CN108330963A CN201810330984.8A CN201810330984A CN108330963A CN 108330963 A CN108330963 A CN 108330963A CN 201810330984 A CN201810330984 A CN 201810330984A CN 108330963 A CN108330963 A CN 108330963A
Authority
CN
China
Prior art keywords
pile foundation
pile
piling
existing
existing pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810330984.8A
Other languages
Chinese (zh)
Inventor
屈伟
章志勇
吕坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changshu Institute of Technology
Original Assignee
Changshu Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changshu Institute of Technology filed Critical Changshu Institute of Technology
Priority to CN201810330984.8A priority Critical patent/CN108330963A/en
Publication of CN108330963A publication Critical patent/CN108330963A/en
Priority to CN201910136862.XA priority patent/CN109577322A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种用于土体内部既有桩基接桩的施工装置:确定既有桩基位置及其桩顶标高、桩顶超灌混凝土高度;采用人工挖孔方式进行土体开挖,并设置砖砌护壁;开挖至既有桩基的超灌部位,进行超灌部位的浮浆破除,破除至新鲜密实的混凝土,并保证既有桩基主筋长度出露满足要求;人工挖孔桩端采用扩大头形式;下放补桩部位钢筋笼并与既有桩基主筋焊接;浇筑补桩部位混凝土并充分振捣密实。本发明解决了地面以下既有桩基接桩的施工难题,传统的处理方法相比,本发明可减少大面积的土方开挖、土方回填及混凝土浇筑量,极大的形成了对地基土的保护,安全可靠并降低了施工成本。

The invention discloses a construction device for connecting existing pile foundations inside the soil body: determining the position of the existing pile foundation, the elevation of the pile top, and the height of overfilled concrete at the top of the pile; excavating the soil body by means of manual digging , and set up a brick retaining wall; excavate to the super-filled part of the existing pile foundation, remove the laitance at the super-filled part, and remove to fresh and dense concrete, and ensure that the length of the main reinforcement of the existing pile foundation meets the requirements; manual excavation The end of the hole pile is in the form of an enlarged head; the reinforcement cage at the supplementary pile is lowered and welded with the main reinforcement of the existing pile foundation; the concrete at the supplementary pile is poured and fully vibrated and compacted. The invention solves the construction problem of connecting existing pile foundations below the ground. Compared with the traditional treatment method, the invention can reduce large-area earthwork excavation, earthwork backfill and concrete pouring, and greatly forms the foundation soil. protection, safe and reliable and reduce construction costs.

Description

一种用于土体内部既有桩基接桩的施工装置A construction device for connecting existing pile foundations in soil

技术领域technical field

本发明涉及一种用于桩基接桩的施工装置,尤其是对土体内部的既有桩基接桩的施工装置。The invention relates to a construction device for connecting piles to pile foundations, in particular to a construction device for connecting piles to existing pile foundations inside the soil.

背景技术Background technique

桩基是既古老而又常见的基础形式,桩的作用是利用本身远大于士的刚度将上部结构的荷载传递到桩周及桩端较坚硬、压缩性小的土或岩石中,达到减小沉降、使建(构)筑物满足正常的使用功能及抗震等要求。由于桩基具有承载力高、稳定性好、沉降及差异沉降小、沉降稳定快、抗震性能好以及能适应各种复杂地质条件等特点而得到广泛使用。桩基础除了在一般工业与民用建筑中主要用于承受竖向抗压荷载外,还在桥梁、港口、公路、船坞、近海钻采平台、高耸及高重建(构)筑物、支挡结构以及抗震工程中用于承受侧向风力、波浪力、土压力、地震力、车辆制动力等水平力及竖向抗拔荷载等。据不完全统计,全国每年桩的使用超过100 万根以上。The pile foundation is an ancient and common foundation form. The function of the pile is to transfer the load of the superstructure to the hard and less compressible soil or rock around the pile and at the pile end by using its stiffness much greater than that of the pile, so as to reduce the Settlement, making buildings (structures) meet the requirements of normal use functions and earthquake resistance. The pile foundation is widely used because of its high bearing capacity, good stability, small settlement and differential settlement, fast settlement stability, good seismic performance, and adaptability to various complex geological conditions. In addition to being mainly used to bear vertical compressive loads in general industrial and civil buildings, pile foundations are also used in bridges, ports, highways, docks, offshore drilling platforms, towering and high reconstruction (structure) buildings, retaining structures and In seismic engineering, it is used to bear lateral wind force, wave force, earth pressure, earthquake force, vehicle braking force and other horizontal forces and vertical pullout loads. According to incomplete statistics, more than 1 million piles are used in China every year.

