CN108978687A - It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method - Google Patents

It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method Download PDF

Info

Publication number
CN108978687A
CN108978687A CN201811022846.XA CN201811022846A CN108978687A CN 108978687 A CN108978687 A CN 108978687A CN 201811022846 A CN201811022846 A CN 201811022846A CN 108978687 A CN108978687 A CN 108978687A
Authority
CN
China
Prior art keywords
pile
landslide
slide
slope
vertical anti
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811022846.XA
Other languages
Chinese (zh)
Inventor
樊军伟
杨仕教
彭成
陈文昭
江俊设
龙慧
胡萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of South China
Original Assignee
University of South China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of South China filed Critical University of South China
Priority to CN201811022846.XA priority Critical patent/CN108978687A/en
Publication of CN108978687A publication Critical patent/CN108978687A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本发明公开了一种滑坡及边坡治理的非直立式抗滑桩结构及安装方法,该方法包括根据勘察资料对滑坡类型、规模、滑坡体厚度、滑坡周界、滑动面类型、滑动面空间位置、滑动主轴及滑坡影响范围内岩土体物理力学参数进行收集调查;根据收集调查所得资料按照现行规范推荐的力学模型进行滑坡推力计算;根据计算所得滑坡推力进行桩长、桩身锚固段长度、桩间距和桩身断面尺寸等几何参数设计;将非直立式抗滑桩及滑坡影响范围内的岩土体按预设角度旋转成直立式抗滑桩后进行桩身内力计算并对非直立式现浇混凝土抗滑桩进行配筋;按设计好的几何参数及配筋进行施工。本发明能够在滑坡及边坡治理过程中节省大笔资金、缩短工期、同时有利于环境保护。

The invention discloses a non-vertical anti-slide pile structure and an installation method for landslide and side slope treatment. The method includes analyzing the landslide type, scale, landslide body thickness, landslide perimeter, sliding surface type, and sliding surface space according to survey data. Collect and investigate the physical and mechanical parameters of the rock and soil mass within the location, sliding principal axis, and landslide influence area; calculate the landslide thrust according to the mechanical model recommended by the current code according to the data collected and investigated; calculate the pile length and the length of the anchorage section of the pile according to the calculated landslide thrust Design of geometric parameters such as pile spacing and pile body section size; the non-vertical anti-slide piles and the rock and soil within the influence range of landslides are rotated into vertical anti-slide piles according to the preset angle, and the internal force of the piles is calculated and the non-vertical anti-slide piles are calculated. Type cast-in-place concrete anti-slide piles are reinforced; construction is carried out according to the designed geometric parameters and reinforcement. The invention can save a large sum of money, shorten the construction period and be beneficial to environmental protection in the landslide and side slope treatment process.

Description

一种滑坡及边坡治理的非直立式抗滑桩结构及安装方法Non-vertical anti-slide pile structure and installation method for landslide and slope treatment

技术领域technical field

本发明涉及土木工程技术领域,具体地说,特别涉及一种滑坡及边坡治理的非直立式抗滑桩结构及安装方法。The invention relates to the technical field of civil engineering, in particular to a non-vertical anti-slide pile structure and installation method for landslide and side slope treatment.

背景技术Background technique

道路交通的建设、水力水电工程的开发、露天矿山的采掘以及城市大规模的扩张与改造,均涉及到边坡工程。我国幅员辽阔,自然条件复杂,由于环境的变迁、气候的变化以及人类不合理地开挖、填筑岩土体,都会形成规模不等、范围不一、高度不同和稳定程度各异的自然或人工边坡。The construction of road traffic, the development of hydraulic and hydropower projects, the mining of open-pit mines, and the large-scale expansion and reconstruction of cities all involve slope engineering. my country has a vast territory and complex natural conditions. Due to environmental changes, climate changes, and unreasonable excavation and filling of rock and soil by humans, natural or artificial slope.

在一定地形地质条件下,由于外界条件的变化,各种自然或人为的因素影响(例如长期受水浸润,削弱坡体下部支撑力量等),破坏了岩土体的力学平衡,使山坡上不稳定岩土体在重力作用下,沿着一定的软弱面(带)作整体的、缓慢或快速的、间歇或连续地向下滑动的不良地质现象,称之为滑坡。Under certain topographic and geological conditions, due to changes in external conditions, various natural or man-made factors (such as long-term water infiltration, weakening the supporting force of the lower part of the slope, etc.), destroy the mechanical balance of the rock and soil, making the hillside unsustainable. The unfavorable geological phenomenon that the stable rock and soil mass slides downward along a certain weak surface (band) under the action of gravity, slowly or rapidly, intermittently or continuously, is called a landslide.

由于边坡失稳而造成的滑坡是十分严重的全球性自然灾害。它常常摧毁建筑物、堵塞交通、造成人员伤亡和巨大的经济损失,给生态环境和工程建设带来极大的危害。我国是一个多山地(丘陵)的国家,山地(丘陵)约占全国国土面积的2/3,是世界上滑坡较多的国家之一。改革开放以来,随着国民经济的蓬勃发展,各种工程活动的大规模建设对坡体地质环境的破坏起到了诱发作用。在铁路、公路、水利、航运、采矿、建筑以及国防建设中遇到的边坡失稳灾害的数量逐年增加,其规模及造成的危害也越来越大。因此,对边坡分析理论的发展及治理方案的开发是我们亟待解决的问题。Landslides caused by slope instability are very serious global natural disasters. It often destroys buildings, blocks traffic, causes casualties and huge economic losses, and brings great harm to the ecological environment and engineering construction. my country is a country with many mountains (hills), and the mountains (hills) account for about 2/3 of the country's land area. It is one of the countries with more landslides in the world. Since the reform and opening up, with the vigorous development of the national economy, the large-scale construction of various engineering activities has induced the destruction of the geological environment of the slope. The number of slope instability disasters encountered in railways, highways, water conservancy, shipping, mining, construction and national defense construction is increasing year by year, and its scale and damage are also increasing. Therefore, the development of the slope analysis theory and the development of the treatment plan are problems to be solved urgently.

