Prior art keywords
pile
afterbody
support
support pile
foundation ditch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710623973.4A
Other languages
Chinese (zh)
Inventor
刁钰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201710623973.4A priority Critical patent/CN107620309A/en
Publication of CN107620309A publication Critical patent/CN107620309A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a kind of foundation pit supporting method.This method includes:First support pile, the second support pile and the first Guan Liang are provided;Wherein the first support pile includes the first pile crown portion, first afterbody and connects the first pile crown portion and the first pile body portion of first afterbody, and the second support pile includes the second pile crown portion, second afterbody and the second pile crown portion of connection and the second pile body portion of second afterbody;Making the first pile body portion at the first position at the edge of foundation ditch to be dug, the first pile crown portion reaches stake bottom precalculated position and tilted to foundation ditch inner side to enter the soil body in the first inclination angle with gravity direction;Making the second pile body portion in the second place at the edge of foundation ditch to be dug, the second pile crown portion reaches stake bottom precalculated position and tilted to foundation ditch inner side to enter the soil body in the second oblique angle with gravity direction;The first Guan Liang is set to be fixedly connected respectively with first afterbody and second afterbody, and on the inside of collateral support group hole edge of first Guan Liang away from foundation ditch center.

Description

Foundation pit supporting method
Technical field
The present invention relates to building foundation pit technical field, more particularly to a kind of method of pattern foundation pit supporting structure.
Background technology
Row of piles supporting is one of widest pattern foundation pit supporting structure form of current domestic application.Row of piles structure and diaphram wall phase Than having many advantages, such as construction technology is simple, cost is low, horizontal layout is flexible.Spaced pile row retaining structure is applied to Without underground water or allow the situation for cheating outer precipitation, continuous wall side by side is formed when setting water-stop curtain or with other hybrid stakes When, it can also be used to weak aquifer water-bearing stratum.
Currently used campshed is Vertical Pile, and it has shortcomings when carrying out pattern foundation pit supporting structure, have impact on campshed Using.First, the displacement at pile top of identical cutting depth is big, and internal force is big, and ground produces moderate finite deformation after making stake, jeopardizes ring around Border.Secondly, easily cause slope protection pile to fracture when the insufficient strength of stake and make instability of foundation pit.Again, base is made using vertical campshed It is smaller to cheat the depth that may be excavated, when cutting depth is larger, campshed is easy to that overturning occurs, therefore supporting construction needs More heavy in section and insertion depth.
The content of the invention
In view of the foregoing, the invention provides a kind of foundation pit supporting method and raked pile, base can be preferably applied to Cheat supporting.
One aspect of the present invention provides a kind of foundation pit supporting method.This method includes:First support pile, second are provided Support pile and the first Guan Liang;Wherein described first support pile includes the first pile crown portion, first afterbody and connection described first Pile crown portion and the first pile body portion of first afterbody, second support pile include the second pile crown portion, second afterbody and Connect the second pile crown portion and the second pile body portion of second afterbody;Make at the first position at the edge of foundation ditch to be dug The first pile body portion in the first oblique angle with gravity direction to enter the soil body, wherein the first pile crown portion reaches stake bottom Precalculated position and tilted on the inside of foundation ditch;Make in the second place at the edge of foundation ditch to be dug the second pile body portion with gravity Direction enters the soil body in the second oblique angle, wherein the second pile crown portion reaches stake bottom precalculated position and rolled into foundation ditch Tiltedly;First Guan Liang is set to be fixedly connected respectively with first afterbody and second afterbody, and first Guan Liang On the inside of collateral support group hole edge away from foundation ditch center.
In one embodiment, first inclination angle is equal to second inclination angle.
In one embodiment, the angle at first inclination angle and second inclination angle is within 5 °.
In one embodiment, first inclination angle is in the range of 0-30 °.
In one embodiment, first inclination angle is in the range of 15-20 °.