目前在桩基础的施工工程中,依然存在诸多不可控因素,影响桩基的成桩质量和成桩效果,施工桩长不满足要求是较为普遍的情况之一。产生施工桩长不满足要求的原因主要分为如下方面:1、施工现场技术交底工作不到位,未对桩长桩径、桩顶标高、桩端标高明确落实到具体管理人员;2、施工现场的管理人员的麻痹大意,各参建单位之间的沟通协调不到位,监理人员旁站工作不到位;3、施工操作人员未听从管理人员的安排,擅自进行下一工序施工。At present, in the construction of pile foundations, there are still many uncontrollable factors that affect the pile quality and effect of pile foundations. One of the more common situations is that the construction pile length does not meet the requirements. The reasons why the construction pile length does not meet the requirements are mainly divided into the following aspects: 1. The technical disclosure work on the construction site is not in place, and the pile length pile diameter, pile top elevation, and pile end elevation have not been clearly implemented to specific management personnel; 2. The construction site The management personnel are careless, the communication and coordination between the participating units are not in place, and the supervision personnel are not in place; 3. The construction operators do not obey the management personnel's arrangement, and proceed to the next process construction without authorization.

桩长不满足要求的典型案例即为桩顶标高未到达设计要求,需在已施工完成的桩基上部进行接桩,接桩后以满足设计的标高要求。若在工程中遇到此类情况,目前传统的处理方法是进行大面积的土方开挖,将地基土开挖至既有桩基桩顶标高位置,对桩顶超灌混凝土进行破除,再进行接桩工作。A typical case where the pile length does not meet the requirements is that the elevation of the pile top does not meet the design requirements, and piles need to be connected on the upper part of the pile foundation that has been constructed to meet the design elevation requirements. If this kind of situation is encountered in the project, the current traditional treatment method is to carry out large-scale earthwork excavation, excavate the foundation soil to the elevation of the pile top of the existing pile foundation, remove the overfilled concrete on the top of the pile, and then carry out Pile work.

此举在处理区域及开挖深度较小的情况下是可行的,对于开挖深度大、范围广的情况存在诸多困难,主要分为以下方面:This is feasible when the processing area and excavation depth are small, but there are many difficulties in the case of large excavation depth and wide range, which are mainly divided into the following aspects:

1、为了将地面标高降至既有桩定标高,需进行大面积的土方开挖,开挖深度过大另需进行基坑的支护工作,此举将极大的增加施工成本,极不经济。1. In order to reduce the ground elevation to the fixed elevation of the existing piles, a large area of earthwork excavation is required. If the excavation depth is too large, the support work for the foundation pit will be required. This will greatly increase the construction cost and greatly increase the construction cost. Uneconomical.

2、进行完接桩后,还需进行土方的回填,是地面标高回归至设计标高,此举同样会增加施工成本,同时在桩头出露区域进行土方的回填,此举的施工难度相当大。2. After the pile connection is completed, earthwork backfilling is required to return the ground elevation to the design elevation. This will also increase the construction cost. At the same time, earthwork backfilling in the exposed area of the pile head is quite difficult. .

3、土方的开挖回填严重破坏地基土的原状性,对地基土的扰动极大,对今后建筑物地基的稳定性、沉降及差异沉降、抗震性能带来诸多不利。3. The excavation and backfilling of the earth will seriously damage the original state of the foundation soil, greatly disturb the foundation soil, and bring many disadvantages to the stability, settlement, differential settlement and seismic performance of the building foundation in the future.

除此之外,大面积的土体开挖回填,对工期的影响会非常大,整个施工过程还存在许多其他的不确定因素,海量的土方运输对现场的管理协调能力也是极大的考验。In addition, excavation and backfilling of large areas of soil will have a great impact on the construction period, and there are many other uncertain factors in the entire construction process. Massive earthwork transportation is also a great test for site management and coordination.

发明内容Contents of the invention

本发明的目的是针对上述现有技术的不足,提供一种安全可靠、技术可行、经济合理的用于土体内部既有桩基接桩的施工装置。The purpose of the present invention is to provide a safe, reliable, technically feasible, economical and reasonable construction device for connecting existing pile foundations inside the soil, aiming at the shortcomings of the above-mentioned prior art.