除了影响边坡稳定的客观因素之外,边坡的变形与破坏都直接或间接地与不合理的削坡、弃土堆填、增大坡角、增加坡高、降低坡体内抗滑阻力或增加坡体质量等人为主观因素有关。此外,城市废水任意排放或地下管网漏水,致使边坡岩土体内常因大量水的渗入而改变了地下水的运动规律,从而降低了边坡岩土体的抗剪强度进一步降低了边坡的稳定程度。In addition to the objective factors affecting the stability of the slope, the deformation and failure of the slope are directly or indirectly related to unreasonable slope cutting, spoil filling, increasing slope angle, increasing slope height, reducing the anti-sliding resistance in the slope or It is related to human subjective factors such as increasing the mass of the slope. In addition, the random discharge of urban waste water or the leakage of underground pipe network will cause the slope rock and soil body to change the law of groundwater movement due to the infiltration of a large amount of water, thereby reducing the shear strength of the slope rock and soil mass and further reducing the slope degree of stability.

相应地针对影响边坡稳定的主要因素目前对于滑坡治理的方案包括:滑坡体挖除、减载反压、挡墙抗滑、格构锚固、抗滑桩等措施并辅之于滑坡体范围内排水工程。Correspondingly, in view of the main factors affecting slope stability, the current landslide treatment plan includes: landslide body excavation, load reduction and back pressure, retaining wall anti-slide, lattice anchorage, anti-slide piles and other measures, supplemented by measures within the scope of landslide body drainage works.

上述方案中除滑坡体范围内排水工程作为辅助手段不能单独作为滑坡治理方案外,其他几种方式均能有效地治理滑坡。但其适用范围均受一定限制,其中滑坡体挖除方案适用于滑坡体规模及范围不能太大;减载反压、挡墙抗滑及格构锚固一般也只适用于滑坡推力较小的小型简单滑坡;由于抗弯刚度大、施工速度快、能深入到滑动面以下,抗滑桩是滑坡支挡中一种比较常用的方案。Among the above schemes, except that the drainage works within the landslide mass range cannot be used as an auxiliary means for landslide control alone, several other methods can effectively control landslides. However, their scope of application is limited to a certain extent. The landslide body excavation scheme is suitable for landslides whose scale and scope should not be too large; Landslide: Anti-slide pile is a commonly used scheme in landslide support due to its high bending stiffness, fast construction speed, and ability to penetrate below the sliding surface.

抗滑桩是深入岩土体的垂直柱形构件。通过桩身将非锚固段承受的滑坡推力传给桩身锚固段侧向岩土体,依靠桩身下部岩土体侧向阻力来承担滑坡推力,从而使边坡保持平衡或稳定。Anti-slide piles are vertical cylindrical members that penetrate deep into the rock and soil mass. Through the pile body, the landslide thrust borne by the non-anchor section is transmitted to the lateral rock and soil mass of the anchor section of the pile body, and the landslide thrust is borne by the lateral resistance of the rock and soil mass under the pile body, so that the slope remains balanced or stable.

抗滑桩有以下优点:Anti-slide piles have the following advantages:

①抗滑能力强,在滑坡推力大、滑动带深的情况下,能够克服抗滑挡土墙难以克服的困难;① Strong anti-sliding ability, in the case of large landslide thrust and deep sliding zone, it can overcome the difficulties that the anti-sliding retaining wall cannot overcome;

②桩位灵活,可以设在滑坡体中最有利抗滑的部位,可以单独使用,也能与其它建筑物配合使用;②Pile positions are flexible, and can be located in the most favorable anti-sliding parts of the landslide body, and can be used alone or in conjunction with other buildings;

③可以沿桩长根据弯矩大小合理地布置钢筋;③ The steel bars can be reasonably arranged along the length of the pile according to the magnitude of the bending moment;

④施工方便,设备简单。采用混凝土或少量钢筋混凝土护壁,安全、可靠;④Convenient construction and simple equipment. Concrete or a small amount of reinforced concrete retaining wall is used, which is safe and reliable;

⑤间隔开挖桩孔,不易恶化滑坡状态,利于整治处于活动中的滑坡,利于抢修工程;⑤ Pile holes are excavated at intervals, which is not easy to deteriorate the state of the landslide, which is beneficial to the regulation of active landslides and is conducive to emergency repair projects;

⑥通过开挖桩孔,能够直接校核地质情况,进而可以检验和修改原来的设计,使之更切合实际,发现问题,易于补救。⑥ By excavating pile holes, the geological conditions can be checked directly, and then the original design can be checked and modified to make it more realistic, and problems can be found and easily remedied.

抗滑桩的桩型有钢筋混凝土预制方桩、管桩、H型钢桩等,最常用的是现浇钢筋混凝土矩形截面桩。通过人工或机械开挖的方式在预定桩位向下垂直成孔,下放钢筋笼完成混凝土浇捣形成直立式抗滑桩。The pile types of anti-slide piles include reinforced concrete prefabricated square piles, pipe piles, H-shaped steel piles, etc., and the most commonly used ones are cast-in-place reinforced concrete rectangular cross-section piles. By manual or mechanical excavation, a hole is formed vertically downward at the predetermined pile position, and the reinforcement cage is lowered to complete the concrete pouring and tamping to form a vertical anti-slide pile.

现有传统直立式抗滑桩的缺点:Disadvantages of existing traditional vertical anti-slide piles:

采用直立式的抗滑桩必然会涉及到滑坡范围内岩土体的开挖或填筑从而导致造价增加和工期延长;The use of vertical anti-slide piles will inevitably involve the excavation or filling of rock and soil within the landslide range, resulting in increased cost and extended construction period;

为穿过滑动面在滑坡体范围内的桩孔开挖作业必然会对滑坡体较长时间的扰动,不利于滑坡及早稳定;The excavation of pile holes within the scope of the landslide body to pass through the sliding surface will inevitably disturb the landslide body for a long time, which is not conducive to the early stabilization of the landslide;

设置在滑坡体坡前的抗滑桩为了桩间土的局部稳定还需要设置桩间挡土板,增加造价及延长工期;The anti-slide piles installed in front of the slope of the landslide body also need to set the soil retaining board between the piles for the local stability of the soil between the piles, which increases the cost and prolongs the construction period;

除桩顶设置冠梁外,抗滑桩难以在桩身非锚固段其他部位设置牢靠连接,不利于整个抗滑桩支挡系统协同工作;In addition to setting the crown beam on the top of the pile, it is difficult to set up a firm connection for the anti-slide pile at other parts of the non-anchor section of the pile body, which is not conducive to the coordinated work of the entire anti-slide pile support system;

完工后的抗滑桩支挡结构均为钢筋混凝土结构,与周边环境难以协调。After completion, the anti-sliding pile retaining structures are all reinforced concrete structures, which are difficult to coordinate with the surrounding environment.

