CN109385997A - The construction method of PHC tubular pole under narrow site condition - Google Patents

The construction method of PHC tubular pole under narrow site condition Download PDF

Info

Publication number
CN109385997A
CN109385997A CN201710661086.6A CN201710661086A CN109385997A CN 109385997 A CN109385997 A CN 109385997A CN 201710661086 A CN201710661086 A CN 201710661086A CN 109385997 A CN109385997 A CN 109385997A
Authority
CN
China
Prior art keywords
pile
tubular pole
stake
loop wheel
wheel machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710661086.6A
Other languages
Chinese (zh)
Other versions
CN109385997B (en
Inventor
王许龙
高志浩
韩树松
王成琳
王志朋
甘剑中
胡泽强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201710661086.6A priority Critical patent/CN109385997B/en
Publication of CN109385997A publication Critical patent/CN109385997A/en
Application granted granted Critical
Publication of CN109385997B publication Critical patent/CN109385997B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/16Arc welding or cutting making use of shielding gas
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles

Abstract

The invention discloses a kind of construction method of PHC tubular pole under narrow site condition, this method carries out the positioning of PHC pipe pile position first and loop wheel machine is in place;Pile monkey is set on loop wheel machine main hook and is adjusted by loop wheel machine erect-position and gin pole angular compliance, guarantees that pile monkey can be by having surveyed the true injection of stake level set;Tubular pole is hung to pile monkey position by loop wheel machine, digs out vertical shallow hole in tubular pole position, tubular pole lower end is entered by hole by loop wheel machine and cooperates tubular pole upper end straightening pile body;The verticality of pile body is calibrated by two theodolites;Starting pile monkey starts piling construction, and pile extension operation is carried out when the pile crown of lower section pile cutoff 0.5m above ground level;Continue piling construction by pile monkey, when stake top be sink to need pile follower close to ground when using Pile feeder pile follower to absolute altitude, and using the deviation of level control stake top absolute altitude.This method easy construction, speed are fast, and pile quality is high, avoid requirement of the conventional stake machine piling to construction site, reduce the destruction to urban operating mechanism and greening, reduce project cost.