In one embodiment, foundation pit supporting method also includes providing the 3rd support pile, wherein the 3rd support pile bag Include prism of third order head, prism of third order afterbody and the connection prism of third order head and the prism of third order body portion of prism of third order afterbody;Treated on edge Dig the edge of foundation ditch and the 3rd opening position different from the first position and the second place makes the prism of third order body portion edge Gravity direction enters the soil body in the 3rd oblique angle, wherein, prism of third order head arrival stake bottom precalculated position and to foundation ditch Inner side tilts;And first Guan Liang is set to be fixedly connected with the prism of third order afterbody.
In one embodiment, first support pile and second support pile is adjacent and distance therebetween is institute State the first support pile or the second support pile stake footpath 2-2.5 times.
In one embodiment, the stake footpath of first support pile and second support pile is 300mm-600mm.
In one embodiment, first Guan Liang is rectangular parallelepiped structure, height dimension of its cross section in gravity direction Not less than 0.6 times of support pile stake footpath and width dimensions are not less than support pile stake footpath.
In one embodiment, the cross section of first Guan Liang is square, and its length of side is more than support pile cross section Full-size.
In one embodiment, the length of side of the cross section of first Guan Liang is the maximum sized 2-3 in support pile cross section Times.
Using the foundation pit supporting method or raked pile of the present invention, pattern foundation pit supporting structure effect can be improved.Such as can be more preferable Suitable for soft clay area ultra-deep, the supporting of super foundation.
Brief description of the drawings
From the detailed description to the embodiment of the present invention below in conjunction with the accompanying drawings, of the invention these and/or other side and Advantage will become clearer and be easier to understand, wherein:
Fig. 1 is the schematic diagram of foundation pit supporting method;
Fig. 2 is foundation pit supporting method schematic diagram provided in an embodiment of the present invention.
Embodiment
In order that those skilled in the art more fully understand the present invention, with reference to the accompanying drawings and detailed description to this hair It is bright to be described in further detail.
Before excavation pit, it usually needs supporting is carried out to foundation ditch using support pile, for example to avoid foundation ditch that side occurs Cave in, influence the construction of foundation ditch.Fig. 1 is a kind of schematic diagram of conventional foundation pit supporting method.Referring to Fig. 1, supporting pile structure bag Three vertical support piles 1 are included, for example, the support pile 1 of this three signals can enter the soil body by the way of being pressed into one by one.Figure Middle support pile 1 gos deep into bottom of foundation ditch below 3, to obtain higher support strength.For example, support pile 1 is located under bottom of foundation ditch Part account for 1 times -3 times of the length of support pile 1, to ensure effective support to foundation ditch.Support pile 1 (is being illustrated three in figure Root) for example be pressed into the soil body after, Guan Liang 2 can be fixedly connected with the outside of three support piles 1.For example may be used the side of the Guan Liang 2 To support foundation ditch side.
One aspect of the present invention provides a kind of foundation pit supporting method.Fig. 2 show the branch using the embodiment of the present invention Maintaining method carries out the schematic diagram of pattern foundation pit supporting structure.Referring to Fig. 2, this method includes:First supporting 4, the second support pile 5 and are provided One Guan Liang 6.Wherein the first support pile 4 includes the first pile crown portion 41 and first of 41, first, the first pile crown portion afterbody 42 and connection First pile body portion 43 of stake afterbody 42.Second support pile 5 includes the second pile crown of 51, second, the second pile crown portion afterbody 52 and connection Portion 51 and the second pile body portion 53 of second afterbody 52.Make at the first position at the edge of foundation ditch to be dug the first pile body portion 43 with Enter the soil body in the first oblique angle with gravity direction, wherein the first pile crown portion 41 reaches stake bottom precalculated position and into foundation ditch Roll oblique.Make in the second place at the edge of foundation ditch to be dug the second pile body portion 53 with gravity direction in the second oblique angle Into the soil body, wherein the second pile crown portion 51 reaches stake bottom precalculated position and tilted to foundation ditch inner side;Make the first Guan Liang 6 respectively with One afterbody 42 is fixedly connected with second afterbody 52, and on the inside of collateral support group hole edge of first Guan Liang 6 away from foundation ditch center. By making support pile obliquely set, support effect can be improved., can be with further, since support pile tilts on the inside of foundation ditch Difficulty of construction is reduced, and makes the supporting to foundation ditch more uniform.