发明内容Contents of the invention

为了消除现有直立式抗滑桩的不利因素,本发明实施例提供了一种滑坡及边坡治理的非直立式抗滑桩结构及安装方法。所述技术方案如下:In order to eliminate the unfavorable factors of the existing vertical anti-slide piles, the embodiment of the present invention provides a non-vertical anti-slide pile structure and installation method for landslide and side slope treatment. Described technical scheme is as follows:

一方面,提供了一种滑坡及边坡治理的非直立式抗滑桩结构,包括:非直立式抗滑桩;坡脚线以上所述非直立式抗滑桩之间设置有桩间横梁,所述非直立式抗滑桩顶部设置有桩顶冠梁;所述非直立式抗滑桩与所述桩间横梁、所述桩顶冠梁连接处桩身上设置有预埋塑料套管,穿过所述预埋塑料套管设置有预应力锚索。On the one hand, a non-vertical anti-slide pile structure for landslide and side slope treatment is provided, including: non-vertical anti-slide piles; inter-pile crossbeams are arranged between the non-vertical anti-slide piles above the slope line, The top of the non-vertical anti-slide pile is provided with a pile top crown beam; the joint between the non-vertical anti-slide pile and the cross beam between the piles and the pile top crown beam is provided with a pre-embedded plastic sleeve on the pile body. A prestressed anchor cable is arranged through the pre-embedded plastic casing.

进一步的,所述非直立式抗滑桩包括:非直立式抗滑桩桩身锚固段和非直立式抗滑桩桩身非锚固段;所述非直立式抗滑桩桩身锚固段依坡角β倾斜地设置于坡前稳定岩土体内,所述非直立式抗滑桩桩身非锚固段设置于滑坡坡面上。Further, the non-vertical anti-slide pile includes: an anchor section of the non-vertical anti-slide pile body and a non-anchor section of the non-vertical anti-slide pile body; the anchor section of the non-vertical anti-slide pile depends on the slope The angle β is arranged obliquely in the stable rock and soil body before the slope, and the non-anchor section of the non-vertical anti-slide pile body is arranged on the slope surface of the landslide.

进一步的,所述非直立式抗滑桩桩型可以是钢筋混凝土预制方桩、管桩、H型钢桩或现浇钢筋混凝土桩。Further, the non-vertical anti-slide pile type may be a reinforced concrete prefabricated square pile, a pipe pile, an H-shaped steel pile or a cast-in-place reinforced concrete pile.

进一步的,所述非直立式抗滑桩断面形式可以是圆形、矩形、三角形、梯形或异形桩。Further, the section form of the non-vertical anti-slide pile may be a circular, rectangular, triangular, trapezoidal or special-shaped pile.

另一方面,提供了一种滑坡及边坡治理的非直立式抗滑桩结构的安装方法,包括:On the other hand, a non-vertical anti-slide pile structure installation method for landslide and slope treatment is provided, including:

步骤一、根据勘察资料对滑坡类型、规模、滑坡体厚度、滑坡周界、滑动面类型、滑动面空间位置、滑动主轴及滑坡范围内岩土体物理力学参数进行收集调查;Step 1. According to the survey data, collect and investigate the landslide type, scale, landslide body thickness, landslide perimeter, sliding surface type, sliding surface spatial position, sliding main axis and rock and soil physical and mechanical parameters within the scope of the landslide;

步骤二、根据步骤一收集调查所得资料按照现行规范推荐的力学模型进行滑坡推力计算;Step 2. According to the data collected and investigated in step 1, calculate the landslide thrust according to the mechanical model recommended by the current code;

步骤三、根据步骤二计算所得滑坡推力进行桩长、锚固深度、桩间距和桩身断面尺寸等几何参数设计;Step 3, carry out the design of geometric parameters such as pile length, anchorage depth, pile spacing and pile body section size according to the landslide thrust calculated in step 2;

步骤四、根据步骤三拟定的抗滑桩设计方案,将非直立式抗滑桩及滑坡影响范围内岩土体按预设角度旋转成直立式抗滑桩后进行桩身内力计算并对非直立式现浇混凝土抗滑桩进行配筋;Step 4. According to the anti-slide pile design plan drawn up in step 3, the non-vertical anti-slide pile and the rock and soil within the affected area of the landslide are rotated into a vertical anti-slide pile according to a preset angle, and then the internal force of the pile body is calculated and the non-vertical anti-slide pile is calculated. Type cast-in-place concrete anti-slide piles for reinforcement;

步骤五、按设计好的几何参数及配筋进行施工。Step 5: Carry out construction according to the designed geometric parameters and reinforcement.

进一步的,所述预设角度为90°-β;式中β为滑坡坡角。Further, the preset angle is 90°-β; where β is the landslide slope angle.

进一步的,所述步骤五、按设计好的几何参数及配筋进行施工,步骤具体如下:Further, the step five is to carry out construction according to the designed geometric parameters and reinforcement, and the steps are as follows:

步骤①修整滑坡坡面,为坡脚线以上坡面桩身非锚固段支模做准备;Step ①Repair the slope surface of the landslide, and prepare for the formwork support of the non-anchored section of the pile body above the toe line of the slope;

步骤②根据设计好的几何参数在坡脚线以下预定桩位按照滑坡坡面角度β斜向下方进行人工挖孔作业并做好桩孔保护,并同时在坡脚线以上坡面设置桩身非锚固段模板;Step ② According to the designed geometric parameters, pre-determined pile positions below the toe line of the slope are carried out manually digging holes obliquely downward according to the angle β of the landslide slope, and the pile holes are well protected. Anchor segment template;

步骤③沿着坡面上设置的模板吊放钢筋笼至坡脚线以下倾斜桩孔内预定深度,并灌注混凝土即可完成一整根抗滑桩的施工;Step ③ Hang the reinforcement cage along the formwork set on the slope to the predetermined depth in the inclined pile hole below the toe line of the slope, and pour concrete to complete the construction of a whole anti-slide pile;

步骤④按照步骤②~步骤③间隔施工完成其他抗滑桩混凝土的浇捣;Step ④ Complete the pouring and tamping of other anti-slide pile concrete according to steps ② to step ③ at intervals;

步骤⑤根据需要设置桩顶冠梁及桩间横梁;Step ⑤ Set pile top crown beams and pile beams as required;

步骤⑥根据需要设置一道桩顶预应力锚索或多道预应力锚索,预应力锚索可以穿过抗滑桩桩身上预埋塑料套管设置也可以设置在桩顶冠梁和桩间横梁上。Step ⑥ Set one prestressed anchor cable or multiple prestressed anchor cables at the top of the pile according to the needs. The prestressed anchor cable can pass through the pre-embedded plastic sleeve on the anti-sliding pile, or it can be installed on the crown beam of the pile and the beam between the piles. superior.