本发明的技术方案为:一种用于土体内部既有桩基接桩的施工装置,其特征在于:包括由下而上排布的既有桩基及补桩桩基,既有桩基桩顶设有超灌混凝土;所述既有桩基内部设有既有桩基主筋,所述既有桩基的顶面为既有桩基桩顶标高面,所述既有桩基主筋上部与超灌混凝土相接;所述补桩桩基由设置在补桩桩基外侧的护壁,补桩桩基下方的桩端扩大头,补桩桩基内部的补桩钢筋笼及补桩混凝土组成;补桩桩基的顶面为设计桩顶标高面;所述护壁由砖块组成,所述桩端扩大头沿补桩桩基向下延伸,包裹在既有桩基外侧;所述补桩钢筋笼由补桩桩基主筋与补桩桩基箍筋焊接而成,补桩桩基主筋与既有桩基主筋通过焊接固定连接,焊接长度为30cm-50cm,所述补桩桩基箍筋间距设置为既有桩基箍筋间距的0.5-1倍,补桩桩基主筋焊接部位箍筋间距设置为既有桩基箍筋间距的0.5-0.8倍;所述既有桩基位于土体内部,既有桩基顶标高面低于设计桩顶标高面,;所述补桩桩基的桩径大于所述既有桩基的桩径,为既有桩基桩径的1.2-1.5倍,所述补桩桩基的桩端扩大头直径为补桩桩基的桩径的1.2-1.5倍。The technical solution of the present invention is: a construction device for connecting existing pile foundations inside the soil, which is characterized in that it includes existing pile foundations and supplementary pile foundations arranged from bottom to top, and the existing pile foundations The top of the pile is provided with super-filled concrete; the inside of the existing pile foundation is provided with the existing main reinforcement of the pile foundation, the top surface of the existing pile foundation is the elevation surface of the pile top of the existing pile foundation, and the upper part of the main reinforcement of the existing pile foundation It is connected with super-filled concrete; the supplementary pile foundation is composed of a retaining wall arranged on the outside of the supplementary pile foundation, a pile end expansion head under the supplementary pile foundation, a supplementary pile reinforcement cage inside the supplementary pile foundation and concrete for supplementary piles The top surface of the supplementary pile foundation is the design pile top elevation surface; the retaining wall is composed of bricks, and the enlarged head of the pile end extends downwards along the supplementary pile foundation and wraps around the existing pile foundation outside; the supplementary pile The reinforcement cage is welded by the main reinforcement of the supplementary pile foundation and the stirrup of the supplementary pile foundation. The main reinforcement of the supplementary pile foundation is fixedly connected with the main reinforcement of the existing pile foundation by welding. The welding length is 30cm-50cm. The stirrup of the supplementary pile foundation The spacing is set to 0.5-1 times the spacing of the existing pile foundation stirrups, and the spacing of the stirrups at the welding part of the main reinforcement of the supplementary pile foundation is set to 0.5-0.8 times the spacing of the existing pile foundation stirrups; the existing pile foundation is located in the soil Inside, the elevation of the top of the existing pile foundation is lower than the elevation of the designed pile top; the pile diameter of the supplementary pile foundation is greater than the pile diameter of the existing pile foundation, which is 1.2-1.5 times the pile diameter of the existing pile foundation , the diameter of the enlarged head at the pile end of the supplementary pile foundation is 1.2-1.5 times the pile diameter of the supplementary pile foundation.

本发明通过设置补桩桩基,将既有桩基桩顶标高面提高到设计桩顶标高面,避免了为了降低既有桩顶标高而大面积的开挖土方,也减少了开挖所带来的基坑支护工作,降低了施工成本;同时既有桩基和接桩桩基均埋设在土体内部,对地基土扰动较小,对今后建筑物地基的稳定性、沉降以及差异沉降、抗震性能等影响相较于土方开挖而言降低很多,工期也更容易控制,避免意外发生。The present invention raises the existing pile foundation pile top elevation to the design pile top elevation by setting the supplementary pile foundation, avoids large-area excavation earthwork in order to reduce the existing pile top elevation, and reduces the excavation costs. The support work of the foundation pit, which reduces the construction cost; at the same time, the existing pile foundation and pile foundation are buried inside the soil, which has little disturbance to the foundation soil, and has great influence on the stability, settlement and differential settlement of the building foundation in the future. Compared with earthwork excavation, the influence of anti-seismic performance is much lower, and the construction period is easier to control to avoid accidents.

作为优选,所述补桩桩基应开挖至既有桩基桩顶标高以下0.5-1m。As a preference, the supplementary pile foundation should be excavated to 0.5-1m below the height of the pile top of the existing pile foundation.

作为优选,补桩桩基的护壁宽度设置为5cm、10cm或15cm。Preferably, the wall width of the supplementary pile foundation is set to 5cm, 10cm or 15cm.

有益效果:本发明公开的一种用于土体内部既有桩基接桩的施工装置,经济合理地实现对土体内部既有桩基的接桩工作,可避免大面积的土方开挖与回填,最大程度的保护地基土不被扰动,保证地基土的稳定性,同时缩短施工工期。Beneficial effects: the invention discloses a construction device for connecting existing pile foundations inside the soil, which economically and reasonably realizes the pile connection work of existing pile foundations inside the soil, and can avoid large-area earth excavation and Backfilling protects the foundation soil from being disturbed to the greatest extent, ensures the stability of the foundation soil, and shortens the construction period at the same time.

附图说明Description of drawings

图1是本发明一种用于土体内部既有桩基接桩的施工装置的施工剖面示意图。Fig. 1 is a construction cross-sectional schematic view of a construction device for connecting existing pile foundations inside the soil according to the present invention.

图2是本发明补桩桩基的结构示意图。Fig. 2 is a schematic structural view of the pile foundation of the present invention.

图3是本发明补桩护壁的结构示意图。Fig. 3 is a schematic structural view of the pile-pile retaining wall of the present invention.

图中:1、设计桩顶标高,2、补桩桩基,3、超灌混凝土,4、既有桩基桩顶标高,5、既有桩基,6、补桩桩基箍筋,7、补桩桩基主筋,8、补桩桩端扩大头,9、既有桩基主筋,10、补桩混凝土,11、护壁,12、补桩钢筋笼。In the figure: 1. Design pile top elevation, 2. Supplementary pile foundation, 3. Overfilled concrete, 4. Existing pile foundation pile top elevation, 5. Existing pile foundation, 6. Supplementary pile foundation stirrups, 7 1. The main reinforcement of the pile foundation, 8. The enlarged head of the pile end of the pile, 9. The main reinforcement of the existing pile foundation, 10. The concrete of the pile, 11. The retaining wall, 12. The reinforcement cage of the pile.

具体实施方式Detailed ways

下面结合附图和具体实施方式对本发明做进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

如图1、图2、图3所示:一种用于土体内部既有桩基接桩的施工装置,包括由下而上排布的既有桩基5及补桩桩基2,既有桩基桩顶超灌混凝土3;As shown in Figure 1, Figure 2, and Figure 3: a construction device for connecting existing pile foundations inside the soil, including existing pile foundations 5 and supplementary pile foundations 2 arranged from bottom to top, both Pile foundation pile top overfilling concrete 3;

所述既有桩基5内部设有既有桩基主筋9,所述既有桩基5的顶面为既有桩基桩顶标高面4,所述既有桩基主筋9上部与超灌混凝土3相接;The existing pile foundation 5 is provided with the existing pile foundation main reinforcement 9 inside, the top surface of the existing pile foundation 5 is the existing pile foundation pile top elevation surface 4, and the existing pile foundation main reinforcement 9 top is connected with the super-filling Concrete 3 connected;

所述补桩桩基2由设置在补桩桩基外侧的护壁11,补桩桩基下方的桩端扩大头8,补桩桩基内部的补桩钢筋笼12及补桩混凝土10组成;补桩桩基2的顶面为设计桩顶标高面1;Described supplementary pile foundation 2 is made up of the retaining wall 11 that is arranged on the supplementary pile foundation outside, the pile end expansion head 8 below the supplementary pile foundation, the supplementary pile reinforcement cage 12 and the supplementary pile concrete 10 inside the supplementary pile foundation; The top surface of the pile foundation 2 is the design pile top elevation surface 1;

所述护壁11由砖块组成,所述桩端扩大头沿补桩桩基向下延伸,包裹在既有桩基外侧,所述补桩钢筋笼12由补桩桩基主筋7与补桩桩基箍筋6焊接组成,补桩桩基主筋7与既有桩基主筋9通过焊接固定连接。The retaining wall 11 is composed of bricks, and the enlarged head of the pile end extends downward along the supplementary pile foundation, and is wrapped around the outside of the existing pile foundation. The foundation stirrups 6 are formed by welding, and the main reinforcements 7 of the supplementary pile foundation are fixedly connected with the existing main reinforcements 9 of the pile foundation by welding.

既有桩基5位于土体内部,既有桩基桩顶标高4低于设计桩顶标高1,不能满足设计要求,需对既有桩基5进行接桩。The existing pile foundation 5 is located inside the soil, and the pile top elevation 4 of the existing pile foundation is lower than the design pile top elevation 1, which cannot meet the design requirements, and the existing pile foundation 5 needs to be connected with piles.

所述补桩桩基2桩径大于既有桩基5桩径,为既有桩基5桩径的1.2-1.5倍。所述补桩桩端扩大头8直径为补桩桩基2桩径的1.2-1.5倍。The 2 pile diameters of the supplementary pile foundation are greater than the 5 pile diameters of the existing pile foundation, and are 1.2-1.5 times of the 5 pile diameters of the existing pile foundation. The diameter of the enlarged head 8 at the end of the pile-filling pile is 1.2-1.5 times the diameter of the pile foundation 2 of the pile-filling pile.

所述补桩桩基2应开挖至既有桩基桩顶标高4以下0.5-1m。The supplementary pile foundation 2 should be excavated to 0.5-1m below the existing pile foundation pile top elevation 4.

所述补桩桩基主筋7需与既有桩基主筋9焊接,焊接长度为30cm-50cm。所述补桩桩基箍筋6间距设置为既有桩基箍筋间距的0.5-1倍,主筋焊接部位箍筋间距设置为既有桩基箍筋间距的0.5-0.8倍。The main reinforcement 7 of the supplementary pile foundation needs to be welded with the existing main reinforcement 9 of the pile foundation, and the welding length is 30cm-50cm. The distance between the 6 stirrups of the supplementary pile foundation is set to 0.5-1 times the distance between the stirrups of the existing pile foundation, and the distance between the stirrups at the welding part of the main reinforcement is set to 0.5-0.8 times the distance between the stirrups of the existing pile foundation.

所示护壁11宽度设置为5cm、10cm或15cm。The width of the shown retaining wall 11 is set to 5 cm, 10 cm or 15 cm.

Claims (3)

1. a kind of constructing device for inside soil body existing pile foundation pile extension, it is characterised in that:Including from bottom to top arranging both There are pile foundation and piling pile foundation, existing pile foundation stake top to be equipped with superfilled concrete;
The existing pile foundation is internally provided with existing pile foundation main reinforcement, and the top surface of the existing pile foundation is existing pile foundation stake top absolute altitude face, Existing pile foundation main reinforcement top connects with superfilled concrete;
The piling pile foundation is by being arranged the retaining wall on the outside of piling pile foundation, the stake end enlarged footing below piling pile foundation, piling pile foundation Internal piling steel reinforcement cage and piling coagulation local soil type at;The top surface of piling pile foundation is design stake top absolute altitude face;
The retaining wall is made of brick, and stake end enlarged footing is extended downwardly along piling pile foundation, is wrapped on the outside of existing pile foundation;Institute It states piling steel reinforcement cage to be welded by piling pile foundation main reinforcement and piling pile foundation stirrup, piling pile foundation main reinforcement is logical with existing pile foundation main reinforcement It crosses and is welded and fixed connection, weld length 30cm-50cm, the piling pile foundation stirrup spacing is set as existing pile foundation stirrup spacing 0.5-1 times, piling pile foundation main reinforcement welding position stirrup spacing is set as 0.5-0.8 times of existing pile foundation stirrup spacing;
The existing pile foundation is located inside soil body, and the high face of existing pile foundation top mark is less than design stake top absolute altitude face;The piling pile foundation Stake diameter be more than the stake diameter of the existing pile foundation, be 1.2-1.5 times of existing pile foundation pile diameter, the stake end expansion of the piling pile foundation 1.2-1.5 times of the stake diameter of a diameter of piling pile foundation.
2. a kind of constructing device for inside soil body existing pile foundation pile extension according to claim 1, it is characterised in that:Institute It is existing pile foundation stake top absolute altitude or less 0.5-1m to state piling pile foundation excavation face absolute altitude.
3. a kind of constructing device for inside soil body existing pile foundation pile extension according to claim 1, it is characterised in that:It mends The retaining wall width of stake pile foundation is set as 5cm, 10cm or 15cm.
CN201810330984.8A 2018-04-13 2018-04-13 A kind of constructing device for inside soil body existing pile foundation pile extension Withdrawn CN108330963A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810330984.8A CN108330963A (en) 2018-04-13 2018-04-13 A kind of constructing device for inside soil body existing pile foundation pile extension
CN201910136862.XA CN109577322A (en) 2018-04-13 2019-02-25 A kind of constructing device for inside soil body existing pile foundation pile extension

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810330984.8A CN108330963A (en) 2018-04-13 2018-04-13 A kind of constructing device for inside soil body existing pile foundation pile extension

Publications (1)

Publication Number Publication Date
CN108330963A true CN108330963A (en) 2018-07-27

Family

ID=62934021

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810330984.8A Withdrawn CN108330963A (en) 2018-04-13 2018-04-13 A kind of constructing device for inside soil body existing pile foundation pile extension
CN201910136862.XA Withdrawn CN109577322A (en) 2018-04-13 2019-02-25 A kind of constructing device for inside soil body existing pile foundation pile extension

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201910136862.XA Withdrawn CN109577322A (en) 2018-04-13 2019-02-25 A kind of constructing device for inside soil body existing pile foundation pile extension

Country Status (1)

Country Link
CN (2) CN108330963A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235427A (en) * 2018-11-20 2019-01-18 中建二局第建筑工程有限公司 A kind of pile extension body, pile splicing structure and pile extension method
CN109778845A (en) * 2019-01-31 2019-05-21 上海建工七建集团有限公司 The construction method and connecting node of deposited reinforced concrete pile pile extension
CN118223476A (en) * 2024-04-10 2024-06-21 上海市城市建设设计研究总院(集团)有限公司 Methods for extending existing pile foundations in soft soil areas

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111764446B (en) * 2020-07-16 2021-09-07 深圳市水务工程检测有限公司 Single-pile static load test auxiliary device

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139703A (en) * 2003-11-06 2005-06-02 Marugo Foundation Corp Reinforcing construction method of existing concrete pile
CN105421445A (en) * 2015-11-01 2016-03-23 天津建城基业集团有限公司 Construction method for non-prestressed centrifugal high-strength concrete pile planted pile
CN205712153U (en) * 2015-12-31 2016-11-23 上海建工五建集团有限公司 Foundation pile structure
CN209703493U (en) * 2018-04-13 2019-11-29 常熟理工学院 A construction device for connecting existing pile foundations in soil

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235427A (en) * 2018-11-20 2019-01-18 中建二局第建筑工程有限公司 A kind of pile extension body, pile splicing structure and pile extension method
CN109778845A (en) * 2019-01-31 2019-05-21 上海建工七建集团有限公司 The construction method and connecting node of deposited reinforced concrete pile pile extension
CN118223476A (en) * 2024-04-10 2024-06-21 上海市城市建设设计研究总院(集团)有限公司 Methods for extending existing pile foundations in soft soil areas

Also Published As

Publication number Publication date
CN109577322A (en) 2019-04-05

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN205742213U (en) Foundation pit supporting construction
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN105239586B (en) Method for supporting foundation pit by adopting support structure
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN105756091B (en) A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings
CN101408023A (en) Method for supporting and protecting row pile pit
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN108978687A (en) It is a kind of landslide and slope treatment non-straight vertical anti-slide pile structure and installation method
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN111021378A (en) Highway subgrade slope broken line type anchoring pile retaining structure and construction method thereof
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN101691760B (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN111236241A (en) Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN219158994U (en) A foundation pit support structure for ultra-deep and large-diameter circular pipe-jacking wells in deep soft soil areas
CN205502063U (en) Combined type retaining structure
CN104727324A (en) Support construction method of irregular basement
CN204311456U (en) Foundation ditch strengthening structure
CN211080248U (en) Deep foundation pit supporting structure of adjacent road under complex geological condition
CN209703493U (en) A construction device for connecting existing pile foundations in soil
CN208167770U (en) Assembled drilledpier foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180727