It should be noted that above-mentioned support pile can enter the corresponding soil body by the way of press-in.Specifically, for example, After above-mentioned first position press-in prefabricated pile, the distance that can be spaced such as 1-2 piles is pressed into next prefabricated pile.The number of support pile Amount can determine that the present invention is without limitation according to size, piling condition, soil layer construction of foundation ditch etc..
In concrete operations, pattern foundation pit supporting structure can be implemented as follows:
(1) measurement and positioning, the pushed position of support pile is determined.
In this step, support pile should be pressed into margin of foundation pit position according to the actual size of foundation ditch, to excavate During foundation ditch, support pile can effectively be supported to the foundation ditch side soil body, prevent from causing the soil body of foundation ditch side to cave in.
(2) it is pile press machine is in place, leveling.
In this step, pile press machine is made to reach precalculated position, so as to the stable application pressure of support pile, Jin Ergeng Good guarantee support pile stabilization enters the soil body.
(3) hang stake and feed stake.
Specifically, in this step, pile press machine can sling support pile, such as support pile can be preset in soil layer table Face, such as support pile can also be entered to a soil body part, complete the initial setting up of support pile.
(4) pile body portion centering straightening.
In this step, such as by support pile precalculated position is navigated to, and position error can be less than 20mm, to ensure to prop up Fender pile effectively supports foundation ditch.In practical operation, in order to accelerate speed of application, support pile to be pressed all can be navigated to first Precalculated position, the soil body is pressed into subsequent step, then by these oriented support piles.For example, it is also possible to one is operated every time Or several support piles, it can be determined according to construction site and condition.Illustrated below exemplified by operating a pile every time.
For example, the stake spacing of adjacent two pile can take 2-2.5 in foundation pit supporting method provided in an embodiment of the present invention Times stake footpath.The deep angle of inclination of stake can be 0-30 °, and further, the deep angle of inclination of stake can be 10-25 °.For example, not Angle of inclination with stake can be with identical or different, and the incline direction of piles with different can be different.
In some embodiments of the invention, the pile crown portion (fore-end for entering the soil body) of all stakes is both facing in foundation ditch Roll it is oblique, i.e., these incline direction it is identical.For example, Fig. 2 illustrates the pile crown portion 41,51 of all support piles to foundation ditch Inner side tilts.So as to simplify difficulty of construction, construction cost is reduced, while makes periphery earth stress consistent, improves supporting effect.Enter One step, the difference at these angle of inclination is for example within 5 °, for example, the angle of inclination of these support piles is completely the same, with Ensure support pile even support foundation ditch, avoid the supporting effect difference of part stake and cause the situation of foundation pit collapse.
(5) piling.
Push every time, for example, stake is goed deep into soil may be about 1.5~2.0m.Then pine folder, rise, then press, then press from both sides.Such as This is repeated, by a section stake pressure.When a section stake is depressed into away from 80~100cm of ground, pile extension can be carried out or be put into Pile feeder, Stake is depressed into designed elevation.Stake bottom depth for example can be excavation of foundation pit depth (31 bottom for showing foundation ditch to be dug in Fig. 2) 2~2.5 times.
(6) pile extension
In certain embodiments, pile extension operation can be carried out in a welding manner.First corner is spot welded during welding and fixed, so After be symmetrically welded.Weld seam should ensure that quality and design size.
(7) pile follower
The pile follower operation of static pressed pile can be carried out using the special Pile feeder (such as iron bag concrete) of in-situ precast.Pile follower In operation, stake can be pushed always, untill final pressure control condition is met by the stake top absolute altitude of piling.
(8) piling is terminated
(9) it is pressed into next pile
It can use and jump pile construction method, 1~2 pile of interval is pressed into next prefabricated pile, repeats the above steps, until will All piles are pressed into the soil body.
It should be noted that under normal circumstances, while campshed construction is tilted, such as water seal curtain can also be carried out Construction.Construction location lateral extent about outside foundation ditch side is tilted at the stake afterbody 0.5-1m of campshed, (the i.e. construction location of water seal curtain Position outside support pile is away from foundation ditch), and the absolute altitude at the mixing pile stake bottom of water seal curtain is identical with raked pile stake bottom absolute altitude.