本发明实施例提供的技术方案带来的有益效果是:The beneficial effects brought by the technical solution provided by the embodiments of the present invention are:

本发明提供了一种滑坡及边坡治理的非直立式抗滑桩结构及方法。①抗滑桩系统协同受力,结构上安全可靠;②非直立式抗滑桩适应坡面角度,减少岩土体的开挖与填筑,能够大幅度降低工程造价与缩短工期;③抗滑桩桩身非锚固段在露天支模浇捣混凝土,桩身质量容易控制,施工工序简单便于操作;④由于滑坡坡面倾斜,桩间土的局部稳定性容易得到满足,因此抗滑桩之间可不用设置挡土结构;⑤坡脚下桩身锚固段挖孔与坡面上桩身非锚固段支模可同时进行,各施工工序之间影响较小;⑥桩身锚固段开挖深度相对较短,人工挖孔作业对滑坡体扰动的影响可降低到最小;⑦在抗滑桩及桩间横梁形成的区格内植草或栽种小型灌木,因此容易做到与周围环境相适应,有利于生态环境保护;⑧适用性广泛,能够应用于各种复杂地质情况、各种地形、各种坡角、各种坡高的滑坡及边坡治理。The invention provides a non-vertical anti-slide pile structure and method for landslide and side slope treatment. ①The anti-slide pile system is coordinating force, and the structure is safe and reliable; ②The non-vertical anti-slide pile adapts to the slope angle, reduces the excavation and filling of rock and soil, and can greatly reduce the project cost and shorten the construction period; ③Anti-slide The non-anchor section of the pile body is poured and rammed concrete in the open-air formwork, the quality of the pile body is easy to control, and the construction process is simple and easy to operate; ④ Due to the slope of the landslide slope, the local stability of the soil between the piles is easy to be satisfied, so the There is no need to set up a retaining structure; ⑤ The excavation of the anchorage section of the pile body at the foot of the slope and the formwork support of the non-anchor section of the pile body on the slope surface can be carried out at the same time, and the influence between each construction process is small; ⑥ The excavation depth of the anchorage section of the pile body is relatively small. Short, the impact of manual digging on landslide disturbance can be minimized; ⑦ plant grass or small shrubs in the grid formed by anti-slide piles and beams between piles, so it is easy to adapt to the surrounding environment and is conducive to ecology Environmental protection; ⑧Wide applicability, can be applied to various complex geological conditions, various terrains, various slope angles, and various slope heights for landslide and slope control.

因此本发明能够在滑坡及边坡治理过程中节省大笔资金、缩短工期、有利于环境保护,是一种值得推广应用的滑坡及边坡治理方案。Therefore, the present invention can save a large sum of money, shorten the construction period, and be beneficial to environmental protection in the landslide and side slope treatment process, and is a landslide and side slope treatment scheme worthy of popularization and application.

附图说明Description of drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For those skilled in the art, other drawings can also be obtained based on these drawings without creative effort.

图1是本发明实施例一的一种滑坡及边坡非直立式抗滑桩治理正立面图;Fig. 1 is a kind of landslide and side slope non-vertical anti-slide pile treatment front elevation view of embodiment one of the present invention;

图2是本发明实施例一的图1中A-A剖面图。Fig. 2 is a sectional view of A-A in Fig. 1 according to Embodiment 1 of the present invention.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明实施方式作进一步地详细描述。In order to make the object, technical solution and advantages of the present invention clearer, the implementation manner of the present invention will be further described in detail below in conjunction with the accompanying drawings.

实施例一Embodiment one

本发明提供了一种滑坡及边坡治理的非直立式抗滑桩结构,参见图1-2,包括:非直立式抗滑桩;所述非直立式抗滑桩包括:非直立式抗滑桩桩身锚固段1和非直立式抗滑桩桩身非锚固段2;所述非直立式抗滑桩桩身锚固段1依坡角β倾斜地设置于坡前稳定岩土体内,所述非直立式抗滑桩桩身非锚固段2设置于滑坡坡面上,图1中还标示有滑坡坡脚线3、滑动面7、滑坡坡面角度β。The present invention provides a non-vertical anti-slide pile structure for landslide and slope treatment, as shown in Figure 1-2, including: non-vertical anti-slide pile; the non-vertical anti-slide pile includes: non-vertical anti-slide A pile body anchorage section 1 and a non-vertical anti-slide pile pile body non-anchor section 2; the non-vertical anti-slide pile pile body anchorage section 1 is arranged obliquely in the stable rock and soil body before the slope according to the slope angle β, and the The non-vertical anti-slide pile body non-anchor section 2 is set on the landslide slope, and the landslide foot line 3, the sliding surface 7, and the landslide slope angle β are also marked in Fig. 1 .

所述非直立式抗滑桩之间设置有桩间横梁4,所述非直立式抗滑桩顶部设置有桩顶冠梁5;所述非直立式抗滑桩与所述桩间横梁4、所述桩顶冠梁5连接处桩身上设置有预埋塑料套管,穿过所述预埋塑料套管设置有预应力锚索6。The non-vertical anti-slide piles are provided with crossbeams 4 between piles, and the top of the non-vertical anti-slide piles is provided with a pile crown beam 5; the non-vertical anti-slide piles and the crossbeams 4, A pre-embedded plastic casing is arranged on the pile at the junction of the pile top crown beam 5, and a prestressed anchor cable 6 is arranged through the pre-embedded plastic casing.

具体地,为适应滑坡坡面角度,将抗滑桩设置为深入坡前稳定岩土体中的非垂直柱形构件。所述非直立式抗滑桩的桩型可以是钢筋混凝土预制方桩、管桩、H型钢桩,本实施例中采用现浇钢筋混凝土桩。所述非直立式抗滑桩的断面形式可以是圆形、矩形、三角形、梯形或异形桩,本实施例中采用矩形断面形式。非直立式抗滑桩的成孔方式可以采用机械成孔或人工开挖成孔的方式,本实施例中采用人工开挖成孔的方式。非直立式抗滑桩按结构形式可以是单桩、单排桩、群桩或钢架桩,本实施例中采用单排桩。非直立式抗滑桩按结构受力方式可以是悬臂桩或锚拉桩,本实施例中采用锚拉桩。Specifically, in order to adapt to the slope angle of the landslide, the anti-slide pile is set as a non-vertical columnar member deep into the stable rock and soil mass before the slope. The pile types of the non-vertical anti-slide piles can be reinforced concrete prefabricated square piles, pipe piles, and H-shaped steel piles. In this embodiment, cast-in-place reinforced concrete piles are used. The section form of the non-vertical anti-slide pile can be circular, rectangular, triangular, trapezoidal or special-shaped pile, and the rectangular section form is adopted in this embodiment. The hole forming method of the non-vertical anti-slide pile can be mechanically or manually excavated. In this embodiment, the method of manually excavating the hole is adopted. The non-vertical anti-sliding piles can be single piles, single-row piles, group piles or steel frame piles according to the structural form, and single-row piles are used in this embodiment. The non-vertical anti-sliding piles can be cantilever piles or anchor piles according to the structural stress mode, and anchor piles are used in this embodiment.

