CN102635120B - Circular deep foundation ditch is without Construction of Supporting structure and construction method - Google Patents

Circular deep foundation ditch is without Construction of Supporting structure and construction method Download PDF

Info

Publication number
CN102635120B
CN102635120B CN201210134562.6A CN201210134562A CN102635120B CN 102635120 B CN102635120 B CN 102635120B CN 201210134562 A CN201210134562 A CN 201210134562A CN 102635120 B CN102635120 B CN 102635120B
Authority
CN
China
Prior art keywords
construction
purlin
pile
stake
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210134562.6A
Other languages
Chinese (zh)
Other versions
CN102635120A (en
Inventor
张全胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201210134562.6A priority Critical patent/CN102635120B/en
Publication of CN102635120A publication Critical patent/CN102635120A/en
Application granted granted Critical
Publication of CN102635120B publication Critical patent/CN102635120B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of circular deep foundation ditch without Construction of Supporting structure and construction method, by carrying out three axes agitating pile construction, bored pile construction, Stabilizing Grout, soil excavation, first encloses purlin construction, continue soil excavation, enclose down purlin construction together, continue soil excavation, carry out the step such as bed course and construction of bottom plates, obtain a kind of primarily of a circle three axes agitating pile, one circle bored pile and multiple tracks enclose the deep footing groove enclosing structure that purlin is formed, this space enclosing structure is without any braced structures, make use of the arch effect of the soil body, reduce the soil pressure acted in space enclosing structure, also utilize the arch effect of enclosing purlin simultaneously and external loads is converted into the internal pressure acting on and enclose purlin, give full play to the feature that concrete anti-compression performance is good, and owing to not supporting, also the process of tearing support and support replacement open is just eliminated, bracing of foundation pit expense is reduced, speed of application is accelerated.

Description

Circular deep foundation ditch is without Construction of Supporting structure and construction method
Technical field
The invention belongs to the realm of building construction, specifically relate to a kind of constructing structure and construction method of circular deep foundation ditch.
Background technology
Along with the rapid development of China's economic and the quickening of urbanization process, land resources is more and more nervous, in order to make full use of land resources, alleviate urban land difficulty, build and become inevitable, in the exploitation process of the underground space to high-altitude and underground development, deep-foundation pit engineering becomes unavoidable problem, foundation ditch is the important component part of highrise building and heavy civil engineering, and in the transformation of mature city, base pit engineering often concentrates on area, down town.Base pit engineering is large-scale soil excavation engineering, and its most direct consequence is the distribution again causing surrounding soil ess-strain, causes the movement of surrounding formation, produces larger ground settlement and differential settlement, unfavorable to surrounding buildings environment.Light then produce building tear, cause the inconvenience of user, heavy then occur the phenomenon of line fracture, house collapse, cause the massive losses of human and material resources, financial resources.Base pit engineering is now day by day towards " dark, difficult, dangerous, large " future development, also day by day serious on the impact of environment.How to guarantee foundation ditch ontological security and reduce to have become to the protection of surrounding enviroment the difficult problem that China's engineering circles faces.
At present generally take agitation pile sealing, castinplace pile to keep off soil for deep foundation ditch, then add the construction method of inner support, or adopt diaphragm wall to keep off native sealing to add the construction method that inner support supports again.Because the above-mentioned construction method generally adopted all employ inner support, and inner support can affect shoveling speed in foundation ditch, and needs support replacement to tear support open, causes that speed of application is slow, the wasting of resources, thus causes cost high.
Summary of the invention
In order to overcome above-mentioned defect, the invention provides a kind of circular deep foundation ditch without Construction of Supporting structure and construction method, this circular deep foundation ditch eliminates support and support replacement without Construction of Supporting structure and construction method, make the reduction of bracing of foundation pit expense, speed of application quickening, make use of the arch effect of the soil body, reduce the soil pressure acted in space enclosing structure, also utilize the arch effect of enclosing purlin simultaneously and external loads is converted into the internal pressure acting on and enclose purlin, give full play to the feature that concrete anti-compression performance is good.
The present invention in order to the technical scheme solving its technical problem and adopt is:
A kind of circular deep foundation ditch is without Construction of Supporting structure, be provided with a circle three axes agitating pile, one circle bored pile and some roads enclose purlin, some described three axes agitating pile surround circle and continuous print one circle, some described bored piles surround circle and the spaced circle of tool, a described circle three axes agitating pile is positioned at the periphery of a described circle bored pile, enclosing purlin described in per pass is all the shaping annular of one-time-concreting, it is Guan Liang that first encloses purlin, described Guan Liang is cast in a described circle stake top for bored pile and the main muscle epimere of bored pile is placed in hat beam, all the other enclose purlin be all cast in described one circle bored pile inner ring side on and be fixedly connected with bored pile, there is spacing in the adjacent purlin in the vertical direction that encloses.
All the other except Guan Liang are enclosed purlin and are all provided with and somely hang muscle, described in hang the main muscle that muscle is welded in described bored pile.
A kind of circular deep foundation ditch support free construction method, comprises the steps:
One, three axes agitating pile construction: set up a corral circular and continuous print three axes agitating pile;
Two, bored pile construction: set up a corral circular and the bored pile at interval within a described circle three axes agitating pile;
Three, the soil body between three axes agitating pile and bored pile adopts grouting and reinforcing;
Four, the top layer earthwork is excavated, then carry out first enclose purlin construction and maintenance to design strength, it is Guan Liang that described first encloses purlin, described Guan Liang is cast in a described circle stake top for bored pile and the main muscle of bored pile is placed in hat beam, ensure that the hat beam one-time-concreting of annular completes;
Five, earth excavation is continued, dig to second and enclose purlin elevation location, then carry out second enclose purlin construction and maintenance to design strength, described second enclose purlin be cast in described one circle bored pile inner ring side on and be fixedly connected with bored pile, ensure that the second of annular encloses purlin one-time-concreting and completes;
Six, earth excavation is continued, dig and enclose purlin elevation location to the 3rd road, then carry out the 3rd road enclose purlin construction and maintenance to design strength, described 3rd road enclose purlin be cast in described one circle bored pile inner ring side on and be fixedly connected with bored pile, ensure that the 3rd road of annular encloses purlin one-time-concreting and completes;
Seven, earth excavation is continued, Wa Zhi n-th encloses purlin elevation location in road, then carry out the n-th road enclose purlin construction and maintenance to design strength, described n-th road enclose purlin be cast in described one circle bored pile inner ring side on and be fixedly connected with bored pile, ensure that the n-th road of annular encloses purlin one-time-concreting and completes;
Eight, continue earth excavation, dig to hole end absolute altitude, then carry out bed course and construction of bottom plates.
In described step one, three axes agitating pile adopts one-sided compression mode or jumps the mode of beating and constructs.
Before carrying out described step one, first carry out levelling of the land and surveying setting-out.
In described step 5, the mode of earth excavation is: arrange the car ramp that leads in hole, take from, move back while the mode excavated, finally close up in car ramp and margin of foundation pit and have a common boundary.
In described step 6, the mode of earth excavation is: the earthwork to be transported near car ramp side in foundation ditch with digging machine, and long-armed digging machine rests in the ground on foundation ditch limit and fetches earth near side, ramp and be placed on cubic metre of earth car and transport outward.
In described step 7 and step 8, the mode of earth excavation is: adopt central island digging mode, pile in the middle of foundation ditch with digging machine by the earthwork, with tower crane, the earthwork is winched to a cubic metre of earth car outward transport.
All the other except Guan Liang are enclosed purlin and are all established when building and somely hang muscle, and will hang muscle and be welded in the main muscle of bored pile.
Complete construction method is carried out in the steps below:
One, levelling of the land: before three axle mixer constructions, first must carry out levelling of the land, remove top layer hard object and the underground obstacle of construction area;
Two, surveying setting-out:
A. the measuring point provided according to Construction unit is reference point, arranges in-site measurement control point and absolute altitude control point;
B. Survey control point is arranged in the center of circle of foundation pit enclosure structure plane;
C. all by stake, position measuring is carried out to each width three axes agitating pile, each root bored pile;
D. three axes agitating pile puts central axis, then by circle fluting, then measuring axis pore is for controlling stake position;
Three, three axes agitating pile construction:
A. according to three axes agitating pile unwrapping wire location, adopt digging machine excavation guide groove, guide groove dimensional requirement center line both sides are wide each 0.5 ~ 0.7 meter, dark 1.0 ~ 1.5 meters;
B., location shaped steel is set: under vertical guide slot direction places two, locate shaped steel, place in parallel guide slots direction on two and locate shaped steel, select according to stake machine size, mark made by upper location shaped steel, marking path is selected according to stake footpath, so that look for stake position in construction;
C. pile-forming machine perching: should according to circular feature, every three axle stake adjustment stride trends, notice that overlap joint beaten by cover, gantry upright post verticality will guarantee verticality≤0.004 of a machine, and position after position of p ile machine again and check, deviate is less than 5cm simultaneously;
D. cement paste preparation: water/binder ratio is 1.5 ~ 2.0, cement adopts more than P.O42.5 portland cement, and cement mixed weight is be stirred soil mass consolidation quality 15% ~ 23%;
E. creep into and stir whitewashing: starter motor, stake machine stirs, and when whitewashing is crept in sinking, subsidence velocity is 0.5m/min ~ 1.0m/min, and whitewashing amount controls measure in total whitewashing 50% ~ 70%, in the suitable Keep agitation whitewashing of stake bottom part;
F. promote and stir whitewashing: promoting hoisting velocity when stirring whitewashing is 1.0m/min ~ 2.0m/min, and whitewashing amount controls measure in total whitewashing 30% ~ 50%;
G. stake machine displacement in place, takes one-sided compression mode or jumps the mode of beating to construct, and makes three axes agitating pile enclose a conglobate circle and continuous;
Four, bored pile construction:
A. position measuring is carried out according to dominating pair of vertices bored pile by root;
B. shield-tube embedment: with stake position central point for the center of circle, dig out the round pool than the design large 250mm ~ 350mm in stake footpath, casing is vertically fixed on stake position place and corrects, after reaching requirement, surrounding clay tamps, and guarantees to stablize, and makes a record and carry out repetition measurement;
C. rig installation in position: rig is installed must level, straight and firm, ensures that drilling rod, rotating disk and casing center are on same plumb line simultaneously;
D. slurrying: mud property requires as following table:
Project Proportion Viscosity (S)
Inject aperture mud ≤1.15 18~22
Delivery port mud ≤1.3 20~26
E. drilling and forming hole: according to design pile-type, select rig, carry out drilling and forming hole construction, bit diameter should equal the intended diameter of stake, bit conical angle should be greater than 120 °, often to veritify bit size in construction, should repair in time or change when finding that wearing and tearing are not up to standard, ensure that expanded diameter meets design requirement;
F. once clear hole: creep into projected depth, by 0.15m ~ 0.25m at the bottom of drilling tool lift-off hole, up and down reciprocatingly lifting low speed revolution, and full pump amount punching, larger particles soil block at the bottom of abundant grinding hole, treats to return out in hole in slurries and can be considered that once hole is complete clearly without clod;
G. downcomer;
H. secondary pile hole cleaning;
I. concreting, formed surround circle and one of interval circle bored pile and be positioned at described one circle three axes agitating pile within;
Five, between three axes agitating pile and bored pile, the soil body adopts grouting and reinforcing;
Six, top layer soil excavation, carry out first enclose purlin construction and maintenance to design strength, described first enclose purlin be Guan Liang and be cast in described one circle the stake top of bored pile and the main muscle epimere of bored pile be placed in hat beam in, ensure that the hat beam one-time-concreting of annular completes;
Seven, first encloses purlin absolute altitude to second and encloses purlin elevation location soil excavation: arrange the car ramp that leads in hole, take from, move back while the mode excavated, finally close up in car ramp and margin of foundation pit and have a common boundary;
Eight, second enclose purlin construction: carry out second enclose purlin construction and maintenance to design strength, ensure the second of annular enclose purlin and following each road thereof enclose purlin all one-time-concreting complete, described second encloses purlin and following each road thereof and encloses purlin and be all cast on the inner ring side of a described circle bored pile, and described second encloses purlin and following each road thereof encloses purlin and all establish when building and somely hang muscle and joint bar, and will muscle and joint bar be hung be welded in the main muscle of bored pile;
Nine, second encloses purlin absolute altitude and encloses purlin elevation location soil excavation to the 3rd road: the earthwork to be transported near car ramp side in foundation ditch with digging machine, fetches earth near side, ramp and be placed on cubic metre of earth car and transport outward in the ground that long-armed digging machine rests in foundation ditch limit;
Ten, the 3rd road enclose purlin construction: carry out the 3rd road enclose purlin construction and maintenance to design strength;
11, the 3rd road encloses purlin absolute altitude and encloses purlin elevation location soil excavation to the 4th road: adopt central island digging mode, pile in the middle of foundation ditch with digging machine by the earthwork, with tower crane, the earthwork is winched to a cubic metre of earth car outward transport;
12, the 4th road encloses purlin construction: while the 3rd road and the 4th road to enclose between purlin central island earthwork outward transport, carry out the 4th road enclose purlin construction and maintenance to design strength;
13, step 11 and step 12 is repeated;
14, n-th road encloses purlin absolute altitude to hole end elevation location soil excavation: adopt central island digging mode, pile in the middle of foundation ditch with digging machine by the earthwork, with tower crane, the earthwork is winched to a cubic metre of earth car outward transport;
15, bed course and construction of bottom plates is carried out;
16, main body construction is carried out.
The invention has the beneficial effects as follows: circular deep foundation ditch of the present invention eliminates braced structures without Construction of Supporting structure and construction method and tears the process of support support replacement open, make the reduction of bracing of foundation pit expense, speed of application quickening, and make use of the arch effect of the soil body, reduce the soil pressure acted in space enclosing structure, also utilize the arch effect of enclosing purlin simultaneously and external loads is converted into the internal pressure acting on and enclose purlin, give full play to the feature that concrete anti-compression performance is good.
Accompanying drawing explanation
Fig. 1 is plan view of the present invention;
Fig. 2 is sectional view of the present invention;
Fig. 3 be of the present invention enclose purlin place hang muscle and joint bar schematic diagram.
Detailed description of the invention
Embodiment 1: a kind of circular deep foundation ditch is without Construction of Supporting structure, be provided with a circle three axes agitating pile 1, one circle bored pile 2 and some roads enclose purlin 3, some described three axes agitating pile surround circle and continuous print one circle, some described bored piles surround circle and the spaced circle of tool, a described circle three axes agitating pile is positioned at the periphery of a described circle bored pile, enclosing purlin described in per pass is all the shaping annular of one-time-concreting, it is Guan Liang that first encloses purlin, described Guan Liang is cast in a described circle stake top for bored pile and the main muscle of bored pile will be placed in hat beam, all the other enclose purlin be all cast in described one circle bored pile inner ring side on and be fixedly connected with bored pile, there is spacing in the adjacent purlin in the vertical direction that encloses.
All the other except Guan Liang are enclosed purlin and are all provided with and somely hang muscle 4 and joint bar 5, described in hang the main muscle 21 that muscle and joint bar are welded in described bored pile 2.
Embodiment 2: a kind of circular deep foundation ditch support free construction method, carry out according to the following steps:
(1) levelling of the land: before three axle mixer constructions, first must carry out levelling of the land, remove top layer hard object and the underground obstacle of construction area, can adopt pading plate method to be convenient to pile frame walking to strengthen load-bearing load;
(2) surveying setting-out:
A. the measuring point provided according to Construction unit is reference point, arranges in-site measurement control point and absolute altitude control point;
B. Survey control point is arranged in the center of circle of foundation pit enclosure structure plane;
C. all by stake, position measuring is carried out to each width three axes agitating pile, each root bored pile;
D. three axes agitating pile puts central axis, and by circle fluting, then measuring axis pore is for controlling stake position;
(3) three axes agitating pile construction
A. according to three axes agitating pile unwrapping wire location, adopt digging machine excavation guide groove, guide groove dimensional requirement center line both sides are wide each 0.5 ~ 0.7 meter, dark 1.0 ~ 1.5 meters;
B. arrange location shaped steel: shaped steel is located under placing two in vertical guide slot direction, specification is H200mm × 200mm, is about 2.5m; Place in parallel guide slots direction on two and locate shaped steel, specification H300mm × 300mm, H350mm × 350mm or H400mm × 400mm, is about 8 ~ 20m; Select according to stake machine size, mark made by upper location shaped steel, and marking path is selected according to stake footpath, so that look for stake position in construction.
C. pile-forming machine perching: should according to circular feature, every three axle stakes adjustment strides trends, notice that overlap joint beaten by cover simultaneously, accomplish to stablize, straight and even.Gantry upright post verticality will guarantee verticality≤1/250 of a machine.Position after position of p ile machine again and check, deviate is less than 5cm.
D. cement paste preparation: generally water/binder ratio is 1.5 ~ 2.0, cement adopts more than P.O42.5 Portland cement, and cement mixed weight is be stirred soil mass consolidation quality 15 ~ 23%;
E. creep into and stir whitewashing: starter motor, stake machine stirs, and when whitewashing is crept in sinking, subsidence velocity is 0.5m/min ~ 1.0m/min, and whitewashing amount controls measure in total whitewashing about 60%, in the suitable Keep agitation whitewashing of stake bottom part.
F. promote and stir whitewashing: promoting hoisting velocity when stirring whitewashing is 1.0m/min ~ 2.0m/min, and whitewashing amount controls measure in total whitewashing about 40%;
G. stake machine displacement in place, takes one-sided compression mode or jumps the mode of beating to construct, and makes three axes agitating pile enclose a conglobate circle and continuous;
(4) bored pile construction
A. position measuring is carried out according to dominating pair of vertices bored pile by root;
B. shield-tube embedment: with stake position central point for the center of circle, dig out the round pool than design large about the 300mm in stake footpath, casing is vertically fixed on stake position place and corrects, after reaching requirement, surrounding clay tamps, and guarantees to stablize, and makes a record and carry out repetition measurement;
C. rig installation in position: rig is installed must level, straight, firm, ensures that drilling rod, rotating disk, casing center are on same plumb line, accomplish sight alignment simultaneously;
D. slurrying: mud property requires as following table:
Project Proportion Viscosity (S)
Inject aperture mud ≤1.15 18~22
Delivery port mud ≤1.3 20~26
E. drilling and forming hole: according to design pile-type, select rig, carry out drilling and forming hole construction, bit diameter should equal the intended diameter of stake, bit conical angle should be greater than 120 °, often to veritify bit size in construction, find that wearing and tearing excessively should to repair in time, to change, ensure that expanded diameter meets design requirement.
F. once clear hole: creep into projected depth, by about 0.2m at the bottom of drilling tool lift-off hole, be up and down reciprocatingly elevated, low speed turns round, the punching of full pump amount, larger particles soil block at the bottom of abundant grinding hole, treats to return out in hole in slurries to can be considered that once hole is complete clearly without clod;
G. downcomer;
H. secondary pile hole cleaning;
I. concreting, formed surround circle and one of interval circle bored pile and be positioned at described one circle three axes agitating pile within;
(5) between three axes agitating pile and bored pile, the soil body adopts grouting and reinforcing;
(6) shallow-layer (top layer) soil excavation, carry out first enclose purlin (Guan Liang) construction and maintenance to design strength, described Guan Liang builds in a described circle stake top for bored pile and the main muscle epimere of bored pile will be inserted in hat beam, ensure that the first of annular encloses purlin one-time-concreting and completes, must not build several times;
(7) first encloses purlin absolute altitude to second and encloses purlin elevation location soil excavation: can arrange the car ramp led in hole, take from, move back while the mode excavated, finally close up in car ramp and margin of foundation pit and have a common boundary;
(8) second enclose purlin construction: carry out second enclose purlin construction and maintenance to design strength, ensure the second of annular enclose purlin and following each road thereof enclose purlin all one-time-concreting complete, described second encloses purlin and following each road thereof and encloses purlin and all build on the inner ring side of a described circle bored pile, and described second encloses purlin and following each road thereof encloses purlin and all establish when building and somely hang muscle 4 and joint bar 5, and will muscle and joint bar be hung be welded in the main muscle 21 of bored pile, as shown in Figure 3;
(9) second encloses purlin absolute altitude and encloses purlin elevation location soil excavation to the 3rd road: the earthwork to be transported near earthwork outward transport car ramp side in foundation ditch with Miniature digging machine, and long-armed digging machine rests in foundation ditch limit, ground and fetches earth near side, ramp and be placed on cubic metre of earth car and transport outward;
(10) the 3rd roads enclose purlin construction: carry out the 3rd road enclose purlin construction and maintenance to design strength, ensure that annular encloses purlin one-time-concreting and completes, must not build several times;
(11) the 3rd roads enclose purlin absolute altitude and enclose purlin elevation location soil excavation to the 4th road: adopt central island digging mode, pile in the middle of foundation ditch with Miniature digging machine by the earthwork, with tower crane, the earthwork are winched to a cubic metre of earth car outward transport;
(12) the 4th roads enclose purlin construction: while the 3rd road and the 4th road to enclose between purlin central island earthwork outward transport, carry out the 4th road enclose purlin construction and maintenance to design strength, ensure that annular encloses purlin one-time-concreting and completes, must not build several times;
(13) (11) and (12) are repeated;
(14) n-th roads enclose purlin absolute altitude to hole end elevation location soil excavation: adopt central island digging mode, pile in the middle of foundation ditch with Miniature digging machine by the earthwork, with tower crane, the earthwork are winched to a cubic metre of earth car outward transport;
(15) bed course and construction of bottom plates is carried out;
(16) main body construction is carried out.
Embodiment 3: (this foundation ditch completes bottom slab concreting on March 15th, 2012 with concerted effort elevator (Kunshan) checkout tower foundation ditch, now just carry out main structure construction) be example, this project is positioned at high-tech industrial park, Kunshan City, Jiangsu Province, the above height in tower body ground about 235m, will become the highest elevator experimental tower in the world after building up.This Deep Foundation Pit cutting depth is 15.10m, and flat shape is circular, diameter 45.8m.Take following construction sequence:
(1) levelling of the land: carry out levelling of the land, removes top layer hard object and the underground obstacle of construction area;
(2) surveying setting-out:
A. the measuring point provided according to Construction unit is reference point, arranges in-site measurement control point, absolute altitude control point;
B. Survey control point is arranged in the center of circle of foundation pit enclosure structure plane, and is fixed and carries out protection;
C. measuring apparatus adopts total powerstation, measures, all carry out position measuring by stake to each width three axes agitating pile, each root drill-pouring soldier pile by wholecircle observation procedure;
D. three axes agitating pile puts central axis, and by circle fluting, then measuring axis pore is for controlling stake position;
(3) three axes agitating pile construction:
A. according to three axes agitating pile unwrapping wire location, adopt digging machine excavation guide groove, center line both sides are wide each 0.6 meter, dark 1.0 meters;
B., location shaped steel is set: two location shaped steel are placed in vertical guide slot direction, specification is 200mm × 200mm, long 2.5m, two location shaped steel specification 300mm × 300mm are placed in parallel guide slots direction, be about 12m, shaped steel makes a mark with red paint every 1.2 meters, looks for stake position in constructability, H profile steel locator card is less than guide groove sideline.
C. pile-forming machine perching: this engineering adopts ZLD150/85-3 type three axle machine, according to circular feature, every three axle stakes adjustment strides trend (every adjustment 2 degree 48 points and 45 seconds), then observe gantry upright post verticality to guarantee verticality≤1/250 of a machine with plumb bob.Position after position of p ile machine again and check, deviate is less than 5cm.
D. cement paste preparation: water/binder ratio is 1.5, cement adopts P.O42.5 Portland cement, and cement mixed weight is be stirred soil mass consolidation quality 20%;
E. creep into and stir whitewashing: starter motor, stake machine stirs, and when whitewashing is crept in sinking, subsidence velocity is 0.8m/min, and whitewashing amount controls in about 60% of whitewashing amount, in the suitable Keep agitation whitewashing of stake bottom part.
F. promote and stir whitewashing: promoting hoisting velocity when stirring whitewashing is 1.5m/min, and whitewashing amount controls measure in total whitewashing about 40%;
G. stake machine displacement in place, takes one-sided compression mode to construct, and makes three axes agitating pile enclose a conglobate circle and continuously;
(4) bored pile construction:
A. position measuring is carried out according to dominating pair of vertices drill-pouring by root;
B. shield-tube embedment: with stake position central point for the center of circle, dig out the round pool of about 300mm larger than design stake footpath, adopt cross searching sash weight method that casing (casing diameter is stake footpath+100mm) is vertically fixed on stake position place to correct, after reaching requirement, surrounding clay tamps, guarantee to stablize, and make a record and carry out repetition measurement;
C. rig installation in position: this engineering adopts GPS-15 type rig, rig is installed must level, straight, firm, ensures that drilling rod, rotating disk, casing center are on same plumb line, accomplish sight alignment simultaneously;
D. slurrying: mud property requires as following table:
Project Proportion Viscosity (S)
Inject aperture mud ≤1.15 18~22
Delivery port mud ≤1.3 20~26
E. drilling and forming hole: according to design pile-type, select rig, carry out drilling and forming hole construction, bit diameter should equal the intended diameter of stake, and bit conical angle 120 °, often will veritify bit size in construction, find that wearing and tearing excessively should to repair in time, to change, ensure that expanded diameter meets design requirement.
F. once clear hole: normal circulation slewing drilling machine enters pore-forming, creeps into projected depth, by about 0.2m at the bottom of drilling tool lift-off hole, up and down reciprocatingly be elevated, low speed turns round, the punching of full pump amount, larger particles soil block at the bottom of abundant grinding hole, treats to return out in hole in slurries and can be considered that once clear hole is complete without clod;
G. downcomer;
H. secondary pile hole cleaning;
I. concreting, formed surround circle and one of interval circle bored pile and be positioned at described one circle three axes agitating pile within;
(5) Stabilizing Grout between three axes agitating pile and bored pile: compaction grouting slurries injection rate is 20%, adopt P.O42.5 level Portland cement, cement: flyash: water glass=1: 0.5: 0.04, water/binder ratio is 0.55, tube pulling height 0.33m, adopt and jump span slip casting, slip casting position is the space between two castinplace piles;
(6) the shallow-layer earthwork is excavated to-0.500m, carry out first enclose purlin (Guan Liang) construction and maintenance to design strength, described Guan Liang is cast in a described circle stake top for bored pile and the main muscle of bored pile inserts 500mm in hat beam, ensure that annular encloses purlin one-time-concreting and completes, must not build several times;
(7) first encloses purlin absolute altitude to second and encloses absolute altitude (-5.950m) position soil excavation at the bottom of purlin: arrange the car ramp led in hole, and laying depth is the steel plate of 5mm, take from south orientation north, move back while the mode excavated, finally close up in north side car ramp and margin of foundation pit and have a common boundary;
(8) second enclose purlin construction: carry out second enclose purlin construction and maintenance to design strength, ensure the second of annular enclose purlin and following each road thereof enclose purlin all one-time-concreting complete, described second encloses purlin and following each road thereof and encloses purlin and be all cast on the inner ring side of a described circle bored pile, and described second encloses purlin and following each road thereof encloses purlin and all establish when building and somely hang muscle and joint bar, and will muscle and joint bar be hung be welded in the main muscle of bored pile;
(9) second encloses purlin absolute altitude and encloses purlin absolute altitude (-10.350m) position soil excavation to the 3rd road: with Miniature digging machine, north side in foundation ditch is transported in the earthwork, and long-armed digging machine rests in the outer north side of foundation ditch and fetches earth and be placed on cubic metre of earth car and transport outward;
(10) the 3rd roads enclose purlin construction: carry out the 3rd road enclose purlin construction and maintenance to design strength, ensure that annular encloses purlin one-time-concreting and completes, must not repeatedly build;
(11) the 3rd roads enclose purlin absolute altitude to hole end absolute altitude (-12.600m) soil excavation: adopt central island digging mode, pile in the middle of foundation ditch with Miniature digging machine by the earthwork, with tower crane, the earthwork are winched to a cubic metre of earth car outward transport;
(12) bed course and construction of bottom plates is carried out;
(13) main body construction is carried out.
Above-described embodiment is only the illustrative principle of the invention and effect thereof, but not for limiting the present invention.The scope of the present invention, should listed by claims.

Claims (1)

1. a circular deep foundation ditch support free construction method, is characterized in that: complete construction method is carried out in the steps below:
One, levelling of the land: before three axle mixer constructions, first must carry out levelling of the land, remove top layer hard object and the underground obstacle of construction area;
Two, surveying setting-out:
A. the measuring point provided according to Construction unit is reference point, arranges in-site measurement control point and absolute altitude control point;
B. Survey control point is arranged in the center of circle of foundation pit enclosure structure plane;
C. all by stake, position measuring is carried out to each width three axes agitating pile, each root bored pile;
D. three axes agitating pile puts central axis, then by circle fluting, then measuring axis pore is for controlling stake position;
Three, three axes agitating pile construction:
A. according to three axes agitating pile unwrapping wire location, adopt digging machine excavation guide groove, guide groove dimensional requirement center line both sides are wide each 0.5 ~ 0.7 meter, dark 1.0 ~ 1.5 meters;
B., location shaped steel is set: under vertical guide slot direction places two, locate shaped steel, place in parallel guide slots direction on two and locate shaped steel, select according to stake machine size, mark made by upper location shaped steel, marking path is selected according to stake footpath, so that look for stake position in construction;
C. pile-forming machine perching: should according to circular feature, every three axle stake adjustment stride trends, notice that overlap joint beaten by cover, gantry upright post verticality will guarantee verticality≤0.004 of a machine, and position after position of p ile machine again and check, deviate is less than 5cm simultaneously;
D. cement paste preparation: water/binder ratio is 1.5 ~ 2.0, cement adopts more than P.O42.5 portland cement, and cement mixed weight is be stirred soil mass consolidation quality 15% ~ 23%;
E. creep into and stir whitewashing: starter motor, stake machine stirs, and when whitewashing is crept in sinking, subsidence velocity is 0.5m/min ~ 1.0m/min, and whitewashing amount controls measure in total whitewashing 50% ~ 70%, in the suitable Keep agitation whitewashing of stake bottom part;
F. promote and stir whitewashing: promoting hoisting velocity when stirring whitewashing is 1.0m/min ~ 2.0m/min, and whitewashing amount controls measure in total whitewashing 30% ~ 50%;
G. stake machine displacement in place, takes one-sided compression mode or jumps the mode of beating to construct, and makes three axes agitating pile enclose a conglobate circle and continuous;
Four, bored pile construction:
A. position measuring is carried out according to dominating pair of vertices bored pile by root;
B. shield-tube embedment: with stake position central point for the center of circle, dig out the round pool than the design large 250mm ~ 350mm in stake footpath, casing is vertically fixed on stake position place and corrects, after reaching requirement, surrounding clay tamps, and guarantees to stablize, and makes a record and carry out repetition measurement;
C. rig installation in position: rig is installed must level, straight and firm, ensures that drilling rod, rotating disk and casing center are on same plumb line simultaneously;
D. slurrying: mud property requires as following table:
Project Proportion Viscosity (S) Inject aperture mud ≤1.15 18~22 Delivery port mud ≤1.3 20~26
E. drilling and forming hole: according to design pile-type, select rig, carry out drilling and forming hole construction, bit diameter should equal the intended diameter of stake, bit conical angle should be greater than 120 °, often to veritify bit size in construction, should repair in time or change when finding that wearing and tearing are not up to standard, ensure that expanded diameter meets design requirement;
F. once clear hole: creep into projected depth, by 0.15m ~ 0.25m at the bottom of drilling tool lift-off hole, up and down reciprocatingly lifting low speed revolution, and full pump amount punching, larger particles soil block at the bottom of abundant grinding hole, treats to return out in hole in slurries and can be considered that once hole is complete clearly without clod;
G. downcomer;
H. secondary pile hole cleaning;
I. concreting, formed surround circle and one of interval circle bored pile and be positioned at described one circle three axes agitating pile within;
Five, between three axes agitating pile and bored pile, the soil body adopts grouting and reinforcing;
Six, top layer soil excavation, carry out first enclose purlin construction and maintenance to design strength, described first enclose purlin be Guan Liang and be cast in described one circle the stake top of bored pile and the main muscle epimere of bored pile be placed in hat beam in, ensure that the hat beam one-time-concreting of annular completes;
Seven, first encloses purlin absolute altitude to second and encloses purlin elevation location soil excavation: arrange the car ramp that leads in hole, take from, move back while the mode excavated, finally close up in car ramp and margin of foundation pit and have a common boundary;
Eight, second enclose purlin construction: carry out second enclose purlin construction and maintenance to design strength, ensure the second of annular enclose purlin and following each road thereof enclose purlin all one-time-concreting complete, described second encloses purlin and following each road thereof and encloses purlin and be all cast on the inner ring side of a described circle bored pile, and described second encloses purlin and following each road thereof encloses purlin and all establish when building and somely hang muscle and joint bar, and will muscle and joint bar be hung be welded in the main muscle of bored pile;
Nine, second encloses purlin absolute altitude and encloses purlin elevation location soil excavation to the 3rd road: the earthwork to be transported near car ramp side in foundation ditch with digging machine, fetches earth near side, ramp and be placed on cubic metre of earth car and transport outward in the ground that long-armed digging machine rests in foundation ditch limit;
Ten, the 3rd road enclose purlin construction: carry out the 3rd road enclose purlin construction and maintenance to design strength;
11, the 3rd road encloses purlin absolute altitude and encloses purlin elevation location soil excavation to the 4th road: adopt central island digging mode, pile in the middle of foundation ditch with digging machine by the earthwork, with tower crane, the earthwork is winched to a cubic metre of earth car outward transport;
12, the 4th road encloses purlin construction: while the 3rd road and the 4th road to enclose between purlin central island earthwork outward transport, carry out the 4th road enclose purlin construction and maintenance to design strength;
13, step 11 and step 12 is repeated;
14, n-th road encloses purlin absolute altitude to hole end elevation location soil excavation: adopt central island digging mode, pile in the middle of foundation ditch with digging machine by the earthwork, with tower crane, the earthwork is winched to a cubic metre of earth car outward transport;
15, bed course and construction of bottom plates is carried out;
16, main body construction is carried out.
CN201210134562.6A 2012-05-04 2012-05-04 Circular deep foundation ditch is without Construction of Supporting structure and construction method Expired - Fee Related CN102635120B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210134562.6A CN102635120B (en) 2012-05-04 2012-05-04 Circular deep foundation ditch is without Construction of Supporting structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210134562.6A CN102635120B (en) 2012-05-04 2012-05-04 Circular deep foundation ditch is without Construction of Supporting structure and construction method

Publications (2)

Publication Number Publication Date
CN102635120A CN102635120A (en) 2012-08-15
CN102635120B true CN102635120B (en) 2016-01-13

Family

ID=46619687

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210134562.6A Expired - Fee Related CN102635120B (en) 2012-05-04 2012-05-04 Circular deep foundation ditch is without Construction of Supporting structure and construction method

Country Status (1)

Country Link
CN (1) CN102635120B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967016A (en) * 2013-02-06 2014-08-06 上海城地建设股份有限公司 Novel vertical pit support structure and construction method thereof
CN103526763A (en) * 2013-09-22 2014-01-22 中冶天工上海十三冶建设有限公司 Cast-in-place pile, root pile and jet grouting pile composite-type foundation pit supporting method
CN103669369B (en) * 2013-12-23 2015-11-04 中国建筑第八工程局有限公司 The supporting and protection structure of foundation ditch and supporting method
CN103741696A (en) * 2013-12-23 2014-04-23 广西科技大学 Vertical enclosing purlin added inner support system
CN104164881A (en) * 2014-07-28 2014-11-26 中国建筑第四工程局有限公司 Piling wall overlapping cantilever foundation pit support construction method and structure
CN105297797A (en) * 2015-11-30 2016-02-03 浙江华展工程研究设计院有限公司 Hoop support form for in-situ protection of existing building in underground space development
CN107130611B (en) * 2017-05-31 2019-12-20 郑州安源工程技术有限公司 Design and construction method of flexible composite anti-seepage assembled recoverable round-section row pile supporting structure
CN107476312A (en) * 2017-08-15 2017-12-15 江西基业科技有限公司 A kind of barricade and its construction method for pattern foundation pit supporting structure
CN107313433A (en) * 2017-08-15 2017-11-03 江西基业科技有限公司 A kind of deep basal pit underground space structure and its construction method
CN107476311A (en) * 2017-08-15 2017-12-15 江西基业科技有限公司 A kind of deep basal pit underground garage and its construction method
CN107326931A (en) * 2017-08-15 2017-11-07 江西基业科技有限公司 A kind of deep basal pit underground grain depot and its construction method
CN107542095A (en) * 2017-08-15 2018-01-05 江西基业科技有限公司 A kind of deep basal pit reservoir and its construction method
CN107354948A (en) * 2017-08-15 2017-11-17 江西基业科技有限公司 A kind of deep basal pit underground storehouse and its construction method
CN107313434A (en) * 2017-08-15 2017-11-03 江西基业科技有限公司 A kind of deep basal pit oil cellar and its construction method
CN109137929A (en) * 2018-08-29 2019-01-04 中铁上海工程局集团有限公司 A kind of construction method connected between concrete annular brace and fender post
CN109736322A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Building enclosure forming method
CN110130357B (en) * 2019-04-01 2021-05-04 南京市第九建筑安装工程有限公司 Construction method of cast-in-place pile top inserting type steel combined stirring pile foundation pit supporting system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1800512A (en) * 2005-01-07 2006-07-12 中船第九设计研究院 Support free construction method for super large diameter circular deep foundation ditch
CN201459770U (en) * 2009-03-11 2010-05-12 浙江中成建工集团有限公司 Joint structure between two different fender bodies in deep foundation pit
CN102268875A (en) * 2011-01-28 2011-12-07 中天建设集团有限公司天津分公司 Foundation pit timbering construction method by overcoring bored piles in two rows of stirring piles
CN102286981A (en) * 2011-07-15 2011-12-21 深圳市鸿荣轩建设工程有限公司 Waterproof curtain and construction method thereof
CN202519677U (en) * 2012-05-04 2012-11-07 张全胜 Unstayed construction structure of round deep foundation pit

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61261527A (en) * 1985-05-15 1986-11-19 Nippon Steel Corp Side wall structure for round underground type structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1800512A (en) * 2005-01-07 2006-07-12 中船第九设计研究院 Support free construction method for super large diameter circular deep foundation ditch
CN201459770U (en) * 2009-03-11 2010-05-12 浙江中成建工集团有限公司 Joint structure between two different fender bodies in deep foundation pit
CN102268875A (en) * 2011-01-28 2011-12-07 中天建设集团有限公司天津分公司 Foundation pit timbering construction method by overcoring bored piles in two rows of stirring piles
CN102286981A (en) * 2011-07-15 2011-12-21 深圳市鸿荣轩建设工程有限公司 Waterproof curtain and construction method thereof
CN202519677U (en) * 2012-05-04 2012-11-07 张全胜 Unstayed construction structure of round deep foundation pit

Also Published As

Publication number Publication date
CN102635120A (en) 2012-08-15

Similar Documents

Publication Publication Date Title
CN102635120B (en) Circular deep foundation ditch is without Construction of Supporting structure and construction method
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN102226336B (en) Foundation reinforcement method
CN103031839B (en) Construction method of hand-dug piles
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN103046557A (en) Foundation pit water-sealing supporting method by using long spiral cement soil mixing structural steel pile
CN104947682A (en) Foundation pit support construction method and device thereof
CN109235426A (en) A kind of construction process for bored pile
CN101793023A (en) Foundation pit construction method
CN102561384A (en) Steel hoop truss type elevated pile cap tower crane foundation construction method and structure
CN103015431B (en) Foundation pit supporting method for manual dig-hole cement-soil steel pile
CN101736757A (en) Two-way synchronous construction method of tube structure of high-rise building
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN113216832B (en) Construction method for water milling and drilling of pile holes in karst areas
CN104264663A (en) Hard cutting construction technology for secant piles
CN205876322U (en) Rich water sand cobble stratum shield constructs business turn over hole system of consolidating
CN108560536A (en) The continuous piling wall construction method of Soil-cement
CN104389320A (en) Construction method of pile foundation anchor rope prestress high retaining wall
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN203411993U (en) Simple and fast retaining wall
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN103758132B (en) The construction technology of the cantilever soldier pile retaining structure on slope is put in a kind of combination
CN111608210A (en) Construction method of pressure bearing type anti-floating anchor rod in water-saturated silt stratum

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant