CN101318606A - 一种多绳摩擦式提升机串绳方法 - Google Patents
一种多绳摩擦式提升机串绳方法 Download PDFInfo
- Publication number
- CN101318606A CN101318606A CNA2007100156895A CN200710015689A CN101318606A CN 101318606 A CN101318606 A CN 101318606A CN A2007100156895 A CNA2007100156895 A CN A2007100156895A CN 200710015689 A CN200710015689 A CN 200710015689A CN 101318606 A CN101318606 A CN 101318606A
- Authority
- CN
- China
- Prior art keywords
- rope
- oil cylinder
- gate valve
- cylinders
- wire rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Control And Safety Of Cranes (AREA)
- Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)
Abstract
一种多绳磨擦式提升机串绳方法,采用了将钢丝绳张力自动平衡装置油缸与专用液压站相联接,打开油缸的闸阀,对自动平衡悬挂装置的油缸进行打压,将四个油缸的活塞杆伸出,箕斗上升,将各油缸的分闸阀关闭,打开其中一个油缸的分闸阀、总闸阀,将油缸的液压油外泄到液压站油池内,另一个导链拉住绳头,边松楔形环的楔块、边提楔形环、再拉绳头,将油缸活塞杆全部缩入油缸内,安装好楔形环卡紧钢丝绳,单根钢丝绳完成串绳工作,按同样步骤将第二、三、四根绳进行串绳,完成一次串绳工作的方法,因而,能省时省力,危险性小,不影响生产,特别适合于矿山提升矿石之用。
Description
技术领域:
本发明涉及一种串绳方法,特别是一种用于多绳摩擦式提升机串绳方法。
背景技术:
多绳磨擦式提升机在使用一段时间后,因提升钢丝绳伸长,影响提升系统安全运行,必须对提升钢丝绳进行串绳,以缩短提升钢丝绳长度,达到安全使用要求。过去的串绳方法是用十几名维修工搭建高空作业平台进行作业,将箕斗停在特定位置,采用20吨导链2付,10吨导链2付将箕斗整个提起,再拆装楔形环,约需12个小时,且因高空作业及劳动强度高造成危险程度大;作业时间连续性强,延误生产。
发明内容:
本发明的目的是一种利用单向自锁卡绳器卡绳锁罐,钢丝绳张力自动平衡装置单根、分次调绳,从而将箕斗上提,缩短提伸钢丝绳长度的多绳磨擦式提升机串绳方法。
本发明的目的是这样实现的:一种多绳摩擦式提升机串绳方法,其特征在于
(1)、选定多绳磨擦式提升系统的提升容器箕斗,作为串绳侧容器,将箕斗停在井口,在钢丝绳张力自动平衡悬挂装置两侧搭建木板,作为维修工人作业平台;
(2)在井塔四层罐笼侧,将两根工字钢平置在四根提升钢丝绳两侧,采用四架单向自锁卡绳器将四根提升钢丝绳卡住;
(3)在钢丝绳张力自动平衡装置上侧3米左右,卡一付板卡,并悬挂2吨导链2个,将钢丝绳张力自动平衡装置油缸与专用液压站相联接,打开油缸的闸阀,对自动平衡悬挂装置的油缸进行打压,将四个油缸的活塞杆伸出,箕斗上升,将各油缸的分闸阀关闭,根据油缸伸长情况进行串绳,打开其中一个油缸的分闸阀、总闸阀,将油缸的液压油外泄到液压站油池内,用2吨导链提住楔形环,防止倒缸,另一个导链拉住绳头,遍松楔形环的楔块、边提楔形环、再拉绳头,将油缸活塞杆全部缩入油缸内,安装好楔形环卡紧钢丝绳,单根钢丝绳完成串绳工作,按同样步骤将第二、三、四根绳进行串绳,完成一次串绳工作,每次约可串绳0.4米以上,用时60分钟;
(4)按同样步骤进行串绳4~5次,将箕斗提起约2米以上,达到检修目的,拆卸掉板卡、卡绳器,对四个调绳油缸进行打压,调节四根钢丝绳张力达到平衡。
本发明与现有技术相比具有以下优点:
由于采用了以上四步串绳方法,因而,能利用单向自锁卡绳器卡绳锁罐,钢丝绳张力自动平衡装置单根、分次调绳,从而将箕斗上提,缩短提伸钢丝绳长度,省时省力,危险性小,不影响生产。
具体实施方式:
(1)、选定多绳磨擦式提升系统的提升容器箕斗,作为串绳侧容器,将箕斗停在井口,在钢丝绳张力自动平衡悬挂装置两侧搭建木板,作为维修工人作业平台;
(2)在井塔四层罐笼侧,将两根工字钢平置在四根提升钢丝绳两侧,采用四架单向自锁卡绳器将四根提升钢丝绳卡住;
(3)在钢丝绳张力自动平衡装置上侧3米左右,卡一付板卡,并悬挂2吨导链2个,将钢丝绳张力自动平衡装置油缸与专用液压站相联接,打开油缸的闸阀,对自动平衡悬挂装置的油缸进行打压,将四个油缸的活塞杆伸出,箕斗上升,将各油缸的分闸阀关闭,根据油缸伸长情况进行串绳,打开其中一个油缸的分闸阀、总闸阀,将油缸的液压油外泄到液压站油池内,用2吨导链提住楔形环,防止倒缸,另一个导链拉住绳头,遍松楔形环的楔块、边提楔形环、再拉绳头,将油缸活塞杆全部缩入油缸内,安装好楔形环卡紧钢丝绳,单根钢丝绳完成串绳工作,按同样步骤将第二、三、四根绳进行串绳,完成一次串绳工作,每次约可串绳0.4米以上,用时60分钟;
(4)按同样步骤进行串绳4-5次,将箕斗提起约2米以上,达到检修目的,拆卸掉板卡、卡绳器,对四个调绳油缸进行打压,调节四根钢丝绳张力达到平衡。
Claims (1)
- 一种多绳磨擦式提升机串绳方法,其特征在于它包括以下步骤:(1)、选定多绳磨擦式提升系统的提升容器箕斗,作为串绳侧容器,将箕斗停在井口,在钢丝绳张力自动平衡悬挂装置两侧搭建木板,作为维修工人作业平台;(2)在井塔四层罐笼侧,将两根工字钢平置在四根提升钢丝绳两侧,采用四架单向自锁卡绳器将四根提升钢丝绳卡住;(3)在钢丝绳张力自动平衡装置上侧3米左右,卡一付板卡,并悬挂2吨导链2个,将钢丝绳张力自动平衡装置油缸与专用液压站相联接,打开油缸的闸阀,对自动平衡悬挂装置的油缸进行打压,将四个油缸的活塞杆伸出,箕斗上升,将各油缸的分闸阀关闭,根据油缸伸长情况进行串绳,打开其中一个油缸的分闸阀、总闸阀,将油缸的液压油外泄到液压站油池内,用2吨导链提住楔形环,防止倒缸,另一个导链拉住绳头,遍松楔形环的楔块、边提楔形环、再拉绳头,将油缸活塞杆全部缩入油缸内,安装好楔形环卡紧钢丝绳,单根钢丝绳完成串绳工作,按同样步骤将第二、三、四根绳进行串绳,完成一次串绳工作,每次约可串绳0.4米以上,用时60分钟;(4)按同样步骤进行串绳4-5次,将箕斗提起约2米以上,达到检修目的,拆卸掉板卡、卡绳器,对四个调绳油缸进行打压,调节四根钢丝绳张力达到平衡。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007100156895A CN101318606A (zh) | 2007-06-06 | 2007-06-06 | 一种多绳摩擦式提升机串绳方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2007100156895A CN101318606A (zh) | 2007-06-06 | 2007-06-06 | 一种多绳摩擦式提升机串绳方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101318606A true CN101318606A (zh) | 2008-12-10 |
Family
ID=40178921
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2007100156895A Pending CN101318606A (zh) | 2007-06-06 | 2007-06-06 | 一种多绳摩擦式提升机串绳方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101318606A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101759085B (zh) * | 2009-11-20 | 2011-09-28 | 徐州市工大三森科技有限公司 | 链式夹绳连续送绳装置 |
CN110451392A (zh) * | 2019-08-31 | 2019-11-15 | 山东黄金矿业(玲珑)有限公司 | 落地式多绳摩擦提升机天轮轴瓦更换方法 |
CN112456276A (zh) * | 2020-11-25 | 2021-03-09 | 中煤新集能源股份有限公司 | 矿用摩擦式提升机调绳工艺 |
CN113353762A (zh) * | 2021-05-12 | 2021-09-07 | 中信重工机械股份有限公司 | 一种矿井提升防过卷的钢丝绳联接装置 |
-
2007
- 2007-06-06 CN CNA2007100156895A patent/CN101318606A/zh active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101759085B (zh) * | 2009-11-20 | 2011-09-28 | 徐州市工大三森科技有限公司 | 链式夹绳连续送绳装置 |
CN110451392A (zh) * | 2019-08-31 | 2019-11-15 | 山东黄金矿业(玲珑)有限公司 | 落地式多绳摩擦提升机天轮轴瓦更换方法 |
CN110451392B (zh) * | 2019-08-31 | 2021-04-27 | 山东黄金矿业(玲珑)有限公司 | 落地式多绳摩擦提升机天轮轴瓦更换方法 |
CN112456276A (zh) * | 2020-11-25 | 2021-03-09 | 中煤新集能源股份有限公司 | 矿用摩擦式提升机调绳工艺 |
CN112456276B (zh) * | 2020-11-25 | 2022-07-05 | 中煤新集能源股份有限公司 | 矿用摩擦式提升机调绳工艺 |
CN113353762A (zh) * | 2021-05-12 | 2021-09-07 | 中信重工机械股份有限公司 | 一种矿井提升防过卷的钢丝绳联接装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109837881B (zh) | 一种全平衡钢丝绳卷扬提升式垂直升船机的平衡重安装及承船厢调平方法 | |
CN100519396C (zh) | 扒杆综合拆卸塔式起重机方法 | |
CN104787652B (zh) | 摩擦式提升机尾绳更换方法 | |
CN103863938B (zh) | 用于搬运风洞实验车的安全吊装装置 | |
CN101318606A (zh) | 一种多绳摩擦式提升机串绳方法 | |
CN110877852A (zh) | 立井摩擦式提升机快速换绳系统及方法 | |
CN203465079U (zh) | 一种多功能试验装置 | |
CN110104568B (zh) | 一种塔式起重机安装自检评估方法 | |
CN107150945B (zh) | 井塔式四绳摩擦提升机首绳更换方法 | |
CN206161433U (zh) | 滑轮组式液压缸加载试验装置 | |
CN106758860A (zh) | 一种跨缆行走索夹吊运安装装置及方法 | |
CN106315426B (zh) | 一种装配建筑用平头式塔机安装、顶升方法 | |
CN105173975A (zh) | 一种多绳缠绕式提升机的同步天轮平衡调整方法 | |
CN105819319B (zh) | 一种立井提升系统的主提升绳调整装置及其调节方法 | |
CN110451392B (zh) | 落地式多绳摩擦提升机天轮轴瓦更换方法 | |
CN110104571A (zh) | 海洋工程起重机的钢丝绳预紧方法 | |
CN110409803B (zh) | 拆卸液压提模装置中心鼓圈的吊装方法 | |
CN107724256A (zh) | 斜拉索换索工艺 | |
CN112456276B (zh) | 矿用摩擦式提升机调绳工艺 | |
CN204624958U (zh) | 吊排 | |
CN107389366B (zh) | 大拉力试验台 | |
CN108545629B (zh) | 利用塔式起重机顶升桁架梁的施工方法 | |
CN107651589B (zh) | 双排导向滑轮及双排多股钢丝绳的导向方法 | |
CN106441961A (zh) | 一种起锚绞盘负载试验系统 | |
CN102061681A (zh) | 固定双吊点悬臂轨道式桁吊安装方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20081210 |