本实施例中,非直立式抗滑桩设计一般应满足以下要求:In this embodiment, the design of non-vertical anti-slide piles should generally meet the following requirements:

(1)抗滑桩提供的阻滑力要使整个滑坡体具有足够的整体稳定性,即滑坡体的稳定安全系数满足相应规范规定的安全系数或可靠指标,同时保证坡体不从桩顶滑出,不从桩间挤出;(1) The anti-sliding force provided by the anti-slide piles should make the entire landslide body have sufficient overall stability, that is, the stability safety factor of the landslide body meets the safety factor or reliability index specified in the corresponding codes, and at the same time, it is ensured that the slope body does not slide from the top of the pile come out, do not squeeze out from between the piles;

(2)抗滑桩桩身要有足够的强度和稳定性,即桩身要有足够的刚度,桩身应力和变形满足规定要求;(2) The pile body of the anti-slide pile should have sufficient strength and stability, that is, the pile body should have sufficient rigidity, and the stress and deformation of the pile body should meet the specified requirements;

(3)桩周的地基抗力和滑体的变形在容许范围内;(3) The foundation resistance around the pile and the deformation of the sliding body are within the allowable range;

(4)抗滑桩桩长及锚固段长度、桩间距、桩结构尺度和桩断面尺寸都比较适当,安全可靠,施工可行、方便,造价较经济。(4) The length of the anti-slide pile, the length of the anchorage section, the distance between the piles, the size of the pile structure and the size of the pile section are relatively appropriate, safe and reliable, feasible and convenient for construction, and relatively economical in cost.

非直立式抗滑桩桩身内力分析时,可以将非直立式抗滑桩及滑坡影响范围内的岩土体按一定角度(90°-β,β为滑坡坡角)旋转成直立式抗滑桩进行桩身内力分析计算并对非直立式混凝土抗滑桩进行配筋。When analyzing the internal force of the non-vertical anti-slide pile, the non-vertical anti-slide pile and the rock and soil within the influence range of the landslide can be rotated at a certain angle (90°-β, β is the slope angle of the landslide) into a vertical anti-slide The internal force of the pile body is analyzed and calculated, and the non-vertical concrete anti-slide pile is reinforced.

实施例二Embodiment two

另一方面,提供了一种滑坡及边坡治理的非直立式抗滑桩结构的安装方法,包括:On the other hand, a non-vertical anti-slide pile structure installation method for landslide and slope treatment is provided, including:

步骤一、根据勘察资料对滑坡类型、规模、滑坡体厚度、滑坡周界、滑动面类型、滑动面空间位置、滑动主轴及滑坡范围内岩土体物理力学参数进行收集调查;Step 1. According to the survey data, collect and investigate the landslide type, scale, landslide body thickness, landslide perimeter, sliding surface type, sliding surface spatial position, sliding main axis and rock and soil physical and mechanical parameters within the scope of the landslide;

步骤二、根据步骤一收集调查所得资料按照现行规范推荐的力学模型进行滑坡推力计算;Step 2. According to the data collected and investigated in step 1, calculate the landslide thrust according to the mechanical model recommended by the current code;

步骤三、根据步骤二计算所得滑坡推力进行桩长、锚固段长度、桩间距和桩身断面尺寸等几何参数的设计;Step 3, carry out the design of geometric parameters such as pile length, anchor length, pile spacing and pile body section size according to the landslide thrust calculated in step 2;

步骤四、根据步骤三拟定的设计方案,将非直立式抗滑桩及滑坡影响范围内的岩土体按预设角度旋转成直立式抗滑桩后进行桩身内力计算并对非直立式现浇混凝土抗滑桩进行配筋;Step 4. According to the design plan drawn up in step 3, the non-vertical anti-slide pile and the rock and soil within the influence range of the landslide are rotated into a vertical anti-slide pile according to a preset angle, and then the internal force of the pile body is calculated and the non-vertical anti-slide pile is calculated. Pouring concrete anti-slide piles for reinforcement;

步骤五、按设计好的几何参数及配筋进行施工。Step 5: Carry out construction according to the designed geometric parameters and reinforcement.

进一步的,所述预设角度为90°-β;式中β为滑坡坡角。Further, the preset angle is 90°-β; where β is the landslide slope angle.

进一步的,所述步骤五、按设计好的几何参数及配筋进行施工,步骤具体如下:Further, the step five is to carry out construction according to the designed geometric parameters and reinforcement, and the steps are as follows:

步骤①修整滑坡坡面,为坡脚线以上坡面桩身非锚固段支模做准备;Step ①Repair the slope surface of the landslide, and prepare for the formwork support of the non-anchored section of the pile body above the toe line of the slope;

步骤②根据设计好的几何参数在坡脚线以下预定桩位按照滑坡坡面角度β斜向下方进行人工挖孔作业并做好桩孔保护,并同时在坡脚线以上坡面上设置桩身非锚固段模板;Step ② According to the designed geometric parameters, pre-determined pile positions below the slope toe line, carry out manual digging operations obliquely downward according to the slope angle β of the landslide, and do a good job of pile hole protection, and at the same time set the pile body on the slope above the slope toe line Non-anchor section formwork;

步骤③沿着坡面上设置的模板吊放钢筋笼至坡脚线以下倾斜桩孔内预定深度,并灌注混凝土即可完成一整根抗滑桩的施工;Step ③ Hang the reinforcement cage along the formwork set on the slope to the predetermined depth in the inclined pile hole below the toe line of the slope, and pour concrete to complete the construction of a whole anti-slide pile;

步骤④按照步骤②~步骤③间隔施工完成其他非直立式抗滑桩混凝土的浇捣;Step ④ Complete the pouring and tamping of other non-vertical anti-slide pile concrete according to steps ② to ③ at intervals;

步骤⑤根据需要设置桩顶冠梁及桩间横梁;Step ⑤ Set pile top crown beams and pile beams as required;

步骤⑥根据需要设置一道桩顶预应力锚索或多道预应力锚索,预应力锚索可以过抗滑桩桩身预埋塑料套管设置也可以设置在桩顶冠梁和桩间横梁上。Step ⑥ Set one prestressed anchor cable or multiple prestressed anchor cables at the top of the pile according to the needs. The prestressed anchor cable can be installed through the pre-embedded plastic casing of the anti-slide pile body or on the crown beam of the pile top and the beam between the piles. .

