CN101723056B - 船舶多波束声学设备安装工艺 - Google Patents

船舶多波束声学设备安装工艺 Download PDF

Info

Publication number
CN101723056B
CN101723056B CN 200910311786 CN200910311786A CN101723056B CN 101723056 B CN101723056 B CN 101723056B CN 200910311786 CN200910311786 CN 200910311786 CN 200910311786 A CN200910311786 A CN 200910311786A CN 101723056 B CN101723056 B CN 101723056B
Authority
CN
China
Prior art keywords
streamlined reefer
reefer housing
guide cover
battle array
beam support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200910311786
Other languages
English (en)
Other versions
CN101723056A (zh
Inventor
胡社来
颜芳
秦启虎
彭耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuchang Shipbuilding Industry Group Co Ltd
Original Assignee
WUCHANG SHIPBUILDING INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUCHANG SHIPBUILDING INDUSTRY Co Ltd filed Critical WUCHANG SHIPBUILDING INDUSTRY Co Ltd
Priority to CN 200910311786 priority Critical patent/CN101723056B/zh
Publication of CN101723056A publication Critical patent/CN101723056A/zh
Application granted granted Critical
Publication of CN101723056B publication Critical patent/CN101723056B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Artificial Fish Reefs (AREA)

Abstract

本发明公开了一种船舶多波束声学设备安装工艺,其特征在于,采用如下步骤,将导流罩分为三部分,对其安装面与下表面进行铣削加工;在内场将导流罩三部分组装,再将多波束支架及封板定位在导流罩上,在导流罩上配钻攻丝,完毕后将多波束支架及封板从导流罩卸下,制作发射阵的定位码板;用滚轮导轨将导流罩推入船体下方,将导流罩用葫芦吊起调平,将导流罩的发射阵用码板固定,并用焊接码板控制安装面的焊接变形,采用对称间断焊接方式将导流罩焊接到船体上;用滚轮导轨将多波束支架推至导流罩下方,用液压小车将多波束支架顶起至导流罩内,调整多波束支架,然后用螺栓锁紧固定;将多波束模块运至导流罩下,用液压小车将多波束模块用螺栓安装至支架内;安装封板,用螺栓固定。

Description

船舶多波束声学设备安装工艺
技术领域
本发明涉及船舶声学设备安装工艺,具体涉及船舶多波束声学设备安装工艺。
背景技术
多波束声学设备往往安装在各种海洋调查船上,其换能器由发射阵和接收阵的多个多波束模块组成,换能器安装在多波束支架内,再水平固定在船体导流罩内,换能器的下表面水平度要求非常高,要求水平误差≤2mm。常规的安装工艺是在船台上将导流罩焊接在船底部后,再加工导流罩下平面,钻孔攻丝后安装多波束支架及模块。但由于此时导流罩是位于船体基线以下,导流罩外形尺度较大、结构相对单薄,而多波束声学设备对导流罩的定位精度要求相当高,因此对于配钻攻丝,码板定位,船台安装的定位基准、焊接要求较高,大量的螺栓孔需配钻攻丝,且是仰视施工,这样按传统的安装方法施工将面临很多困难,且耗时长,延误了工期。
发明内容
本发明所要解决的技术问题是设计一种新的船舶多波束声学设备安装工艺,能解决传统的安装方法面临的安装困难问题。
为解决上述技术问题,本发明公开的一种船舶多波束声学设备安装工艺,船舶多波束声学设备包括多波束支架、多波束模块、封板,其特征在于,包括如下步骤:
第一步,将导流罩分为三部分,即导流罩发射阵、导流罩接受阵一、导流罩接受阵二,运至加工场地,对其安装面与下表面进行铣削加工,使加工面的粗糙度Ra≤12.5,安装面的平面度误差≤1mm;
第二步,在内场将导流罩发射阵、导流罩接受阵一、导流罩接受阵二组装成导流罩并调平,再将多波束支架及封板临时定位在导流罩上,调平后在导流罩上配钻攻丝,完毕后将多波束支架及封板从导流罩卸下;同时制作导流罩发射阵的定位码板;
第三步,用滚轮导轨将导流罩推入船体下方,将导流罩用葫芦吊起调平,使其安装面的水平度误差≤1mm,将导流罩发射阵用定位码板固定,定位码板上用定位销做记号,并用焊接码板控制安装面的焊接变形,采用对称间断焊接方式将导流罩焊接到船体上,用激光随时监控焊接变形对导流罩水平度的影响,并随时调整焊接方式;
第四步,用滚轮导轨将多波束支架推至导流罩下方,用液压小车将多波束支架顶起至导流罩内,调整多波束支架,并用激光监测,使其满足水平方向水平度误差≤1mm要求,然后用螺栓锁紧固定;
第五步,将多波束模块运至导流罩下,用液压小车将所有多波束模块依次顶至多波束支架内,并用螺栓锁紧固定,检查多波束模块下表面的平面度;
第六步,安装封板,并用螺钉固定。
本发明的有益效果是,操作简单方便,安全可靠,有效的解决了多波束设备安装过程中施工的难题,节约了大量的人力物力,弥补了原有声学设备安装中的不足和局限性,为多波束设备的安装开辟了新的安装方式。
附图说明
下面结合附图和具体实施方式对本发明的技术方案作进一步
具体说明。
图1为本发明一个实施例的导流罩分解示意图
图2为本发明一个实施例的定位码板示意图
图3为本发明一个实施例的焊接码板局部放大示意图
图4为本发明一个实施例的导流罩运输示意图
图5为本发明一个实施例的多波束支架运输示意图
图6为本发明一个实施例的多波束支架顶升示意图
图7为本发明一个实施例的多波束换能器模块顶升示意图
具体实施例
天然气水合物综合调查船的导流罩4在分段车间制造完毕后,由于厂内资源及受船台空间限制,将导流罩将导流罩4分为三部分,即导流罩发射阵401、导流罩接受阵一402、导流罩接受阵二403,如图1,其中导流罩发射阵从中间一分为二,将其运至成套机加车间的的铣床上,对导流罩4进行铣平面,完成后再送到轮机车间,用枕木将导流罩4各部分对接,用激光检测,调整导流罩使其下平面水平误差≤1mm,在导流罩两边的对接处用两块定位码板8分别做上定位销9记号,如图2所示,再将多波束支架5及封板7临时安装在导流罩4上,调平后对导流罩4配钻攻丝,完毕后将多波束支架5及封板7从导流罩4卸下,加工固定码板,待一切完毕后,用滚轮导轨2将导流罩推入船体1下方,如图4所示,将导流罩4各部分用葫芦吊起对接调平,并用定位码板8和定位销9定位导流罩4,并用焊接码板10控制安装面的焊接变形,如图3所示,通过激光检测,使导流罩下平面水平度误差≤1mm,并采用对称间断焊接方式将导流罩4焊接到船体1上,用激光随时监控焊接变形对导流罩水平度的影响,并随时调整焊接方式,如图5、图6所示,用滚轮导轨2将多波束支架5推至导流罩4下方,用液压小车6将多波束支架5顶起至导流罩4内,调整多波束支架5,并用激光监测,使其满足水平度要求,然后用螺栓锁紧固定,将多波束模块3运至导流罩4下,用液压小车6将所有模块依次顶至多波束支架5内,如图7,并用螺栓锁紧固定,检查模块下表面的平面度,满足平面度误差≤2mm,待模块安装完毕后,将封板7装上并用螺钉固定。
最后所应说明的是,以上具体实施方式仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的精神和范围,其均应涵盖在本发明的权利要求范围当中。

Claims (1)

1.一种船舶多波束声学设备安装工艺,船舶多波束声学设备包括多波束支架(5)、多波束换能器模块(3)、封板(7),其特征在于,包括如下步骤:
第一步,将导流罩(4)分为三部分,即导流罩发射阵(401)、导流罩接受阵一(402)、导流罩接受阵二(403),运至加工场地,对其安装面与下表面进行铣削加工,使加工面的粗糙度Ra≤12.5,安装面的平面度误差1mm;
第二步,在内场将导流罩发射阵(401)、导流罩接受阵一(402)、导流罩接受阵二(403)组装成导流罩(4)并调平,再将多波束支架(5)及封板(7)临时定位在导流罩(4)上,调平后在导流罩(4)上配钻攻丝,完毕后将多波束支架(5)及封板(7)从导流罩(4)卸下;同时制作导流罩发射阵(401)的定位码板(8);
第三步,用滚轮导轨(2)将导流罩(4)推入船体(1)下方,将导流罩(4)用葫芦吊起调平,使其安装面的水平度误差≤1mm,将导流罩发射阵(401)用定位码板(8)固定,定位码板(8)上用定位销(9)做记号,并用焊接码板(10)控制安装面的焊接变形,采用对称间断焊接方式将导流罩(4)焊接到船体(1)上,用激光随时监控焊接变形对导流罩水平度的影响,并随时调整焊接方式;
第四步,用滚轮导轨(2)将多波束支架(5)推至导流罩(4)下方,用液压小车(6)将多波束支架(5)顶起至导流罩(4)内,调整多波束支架(5),并用激光监测,使其满足水平方向水平度误差≤1mm要求,然后用螺栓锁紧固定;
第五步,将多波束换能器模块(3)运至导流罩(4)下,用液压小车(6)将所有多波束换能器模块(3)依次顶至多波束支架(5)内,并用螺栓锁紧固定,检查多波束换能器模块(3)下表面的平面度;
第六步,安装封板(7),并用螺钉固定。
CN 200910311786 2009-12-18 2009-12-18 船舶多波束声学设备安装工艺 Active CN101723056B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910311786 CN101723056B (zh) 2009-12-18 2009-12-18 船舶多波束声学设备安装工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910311786 CN101723056B (zh) 2009-12-18 2009-12-18 船舶多波束声学设备安装工艺

Publications (2)

Publication Number Publication Date
CN101723056A CN101723056A (zh) 2010-06-09
CN101723056B true CN101723056B (zh) 2013-03-20

Family

ID=42444753

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910311786 Active CN101723056B (zh) 2009-12-18 2009-12-18 船舶多波束声学设备安装工艺

Country Status (1)

Country Link
CN (1) CN101723056B (zh)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102464087B (zh) * 2010-11-09 2016-06-08 中国舰船研究设计中心 大型水声测量试验船多个功能测量区域设计方法
CN103419901B (zh) * 2013-07-11 2017-04-26 中国人民解放军92859部队 一种浸入式船用声学平台
CN103482020B (zh) * 2013-09-29 2016-03-23 武昌船舶重工集团有限公司 一种用于多波束安装的基座及多波束安装方法
CN103862235B (zh) * 2014-02-26 2016-03-30 招商局重工(江苏)有限公司 一种自升式钻井平台悬臂梁轨道的制作方法
CN106335602B (zh) * 2016-11-15 2018-03-20 中国舰船研究设计中心 科考船用的升降式多波束声学设备导流罩
CN108454801B (zh) * 2018-03-30 2019-08-13 中船重工(武汉)船舶与海洋工程装备设计有限公司 一种船舶声学设备防腐装置
CN109911105B (zh) * 2019-03-29 2021-01-08 广船国际有限公司 一种测量设备的座架的安装方法
CN110254618A (zh) * 2019-06-28 2019-09-20 中船黄埔文冲船舶有限公司 一种船舶多波束换能器阵列的安装装置及其安装方法
CN114750897B (zh) * 2022-04-29 2023-04-14 江南造船(集团)有限责任公司 一种科考船舶底部“t”字流线型多波束附体结构建造方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3962764A (en) * 1975-01-15 1976-06-15 Rca Corporation Method of installing a mount assembly in a multi-beam cathode ray tube

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3962764A (en) * 1975-01-15 1976-06-15 Rca Corporation Method of installing a mount assembly in a multi-beam cathode ray tube

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张海涛等.多波束测深系统换能器的安装校准分析.《海洋通报》.2009,第28卷(第1期),第1102-107页. *
王闰成.多波束测深系统的安装校准.《海洋测绘》.2003,第23卷(第1期),第34-37页. *
胡社来等.某综合调查船声学换能器安装工艺.《船海工程》.2011,第40卷(第1期),第51-53页. *

Also Published As

Publication number Publication date
CN101723056A (zh) 2010-06-09

Similar Documents

Publication Publication Date Title
CN101723056B (zh) 船舶多波束声学设备安装工艺
CN110525576B (zh) 一种舰船甲板基座结构及舰船甲板基座结构安装方法
CN110466680B (zh) 一种双排舱型船总段的搭载方法
CN101323351B (zh) 一种船舶舵系照光及安装的方法
CN102975817A (zh) 折叠式舱口盖和舱口围整体安装工艺方法
KR101695879B1 (ko) 부유식 해양플랜트의 상부구조물 설치방법
CN101306717A (zh) 一种船舶建造中轴系照光方法
CN110182313B (zh) 30万吨浮式生产储油轮艏货舱舷侧总段异地总组工艺
CN101913409A (zh) 一种用于船舶建造的轴系对中工艺改进方法
CN102923254B (zh) 干式台车法船舶切断加长改装技术
CN110758674A (zh) 一种船舶锚绞机总段阶段的安装方法
US20170089060A1 (en) Containerlike monolithic assembly of sets of framework structure components for large-scale industrial facility construction
CN103661807A (zh) 预先安装压力导轨架的舷侧分段合拢的定位方法
CN110481701B (zh) 一种舱盖支承部件的安装及调试方法
CN102887220A (zh) 一种电力推进器基座及其装焊方法
CN110877679A (zh) 一种格栅板在分段上的预装工艺
CN110877688A (zh) 双相不锈钢化学品船舷侧横隔舱分段的吊装及加强方法
CN109720502B (zh) 一种单点系泊浮筒转台的建造方法
CN109665441B (zh) 浮船坞起重机轨道安装方法
JP2007261413A (ja) 船体に原動機を据付ける方法
CN102528306B (zh) 海洋石油钻井架制造工法
CN113501105A (zh) 一种多用途重吊船支撑块箱在分段上的安装方法
CN104259808B (zh) 海上井架拼装及整吊上船方法
KR20130008113A (ko) 블록 정도 관리 시스템
CN102020207A (zh) 法兰式全回转重型起重机安装方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: WUCHANG SHIPBUILDING INDUSTRY GROUP CO., LTD.

Free format text: FORMER NAME: WUCHANG SHIPBUILDING INDUSTRY CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 430060 Hubei city of Wuhan province Wuchang Ziyang Road No. 2

Patentee after: WUCHANG SHIPBUILDING INDUSTRY GROUP CO., LTD.

Address before: 430060 Hubei city of Wuhan province Wuchang Ziyang Road No. 2

Patentee before: Wuchang Shipbuilding Industry Co., Ltd.