In certain embodiments, for example, the construction procedure of water seal curtain can be carried out as follows:
1st, position:Deep mixer, which reaches, refers to fixed pile, centering.
2nd, sinking is stirred in advance:After the cooling water circulation of deep mixer is normal, starts mixer motor, loosen mixer and hang Rope makes mixer cut native sinking along leading truck stirring.
3rd, cement mortar is prepared:When deep mixer sinks to certain depth, that is, start to stir by the match ratio that design determines Cement mortar is mixed, pours into cement mortar in aggregate bin before treating mud jacking.
4th, lifting whitewashing stirring:After deep mixer sinks to projected depth, open slurry pump and cement mortar is pressed into ground In, and while whitewashing, while rotate, while in strict accordance with design determine lifting speed lifting deep mixer.
5th, upper and lower stirring is repeated:When deep mixer is promoted to the top surface absolute altitude of projected depth, the cement mortar in aggregate bin Should just it empty.To make weak soil and cement mortar stir, mixer can be sunk in soil in rotation again, to design reinforcement Mixer is being lifted out ground after depth.
6th, clean:Cement mortar remaining in whole pipelines is cleaned, and the weak soil for being adhered to stirring-head is cleaned up.
7th, shift:Deep mixer is moved into next position, repeated the above steps.
By setting water seal curtain to each support pile, it can be ensured that support pile reliably works, in strengthening supporting stake intensity While, the infiltration phenomenon that may occur during excavation pit can be avoided.
It is pointed out that under normal circumstances, the construction of the every support pile property entered water seal curtain respectively can be directed to.Example Such as, can be after support pile is all pressed into the soil body, uniformly the property entered water seal curtain is constructed, to improve efficiency of construction.But also may be used Be it is every press-in a piece support pile after, that is, the property entered water seal curtain construct, the invention is not limited in this regard.
In some embodiments of the invention, such as Guan Liang construction can be carried out after the construction of water seal curtain is completed.Guan Liang Construction can be carried out as follows:
1st, the Guan Liang earthwork is excavated using mechanical subregion, such as is first excavated the first layer earthwork to support pile and designed stake top (before i.e. Stake afterbody described in text) elevation location, start to abolish a laitance to designed elevation after soil more than removing.The concrete of stake core top surface will Dabbing processing, removes stake top scum silica frost.As designed elevation pile crown concrete strength does not reach design requirement, must continue to abolish until concrete quality Reach design requirement, together pouring molding during insufficient absolute altitude section Guan Liang concrete.
2nd, inter-pile soil for example manually leveling to hat bottom elevation, and ram tamp it is closely knit.
3rd, reinforcement fabrication can be carried out by Guan Liang section arrangement of reinforcement after stake tail end is abolished.Steel Reinforcing Bar Material, colligation error ensure full Sufficient design and construction code requirement.The binding site poured to Guan Liang segmentation for example can be with reserved steel bar.
4th, to Guan Liang absolute altitude check simultaneously installation form.Must ensure during template support form stable, firmly, to prevent pouring Template deformation during concrete.Template sectional dimension is made by Guan Liang section.
5th, reinforced bar engineering is completed.Vertical muscle should use preferably with HRB335 levels or HRB400 level reinforcing bars, stirrup and tension rib HPB300 levels and HRB335 level reinforcing bars.Lateral longitudinal muscle diameter is no less than 20mm, and spacing not should be greater than 200mm;Top bottom surface indulges muscle Diameter is no less than 20mm, and spacing not should be greater than 300mm;Stirrup diameter is no less than 8mm, and spacing not should be greater than 250mm;Drawknot Muscle diameter should use 6~12mm, and spacing not should be greater than 500mm.
6th, concreting and maintenance are completed.Strength grade of concrete is not lower than C25, and campshed cage bar anchors into Guan Liang and should not Less than 35d (d is bar diameter).
Embodiments of the invention give water seal curtain and the set-up mode of Guan Liang, but the present invention is not intended to limit water proof The form of construction work of curtain and Guan Liang, those skilled in the art can use other forms of construction work or above-mentioned form of construction work carried out Improve, to obtain more preferable construction effect.
In the practical operation of pattern foundation pit supporting structure, it can be selected according to situations such as the soil layer feature residing for foundation ditch, surrounding enviroment Appropriate pattern foundation pit supporting structure mode.Support pile is briefly introduced several support patterns of foundation ditch below, but is not intended to limit The system present invention.
1st, cantilever pile supporting.When excavation of foundation pit is shallower, geological conditions is preferable, environmental requirement (especially deformation requirements) is not high When, cantilever pile support form can be used.After cantilever pile pile strength reaches regulation requirement, it is possible to carry out opening for soil layer Dig.
2nd, Internal-shoring Supporting.When excavation of foundation pit area is larger, ground is weak, environmental requirement is high, inner bearing type can be used Supporting.Pit earthwork is excavated to the base surface at first of reinforced concrete brace bottom first, then chisels supporting construction With the joint face of purlin, and reinforced concrete support cushion construction is carried out, subsequent colligation spacer bar, prop up vertical side template, complete After-pouring concrete is simultaneously conserved, and form removal and cleaning work are carried out when concrete strength reaches regulation.
3rd, anchor formula supporting is drawn.When foundation ditch soil layer condition is preferable, reaches and draw anchor condition, and when surrounding enviroment are less demanding, It can use and draw anchor formula supporting.When foundation ditch soil layer first is excavated at first of anchor pole center line certain depth below, machine is utilized Tool drills, and makes anchor pole according to the rules and inserts and send rod member, then carries out slip casting and form anchoring section, finally when anchoring body reaches certain Tensioning and locking are carried out after intensity.
It may be noted that for the foundation ditch of stage excavation, for example, different campshed support forms can be directed to, repeat above-mentioned Step carries out construction until being excavated to the bottom of foundation ditch.After foundation ditch is dug, such as Foundation Pit bottom can be cleared up, be whole It is flat, and carry out subsequent work.
In the above-described embodiments, the first Guan Liang for example can be rectangular parallelepiped structure, its height (gravity side during actual use To size) be not less than 0.6 times of support pile stake footpath, and width is not less than support pile stake footpath.The cross section of first Guan Liang is for example Can be square, and the both sides of the first Guan Liang in the width direction are at least the first Guan Liang beyond the length of support pile The 1/2 of the cross section length of side.Pass through the shape of the first Guan Liang of setting and the correspondingly-sized relation with support pile, it can be ensured that raked pile Stability Analysis of Structures, so as to more preferable supporting foundation pit.
In other embodiments of the invention, the pile crown portion of support pile for example can be cone shape.For example, along support pile On length direction, the length of cone for example can be the 1/20-1/10 of supporting pile length, and the cone angle of cone is, for example, 30-45 °. By the way that pile crown portion is arranged into cone shape, and the length and cone angle size of cone are set, can make support pile it is easier enter Enter the soil body.
Preferably, annular groove can be set close to the position of cone afterbody around pile body portion, the depth of groove is, for example, stake footpath 1/25-1/30, the width of groove for example can be 1-2cm., can be with by setting annular groove close to the position of cone in pile body portion Support pile is set to be engaged each other with the soil body of contact after entering the soil body, so as to further improve the stability of support pile.
In one embodiment, the cross section of support pile for example can with Ω shapes, so as to so that support pile it is easier enter Enter the soil body, and its interaction force with the soil body can be increased, and then improve pattern foundation pit supporting structure effect.
In one embodiment, the cross section of support pile can be trapezoidal.For example, trapezoidal bond length is the 1/ of long side 2-1/4, so as to both support pile be made to be readily pressed into the soil body, the active force of the support pile and the soil body into the soil body can be made again It is stronger, so as to improve the stability to pattern foundation pit supporting structure.
Another aspect of the invention provides a kind of campshed for including above-mentioned inclination pilework.Obviously, the campshed has Techniques discussed above effect, will not be described here.
It is described above various embodiments of the present invention, described above is exemplary, and non-exclusive, and It is not limited to disclosed each embodiment.In the case of without departing from the scope and spirit of illustrated each embodiment, for this skill Many modifications and changes will be apparent from for the those of ordinary skill in art field.Therefore, protection scope of the present invention should It should be defined by scope of the claims.

Claims (10)

  1. A kind of 1. foundation pit supporting method, it is characterised in that including:
    First support pile, the second support pile and the first Guan Liang are provided;Wherein described first support pile includes the first pile crown portion, the One afterbody and the first pile crown portion and the first pile body portion of first afterbody are connected, second support pile includes the Two pile crown portions, second afterbody and connection the second pile crown portion and the second pile body portion of second afterbody;
    Make at the first position at the edge of foundation ditch to be dug the first pile body portion with gravity direction in the first oblique angle Into the soil body, wherein the first pile crown portion reaches stake bottom precalculated position and tilted to foundation ditch inner side;
    Make in the second place at the edge of foundation ditch to be dug the second pile body portion with gravity direction in the second oblique angle Into the soil body, wherein the second pile crown portion reaches stake bottom precalculated position and tilted to foundation ditch inner side;
    First Guan Liang is set to be fixedly connected respectively with first afterbody and second afterbody, and first Guan Liang On the inside of collateral support group hole edge away from foundation ditch center.
  2. 2. foundation pit supporting method according to claim 1, it is characterised in that incline equal to described second at first inclination angle Angle.
  3. 3. foundation pit supporting method according to claim 1, it is characterised in that first inclination angle and second inclination angle Angle is within 5 °.
  4. 4. foundation pit supporting method according to claim 1, it is characterised in that first inclination angle is in the range of 0-30 °.
  5. 5. foundation pit supporting method according to claim 4, it is characterised in that scope of first inclination angle at 15-20 ° It is interior.
  6. 6. foundation pit supporting method according to claim 1, it is characterised in that also include providing the 3rd support pile, wherein institute Stating the 3rd support pile includes the 3rd of prism of third order head, prism of third order afterbody and the connection prism of third order head and prism of third order afterbody the Pile body portion;
    Make described the at the edge along foundation ditch to be dug and the 3rd opening position that is different from the first position and the second place Three pile body portions enter the soil body along gravity direction in the 3rd oblique angle, wherein, the prism of third order head reaches stake bottom pre-determined bit Put and tilted to foundation ditch inner side;And
    First Guan Liang is set to be fixedly connected with the prism of third order afterbody.
  7. 7. foundation pit supporting method according to claim 1, it is characterised in that first support pile and second supporting Stake adjacent and the distance between first support pile and described second support pile are first support pile or described second 2-2.5 times of fender pile stake footpath.
  8. 8. inclination pilework according to claim 7, it is characterised in that first support pile and second support pile Stake footpath be 300mm-600mm.
  9. 9. foundation pit supporting method according to claim 1, it is characterised in that first Guan Liang is rectangular parallelepiped structure, its Cross section is not less than support pile stake footpath in the height dimension of gravity direction not less than 0.6 times of support pile stake footpath and width dimensions.
  10. 10. foundation pit supporting method according to claim 9, it is characterised in that the cross section of first Guan Liang is pros Shape, its length of side are more than the full-size of support pile cross section.
CN201710623973.4A 2017-07-27 2017-07-27 Foundation pit supporting method Pending CN107620309A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710623973.4A CN107620309A (en) 2017-07-27 2017-07-27 Foundation pit supporting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710623973.4A CN107620309A (en) 2017-07-27 2017-07-27 Foundation pit supporting method

Publications (1)

Publication Number Publication Date
CN107620309A true CN107620309A (en) 2018-01-23

Family

ID=61088873

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710623973.4A Pending CN107620309A (en) 2017-07-27 2017-07-27 Foundation pit supporting method

Country Status (1)

Country Link
CN (1) CN107620309A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440780A (en) * 2018-11-24 2019-03-08 天津大学 Active inclination Single row pillars foundation pit supporting method
CN111287194A (en) * 2020-02-19 2020-06-16 天津大学 Recyclable foundation pit supporting structure using inclined steel sheet piles and supporting method thereof
CN111287193A (en) * 2020-02-19 2020-06-16 天津大学 Foundation pit supporting structure utilizing steel sheet piles and concrete precast piles and supporting method thereof
CN113089682A (en) * 2021-03-18 2021-07-09 兰州大学 High-strength tubular pile foundation pit supporting structure for geotechnical engineering

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101408023A (en) * 2008-11-11 2009-04-15 天津大学 Method for supporting and protecting row pile pit
CN102864781A (en) * 2012-09-29 2013-01-09 成都四海岩土工程有限公司 Foundation pit supporting method utilizing inclined piles
CN103132532A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit support method for row of piles

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101408023A (en) * 2008-11-11 2009-04-15 天津大学 Method for supporting and protecting row pile pit
CN102864781A (en) * 2012-09-29 2013-01-09 成都四海岩土工程有限公司 Foundation pit supporting method utilizing inclined piles
CN103132532A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit support method for row of piles

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440780A (en) * 2018-11-24 2019-03-08 天津大学 Active inclination Single row pillars foundation pit supporting method
CN111287194A (en) * 2020-02-19 2020-06-16 天津大学 Recyclable foundation pit supporting structure using inclined steel sheet piles and supporting method thereof
CN111287193A (en) * 2020-02-19 2020-06-16 天津大学 Foundation pit supporting structure utilizing steel sheet piles and concrete precast piles and supporting method thereof
CN113089682A (en) * 2021-03-18 2021-07-09 兰州大学 High-strength tubular pile foundation pit supporting structure for geotechnical engineering

Similar Documents

Publication Publication Date Title
CN109440778B (en) Active bidirectional inclined row pile foundation pit supporting method
CN107366290A (en) Foundation pit supporting method and raked pile
CN107620309A (en) Foundation pit supporting method
CN113614315A (en) Method of constructing a structure
CN108625377A (en) A kind of foundation pit diagonal brace pile construction method and its auxiliary tool
CN107740419A (en) Foundation pit supporting method and raked pile
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN111636417A (en) Grouting type steel pipe pile and construction method thereof
CN109440779B (en) Active type X-shaped double-row pile foundation pit supporting method
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN109267575A (en) The construction method of pattern foundation pit supporting structure is cheated in the hole of Soft Soil Area
CN107574825A (en) Foundation pit supporting method and raked pile
CN109440781B (en) Active inclined double-row pile foundation pit supporting method
CN210106749U (en) Counter-force structure of soft soil foundation super large section push pipe jacking operation
CN207193988U (en) Raked pile
CN111287194A (en) Recyclable foundation pit supporting structure using inclined steel sheet piles and supporting method thereof
CN107630456A (en) Foundation pit supporting method and raked pile
CN216339582U (en) Combined inclined support for foundation pit support
CN207073136U (en) Raked pile
CN209620033U (en) Active inclined in two-way supporting and protecting row pile pit structure
CN207362852U (en) Raked pile
CN207331701U (en) Raked pile
CN212248262U (en) Recoverable foundation pit supporting structure using inclined steel sheet piles
CN109440780B (en) Active type inclined single-row pile foundation pit supporting method
CN210049264U (en) Assembled foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180123