Description

The construction method of PHC tubular pole under narrow site condition
Technical field
The present invention relates to a kind of construction methods of PHC tubular pole under narrow site condition.
Background technique
PHC tubular pole, i.e. PHC piles, bearing capacity of single pile is high, has a wide range of application, and factory Change, specialized, standardized production, pile quality is reliable, and transporting and hoisting is convenient, and pile extension is quick, and mechanized construction degree is high, behaviour Make simply, easy to control, in bearing capacity, anti-bending strength, anti-dial easily are guaranteed in performance, therefore obtain in recent years extremely widespread Application.With the propulsion of national urban construction, the implementation of infrastructure is such as parallel in some more special construction sites When implementing PHC tube pile construction on the outside of pipeline crack, greenbelt, with high costs needed for removal and leveling place, this just needs one kind Under narrow site condition, the method that across obstacle carries out PHC tube pile construction, urban operating mechanism is being protected not to be destroyed as far as possible In the case where, carry out tube pile construction.
Usual PHC tube pile construction machinery is crawler type or walking-type pile driver, both are mechanical from great, to site requirements Height, construction site require accessible, smooth and can satisfy a foundation bearing capacity for machine walking.Especially municipal pipeline is constructed In, basement process cost is high, and construction involves many areas, and coordination difficulty is big, big on influences such as project cost, quality, safety, progresses.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of construction methods of PHC tubular pole under narrow site condition, originally Method easy construction, speed are fast, and pile quality is high, avoid a large amount of mud contaminations generated using cast-in-situ bored pile or conventional stake machine The requirement driven piles to construction site reduces the destruction to urban operating mechanism and greening, reduces project cost.
In order to solve the above technical problems, the construction method of PHC tubular pole includes the following steps: under the narrow site condition of the present invention
Step 1: according to PHC tube pile construction detail drawing, it is accurately positioned the position of PHC tubular pole using total station, and loop wheel machine is accurately Position;
Step 2: by pile monkey be set to crane hook main hook on and with crane hydraulic system connection, hydraulic system pipeline length meet Tubular pole is adjusted in the length requirement of highs and lows by loop wheel machine erect-position and gin pole angular compliance, guarantees loop wheel machine erect-position Stability and pile monkey can be by having surveyed the true injection of stake level set;
It with anchor point is to justify in tubular pole position Step 3: by loop wheel machine hung tubular pole to pile monkey position using two o'clock lifting method Tubular pole lower end is entered hole by loop wheel machine and cooperates tubular pole upper end by the heart slightly larger than the vertical shallow hole that deep 500mm is dug out in tubular pole outer ring Smoothly straightening pile body;
Step 4: intersecting theodolite in 90 ° using two is set up in the position away from stake position certain distance, successively pass through two warps Latitude instrument detects the verticality of pile body, cooperates repeated detection adjustment by loop wheel machine and theodolite, guarantees pile body degree control 1% Within;
Step 5, starting pile monkey start piling construction, pile extension operation are carried out when the pile crown of lower section pile cutoff 0.5m above ground level, is connect Section pile cutoff keeps the straight and verticality by saving tubular pole on theodolite centering up and down when stake, section pile cutoff surrounding up and down symmetrically into Row welding and natural cooling;
Step 6: by pile monkey continue piling construction, when stake top be sink to need pile follower close to ground when, detect the verticality of tubular pole And check stake top quality, using Pile feeder pile follower to absolute altitude after meeting the requirements, and using the deviation of level control stake top absolute altitude.
Further, tolerance≤10mm of PHC tubular pole position.
Further, the radial misalignment of the vertical shallow hole should not exceed 50mm.
Further, the welding of the pile cutoff of section up and down uses CO2Gas shielded arc welding, the upper and lower dislocation deviation for saving pile cutoff≤ 2mm saves the gap between pile cutoff faying face up and down and is not more than 2mm, and it is long to be not greater than stake for section pile cutoff node rise of arch of curve up and down 0.1%, and it is not more than 20mm, and pile extension carries out after lower section pile cutoff passes through hard stratum.
Further, the end of section up and down mismatch≤2mm of the pile cutoff welding of section up and down, undercut depth≤0.5mm, and And pore-free, without overlap, free from flaw.
Further, the loop wheel machine is the crawler type or autocrane for having major-minor suspension hook, main hook suspension hydraulic pile monkey, auxiliary hook It hangs stake and cooperates and feed stake, centering and pile follower.
Since the construction method of PHC tubular pole under the narrow site condition of the present invention uses above-mentioned technical proposal, i.e. this method first It carries out the positioning of PHC tubular pole and loop wheel machine is in place;Pile monkey is set to loop wheel machine main hook and is adjusted by loop wheel machine erect-position and gin pole angular compliance, protects Card pile monkey can be by having surveyed the true injection of stake level set;Tubular pole is hung to pile monkey position by loop wheel machine, is dug out in tubular pole position vertical Tubular pole lower end is entered hole by loop wheel machine and cooperates tubular pole upper end straightening pile body by straight shallow hole;Pile body is calibrated by two theodolites Verticality;Starting pile monkey starts piling construction, and pile extension operation is carried out when the pile crown of lower section pile cutoff 0.5m above ground level;Pass through Pile monkey continues piling construction, when stake top be sink to need pile follower close to ground when using Pile feeder pile follower to absolute altitude, and use level The deviation of instrument control stake top absolute altitude.This method easy construction, speed are fast, and pile quality is high, avoid generating using cast-in-situ bored pile A large amount of mud contaminations or the requirement driven piles to construction site of conventional stake machine, reduce the destruction to urban operating mechanism and greening, reduce Project cost.
Specific embodiment
The construction method of PHC tubular pole includes the following steps: under the narrow site condition of the present invention
Step 1: according to PHC tube pile construction detail drawing, it is accurately positioned the position of PHC tubular pole using total station, and loop wheel machine is accurately Position;
Step 2: by pile monkey be set to crane hook main hook on and with crane hydraulic system connection, hydraulic system pipeline length meet Tubular pole is adjusted in the length requirement of highs and lows by loop wheel machine erect-position and gin pole angular compliance, guarantees loop wheel machine erect-position Stability and pile monkey can be by having surveyed the true injection of stake level set;
It with anchor point is to justify in tubular pole position Step 3: by loop wheel machine hung tubular pole to pile monkey position using two o'clock lifting method Tubular pole lower end is entered hole by loop wheel machine and cooperates tubular pole upper end by the heart slightly larger than the vertical shallow hole that deep 500mm is dug out in tubular pole outer ring Smoothly straightening pile body;
Step 4: intersecting theodolite in 90 ° using two is set up in the position away from stake position certain distance, successively pass through two warps Latitude instrument detects the verticality of pile body, cooperates repeated detection adjustment by loop wheel machine and theodolite, guarantees pile body degree control 1% Within;
Step 5, starting pile monkey start piling construction, pile extension operation are carried out when the pile crown of lower section pile cutoff 0.5m above ground level, is connect Section pile cutoff keeps the straight and verticality by saving tubular pole on theodolite centering up and down when stake, section pile cutoff surrounding up and down symmetrically into Row welding and natural cooling;
Step 6: by pile monkey continue piling construction, when stake top be sink to need pile follower close to ground when, detect the verticality of tubular pole And check stake top quality, using Pile feeder pile follower to absolute altitude after meeting the requirements, and using the deviation of level control stake top absolute altitude.
Preferably, tolerance≤10mm of PHC tubular pole position.
Preferably, the radial misalignment of the vertical shallow hole should not exceed 50mm.
Preferably, the welding of the pile cutoff of section up and down uses CO2Gas shielded arc welding, the upper and lower dislocation deviation for saving pile cutoff≤ 2mm saves the gap between pile cutoff faying face up and down and is not more than 2mm, and it is long to be not greater than stake for section pile cutoff node rise of arch of curve up and down 0.1%, and it is not more than 20mm, and pile extension carries out after lower section pile cutoff passes through hard stratum.
Preferably, the end of section up and down mismatch≤2mm of the pile cutoff welding of section up and down, undercut depth≤0.5mm, and And pore-free, without overlap, free from flaw.
Preferably, the loop wheel machine is the crawler type or autocrane for having major-minor suspension hook, main hook suspension hydraulic pile monkey, auxiliary hook It hangs stake and cooperates and feed stake, centering and pile follower.
For this method after the completion of pile foundation construction, stake hole need to go along with sb. to guard him processing using the backfill of block stone or bamboo sheathing in time, it is ensured that scene Construction safety.When work progress need to record pile sinking overall process, pile sinking or pile follower simultaneously every root canal should be recorded in detail by related standard Pile penetration that the pile No. of stake, operating time, plektron, hydraulic pressure, amplitude, global vibration number, embedded depth, last ten hit, stake The initial data such as in-plane displancement and inclination carry out the hidden record of welding to pile extension welding;It should also record in pile driving process and send out simultaneously Raw abnormal conditions;After completing construction, telephone-moving to next position.
The particularly suitable surface layer of this method is the municipal pipeline construction in artificial earth fill or coastal sludge place, significantly improves and applies Work efficiency rate, and pile quality is high, easy construction, speed are fast, avoid a large amount of mud contaminations generated using cast-in-situ bored pile or normal Place handles the destruction to urban operating mechanism and greening when advising the piling of stake machine.
This method beats stake using the large-scale crane fluid,matching piling for having major-minor suspension hook, is particularly suitable for municipal pipeline field The construction on ground, sufficiently long arm of crane can effective avoiding obstacles, and pile monkey using crane hydraulic system drive, have section Save fuel oil, protection environment, the advantages that construction noise is small, the tube pile construction being suitble under narrow site condition.
The advantages of hammer piling speed of application is fast, pile quality is high, energy conservation and environmental protection can be given full play to by this method.And And using existing town road as loop wheel machine walking road, place processing cost is few, and save the cost is speeded up the work, and uses Reasonable design, avoids underground utilities, and the measure cost for reducing pipeline protection and the destruction of the urban operating mechanisms such as greening on the ground avoid Or it is reduced as far as possible because of the influence generated to road traffic of constructing.

Claims (6)

1. the construction method of PHC tubular pole under a kind of narrow site condition, it is characterised in that this method includes the following steps:
Step 1: according to PHC tube pile construction detail drawing, it is accurately positioned the position of PHC tubular pole using total station, and loop wheel machine is accurately Position;
Step 2: by pile monkey be set to crane hook main hook on and with crane hydraulic system connection, hydraulic system pipeline length meet Tubular pole is adjusted in the length requirement of highs and lows by loop wheel machine erect-position and gin pole angular compliance, guarantees loop wheel machine erect-position Stability and pile monkey can be by having surveyed the true injection of stake level set;
It with anchor point is to justify in tubular pole position Step 3: by loop wheel machine hung tubular pole to pile monkey position using two o'clock lifting method Tubular pole lower end is entered hole by loop wheel machine and cooperates tubular pole upper end by the heart slightly larger than the vertical shallow hole that deep 500mm is dug out in tubular pole outer ring Smoothly straightening pile body;
Step 4: intersecting theodolite in 90 ° using two is set up in the position away from stake position certain distance, successively pass through two warps Latitude instrument detects the verticality of pile body, cooperates repeated detection adjustment by loop wheel machine and theodolite, guarantees pile body degree control 1% Within;
Step 5, starting pile monkey start piling construction, pile extension operation are carried out when the pile crown of lower section pile cutoff 0.5m above ground level, is connect Section pile cutoff keeps the straight and verticality by saving tubular pole on theodolite centering up and down when stake, section pile cutoff surrounding up and down symmetrically into Row welding and natural cooling;
Step 6: by pile monkey continue piling construction, when stake top be sink to need pile follower close to ground when, detect the verticality of tubular pole And check stake top quality, using Pile feeder pile follower to absolute altitude after meeting the requirements, and using the deviation of level control stake top absolute altitude.
2. the construction method of PHC tubular pole under narrow site condition according to claim 1, it is characterised in that: the PHC pipe Tolerance≤10mm of stake position.
3. the construction method of PHC tubular pole under narrow site condition according to claim 1, it is characterised in that: described vertical The radial misalignment of shallow hole should not exceed 50mm.
4. the construction method of PHC tubular pole under narrow site condition according to claim 1, it is characterised in that: above and below described The welding for saving pile cutoff uses CO2Gas shielded arc welding saves dislocation deviation≤2mm of pile cutoff up and down, saves between pile cutoff faying face up and down Gap be not more than 2mm, save pile cutoff node rise of arch of curve up and down and be not greater than long 0.1% of stake, and be not more than 20mm, and connect Stake carries out after lower section pile cutoff passes through hard stratum.
5. the construction method of PHC tubular pole under narrow site condition according to claim 1, it is characterised in that: above and below described Save pile cutoff welding the end of section up and down mismatch≤2mm, undercut depth≤0.5mm, and pore-free, without overlap, free from flaw.
6. the construction method of PHC tubular pole under narrow site condition according to claim 1, it is characterised in that: the loop wheel machine To have the crawler type of major-minor suspension hook or autocrane, main hook suspension hydraulic pile monkey, auxiliary hook hangs stake and cooperates and feeds stake, centering and send Stake.
CN201710661086.6A 2017-08-04 2017-08-04 Construction method of PHC tubular pile under narrow field condition Active CN109385997B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710661086.6A CN109385997B (en) 2017-08-04 2017-08-04 Construction method of PHC tubular pile under narrow field condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710661086.6A CN109385997B (en) 2017-08-04 2017-08-04 Construction method of PHC tubular pile under narrow field condition

