2是面层钢筋层,3是底层钢筋层,4是轨枕,5是钢轨,6是扣件。
图中黑圆圈表示钢筋。
具体实施方式
具体实施方式如下:
一种路基双块式无砟轨道道床施工工艺,它包括如下步骤:
第一步,确保路基沉降满足施工要求:
第二步,清理路基基础面:
清除路基基础面上的浮渣、灰尘及杂物;
第三步,采用滑膜摊铺机施工混凝土支承层1:
a)支承层测量放线:
通过CPIII控制网测试支承层两侧引导线的位置,引导线位于摊铺机
两侧;引导线到线路中线的距离为2.9m,高度距设计路基面50cm;引导线拉杆纵向间距为10m,曲线地段为5m;
b)确定混合料的施工配合比:
原材料重量比为:水泥、矿物掺合料1%,粗、细骨料比例2%,拌合水比
例1%,其投料顺序为:细骨料一水泥一煤炭粉一搅拌均匀后加水一粗骨料;支承层混合料充分搅拌、使各种材料混合均匀、颜色一致后,将混合料运输到施工现场备用;
c)混合料摊铺:
首次摊铺前,采用钉桩或引导线法校准滑模摊铺机挤压底板4角点高程
和侧模前进方向,开动摊铺机进入设好的线位,然后在摊铺范围内均匀布料,布料与摊铺速度相协调,纵向布料长度超过5m后,启动摊铺机开始摊铺作业;
d)支承层切缝、养护:
支承层摊铺完成12小时内,按纵向5m间距切割出一道横向缝,缝深为
支承层混凝土厚度的1/3;切缝后,在支承层表面洒水并覆盖塑料薄膜养生5天;
第四步,支承层表面进行拉毛处理:
对支承层表面进行拉毛处理,确保与道床板的粘结牢固;
第五步,组装轨排:
a)铺设道床底层钢筋层3;
b)铺设预制好的轨枕4:
首先在铺设轨枕4前用画线器将轨枕两端的位置直接画在混凝土支承层1上,然后将轨枕4从存放地抬到轨枕划线位置,在底层钢筋层3上按照画好的轨枕两端的位置放置轨枕4;
c)铺设钢轨5:
铺设钢轨5前,清除轨枕承轨台上的垃圾,人工配合吊车将钢轨5吊放到轨枕承轨槽垫板上,两段钢轨5的端头通过鱼尾板进行连接,钢轨接头缝隙根据轨温定;
d)调整轨枕间距:
将两股钢轨5端头放正,并使其对正无砟轨道铺设起点位置处,根据设计图纸,在钢轨上画标识线标识出轨枕的中心位置,人工使用套橡胶的撬棍将或橡皮锤将轨枕中心调整到标识线位置处;
e)紧固扣件6
扣件弹条朝钢轨的一侧完全扣在干净的钢轨5轨底上,扣件弹条背向钢轨的一侧在角形支撑板上,先用扭距扳手紧固螺栓,再用螺拴紧松机拧紧扣件6,钢轨5两侧的扣件6同时施加扭矩,并用塞尺检查扣件弹条与轨底之间的间隙,保证不大于0.5mm;
第六步,铺设面层钢筋层2
在钢轨5上安装竖向支撑装置,并用起道机粗调轨排标高和中线,然
后在道床上安装面层钢筋层2;所有横向和纵向钢筋的节点之间加垫绝缘材料,内部的钢筋节点绝缘,道床板缴横向钢筋不形成回路,不产生电磁感应,从而道床板对钢轨信号传输距离不会由此产生影响;
第七步,精调轨排
采用轨道检测小车测量轨排几何形位与设计值进行比较,并通过侧向调整和竖向调整装置精调轨排;
第八步,道床板混凝土浇筑
满足设计要求后,灌注道床混凝土固定轨排,当达到初凝后,拆除支撑装置;道床板混凝土浇筑完成12个小时后,用钢轨运输平车将钢轨5运输到下一施工段继续使用。

Claims (1)

1.一种路基双块式无砟轨道道床施工工艺,它包括如下步骤:
第一步,确保路基沉降满足施工要求:
第二步,清理路基基础面:清除路基基础面上的浮渣、灰尘及杂物;
第三步,采用滑膜摊铺机施工混凝土支承层(1):
a)支承层测量放线:
通过CPIII控制网测试支承层两侧引导线的位置,引导线位于摊铺机两侧;引导线到线路中线的距离为2.9m,高度距设计路基面50cm;引导线拉杆纵向间距为10m,曲线地段为5m;
b)确定混合料的施工配合比:
原材料重量比为:水泥、矿物掺合料1%,粗、细骨料比例2%,拌合水比例1%,其投料顺序为:细骨料一水泥一粉煤灰一搅拌均匀后加水一粗骨料;支承层混合料充分搅拌、使各种材料混合均匀、颜色一致后,将混合料运输到施工现场备用;
C)混合料摊铺:
首次摊铺前,采用钉桩或引导线法校准滑模摊铺机挤压底板4角点高程和侧模前进方向,开动摊铺机进入设好的线位,然后在摊铺范围内均匀布料,布料与摊铺速度相协调,纵向布料长度超过5m后,启动摊铺机开始摊铺作业;
d)支承层切缝、养护:
支承层摊铺完成12小时内,按纵向5m间距切割出一道横向缝,缝深为支承层混凝土厚度的1/3;切缝后,在支承层表面洒水并覆盖塑料薄膜养生5天;
第四步,支承层表面进行拉毛处理:
对支承层表面进行拉毛处理,确保与道床板的粘结牢固;
第五步,组装轨排:
a)铺设道床底层钢筋层(3);
b)铺设预制好的轨枕(4):
首先在铺设轨枕(4)前用画线器将轨枕两端的位置直接画在混凝土支承层(1)上,然后将轨枕(4)从存放地抬到轨枕划线位置,在底层钢筋层(3)上按照画好的轨枕两端的位置放置轨枕(4);
c)铺设钢轨(5):
铺设钢轨(5)前,清除轨枕承轨台上的施工杂物,人工配合吊车将钢轨(5)吊放到轨枕承轨槽垫板上,两段钢轨(5)的端头通过鱼尾板进行连接,钢轨接头缝隙根据轨温定;
d)调整轨枕间距:
将两股钢轨(5)端头放正,并使其对正无砟轨道铺设起点位置处,根据设计图纸,在钢轨上画标识线标识出轨枕的中心位置,人工使用套橡胶的撬棍或橡皮锤将轨枕中心调整到标识线位置处;
e)紧固扣件(6)
扣件弹条朝钢轨的一侧完全扣在干净的钢轨(5)轨底上,扣件弹条背向钢轨的一侧在角形支撑板上,先用扭距扳手紧固螺栓,再用螺拴紧松机拧紧扣件(6),钢轨(5)两侧的扣件(6)同时施加扭矩,并用塞尺检查扣件弹条与轨底之间的间隙,保证不大于0.5mm;
第六步,铺设面层钢筋层(2)
用起道机粗调轨排标高和中线,到位后在钢轨(5)上设置竖向支撑装置并牢固支撑轨排,安装地锚式侧向调整装置,与双块式轨枕桁架钢筋连接,然后在道床上安装面层钢筋层(2);所有横向和纵向钢筋的节点之间加垫绝缘材料,内部的钢筋节点绝缘,道床板纵横向钢筋不形成回路,不产生电磁感应,从而道床板对钢轨信号传输距离不会由此产生影响;
第七步,精调轨排
采用轨道检测小车测量轨排几何形位与设计值进行比较,并通过地锚式侧向调整装置和 竖向调整装置精调轨排标高和中线位置,到位后锁紧调整装置、可靠固定轨排;
第八步,道床板混凝土浇筑
满足设计要求后,灌注道床板混凝土固定轨排,当达到初凝后,松开钢轨扣件和竖向支撑装置;道床板混凝土浇筑完成12个小时后,用钢轨运输平车将钢轨(5)运输到下一施工段继续使用。 
CN200910312558A 2009-12-30 2009-12-30 路基双块式无砟轨道道床施工工艺 Expired - Fee Related CN101748662B (zh)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN200910312558A CN101748662B (zh) 2009-12-30 2009-12-30 路基双块式无砟轨道道床施工工艺
PCT/CN2010/079302 WO2011079677A1 (zh) 2009-12-30 2010-11-30 路基双块式无砟轨道道床施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910312558A CN101748662B (zh) 2009-12-30 2009-12-30 路基双块式无砟轨道道床施工工艺

Publications (2)

Publication Number Publication Date
CN101748662A CN101748662A (zh) 2010-06-23
CN101748662B true CN101748662B (zh) 2012-10-03

Family

ID=42476239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910312558A Expired - Fee Related CN101748662B (zh) 2009-12-30 2009-12-30 路基双块式无砟轨道道床施工工艺

Country Status (2)

Country Link
CN (1) CN101748662B (zh)
WO (1) WO2011079677A1 (zh)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101748662B (zh) * 2009-12-30 2012-10-03 中铁八局集团有限公司 路基双块式无砟轨道道床施工工艺
CN102561114B (zh) * 2010-12-16 2015-08-26 拜耳材料科技(中国)有限公司 一种聚氨酯铁路道床、及其制备方法和应用
CN102296495B (zh) * 2011-05-25 2013-01-23 中铁二十局集团第四工程有限公司 大温差、强风沙条件下长钢轨铺设及焊接施工工艺
CN102966008A (zh) * 2011-08-31 2013-03-13 中国铁道科学研究院铁道建筑研究所 无砟轨道系统
CN102409580B (zh) * 2011-09-08 2013-07-17 中铁十二局集团有限公司 350km/h高铁双线路基曲线段M型基床及其填筑方法
CN102608297B (zh) * 2012-02-23 2014-12-10 上海市城市建设设计研究总院 道床板基础脱空试验模拟结构
CN102995507B (zh) * 2012-11-15 2015-01-07 中国铁道科学研究院铁道建筑研究所 一种刮除无砟轨道上拱的方法
CN103603236A (zh) * 2013-11-06 2014-02-26 中铁四局集团有限公司 一种双块式无砟轨道道床板裂纹控制方法
CN104153259A (zh) * 2014-08-20 2014-11-19 中国铁道科学研究院铁道建筑研究所 一种用于沉降无砟轨道的注浆抬升快速修复方法
CN106758555B (zh) * 2017-01-13 2018-06-12 中铁工程机械研究设计院有限公司 地铁板式道床施工方法
CN106758563B (zh) * 2017-03-02 2018-04-06 兰州理工大学 用于无砟轨道新旧混凝土粘结的轨枕构造及施工方法
CN107522429B (zh) * 2017-08-18 2020-08-11 北京交通大学 一种预制道砟-沥青轨道及其制备方法
CN108252165A (zh) * 2018-03-30 2018-07-06 中铁二局第四工程有限公司 一种中低速磁悬浮低置线路路基结构及其施工方法
CN108614073B (zh) * 2018-04-10 2022-02-01 同济大学 考虑边界效应的双线轨道路基缩尺试验模型系统
CN108611929A (zh) * 2018-05-15 2018-10-02 中铁第四勘察设计院集团有限公司 一种既有线无砟轨道地段插铺道岔的方法
CN109110640B (zh) * 2018-06-29 2020-01-14 中建港务建设有限公司 全自动化集装箱堆场非桩基可调式轨道基座的施工方法
CN108951372B (zh) * 2018-09-14 2020-12-18 中铁四局集团第一工程有限公司 一种用于高速铁路无砟轨道路基支承层摊铺施工的施工方法
CN110565450A (zh) * 2019-09-26 2019-12-13 中铁五局集团有限公司 一种刚性短路基地段双块式无砟轨道结构及施工方法
CN112851258A (zh) * 2021-02-06 2021-05-28 山东交通职业学院 一种分层式减振无砟道床

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1497324A1 (ru) * 1986-01-09 1989-07-30 Всесоюзный Научно-Исследовательский Институт Железнодорожного Транспорта Устройство дл сооружени безбалластного железнодорожного пути
EP0621370A1 (de) * 1993-04-22 1994-10-26 Walter Bau-Aktiengesellschaft Verfahren zum Herstellen eines schotterlosen Gleisoberbaus und ein nach dem Verfahren hergestellter Gleisoberbau
CN101215814A (zh) * 2007-12-29 2008-07-09 南车洛阳机车有限公司 双块式无碴轨道轨枕铺设施工方法及设备
CN101289828A (zh) * 2008-05-22 2008-10-22 北京铁五院工程机械科技开发有限公司 双块式无砟轨道的施工装备及施工工艺
CN101503870A (zh) * 2008-12-03 2009-08-12 中铁八局集团第一工程有限公司 一种双块式无砟轨道道床板的施工方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19837950C5 (de) * 1997-09-18 2012-03-15 Rail.One Gmbh Verfahren zur Herstellung einer Festen Fahrbahn für schienengebundenen Verkehr und Vorrichtung zur Durchführung des Verfahrens
ES2211386T3 (es) * 1999-02-08 2004-07-16 Hochtief Aktiengesellschaft Procedimiento para la fabricacion de una via ferrea sin balasto.
CN101413236B (zh) * 2008-09-26 2011-04-06 中铁十二局集团第二工程有限公司 Crtsⅱ型双块式无砟轨道道床板施工方法
CN101748662B (zh) * 2009-12-30 2012-10-03 中铁八局集团有限公司 路基双块式无砟轨道道床施工工艺

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1497324A1 (ru) * 1986-01-09 1989-07-30 Всесоюзный Научно-Исследовательский Институт Железнодорожного Транспорта Устройство дл сооружени безбалластного железнодорожного пути
EP0621370A1 (de) * 1993-04-22 1994-10-26 Walter Bau-Aktiengesellschaft Verfahren zum Herstellen eines schotterlosen Gleisoberbaus und ein nach dem Verfahren hergestellter Gleisoberbau
CN101215814A (zh) * 2007-12-29 2008-07-09 南车洛阳机车有限公司 双块式无碴轨道轨枕铺设施工方法及设备
CN101289828A (zh) * 2008-05-22 2008-10-22 北京铁五院工程机械科技开发有限公司 双块式无砟轨道的施工装备及施工工艺
CN101503870A (zh) * 2008-12-03 2009-08-12 中铁八局集团第一工程有限公司 一种双块式无砟轨道道床板的施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宋红红.双块式无砟轨道施工技术初探.《铁道工程学报》.2007,82-86. *
陈骁文.双块式无砟轨道施工工艺及施工精度控制.《铁道建筑》.2009,(第2期),108-110. *

Also Published As

Publication number Publication date
WO2011079677A1 (zh) 2011-07-07
CN101748662A (zh) 2010-06-23

Similar Documents

Publication Publication Date Title
CN101748662B (zh) 路基双块式无砟轨道道床施工工艺
CN101503870B (zh) 一种双块式无砟轨道道床板的施工方法
CN108951425A (zh) 现浇预应力混凝土连续箱梁一次性浇筑成型施工方法
CN103352400B (zh) 预制嵌入式轨道板
CN107313314B (zh) 一种地铁车辆段预留立柱检查坑轨道施工方法
CN101418535B (zh) 轨道交通隧道内整体道床的施工方法
CN106868959A (zh) 一种高铁无砟轨道线路快速修复的方法
CN103321111B (zh) 有轨电车轨道连铺的施工方法
CN109706846B (zh) 用于斜坡地基的高、窄桥盖梁穿心钢棒施工方法
CN111764216A (zh) 一种装配式混凝土道路板施工方法及应用
CN103952951A (zh) 一种用于高速铁路无砟轨道施工的工艺
CN108330835A (zh) 定型支架的施工方法
CN112411265A (zh) 一种适用于大跨度桥梁的无砟轨道结构及安装方法
CN102797223B (zh) 海塘区客运专线膺架法现浇道岔连续梁施工方法
CN111997066A (zh) 用于边坡加固的装配式预应力锚索框架梁制作及施工方法
CN101838967B (zh) 桥上双块式无砟轨道道床施工工艺
CN112211113A (zh) 高桥墩大跨度钻石造型盖梁现浇施工方法
CN104631332A (zh) 预应力混凝土t梁原位预制架设施工方法
CN114645490A (zh) 城市轨道交通地下线预制板无砟轨道施工方法
CN101691726A (zh) 一种双块式无砟轨道施工工艺
CN101736660B (zh) 无砟轨道人工轨排法
CN114032724B (zh) 一种装配式再生混凝土乡村路面
CN102733406B (zh) 大型工业厂房内整体道床铁路施工方法
CN114457682A (zh) 一种现浇混凝土桥梁的现浇施工方法
CN103374865A (zh) 无砟轨道板纵连铺设施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180507

Address after: 610000 north two section of the first ring road, Chengdu, Sichuan Province, No. 100

Patentee after: NO.2 ENGINEERING COMPANY OF CHINA RAILWAY NO.8 ENGINEERING GROUP Co.,Ltd.

Address before: 610036 Jinke East Road, Jinniu District, Chengdu, Sichuan Province, No. 68

Patentee before: CHINA RAILWAY NO. 8 ENGINEERING GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121003

Termination date: 20211230