本实施例中,鉴于一般滑坡坡面通常有一定的坡度(坡角一般小于90°),综合考虑传统直立式抗滑桩的优缺点,本发明提供了一种滑坡及边坡治理的非直立式抗滑桩结构及安装方法。该方法能够适应滑坡体坡面角度,在滑坡坡脚线以下预定桩位按照滑坡坡面角度β斜向下方通过人工或机械开挖方式开挖抗滑桩桩身锚固段桩孔,同时在坡脚线以上坡面上设置抗滑桩桩身非锚固段模板,然后将钢筋笼沿着坡面上桩身非锚固段模板倾斜吊放到坡脚下方倾斜桩孔预定深度后完成一整根抗滑桩混凝土的浇捣。In this embodiment, in view of the fact that the general landslide slope usually has a certain slope (the slope angle is generally less than 90°), and considering the advantages and disadvantages of traditional vertical anti-slide piles, the present invention provides a non-vertical pile for landslide and slope control. Type anti-slide pile structure and installation method. This method can adapt to the slope angle of the landslide body, and the predetermined pile position below the footline of the landslide slope is obliquely downward according to the angle β of the slope surface of the landslide, and the pile hole of the anchorage section of the anti-slide pile body is excavated by manual or mechanical excavation. Set the formwork of the non-anchor section of the anti-slide pile on the slope above the foot line, and then tilt the steel cage along the formwork of the non-anchor section of the pile body on the slope to the predetermined depth of the inclined pile hole below the foot of the slope to complete a whole anti-slide pile. Pouring and pounding of slide pile concrete.

本发明实施例提供的技术方案带来的有益效果是:The beneficial effects brought by the technical solution provided by the embodiments of the present invention are:

本发明提供了一种滑坡及边坡治理的非直立式抗滑桩结构及安装方法。①抗滑桩系统协同受力,结构上安全可靠;②非直立式抗滑桩适应坡面角度,减少岩土体的开挖与填筑,能够大幅度降低工程造价与缩短工期;③抗滑桩桩身非锚固段在露天支模浇捣混凝土,桩身质量容易控制,施工工序简单便于操作;④由于滑坡坡面倾斜,桩间土的局部稳定性容易得到满足,因此抗滑桩之间可不用设置挡土结构;⑤坡脚下桩身锚固段挖孔与坡面上桩身非锚固段支模可同时进行,各施工工序之间影响较小;⑥桩身锚固段开挖深度相对较短,人工挖孔作业对滑坡体扰动的影响可降低到最小;⑦在抗滑桩及桩间横梁形成的区格内植草或栽种小型灌木,因此容易做到与周围环境相适应,有利于生态环境保护;⑧适用性广泛,能够应用于各种复杂地质情况、各种地形、各种坡角、各种坡高的滑坡及边坡治理。The invention provides a non-vertical anti-slide pile structure and an installation method for landslide and side slope treatment. ①The anti-slide pile system is coordinating force, and the structure is safe and reliable; ②The non-vertical anti-slide pile adapts to the slope angle, reduces the excavation and filling of rock and soil, and can greatly reduce the project cost and shorten the construction period; ③Anti-slide The non-anchor section of the pile body is poured and rammed concrete in the open-air formwork, the quality of the pile body is easy to control, and the construction process is simple and easy to operate; ④ Due to the slope of the landslide slope, the local stability of the soil between the piles is easy to be satisfied, so the There is no need to set up a retaining structure; ⑤ The excavation of the anchorage section of the pile body at the foot of the slope and the formwork support of the non-anchor section of the pile body on the slope surface can be carried out at the same time, and the influence between each construction process is small; ⑥ The excavation depth of the anchorage section of the pile body is relatively small. Short, the impact of manual digging on landslide disturbance can be minimized; ⑦ plant grass or small shrubs in the grid formed by anti-slide piles and beams between piles, so it is easy to adapt to the surrounding environment and is conducive to ecology Environmental protection; ⑧Wide applicability, can be applied to various complex geological conditions, various terrains, various slope angles, and various slope heights for landslide and slope control.

因此本发明能够在滑坡及边坡治理过程中节省大笔资金、缩短工期、有利于环境保护,是一种值得推广应用的滑坡及边坡治理方案。Therefore, the present invention can save a large sum of money, shorten the construction period, and be beneficial to environmental protection in the landslide and side slope treatment process, and is a landslide and side slope treatment scheme worthy of popularization and application.

以上仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention Inside.

Claims (7)

1.一种滑坡及边坡治理的非直立式抗滑桩结构,其特征在于,包括:非直立式抗滑桩;坡脚线以上所述非直立式抗滑桩之间设置有桩间横梁,所述非直立式抗滑桩顶部设置有桩顶冠梁;所述非直立式抗滑桩与所述桩间横梁、所述桩顶冠梁连接处桩身上设置有预埋塑料套管,穿过所述预埋塑料套管设置有预应力锚索。1. A non-vertical anti-slide pile structure for landslide and slope control, characterized in that it comprises: non-vertical anti-slide piles; crossbeams between piles are arranged between the non-vertical anti-slide piles above the foot line , the top of the non-vertical anti-slide pile is provided with a pile top crown beam; the non-vertical anti-slide pile is provided with a pre-embedded plastic sleeve at the junction of the non-vertical anti-slide pile, the cross beam between the piles, and the pile top crown beam, A prestressed anchor cable is arranged through the pre-embedded plastic casing. 2.如权利要求1所述的滑坡及边坡治理的非直立式抗滑桩结构,其特征在于,所述非直立式抗滑桩包括:非直立式抗滑桩桩身锚固段和非直立式抗滑桩桩身非锚固段两部分;所述非直立式抗滑桩桩身锚固段依坡角β倾斜地设置于坡前稳定岩土体中,所述非直立式抗滑桩桩身非锚固段设置于滑坡坡面上。2. The non-vertical anti-slide pile structure for landslide and slope control as claimed in claim 1, wherein said non-vertical anti-slide pile comprises: non-vertical anti-slide pile anchorage section and non-vertical There are two parts of the non-anchor section of the non-vertical anti-slide pile body; the anchor section of the non-vertical anti-slide pile body is obliquely arranged in the stable rock and soil before the slope according to the slope angle β, and the non-vertical anti-slide pile body The non-anchor section is set on the landslide slope. 3.如权利要求2所述的滑坡及边坡治理的非直立式抗滑桩结构,其特征在于,所述非直立式抗滑桩桩型可以是钢筋混凝土预制方桩、管桩、H型钢桩或现浇钢筋混凝土桩。3. the non-vertical anti-slide pile structure of landslide and slope control as claimed in claim 2, is characterized in that, described non-vertical anti-slide pile pile type can be reinforced concrete prefabricated square pile, pipe pile, H-shaped steel piles or cast-in-place reinforced concrete piles. 4.如权利要求3所述的滑坡及边坡治理的非直立式抗滑桩结构,其特征在于,所述非直立式抗滑桩断面形式可以是圆形、矩形、三角形、梯形或异形桩。4. The non-vertical anti-slide pile structure for landslide and slope control as claimed in claim 3, wherein the cross-sectional form of the non-vertical anti-slide pile can be circular, rectangular, triangular, trapezoidal or special-shaped piles . 5.一种滑坡及边坡治理的非直立式抗滑桩结构安装方法,其特征在于,包括:5. A non-vertical anti-slide pile structure installation method for landslide and slope control, characterized in that, comprising: 步骤一、根据勘察资料对滑坡类型、规模、滑坡体厚度、滑坡周界、滑动面类型、滑动面空间位置、滑动主轴及滑坡范围内岩土体物理力学参数进行收集调查;Step 1. According to the survey data, collect and investigate the landslide type, scale, landslide body thickness, landslide perimeter, sliding surface type, sliding surface spatial position, sliding main axis and rock and soil physical and mechanical parameters within the scope of the landslide; 步骤二、根据步骤一收集调查所得资料按照现行规范推荐的力学模型进行滑坡推力计算;Step 2. According to the data collected and investigated in step 1, calculate the landslide thrust according to the mechanical model recommended by the current code; 步骤三、根据步骤二计算所得滑坡推力进行桩长、桩身锚固段长度、桩间距和桩身断面尺寸等几何参数设计;Step 3, according to the landslide thrust calculated in step 2, carry out geometric parameter design such as pile length, pile body anchorage section length, pile spacing and pile body section size; 步骤四、根据步骤三拟定的抗滑桩设计方案,将非直立式抗滑桩及滑坡影响范围内的岩土体按预设角度旋转成直立式抗滑桩后进行桩身内力计算并对非直立式现浇混凝土抗滑桩进行配筋;Step 4. According to the anti-slide pile design scheme drawn up in step 3, the non-vertical anti-slide pile and the rock and soil within the influence range of the landslide are rotated into a vertical anti-slide pile according to a preset angle, and the internal force of the pile body is calculated and the non-vertical anti-slide pile is calculated. Vertical cast-in-place concrete anti-slide piles are reinforced; 步骤五、按设计好的几何参数及配筋进行施工。Step 5: Carry out construction according to the designed geometric parameters and reinforcement. 6.如权利要求5所述的方法,其特征在于,所述预设角度为90°-β;式中β为滑坡坡角。6. The method according to claim 5, wherein the preset angle is 90°-β; wherein β is the slope angle of the landslide. 7.如权利要求6所述的方法,其特征在于,所述步骤五、按设计好的几何参数及配筋进行施工,步骤具体如下:7. The method according to claim 6, characterized in that, said step 5, constructing according to the designed geometric parameters and reinforcement, the steps are as follows: 步骤①修整滑坡坡面,为坡脚线以上坡面桩身非锚固段支模做准备;Step ①Repair the slope surface of the landslide, and prepare for the formwork support of the non-anchored section of the pile body above the toe line of the slope; 步骤②根据设计好的几何参数在坡脚线以下预定桩位按照滑坡坡面角度β斜向下方进行人工挖孔作业并做好桩孔保护,并同时在坡脚线以上坡面设置桩身非锚固段模板;Step 2. According to the designed geometric parameters, pre-determined pile positions below the slope toe line, carry out manual digging operations obliquely downward according to the slope angle β of the landslide, and do a good job of pile hole protection, and at the same time, set the pile body on the slope above the slope toe line. Anchor segment template; 步骤③沿着坡面上设置的模板吊放钢筋笼至坡脚线以下倾斜桩孔内预定深度,并灌注混凝土即可完成一整根抗滑桩的施工;Step ③ Hang the reinforcement cage along the formwork set on the slope to the predetermined depth in the inclined pile hole below the toe line of the slope, and pour concrete to complete the construction of a whole anti-slide pile; 步骤④按照步骤②~步骤③间隔施工完成其他抗滑桩混凝土的浇捣;Step ④ Complete the pouring and tamping of other anti-slide pile concrete according to steps ② to step ③ at intervals; 步骤⑤根据需要设置桩顶冠梁及桩间横梁;Step ⑤ Set pile top crown beams and pile beams as required; 步骤⑥根据需要设置一道桩顶预应力锚索或多道预应力锚索,预应力锚索可以穿过抗滑桩桩身上预埋塑料套管设置也可以设置在桩顶冠梁和桩间横梁上。Step ⑥ Set up one prestressed anchor cable or multiple prestressed anchor cables at the top of the pile as required. The prestressed anchor cable can be installed through the pre-embedded plastic sleeve on the anti-slide pile, or it can be installed on the crown beam of the pile and the beam between the piles. superior.
CN201811022846.XA 2018-09-03 2018-09-03 It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method Pending CN108978687A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811022846.XA CN108978687A (en) 2018-09-03 2018-09-03 It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811022846.XA CN108978687A (en) 2018-09-03 2018-09-03 It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method

Publications (1)

Publication Number Publication Date
CN108978687A true CN108978687A (en) 2018-12-11

Family

ID=64546936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811022846.XA Pending CN108978687A (en) 2018-09-03 2018-09-03 It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method

Country Status (1)

Country Link
CN (1) CN108978687A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185049A (en) * 2019-06-14 2019-08-30 杭州电子科技大学 A kind of friction pile for slope treatment
CN110318406A (en) * 2019-06-14 2019-10-11 杭州电子科技大学 Anti-slide pile for slope treatment
CN110439011A (en) * 2019-09-04 2019-11-12 中国电建集团中南勘测设计研究院有限公司 A kind of side slope antiskid supporting construction and its construction method
CN113463666A (en) * 2021-07-12 2021-10-01 中国电建集团成都勘测设计研究院有限公司 Row pile structure for soil cutting slope and construction method thereof
CN114482091A (en) * 2022-02-09 2022-05-13 中铁二十三局集团第四工程有限公司 Construction method of side slope anchoring pile
CN116289758A (en) * 2022-09-09 2023-06-23 国能大渡河流域水电开发有限公司 A composite anti-slide pile structure and its construction method for soil slope reinforcement in reservoir area
CN118668549A (en) * 2024-08-13 2024-09-20 内蒙古交通设计研究院有限责任公司 Interface type landslide highway emergency communication-keeping disposal structure and method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201148621Y (en) * 2008-01-11 2008-11-12 肖世国 Composite structure of miniature anti-slide piles
CN101408023A (en) * 2008-11-11 2009-04-15 天津大学 Method for supporting and protecting row pile pit
CN202401461U (en) * 2011-12-01 2012-08-29 广东省基础工程公司 Novel foundation pit shoring structure
CN102864781A (en) * 2012-09-29 2013-01-09 成都四海岩土工程有限公司 Foundation pit supporting method utilizing inclined piles
CN203498841U (en) * 2013-09-30 2014-03-26 中国建筑股份有限公司 Inclined pile vertical anchor rod supporting structure used for foundation pit supporting
CN106650118A (en) * 2016-12-27 2017-05-10 青岛理工大学 Optimization design method for governing parameters of side slope slide-resistant pile
CN206220122U (en) * 2016-11-11 2017-06-06 叶晓明 Novel self-balanced retaining wall
CN108396773A (en) * 2018-03-30 2018-08-14 四川志德岩土工程有限责任公司 A kind of loose-leaf type peg board retaining wall
CN208763028U (en) * 2018-09-03 2019-04-19 南华大学 A non-vertical anti-slide pile structure for landslide and slope treatment

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201148621Y (en) * 2008-01-11 2008-11-12 肖世国 Composite structure of miniature anti-slide piles
CN101408023A (en) * 2008-11-11 2009-04-15 天津大学 Method for supporting and protecting row pile pit
CN202401461U (en) * 2011-12-01 2012-08-29 广东省基础工程公司 Novel foundation pit shoring structure
CN102864781A (en) * 2012-09-29 2013-01-09 成都四海岩土工程有限公司 Foundation pit supporting method utilizing inclined piles
CN203498841U (en) * 2013-09-30 2014-03-26 中国建筑股份有限公司 Inclined pile vertical anchor rod supporting structure used for foundation pit supporting
CN206220122U (en) * 2016-11-11 2017-06-06 叶晓明 Novel self-balanced retaining wall
CN106650118A (en) * 2016-12-27 2017-05-10 青岛理工大学 Optimization design method for governing parameters of side slope slide-resistant pile
CN108396773A (en) * 2018-03-30 2018-08-14 四川志德岩土工程有限责任公司 A kind of loose-leaf type peg board retaining wall
CN208763028U (en) * 2018-09-03 2019-04-19 南华大学 A non-vertical anti-slide pile structure for landslide and slope treatment

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185049A (en) * 2019-06-14 2019-08-30 杭州电子科技大学 A kind of friction pile for slope treatment
CN110318406A (en) * 2019-06-14 2019-10-11 杭州电子科技大学 Anti-slide pile for slope treatment
CN110185049B (en) * 2019-06-14 2021-05-04 宁夏盐池振兴水利开发工程有限公司 An anti-sliding pile for slope treatment
CN110439011A (en) * 2019-09-04 2019-11-12 中国电建集团中南勘测设计研究院有限公司 A kind of side slope antiskid supporting construction and its construction method
CN110439011B (en) * 2019-09-04 2024-01-30 中国电建集团中南勘测设计研究院有限公司 Side slope anti-slip supporting structure and construction method thereof
CN113463666A (en) * 2021-07-12 2021-10-01 中国电建集团成都勘测设计研究院有限公司 Row pile structure for soil cutting slope and construction method thereof
CN114482091A (en) * 2022-02-09 2022-05-13 中铁二十三局集团第四工程有限公司 Construction method of side slope anchoring pile
CN114482091B (en) * 2022-02-09 2024-06-04 中铁二十三局集团第四工程有限公司 Construction method of slope anchoring pile
CN116289758A (en) * 2022-09-09 2023-06-23 国能大渡河流域水电开发有限公司 A composite anti-slide pile structure and its construction method for soil slope reinforcement in reservoir area
CN118668549A (en) * 2024-08-13 2024-09-20 内蒙古交通设计研究院有限责任公司 Interface type landslide highway emergency communication-keeping disposal structure and method
CN118668549B (en) * 2024-08-13 2025-02-25 内蒙古交通设计研究院有限责任公司 An emergency maintenance structure and method for interface landslide highway

Similar Documents

Publication Publication Date Title
Chen et al. Recent advances in high slope reinforcement in China: Case studies
CN104652443B (en) Construction method of the interim horizontal support of deep basal pit as permanent structure beam
CN110374111B (en) Slope releasing and steel pipe pile anchor cooperative supporting system
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN101476466B (en) Construction method of anti-sliding tunnel with prestressed anchor cable and new structure for prevention and control of huge thick landslide
CN207633352U (en) A kind of slope reinforcement structure for rapid rescue construction
CN107130613A (en) Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN111851597B (en) Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method
CN105735345A (en) Composite type supporting and retaining structure and construction method adopting supporting and retaining structure
CN103556602B (en) Structural body for preventing starting of gully debris flows and design method of structural body
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN208763028U (en) A non-vertical anti-slide pile structure for landslide and slope treatment
CN110735436A (en) cutting rock slope reinforced structure
CN104727324B (en) Irregular basement construction method for supporting
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN109881683A (en) A kind of more sublevel retaining structures and its construction method for combining artificial earth fill's grouting reinforcement technique
CN205502063U (en) Combined type retaining structure
CN111851515B (en) Adjacent foundation pit cooperative construction enclosure structure and construction method thereof
CN110939139B (en) Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles
CN109306712A (en) Upper pipe working well is inverse to build construction
Yao et al. Numerical analysis of the influence of isolation piles in metro tunnel construction of adjacent buildings
CN209941754U (en) High-voltage power pipe culvert in-situ protection structure
CN111894017A (en) Miniature pile group slope reinforcing structure
CN201908313U (en) Side slope reinforcement structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211

RJ01 Rejection of invention patent application after publication