Publications (2)

Publication Number Publication Date
CN109385997A true CN109385997A (en) 2019-02-26
CN109385997B CN109385997B (en) 2021-01-15

Family

ID=65413389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710661086.6A Active CN109385997B (en) 2017-08-04 2017-08-04 Construction method of PHC tubular pile under narrow field condition

Country Status (1)

Country Link
CN (1) CN109385997B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258556A (en) * 2019-06-21 2019-09-20 中国水利水电第四工程局有限公司 A kind of pile extension method of engineering tubular pile construction
CN110872843A (en) * 2019-11-29 2020-03-10 深圳宏业基岩土科技股份有限公司 Construction method for controlling verticality of foundation pit section steel lattice column

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010180689A (en) * 2009-04-20 2010-08-19 Toyo Constr Co Ltd Soundproof device for hydraulic hammer
CN103225303A (en) * 2013-04-28 2013-07-31 上海宝冶集团有限公司 Construction method for driving piles in narrow space
CN106193036A (en) * 2015-04-30 2016-12-07 五冶集团上海有限公司 PHC tube pile of major diameter construction method
CN106284351A (en) * 2016-10-14 2017-01-04 江苏聚亿智能科技有限公司 There is the photovoltaic piling machine of hi-Fix

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010180689A (en) * 2009-04-20 2010-08-19 Toyo Constr Co Ltd Soundproof device for hydraulic hammer
CN103225303A (en) * 2013-04-28 2013-07-31 上海宝冶集团有限公司 Construction method for driving piles in narrow space
CN106193036A (en) * 2015-04-30 2016-12-07 五冶集团上海有限公司 PHC tube pile of major diameter construction method
CN106284351A (en) * 2016-10-14 2017-01-04 江苏聚亿智能科技有限公司 There is the photovoltaic piling machine of hi-Fix

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258556A (en) * 2019-06-21 2019-09-20 中国水利水电第四工程局有限公司 A kind of pile extension method of engineering tubular pile construction
CN110872843A (en) * 2019-11-29 2020-03-10 深圳宏业基岩土科技股份有限公司 Construction method for controlling verticality of foundation pit section steel lattice column

Also Published As

Publication number Publication date
CN109385997B (en) 2021-01-15

Similar Documents

Publication Publication Date Title
CN106369223A (en) Pipe-jacking construction method for mealy sand stratum
CN103114599B (en) Deep basal pit sealing dewatering device and construction method thereof
CN101418570A (en) Foundation pit supporting method with double rows of piles
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN101408023A (en) Method for supporting and protecting row pile pit
CN104455726A (en) Pipe-jacking construction method for pipeline bottom grouting reinforcement
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN107034884A (en) The steel pile casting constructing device and method of the big oblique rock surface of shallow overburden profundal zone flow velocity
CN102704480B (en) Construction method for processing ultra-thick quicksand layer of pile foundation by using front-end vibration steel casing
CN112030956A (en) Karst stratum bored pile construction method
CN110984133A (en) Construction method for foundation of deep-water shallow-covering-layer trestle
CN108842802A (en) Piles in Karst Region base construction method
WO2024007591A1 (en) Rock-socketed monopile construction method based on double-casing pile stabilizing platform
CN113431039A (en) Construction method of bridge implanted pile
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN109385997A (en) The construction method of PHC tubular pole under narrow site condition
CN104947664A (en) Thick stone sea-filling layer prestressing force high-strength concrete square pile construction method
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN103132532A (en) Foundation pit support method for row of piles
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam
CN102605781A (en) Rocky bed steel pipe pile sinking construction process
CN203113361U (en) Deep foundation pit sealing precipitation device
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
CN106337418A (en) Supporting structure and supporting method of deep foundation pit in narrow area
CN103132522B (en) Shallow thick mud layer soft soil area driven pile construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant