CN101408023A - Method for supporting and protecting row pile pit - Google Patents

Method for supporting and protecting row pile pit Download PDF

Info

Publication number
CN101408023A
CN101408023A CNA2008101529252A CN200810152925A CN101408023A CN 101408023 A CN101408023 A CN 101408023A CN A2008101529252 A CNA2008101529252 A CN A2008101529252A CN 200810152925 A CN200810152925 A CN 200810152925A CN 101408023 A CN101408023 A CN 101408023A
Authority
CN
China
Prior art keywords
pile
foundation pit
piles
row
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008101529252A
Other languages
Chinese (zh)
Inventor
郑刚
杨建民
程雪松
邓旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CNA2008101529252A priority Critical patent/CN101408023A/en
Publication of CN101408023A publication Critical patent/CN101408023A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种排桩基坑支护方法,所述排桩是向基坑外侧倾斜的单排排桩,该方法包括以下步骤:(a)根据场地条件和计算分析,确定排桩倾斜角度、确定桩长与桩身强度、确定基坑支护结构、确定基坑的开挖级数;(b)施工排桩;(c)施工基坑支护结构;(d)开挖基坑;(e)对基坑坑底进行清理、整平,并进行下一步的施工工作。本发明能够在很大程度上减小桩顶位移,减小桩身弯矩,降低工程造价,增加开挖深度以及使发生倾覆破坏的可能性减小。

Figure 200810152925

The invention discloses a pile row foundation pit support method. The pile row is a single row of pile piles inclined to the outside of the foundation pit. The method comprises the following steps: (a) determining the pile row inclination according to site conditions and calculation and analysis Angle, determination of pile length and pile body strength, determination of foundation pit support structure, determination of excavation levels of foundation pit; (b) construction of piles; (c) construction of foundation pit support structure; (d) excavation of foundation pit (e) Cleaning and leveling the bottom of the foundation pit, and carrying out the next step of construction work. The invention can largely reduce pile top displacement, reduce pile body bending moment, reduce engineering cost, increase excavation depth and reduce the possibility of overturning damage.

Figure 200810152925

Description

排桩基坑支护方法 Method of row pile foundation pit support

技术领域 technical field

本发明涉及地基基础领域,特别涉及一种利用排桩进行基坑支护的方法。The invention relates to the field of foundation foundations, in particular to a method for supporting foundation pits by using row piles.

背景技术 Background technique

桩排支护结构具有施工工艺简单、成本低、平面布置灵活等诸多优点,是目前国内、外应用最广泛的基坑支护形式之一。排桩支护结构可以分为悬臂式、拉锚式和内撑式三种支护类型。当基坑开挖较浅、地质条件较好、支护结构变形和坑外地面沉降控制要求不高时,可采用悬臂式排桩支护形式。排桩支护还可以结合坑内支撑或锚杆锚固提高支护能力。在软土地区当基坑开挖面积较大、支护结构变形和坑外地面沉降要求较高时,可采用内撑式排桩支护形式。当基坑土质条件可以设置锚杆,并且对周边环境影响不大时,还可采用拉锚式排桩支护形式。The pile row support structure has many advantages such as simple construction technology, low cost, and flexible layout. It is one of the most widely used forms of foundation pit support at home and abroad. The support structure of row piles can be divided into three types: cantilever type, pull-anchor type and internal support type. When the excavation of the foundation pit is shallow, the geological conditions are good, and the deformation of the support structure and the control of ground settlement outside the pit are not high, the cantilever pile row support form can be used. Pile row support can also be combined with pit support or bolt anchorage to improve support capacity. In the soft soil area, when the excavation area of the foundation pit is large, the deformation of the support structure and the ground settlement outside the pit are high, the support form of the inner support row pile can be adopted. When the soil conditions of the foundation pit can be set with anchor rods and the surrounding environment is not greatly affected, the anchor-type row pile support form can also be used.

目前的排桩支护结构均采用竖直桩,利用竖直排桩进行基坑支护时存在的常见问题是:桩顶容易产生较大位移,致使桩后基坑外地面产生较大变形,危及周围环境;当桩的强度不够时容易导致护坡桩折断而使基坑失稳;基坑可开挖的深度较小,开挖深度增大时容易倾覆。The current row of pile support structures all use vertical piles. The common problem when using vertical row of piles for foundation pit support is that the top of the pile is prone to large displacement, resulting in large deformation of the ground outside the foundation pit behind the pile. It endangers the surrounding environment; when the strength of the pile is not enough, it is easy to cause the slope protection pile to break and make the foundation pit unstable; the excavable depth of the foundation pit is small, and it is easy to overturn when the excavation depth increases.

一根或两根等少量的斜桩广泛应用于码头、桥梁、送电铁塔等工程桩基中,可采用吊打预制桩、钻孔灌注桩、套管螺旋钻成桩和人工挖孔桩等多种施工方法,是一项比较成熟的施工技术。A small number of inclined piles such as one or two are widely used in pile foundations of docks, bridges, power transmission towers, etc., and can be used for hanging prefabricated piles, bored piles, casing auger drilled piles, and artificially dug piles, etc. A variety of construction methods, is a relatively mature construction technology.

发明内容 Contents of the invention

本发明为解决公知技术中存在的技术问题而提供一种能够在很大程度上减小桩顶位移,减小桩身弯矩,降低工程造价,增加开挖深度以及使发生倾覆破坏的可能性减小的排桩基坑支护方法。In order to solve the technical problems existing in the known technology, the present invention provides a method that can greatly reduce the pile top displacement, reduce the pile body bending moment, reduce the engineering cost, increase the excavation depth and make the possibility of overturning damage occur. Reduced row pile foundation pit support method.

本发明为解决公知技术中存在的技术问题所采取的技术方案是:一种排桩基坑支护方法,所述排桩是向基坑外侧倾斜的单排排桩,该方法包括以下步骤:The technical solution adopted by the present invention for solving the technical problems existing in the known technology is: a pile row foundation pit support method, the pile row is a single row of pile piles inclined to the outside of the foundation pit, and the method includes the following steps:

(a)根据场地条件和计算分析,确定排桩倾斜角度、确定桩长与桩身强度、确定基坑支护结构、确定基坑的开挖级数;(a) According to site conditions and calculation and analysis, determine the inclination angle of the pile row, determine the length of the pile and the strength of the pile body, determine the support structure of the foundation pit, and determine the excavation stages of the foundation pit;

(b)施工排桩;(b) Construction pile arrangement;

(c)施工基坑支护结构;(c) construction of foundation pit support structure;

(d)开挖基坑;(d) excavation of foundation pits;

(e)对基坑坑底进行清理、整平,并进行下一步的施工工作。(e) Clean up and level the bottom of the foundation pit, and proceed to the next step of construction.

所述排桩的倾斜角度为:1~15°。The inclination angle of the row of piles is 1-15°.

所述排桩为钻孔灌注桩或预制桩或套管钻孔灌注桩。The row piles are bored cast-in-place piles, prefabricated piles or casing bored cast-in-place piles.

所述基坑支护结构为悬臂桩式支护或内撑式式支护或拉锚式支护。The support structure of the foundation pit is a cantilever pile type support, an inner support type support or an anchor type support.

本发明具有的优点和积极效果是:本发明是对普通竖直桩排支护的改进,用适当角度的倾斜排桩代替竖直排桩,根据场地条件和安全稳定性验算结果,使基坑支护的排桩整体向基坑外侧倾斜某一特定角度。此种方法克服了竖直排桩支护的很多不足,能够在很大程度上减小桩顶位移,减小桩身弯矩,降低工程造价,增加开挖深度以及使发生倾覆破坏的可能性减小。本发明和已有技术相比具有以下优点:在开挖深度相同的情况下该方法可以在很大程度上减小桩顶位移,使桩后地面变形大大减小,避免对周围环境造成破坏,同时可以减小桩身弯矩,使桩身配筋量显著降低,从而降低工程造价,具有很大的经济效益;当桩长和桩设计强度与普通排桩相同时,可以使开挖深度增加,具有较好的技术价值;由于开挖面倾斜,基坑发生倾覆破坏的可能性减小,有利于基坑工程的安全。由于以上倾斜桩支护的优点,原本可能需要采用内撑式支护或拉锚式支护的基坑工程,此时仅利用悬臂桩支护就可以满足设计要求,从而使设计施工更加简便,并且节约材料,降低工程造价。适用于使用排桩进行支护的基坑工程,相对于竖直排桩基坑支护方法,应用本发明可以增加基坑开挖深度、减小支护桩桩顶位移、增加排桩抗倾覆性、减小排桩设计强度,能够进一步地降低工程造价。The advantages and positive effects of the present invention are as follows: the present invention is an improvement to the support of ordinary vertical pile rows, replacing vertical piles with inclined piles with appropriate angles, and according to site conditions and safety and stability checking results, the foundation pit The supporting row of piles is inclined at a certain angle to the outside of the foundation pit as a whole. This method overcomes many deficiencies of vertical pile support, can greatly reduce pile top displacement, reduce pile body bending moment, reduce engineering cost, increase excavation depth and reduce the possibility of overturning damage decrease. Compared with the prior art, the present invention has the following advantages: in the case of the same excavation depth, the method can greatly reduce the pile top displacement, greatly reduce the deformation of the ground behind the pile, and avoid damage to the surrounding environment. At the same time, it can reduce the bending moment of the pile body, so that the reinforcement amount of the pile body can be significantly reduced, thereby reducing the project cost and having great economic benefits; when the pile length and pile design strength are the same as ordinary piles, the excavation depth can be increased , has good technical value; due to the slope of the excavation surface, the possibility of overturning damage to the foundation pit is reduced, which is beneficial to the safety of the foundation pit project. Due to the advantages of the above inclined pile support, the foundation pit project that may originally need to use internal support or pull anchor support can meet the design requirements only by using cantilever pile support, thus making the design and construction easier. And save material, reduce engineering cost. It is applicable to the foundation pit engineering supported by rows of piles. Compared with the vertical pile foundation pit support method, the application of the present invention can increase the excavation depth of the foundation pit, reduce the displacement of the pile tops of the supporting piles, and increase the anti-overturning resistance of the rows of piles. Sex, reduce the design strength of row piles, can further reduce the project cost.

附图说明 Description of drawings

图1是本发明悬臂支护的示意图;Fig. 1 is the schematic diagram of cantilever support of the present invention;

图2是本发明拉锚式支护的示意图;Fig. 2 is the schematic diagram of anchor type support of the present invention;

图3是本发明内撑式支护的示意图。Fig. 3 is a schematic diagram of the inner support of the present invention.

图中:1、排桩,2、冠梁,3、基坑坑底,4、锚杆,5、内部支撑。In the figure: 1. Row of piles, 2. Crown beam, 3. Foundation pit bottom, 4. Anchor rod, 5. Internal support.

具体实施方式 Detailed ways

为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:

请参阅图1~图3,本发明利用倾斜排桩进行基坑支护包括以下步骤:Please refer to Fig. 1~Fig. 3, the present invention utilizes inclined row pile to carry out foundation pit support and comprises the following steps:

(a)根据场地条件和安全稳定计算分析,确定最优的单排排桩1向基坑外侧倾斜的角度,排桩的倾斜角度可以为:1~15°;对桩长与桩身强度进行设计,利用倾斜排桩进行基坑支护的结构类型与普通竖直排桩相同,根据不同场地条件和工程状况,可分别采用悬臂桩支护、内撑式支护或拉锚式支护。如果悬臂桩支护不满足设计要求,可以根据实际情况采用内撑式支护或拉锚式支护,并对支撑或锚杆进行设计,确定基坑的开挖级数;(a) According to the site conditions and the calculation and analysis of safety and stability, determine the optimal angle of inclination of the single row of piles 1 to the outside of the foundation pit. The inclination angle of the row of piles can be: 1-15°; According to different site conditions and engineering conditions, cantilever pile support, internal support or pull-anchor support can be used respectively. If the cantilever pile support does not meet the design requirements, internal support or anchor support can be used according to the actual situation, and the support or anchor rod can be designed to determine the excavation level of the foundation pit;

(b)施工排桩1。由于排桩为倾斜式支护,当土质条件比较好时,可采用钻孔灌注桩;当土质条件比较差,容易发生塌孔现象时,可采用预制桩或套管螺旋钻机钻孔灌注成桩。倾斜排桩施工可采用多种方法,如吊打预制桩、钻孔灌注桩、套管螺旋钻钻孔灌注成桩和人工挖孔桩等。其中套管螺旋钻钻孔灌注成桩施工工法,具有钻孔速度快、成桩质量高、套管护壁不易塌孔、桩身倾斜度可准确控制等优点而得到广泛应用。(b) Construction row pile 1. As the row of piles is an inclined support, when the soil condition is relatively good, bored piles can be used; when the soil condition is relatively poor and hole collapse is prone to occur, prefabricated piles or casing auger drilling machines can be used to drill and pour into piles . Various methods can be used for the construction of inclined piles, such as hanging prefabricated piles, bored piles, casing auger drilled piles and artificially dug piles. Among them, the construction method of casing auger drilling and pouring into piles has been widely used because of its advantages such as fast drilling speed, high pile quality, casing wall protection is not easy to collapse holes, and the inclination of pile body can be accurately controlled.

(c)施工基坑支护结构。对于单排桩的支护结构,根据基坑所处的土层特点、周边环境等情况,可以分为以下三种形式:(c) Construction of foundation pit support structure. For the support structure of single-row piles, according to the characteristics of the soil layer where the foundation pit is located and the surrounding environment, it can be divided into the following three forms:

①悬臂桩支护。请参阅图1,当基坑开挖较浅、地质条件较好、变形控制要求不高时,可以采用排桩1上设置冠梁2的悬臂桩支护形式。在悬臂桩桩身强度达到规定要求后,就可以进行土层的开挖。① Cantilever pile support. Please refer to Figure 1. When the excavation of the foundation pit is relatively shallow, the geological conditions are good, and the requirements for deformation control are not high, the support form of cantilever piles with a crown beam 2 on the row of piles 1 can be used. After the strength of the cantilever pile meets the specified requirements, the excavation of the soil layer can be carried out.

②内撑式支护。请参阅图3,当基坑开挖面积较大、地基软弱、变形控制要求高时,可以采用排桩1内侧设置内部支撑5的内撑式支护。首先将基坑土方开挖至第一道钢筋混凝土支撑梁底的垫层底面,然后凿开支护结构与围檩的连接面,并进行钢筋混凝土支撑垫层施工,随后绑扎支撑钢筋,支立侧模板,完成后浇筑混凝土并养护,当混凝土强度达到规定时进行拆模和清理工作。② Internal support. Please refer to Fig. 3, when the excavation area of the foundation pit is large, the foundation is weak, and the deformation control requirements are high, the internal support of the internal support 5 arranged inside the row of piles 1 can be used. First, excavate the earthwork of the foundation pit to the bottom of the cushion at the bottom of the first reinforced concrete support beam, then cut out the connection surface between the retaining structure and the purlin, and carry out the construction of the reinforced concrete support cushion, and then tie the support steel bars to support the side After the formwork is completed, the concrete is poured and maintained. When the concrete strength reaches the specified level, the formwork removal and cleaning work will be carried out.

③拉锚式支护。请参阅图2,当基坑土层条件较好,达到拉锚条件,并且周边环境要求不高时,可以采用排桩1外侧设置锚杆4的拉锚式支护。当基坑首先土层开挖至第一道锚杆中心线以下一定深度处,利用机械钻孔,按照规定制作锚杆并插送杆件,随后进行注浆形成锚固段,最后当锚固体达到一定强度后将其进行张拉及锁定。③Anchor support. Please refer to Fig. 2, when the condition of the soil layer of the foundation pit is good enough to meet the conditions for pulling the anchor, and the surrounding environment requirements are not high, the anchoring type support with the anchor rod 4 arranged outside the row of piles 1 can be used. When the foundation pit is firstly excavated to a certain depth below the center line of the first anchor rod, mechanical drilling is used to make anchor rods and insert rods according to regulations, and then grouting is carried out to form the anchor section. Finally, when the anchor body reaches After a certain strength, it is stretched and locked.

(d)开挖基坑。对于分级开挖的基坑,针对不同的排桩支护形式,重复步骤(c)施工直至开挖至基坑底部。(d) Excavation of foundation pit. For foundation pits excavated in stages, for different pile row support forms, repeat step (c) until the bottom of the foundation pit is excavated.

(e)对基坑坑底3进行清理、整平,并进行下一步的施工工作。(e) Clean up and level the bottom 3 of the foundation pit, and carry out the next construction work.

本发明采用具有一定斜度的排桩对基坑进行支护,增加基坑稳定性和抗倾覆性;排桩外侧具有倾斜度的土体对排桩土压力降低,减小排桩顶端位移和桩身弯矩,从而相对提高排桩支护刚度和增加基坑开挖深度。The invention adopts row piles with a certain slope to support the foundation pit, which increases the stability and overturning resistance of the foundation pit; the soil body with slope on the outside of the pile row reduces the soil pressure on the pile row, and reduces the displacement and displacement of the top of the pile row. Bending moment of the pile body, thereby relatively improving the support stiffness of the row of piles and increasing the excavation depth of the foundation pit.

实施例1Example 1

某宿舍楼基坑工程长65.0m,宽15.0m,基坑挖深5.120m,岩土工程勘察报告显示地面至埋深2m范围内为杂填土,埋深2m至埋深12m范围内为粉土。该基坑工程施工场地周边无重要建筑,支护结构采用倾斜排桩悬臂支护,倾斜度为10°,支护桩长11m,桩径800mm,桩距100mm,采用吊打预制桩施工工法。坑内采用疏干井降水,明挖法施工,基坑四个直角处采用45°坡角放坡处理。The foundation pit project of a dormitory building is 65.0m long, 15.0m wide, and the excavation depth is 5.120m. The geotechnical engineering investigation report shows that the range from the ground to the buried depth of 2m is miscellaneous fill, and the range from the buried depth of 2m to 12m is powder earth. There are no important buildings around the construction site of the foundation pit project. The support structure adopts cantilever support of inclined piles with an inclination of 10°. The support piles are 11m long, 800mm in pile diameter, and 100mm in pile distance. Drainage wells are used for dewatering in the pit, and the open cut method is used for construction. The four right angles of the foundation pit are sloped at a slope angle of 45°.

实施例2Example 2

某地铁车站基坑工程长190.0m,宽20.7m,基坑挖深14.070m。长边方向两侧采用倾斜排桩加锚杆支护结构,两端采用地下连续墙提前封堵。The foundation pit project of a subway station is 190.0m long, 20.7m wide, and 14.070m deep. The two sides of the long side adopt inclined row piles and bolt support structure, and the two ends are blocked in advance by underground diaphragm walls.

在基坑开挖深度范围内的地层自上而下垂直分布为:填土,厚度2.70~4.50m;②淤泥,厚度8.10~13.00m;③粗砾砂,厚度1.0~8.0m;④粉质粘土,厚度0.18~2.80m;⑤残积砂质粘性土,厚度1.40~13.10m;⑥全风化花岗岩,厚度0.85~7.85m;⑦-1砂状强风化花岗岩,厚度0.40~14.50m;⑦-2碎块状强风化花岗岩,厚度1.0~3.9m;⑧中风化花岗岩,厚度1.10~12.20m;⑨微风化花岗岩。The vertical distribution of strata within the excavation depth range of the foundation pit from top to bottom is: fill soil, thickness 2.70-4.50m; ②silt, thickness 8.10-13.00m; ③coarse gravel sand, thickness 1.0-8.0m; ④silty Clay, thickness 0.18-2.80m; ⑤ residual sandy cohesive soil, thickness 1.40-13.10m; ⑥ fully weathered granite, thickness 0.85-7.85m; ⑦-1 sandy strongly weathered granite, thickness 0.40-14.50m; ⑦-2 Fragmented strongly weathered granite, with a thickness of 1.0-3.9m; ⑧medium weathered granite, with a thickness of 1.10-12.20m; ⑨slightly weathered granite.

支护结构采用倾斜排桩加锚杆支护,排桩倾斜度为10°,支护桩长29m,桩径800mm,桩距100mm,采用套管螺旋钻机钻孔灌注成桩。The support structure adopts inclined row of piles and bolt support. The inclination of the row of piles is 10°. The length of the supporting piles is 29m, the diameter of the piles is 800mm, and the distance between piles is 100mm.

锚杆锚固段长度19m,锚杆位于桩顶下3.20m、7.35m和9.95m处共三排,锚孔直径150mm,锚杆倾角α=15°,锚杆间距1.5m,选用2根28mm的III级(HRB400)钢筋。The length of the anchorage section of the anchor bolt is 19m. The anchor bolts are located in three rows at 3.20m, 7.35m and 9.95m below the pile top. The diameter of the anchor hole is 150mm. The inclination angle of the anchor bolts is α=15°. Grade III (HRB400) steel bars.

实施例3Example 3

某圆形基坑,直径126米,坑深12.650米,采用倾斜排桩和反压土进行基坑支护。基坑现场地面标高为海拔2.143米,地面至标高-18米范围内为杂填土和粉土,标高-18米至标高-27米为粉质粘土,土质条件较好。基坑内布置管井进行疏干降水。A circular foundation pit with a diameter of 126 meters and a depth of 12.650 meters is supported by inclined row piles and back pressure soil. The ground elevation of the foundation pit site is 2.143 meters above sea level, the range from the ground to the elevation -18 meters is miscellaneous fill and silt, the elevation -18 meters to the elevation -27 meters is silty clay, and the soil quality is good. Tube wells are arranged in the foundation pit for dewatering and dewatering.

基坑支护结构采用倾斜排桩悬臂支护,排桩倾斜角度为1°,支护桩长26m,桩径800mm,桩底端中心距为850mm,采用套管螺旋钻机钻孔灌注成桩。The support structure of the foundation pit adopts cantilever support of inclined row of piles. The inclination angle of the row of piles is 1°. The length of the supporting piles is 26m, the diameter of the piles is 800mm, and the distance between the centers of the pile bottoms is 850mm.

坑底预留反压土,反压土高3.5米,坑底部分反压土环形带宽为6米,反压土顶端环形带宽2.5米,反压土土坡坡度为45°,反压土表面喷素混凝土护面。Back pressure soil is reserved at the bottom of the pit. The height of the back pressure soil is 3.5 meters. Sprayed concrete facing.

本发明的基本原理是:边坡坡度小比坡度大时更稳定,更不容易发生倾覆破坏与整体稳定破坏。同理,存在一定坡度的边坡比竖直的边坡要稳定,因此对支护结构的要求更低。本发明的方法正是基于这种思想,在场地允许的情况下,采用具有一定斜度的排桩对基坑进行支护。用斜桩进行基坑支护时,桩后具有滑动趋势的楔形体要比桩竖直时的楔形体要小,原因是桩后楔形体因为坡度少了一部分。因此,土体对桩的作用力会大幅减小,这样桩顶位移和桩身受力都会减小很多。理论上来说,桩的斜度越大,桩的受力和桩顶位移越小,从而越经济,但是桩的斜度不能无限制的增大,因为由于施工场地的限制,可能没有足够的空间使桩的斜度太大,另一方面,桩的斜度大时,其基坑深度以下的桩由于伸到基坑内部空间以下,可能会影响桩基的施工。另外桩的倾斜会使桩长增大,抵消一部分因桩身强度降低带来的经济性,并且使支护桩施工难度增大。因此斜桩支护在实际应用过程中,其斜度的确定应充分考虑各方面的因素。The basic principle of the invention is: the side slope with small slope is more stable than that with large slope, and is less prone to overturning damage and overall stability damage. Similarly, slopes with a certain slope are more stable than vertical slopes, so the requirements for supporting structures are lower. The method of the present invention is just based on this idea, and the foundation pit is supported by rows of piles with a certain slope when the site permits. When inclined piles are used for foundation pit support, the wedge-shaped body with sliding tendency behind the pile is smaller than the wedge-shaped body when the pile is vertical, because the wedge-shaped body behind the pile is partly less due to the slope. Therefore, the force of the soil on the pile will be greatly reduced, so that the displacement of the pile top and the force of the pile body will be greatly reduced. Theoretically speaking, the larger the slope of the pile, the smaller the force of the pile and the displacement of the pile top, which is more economical, but the slope of the pile cannot be increased without limit, because due to the limitation of the construction site, there may not be enough space Make the inclination of pile too large, on the other hand, when the inclination of pile is big, the pile below its foundation pit depth may affect the construction of pile foundation owing to stretching below foundation pit internal space. In addition, the inclination of the pile will increase the length of the pile, offset part of the economy caused by the reduction of the strength of the pile body, and make the construction of the supporting pile more difficult. Therefore, in the actual application process of inclined pile support, the determination of its inclination should fully consider various factors.

尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以作出很多形式,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention.

Claims (4)

1.一种排桩基坑支护方法,其特征在于,所述排桩是向基坑外侧倾斜的单排排桩,该方法包括以下步骤:1. a row of pile foundation pit support method is characterized in that, described pile row is the single row of pile row that inclines to the outside of foundation pit, and the method may further comprise the steps: (a)根据场地条件和计算分析,确定排桩倾斜角度、确定桩长与桩身强度、确定基坑支护结构、确定基坑的开挖级数;(a) According to site conditions and calculation and analysis, determine the inclination angle of the pile row, determine the length of the pile and the strength of the pile body, determine the support structure of the foundation pit, and determine the excavation stages of the foundation pit; (b)施工排桩;(b) Construction pile arrangement; (c)施工基坑支护结构;(c) construction of foundation pit support structure; (d)开挖基坑;(d) excavation of foundation pits; (e)对基坑坑底进行清理、整平,并进行下一步的施工工作。(e) Clean up and level the bottom of the foundation pit, and proceed to the next step of construction. 2.根据权利要求1所述的排桩基坑支护方法,其特征在于:所述排桩的倾斜角度为:1~15°。2. The foundation pit support method according to claim 1, characterized in that: the inclination angle of the pile row is 1-15°. 3.根据权利要求2所述的排桩基坑支护方法,其特征在于:所述排桩为钻孔灌注桩或预制桩或套管钻孔灌注桩。3. The foundation pit supporting method according to claim 2, characterized in that: said piles are bored piles, prefabricated piles or casing bored piles. 4.根据权利要求2所述的排桩基坑支护方法,其特征在于:所述基坑支护结构为悬臂桩式支护或内撑式式支护或拉锚式支护。4. The foundation pit support method according to claim 2, characterized in that: the foundation pit support structure is a cantilever pile type support or an inner support type support or an anchor type support.
CNA2008101529252A 2008-11-11 2008-11-11 Method for supporting and protecting row pile pit Pending CN101408023A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008101529252A CN101408023A (en) 2008-11-11 2008-11-11 Method for supporting and protecting row pile pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008101529252A CN101408023A (en) 2008-11-11 2008-11-11 Method for supporting and protecting row pile pit

Publications (1)

Publication Number Publication Date
CN101408023A true CN101408023A (en) 2009-04-15

Family

ID=40571213

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008101529252A Pending CN101408023A (en) 2008-11-11 2008-11-11 Method for supporting and protecting row pile pit

Country Status (1)

Country Link
CN (1) CN101408023A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864781A (en) * 2012-09-29 2013-01-09 成都四海岩土工程有限公司 Foundation pit supporting method utilizing inclined piles
CN103114595A (en) * 2013-01-06 2013-05-22 厦门源昌城建集团有限公司 Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN103132530A (en) * 2011-11-29 2013-06-05 上海市基础工程有限公司 Guard relay pile construction method under land and rock combination geological conditions
CN103132532A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit support method for row of piles
CN103485347A (en) * 2012-06-07 2014-01-01 叶强 Batter pile used for building foundation pit support and construction method thereof
CN103510524A (en) * 2012-06-26 2014-01-15 邹宗煊 Inclined circular annular pile and construction method thereof
CN103669365A (en) * 2012-08-29 2014-03-26 张绍球 External diagonal-pulling and internal diagonal-bracing herringbone foundation pit supporting pile and construction method thereof
CN106638609A (en) * 2016-11-21 2017-05-10 上海建工二建集团有限公司 Upright post pile
CN107620309A (en) * 2017-07-27 2018-01-23 天津大学 Foundation pit supporting method
CN108978687A (en) * 2018-09-03 2018-12-11 南华大学 It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method
CN110468850A (en) * 2019-08-29 2019-11-19 天津大学 A kind of oblique cement mixing method foundation pit supporting system and method for protecting support
CN111720142A (en) * 2020-05-28 2020-09-29 三明学院 An advanced support method for man-dug piles suitable for karst strata
CN112832296A (en) * 2020-12-31 2021-05-25 广东大禹水利建设有限公司 Strong-permeable stratum anti-seepage method for pump station construction
CN114561961A (en) * 2022-04-19 2022-05-31 中国建筑一局(集团)有限公司 Foundation pit pile-anchor supporting system for reducing anchor cable penetration depth and construction method thereof

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132530B (en) * 2011-11-29 2015-10-14 上海市基础工程集团有限公司 Tu Yan is in conjunction with the construction method of guard relay pile under geological conditions
CN103132530A (en) * 2011-11-29 2013-06-05 上海市基础工程有限公司 Guard relay pile construction method under land and rock combination geological conditions
CN103485347A (en) * 2012-06-07 2014-01-01 叶强 Batter pile used for building foundation pit support and construction method thereof
CN103510524A (en) * 2012-06-26 2014-01-15 邹宗煊 Inclined circular annular pile and construction method thereof
CN103669365A (en) * 2012-08-29 2014-03-26 张绍球 External diagonal-pulling and internal diagonal-bracing herringbone foundation pit supporting pile and construction method thereof
CN102864781A (en) * 2012-09-29 2013-01-09 成都四海岩土工程有限公司 Foundation pit supporting method utilizing inclined piles
CN103114595A (en) * 2013-01-06 2013-05-22 厦门源昌城建集团有限公司 Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN103132532A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit support method for row of piles
CN106638609A (en) * 2016-11-21 2017-05-10 上海建工二建集团有限公司 Upright post pile
CN107620309A (en) * 2017-07-27 2018-01-23 天津大学 Foundation pit supporting method
CN108978687A (en) * 2018-09-03 2018-12-11 南华大学 It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method
CN110468850A (en) * 2019-08-29 2019-11-19 天津大学 A kind of oblique cement mixing method foundation pit supporting system and method for protecting support
CN111720142A (en) * 2020-05-28 2020-09-29 三明学院 An advanced support method for man-dug piles suitable for karst strata
CN112832296A (en) * 2020-12-31 2021-05-25 广东大禹水利建设有限公司 Strong-permeable stratum anti-seepage method for pump station construction
CN114561961A (en) * 2022-04-19 2022-05-31 中国建筑一局(集团)有限公司 Foundation pit pile-anchor supporting system for reducing anchor cable penetration depth and construction method thereof

Similar Documents

Publication Publication Date Title
CN101408023A (en) Method for supporting and protecting row pile pit
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN100465386C (en) Foundation Pit Supporting Method with Pile and Anchor
CN100580190C (en) Building foundation pit support structure
CN104631438B (en) Long auger guncreting uplift pile construction method
CN111236040A (en) D-shaped temporary beam erecting method for underneath passing through railway frame bridge type tunnel
CN206220105U (en) A kind of double-deck Frozen Soil Cylinder anchoring soil nailed wall retaining structure system
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN206034454U (en) Supporting construction
CN112922020A (en) Fan cylindrical foundation consisting of secant piles and construction method
CN218204422U (en) Foundation pit supporting structure of PRC tubular pile and prestressed anchorage cable combination
CN111042161B (en) A flexible treatment structure for high slopes with landslide accumulation and its construction method
CN211200426U (en) Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN205502063U (en) Combined type retaining structure
CN103132532A (en) Foundation pit support method for row of piles
CN111877358B (en) A support structure, building and construction method for a foundation pit with upper soil layer and lower soft rock
CN207109796U (en) Deep & thick silt matter riverbed piping lane crosses the river double steel plate pile cofferdam structure
CN220433745U (en) Structure for resisting floating by supporting piles during construction of cyclone well
CN207878200U (en) Face bank subgrade support retainer structure
CN215593875U (en) A new type of prefabricated ecological permeable flood control wall structure
CN212405174U (en) Supporting structure and building of soft rock foundation pit at lower part of upper soil layer
CN211621555U (en) Uplift pile prefabricated with uplift block
CN203334294U (en) Combined foundation pit supporting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090415